Justification and Approval For Other than Full and Open Competition

Requisition Number:

Form Updated 10/26/2021

Justification & Approval For Other than Full and Open Competition

As a legislative branch agency, the Library is subject to the competition and advertising requirements of 41 U.S.C. § 6101. Like the Competition in Contracting Act and the FAR, 41 U.S.C. § 6101 does not require competition when a contracting officer certifies that only one source or brand-name item is available, when dictated by public exigency, or when otherwise authorized by law.

This document sets forth the justification and approval for award of a contract or order by means providing for other than full and open competition per 41 U.S.C. § 6101, LCR 7-210, and, as applicable, FAR 6.302, FAR 13.106-1, FAR 8.405, and FAR 16.505. Contracting without competition shall not be justified on the basis of a lack of advance planning or concerns related to availability of funds.

This form shall be used to support instances where competition will be limited to a single source, a limited number of sources, including where a brand name product is required.

Part 1 – Identification

1. Contracting Agency and Activity: Library of Congress, Congressional Research Service, Office of the Director

2. Nature of Action Being Approved Contract (or modification) LoC or Leg Branch Order (or modification) GSA Schedule or GWAC: Identify Schedule/Contract Other: Identify

Requisition Number: RQCRS20230004 Contractor (or Brand Name): Passenger Railroad Corporation Estimated Value (Base and all options):

Period of Performance

3. Description of Supplies or Services Required to Meet Library Needs

Describe the supplies or services that are required to meet the Library’s minimum needs and the delivery schedule required to meet those needs. Do not focus on a description of the program.

The Library requires the following supplies or services: Charter rail service from Union Station in Washington, DC to Philadelphia, PA for ; CRS staff, and other speakers. This rails service will include:

• Two (2) locomotives;

• Four (4) 72 seat coaches; and

• Three (3) dinettes

For a total of 200 passengers to include: 4 Service Attendances, Engineer/Conductor/Asst. Conductor, and a Mechanical Rider.

It will also include the option of adding an additional coach and dinette bundle for a 100 additional passengers.

*The exercising of the optional requirement to add an additional Coach and All Table Dinette for an additional 100 passengers would add a to be determined amount to the total price of this contract.

Requisition Number:

Form Updated 7/2/2020

Part 2 – Program Office Justification & Approval

4. Authority for Contracting Without Competition Over $250,000 For this requirement over $250,000, under FAR part 6, the basis for contracting without providing for full and open competition is:

There is only one responsible source and no other supplies or services will satisfy Library requirements.

41 U.S.C. § 6101(b)(2)(C); FAR 6.302-1.

Library’s minimum needs can only be satisfied by contractor’s unique capabilities or products. FAR 6.302-1(b)(1).

Source controls copyrights, patents, raw materials, or secret processes cannot be acquired otherwise, or similar circumstances. FAR 6.302- 1(b)(2).

Other exception identified in FAR 6.302-1: Identify the exception

There is such unusual & compelling urgency that the Government would be seriously injured if competition is not limited.

41 U.S.C. § 6101(b)(2)(B); FAR 6.302-2. Option years are not permitted.

Source is expressly authorized or required by statute (e.g., AbilityOne, UNICOR, GPO, GSA Public Buildings Service, Appropriations Act, etc.) per 41 U.S.C. § 6101(b)(1) and FAR 6.302-5: Identify the authority Other basis authorized in 41 U.S.C. § 6101(b) or FAR part 6.302: Identify the exception

Library’s needs can only be satisfied by a brand-name product or item which is essential to the Government’s requirement. FAR 6.302-1(c).

The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable IT Standard Data Sheet)

Up to and including $250,000 For this requirement up to $250,000, using simplified acquisition procedures under FAR part 13, the basis for contracting without providing for full and open competition is:

Only one responsible source is reasonably available to meet Library requirements. 41 U.S.C. § 6101(b); FAR 13.106-1.

Product or service is reasonably available from only one source.

Source controls copyrights, patents or other exclusive licensing arrangements.

Urgent circumstances; only one source can reasonably deliver by required date. Option years are not permitted.

Source is expressly authorized or required by statute: Identify the authority

Library’s needs can only be satisfied by a brand-name product The Product is listed the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable IT Standard Data Sheet)

GSA Schedule Order For this GSA schedule order under FAR part 8, the basis for not competing among GSA schedule-holders and/or specifying a brand name product or item is:

An urgent and compelling need exists, and following GSA procedures would result in unacceptable delays.

FAR 8.405-6(a)(1)(i)(A).

Only one GSA source is capable of fulfilling the requirement at the level of quality required because the supplies or services are unique or highly specialized. FAR 8.405-6(a)(1)(i)(B).

In the interest of economy and efficiency, the new work is a logical follow-on to an original order that was placed competitively among GSA schedule-holders (i.e., the original order was not sole-source or limited-source.) FAR 8.405-6(a)(1)(i)(C).

Library’s needs can only be satisfied by a brand-name product The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable IT Standard Data Sheet)

Order Under Multiple Award Indefinite-Delivery Contract or GWAC For this order under FAR subpart 16.5, the basis for contracting without providing for full and open competition is:

The need is so urgent fair opportunity would result in unacceptable delays. 41 U.S.C. § 6101(b)(2)(C) and FAR 16.505(b)(2)(i)(A).

The Library’s minimum needs can only be satisfied by contractor’s unique capabilities or products. 41 U.S.C. § 6101(b)(1) and FAR

16.505(b)(2)(i)(B).

A logical follow-on order in the interest of economy and efficiency. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(i)(2)(C).

To satisfy a minimum guarantee. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(2)(D).

Authorized or required by statute. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(2)(E).

The Library’s minimum needs can only be satisfied by a brand-name product or item which is essential to the Government’s requirement. 41 U.S.C. § 6101(b)(2)(B) and FAR 16.505(a)(4)(i).

The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable IT Standard Data Sheet)

Requisition Number:

Form Updated 7/2/2020

Part 4 – Competition Advocate Approval (Required for actions valued at greater than $700,000)

Approved. Based on the information, determinations, and certifications provided by the program office and the contracting officer, and in accordance with the instructions below, I approve contracting without competition for this requirement.

Option periods: No Yes, Number through Date

Not Approved. As explained below, I do not approve contracting without competition for this requirement.

Comments or instructions:

________________________ Assist/Assoc General Counsel __________________________________ ________________ Name Title

Signature

Date

Part 5 – Senior Procurement Executive (Required for actions valued at greater than $13,500,000)

17. Head of the Procurement Activity Approval

Approved. Based on the information, determinations, and certifications provided by the program office and the contracting officer, and in accordance with the instructions below, I approve contracting without competition for this requirement.

Not Approved. As explained below, I do not approve contracting without competition for this requirement.

Comments or instructions:

Name

Director, Contracts and Grants

Signature

Date