- Solicitation number
- JustificationApproval2613
About this file
This document is a Department of the Air Force Justification for Other Than Full and Open Competition (CUI) approving a sole-source contract award.
The contract is awarded to Amentum Technology, Inc. (CAGE 07486) for Sensitive Compartmented Information Facility (SCIF) Management and Oversight Services supporting the North American Aerospace Defense Command (NORAD) Cheyenne Mountain Complex-Integrated Tactical Warning/Attack Assessment (NCMC-ITW/AA) Program Office under Space Systems Command, Battlespace Management Command, Control, Communication & Space Intelligence - Colorado (SSC/BCK-CO). The four-year contract includes one base year (26 December 2026 – 25 December 2027) and three option years, with services required to support classified engineering development up to the secret level for Nuclear Command, Control, and Communications (NC3) Missile Warning and Legacy Space Command (LSC2) missions. The contractor must provide a fully accredited System Integration Laboratory/SCIF with active Authority to Connect (ATC) and Authority to Operate (ATO) for the NIIDE system connection within the Test Development Facility by 26 December 2026 to prevent mission capability gaps.
The justification for sole-source award under 10 U.S.C. 3204(a)(1) centers on Amentum being the only responsible source capable of meeting the compressed timeline. A Sources Sought Notice (FA8723-26-R-B003) posted 7 October 2025 through 14 November 2025 received fourteen responses; only one vendor could meet all three objectives including the required delivery date, while nine vendors could not meet the 26 December 2026 deadline, with most requiring 12-24 months minimum versus Amentum's ability to roll over its existing ATO (normally a 48-month process). Any competing contractor would need 16-24 months minimum to establish accreditation and obtain a new ATO, creating unacceptable delays to national security capabilities. The existing ATO is transferable to a follow-on contract if the Security Assessment Report is submitted 90 days prior to current contract expiration, enabling continuous performance without interruption.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of the Air Force: Justification for Other Than Full and Open Competition
CUI
March 2026 Page 2 of 5March 2026 Page 2 of 5
I. Agency and Contracting Activity (RFO 6.104-1(a)(1)):
J&A #26-13
Agency: North American Aerospace Defense Command (NORAD) Cheyenne Mountain Complex-Integrated Tactical Warning/ Attack Assessment (NCMC-ITW/AA) Program Office, SYD 85/BMN.
Contracting Activity: Space Systems Command, Battlespace Management Command, Control, Communication & Space Intelligence - Colorado, SSC/BCK-CO.
II. Nature and/or description of the action being approved (RFO 6.104-1(a)(2)):
This document approves the award of a contract on a sole source basis to Amentum Technology, Inc. Commercial and Government Entity (CAGE) 07486 for Sensitive Compartmented Information Facility (SCIF) Management and Oversight Services supporting a Systems Integration Lab (SIL) in an established NCMC-ITW/AA development environment to include in support of the North American Aerospace Defense Command (NORAD) Cheyenne Mountain Complex-Integrated Tactical Warning/Attack Assessment (NCMC-ITW/AA) Program Office. This justification is made on an Individual basis. Four (4) year contract, with one base year (26 Dec 2026 - 25 Dec 2027), and 3 option years (26 Dec
20XX - 25 Dec 20XX). The options are included for flexibility to accommodate the uncertainty of the full DCSA accreditation and ATO approval process
III. Description of supplies/services required to meet agency needs (RFO 6.104-1(a)(3)):
The services described herein are for the continued sustainment and enhancement of the Nuclear Command, Control, and Communications (NC3) Missile Warning and Legacy Space Command (LSC2) missions. This requires contractor personnel to have secure, reliable access to the NCMC-ITW/AA development environment form a System Integration Laboratory/Sensitive Compartmented Information Facility (SIL/SCIF).
The required SIL/SCIF services must support classified engineering development up to the secret (S) level for
. The facility must be fully accredited by the Defense Counterintelligence and Security Agency (DCSA) and possess an active Authority to Connect (ATC) and Authority to Operate (ATO) for the NIIDE system connection within the Test Development Facility (TDF). The TDF is an operationally representative government environment used for testing and fielding critical warfighting capabilities. Access to this development and integration environment is essential for ingesting and replaying synthetic models, performing system enhancements, and deploying cybersecurity updates.
A critical component of this effort is the provision of a secure facility that consolidates contractor resources to enhance mission effectiveness and security. the SIL/SCIF services, including an active ATO for the NIIDE connection, must be fully operational no later than 26 December 2026 to prevent a gap in mission support. The total estimated value of this effort is including all options.
IV. Statutory Authority Permitting Other Than Full and Open Competition (RFO 6.104-1(a)(4)):
10 U.S.C. 3204(a)(1), Only one responsible source and no other supplies or services will satisfy agency requirements.
V. Rationale for Use of Authority (RFO 6.104-1(a)(5)):
This acquisition is for a follow-on contract for the continued provision of highly specialized services supporting the Nuclear Command, Control, and Communications (NC3) Missile Warning and Legacy Space Command (LSC2) missions, as described in Section III. Awarding this contract to any source other than the incumbent, Amentum, would result in substantial and
March 2026 Page 3 of 5March 2026 Page 3 of 5 unacceptable delays in fulfilling the agency's requirements, leading to a significant loss of mission capability.
Amentum is the only source that can meet the Government's required availability date of 26 December 2026. The contractor currently operates a fully accredited SIL/SCIF with the necessary ATC and an active ATO for the NIIDE system connection. The existing and active ATO, which is transferable to a follow-on contract, is the critical enabler and represents the unique qualification that no other contractor possesses. Per DCSA policy, an existing ATO can be rolled over to a new contract if the Security Assessment Report (SAR) package is submitted at least 90 days prior to the current contract's expiration. This provision allows for continuous performance without interruption.
Any other contractor would need to establish, accredit, and obtain an ATO for a new facility. The Government's market research indicates this process would take a minimum of 16-24 months, with the historical precedent for this specific NIIDE connection being 48 months. This timeline does not meet the Government's need for services to be in place by 26 December 2026 and would create an unacceptable gap in mission support. Failure to leverage the incumbent's existing ATO by missing the 90-day submission window would force the entire multi-year approval process to start from the beginning.
This delay is unacceptable due to the direct impact on national security capabilities. The quantified impact of this delay is as follows:
The 12-18 month delay estimated by potential new vendors represents the bare minimum time to replicate the infrastructure, not to achieve full mission capability. Furthermore, this NIIDE connection requirement
Competing this requirement separately now would introduce this same unacceptable delay for a second time, compounding risk and disrupting the NCMC-ITW/AA mission. Therefore, Amentum is the only source capable of fulfiling the requirement without causing mission-critical delays.
VI. Integrated Market Analysis and Efforts to Solicit Competition (RFO 6.104-1(a)(6), (8), and (10)):
Market Intelligence: Historical acquisition via the NISSC II contract, the contractor stood up a systems integration lab in an off-base facility, to allow for the development of the NIIDE connection and expanded the use of the Research, Development, and Test environment, expanding the government's TDF capacity by However, this NIIDE connection to the systems integration lab space took 48 months to obtain the ATO DCSA accreditation. This length of time to establish a new NIIDE connection would cause an unacceptable delay to the warfighter's capabilities.
Efforts to Solicit Competition: A Sources Sought Notice/RFI, FA8723-26-R-B003, was posted on 07 October 2025 originally due on 07 November, and extended to 14 November on SAM.gov, open to any registrant in SAM.gov as required by subpart
5.2. An additional response was permitted on 11 December 2025 based on our legal advisor's recommendation. Fourteen
(14) responses were received from interested vendors. Two (2) interested vendors responded, but only with capability statements which did not address the specific capabilities in the Sources Sought. Only one (1) of the interested vendors responded was technically capable of addressing all three of the required objectives. Nine (9) of the interested vendors were capable of meeting Objectives two and three, but not one, which spoke to the required need date of 26 June 2026. Of these nine vendors, three (3) estimated the earliest date which could be met is fourteen (14) months from date of award; and one
(1) vendor estimated the earliest date which could be met is 24 months from date of award.
The key capabilities vendors were required to prove to be considered viable were:
1) Facility Establishment & Operations including Timeline to SIL accreditation, ATC, and ATO approval for the NIIDE
March 2026 Page 4 of 5March 2026 Page 4 of 5 connection to start on 26 June 2026.
2) Security & Compliance
3) Integration, Collaboration, Innovation, & Cost Effectiveness (and Rough Order of Magnitude)
Results/Conclusion:
Each of these respondents would require at least 12 months to get the SIL to full operational capacity, however the average of the respondents is . The realism in this projection is extremely optimistic based on concurrent timelines, clean package submittal, and review times by the government SCAs done in record time. Historically, it has taken 48 months to achieve the NIIDE connection to ATC/ATO approval.
Four of the thirteen respondents (this excludes the incumbent) provided the number of months it would take to stand up a systems integration lab to our requirements. Three of these respondents demonstrated experience with NCMC-ITW/AA development environment, or provide descriptive details on how they could leverage existing infrastructure to reduce costs or accelerate implementation for the purpose of establishing SILs and SCIFs. e.g., no identified locations in the greater Colorado Springs area were identified in any of the responses; however use of existing infrastructure was stated.
VII. Determination of Fair and Reasonable Cost (RFO 6.104-1(a)(7)):
The Contracting Officer is responsible for evaluating, determining, and documenting the anticipated contract cost/price is fair and reasonable in accordance with RFO Subpart 15.4, Contract Pricing.
March 2026 Page 5 of 5March 2026 Page 5 of 5
VIII. Any Other Facts Supporting the Justification (RFO 6.104-1(a)(9)):
Under the NISSC II Task Order, the full approval for the NIIDE connection for the contractor facility took a total of four years.
The process began in August of 2020 and full ATO for NIIDE connection was received in November 2024. This ATO approval was the last step of many and most are out of the contractor's direct control: 21 CS approval for NIPR/SIPR; USSF approval for ATC to NIIDE in TDF - DCSA approval of SCIF for which the NIIDE connection is housed; and finally ATO approval by DCSA for the NIIDE connection itself.
IX. Actions to Overcome Barriers to Competition (RFO 6.104-1(a)(11):
In an effort to overcome barriers to competition, SSC SYD 85/BMN submitted facility requirements in April 2025 for two potential locations.
The requirement relevant to the SIL effort:
- Secure Access Program Facility (SAPF);
- Unclassified (NIPR) and Classified (SIPR) communications connections;
- Connection to the Government's Development Environment hosted on Peterson SFB );