This document is a Limited Sources Justification Order for the Department of Veterans Affairs (VA), Network Contracting Office 21 (NCO 21) to establish a 6-month delivery order for automated clinical laboratory chemistry analyzers. The intent is to continue using the incumbent contractor, Beckman Coulter, Inc., while the VA Southern Nevada Healthcare System (VASNHCS) transitions to a successor contractor under a recently awarded long-term contract. This short-term order is justified due to the incumbent's unique qualifications, the need to maintain continuity of patient care, and the significant administrative burden that would be required to onboard a new provider during the transition period. The total estimated value of the proposed action is TBD. The VA will award this sole source delivery order against Beckman Coulter's existing Federal Supply Schedule contract.

View the file

Other files

File Type Posted
V797D-70260 36C26125F0016_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Effective Date: 02/01/2022 Page 1 of 4

LIMITED SOURCES JUSTIFICATION

ORDER >SAT

FAR PART 8.405-6

Acquisition Plan Action ID: ___36C261-24-AP-5003___

(1) Contracting Activity: Department of Veterans Affairs, Regional Procurement Office West

(RPOW), Network Contracting Office (NCO) 21, on behalf of VA Southern Nevada Healthcare

System (VASNHCS).

2237: 593-25-1-968-0023

(2) Description of Action: This acquisition is conducted under the authority of the Multiple-

Award Schedule Program (41 U.S.C. 152(3) and 40 U.S.C. 501). Pursuant to Federal Supply

Schedule (FSS) Group 66 III and FSS Contract Clause I-FSS-646, it is the intent of the

Department of Veterans Affairs (VA), Network Contracting Office 21 (NCO 21) to establish a new requirement for a Cost-Per-Reportable-Result (CPRR) delivery order for automated clinical laboratory chemistry analyzers for a period of 6 months.

Order against: FSS Contract Number: ___V797D-70260____

Name of Proposed Contractor: Beckman Coulter, Inc.

Street Address: 250 S. Kramer Blvd.

City, State, Zip: Brea, CA 92821

Phone: 714-872-6271

(3) Description of Supplies or Services:

The estimated value of the proposed action is

The intent of the Government is to establish a 6-month delivery order with the incumbent, Beckman Coulter, for chemistry and immunoassay testing while the station transitions to the successor contractor. Current instrumentation, software, ancillary equipment, and analyzer specific reagents will be used. The Contractor is required to provide a continuously stocked inventory of reagents, standards, controls supplies, disposables and any other materials required to properly perform tests on the equipment such that equipment operations are not interrupted.

(4) Identify the Authority and Supporting Rationale (see below and if applicable, a demonstration of the proposed contractor’s unique qualifications to provide the required supply or service.

FAR 8.405-6(a)(1)(A): An urgent and compelling need exists and following the ordering procedures would result in unacceptable delays:

https://www.acquisition.gov/far/part-8#FAR_8_405_6 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.gpo.gov/fdsys/pkg/USCODE-2011-title40/pdf/USCODE-2011-title40-subtitleI-chap5-subchapI-sec501.pdf

Effective Date: 02/01/2022 Page 2 of 4

FAR 8.405-6(a)(1)(B): Only one source is capable of providing the supplies or services required at the level of quality required because the supplies or services are unique or highly specialized;

The contractor is the current incumbent providing the supplies and services to the VASNHCS and has been performing satisfactorily. There is no other vendor that can mobilize and perform this requirement without a lapse in performance. Failure to obtain and provide the required reagents and supplies could be detrimental to Veteran patient care and the VA's efforts to provide early detection, accurate, reliable, and precise diagnosis for various medical conditions. The completion of an overhaul of the current chemistry analyzer system would not be in the best interest of the government, would require extensive manpower and funds to execute, and would not be in the best interest of taxpayer dollars considering a new long-term procurement is currently in the solicitation phase.

VASNHCS is requesting a short-term contract with Beckman Coulter to continue with their current two (2) DxC 700 AUs chemistry analyzers until the delivery of analyzer(s) and automation track, including all requirements related to installation, validation, and calibration services has been completed.

The laboratory has specific regulatory and accreditation guidelines for evaluating the many technical factors that could be affected any time there is a change in the way a test is performed.

This evaluation must be completed and reviewed prior to any patient results being reported.

Changes in test performance include, but are not limited to: different reagent manufacturer, different method of performing test, different analyzer.

If the contract for the chemistry analyzer for the current Beckman Coulter DxC 700 AU analyzers is awarded to another vendor, the laboratory would be required to perform a complete method validation for each test performed. Method validation includes studies of accuracy, linearity, precision, sensitivity, specificity, carryover, verifying critical values and reference ranges, developing new quality control ranges, writing new Standing Operating Procedures, changing the information in the lab information package, ensuring the same sample type and units of measurement, just to name a few. Most of these require the use of reagents, greatly increasing the amount needed even before patient testing can begin. During this time, the station will still need to purchase reagents from Beckman Coulter until the process is complete which can take a couple of months depending on the number of tests and staffing of the laboratory.

Due to the limitations placed on the laboratory by accreditation standards and the ongoing project to replace all chemistry and immunochemistry analyzers as soon as possible, it would place an undue burden on the laboratory at this time to award a contract for the chemistry analyzers to anyone but Beckman Coulter in the short-term.

FAR 8.405-6(a)(1)(C): In the interest of economy and efficiency, the new work is a logical follow-on to an original Federal Supply Schedule order provided that the original order was placed in accordance with the applicable Federal Supply Schedule ordering procedures. The original order must not have been previously issued under sole source or limited source procedures.

Effective Date: 02/01/2022 Page 3 of 4

FAR 8.405-6(b): Items peculiar to one manufacturer:

A patent, copyright or proprietary data limits competition. The proprietary data is:

These are “direct replacements” parts/components for existing equipment.

The material/service must be compatible in all aspects (form, fit and function) with existing systems presently installed/performing.

(5) Describe Why You Believe the Order Represents the Best Value consistent with FAR

8.404(d) to aid the contracting officer in making this best value determination:

Per the authority cited in number 4 above, pricing awarded under this contract will be consistent with and/or better than current Federal Supply Schedule (FSS) pricing. By placing a short-term order with the current manufacturer, there are significant cost savings to the Government by procuring on a sole source basis to avoid added administrative work associated with using a different chemistry provider.

(6) Describe the Market Research Conducted among schedule holders and the results or a statement of the reason market research was not conducted.

Market research was not conducted. The new long term VISN Chemistry IA CPRR IDIQ was recently awarded, and this delivery order is to cover the transition from the incumbent to the successor contractor.

(7) Any Other Facts Supporting the Justification:

6-month bridge contract with current vendor, Beckman Coulter, would be most advantageous to government and least disruptive to the continuity of patient care while waiting for the delivery of analyzer(s) and automation track, including all requirements related to installation, validation, and calibration services is completed.

In the interim the supplies and services must continue for the veterans who obtain care from the

VASNHCS. The supplies and services are critical for VASNHCS, there is no other viable alternative available to avoid disruption in patient care.

(8) A Statement of the Actions, if any, the agency may take to remove or overcome any barriers that led to the restricted consideration before any subsequent acquisition for the supplies or services is made:

As previously described, the long-term replacement contract was recently awarded, and this delivery order allows for the transition timeline between the incumbent and the successor contractor.

Effective Date: 02/01/2022 Page 4 of 4

(9) Requirements Certification: I certify that the requirement outlined in this justification is a

Bona Fide Need of the Department of Veterans Affairs and that the supporting data under my cognizance, which are included in the justification, are accurate and complete to the best of my knowledge. I understand that processing of this limited sources justification restricts consideration of Federal Supply Schedule contractors to fewer than the number required by FAR Subpart 8.4.

SIGNATURE DATE

Derrick Witherspoon Core Lab Supervisor P&LMS

VA Southern Nevada HCS

(10) Approvals in accordance with the VHAPM Part 806.3 OFOC SOP:

a. Contracting Officer’s Certification (required): I certify that the foregoing justification is accurate and complete to the best of my knowledge and belief.

CONTRACTING OFFICER SIGNATURE DATE

Mandy Thompson Network Contracting Office 21 (NCO 21)

b. One Level Above the Contracting Officer (Required over the SAT but not exceeding

$750K): I certify the justification meets requirements for other than full and open competition.

SIGNATURE DATE

Maxwell W. Derck

Acting Division II Chief

Network Contracting Office 21 (NCO 21) https://dvagov.sharepoint.com/sites/VHAProcurement/VHAPM2/VHAPM_Part_806.3.aspx https://dvagov.sharepoint.com/sites/VHAProcurement/VHAPM2/VHAPM_Part_806.3.aspx