Statement of Work Summary: FBI Quantico Job Order Contract Facilities & Logistics Services
This Statement of Work is issued by the Federal Bureau of Investigation (FBI) Facilities & Logistics Services Division, Real Property Management Section for a Job Order Contract (JOC) to support construction, alteration, repair, and maintenance services at the FBI Complex in Quantico, Virginia. The contract encompasses construction, renovation, repair, alteration, and maintenance of industrial, commercial, office, and utility projects, including project management, planning, estimating, labor, transportation, materials, equipment, tools, supervision, and minimal design work. The JOC is structured as a single-award Indefinite Quantity, Indefinite Delivery (IDIQ) contract with a one-year base period and four optional one-year renewal periods. Task orders will be issued as needed throughout the contract term, with pricing based on RS Means Complete Online Full Library unit pricing adjusted by contractor-supplied coefficients for standard work hours (6:00 a.m. to 6:00 p.m. EST, Monday through Friday, excluding federal holidays) and nonstandard work hours. The Government will conduct joint scope meetings with the contractor to define work requirements, provide task order requests for proposals (TORP), and issue task orders upon acceptance of complete and accurate proposals. No specific response dates or bidder conference information is provided in this SOW; however, contractors are expected to respond to standard task order proposals within 48 hours and to emergency task orders within 2 hours.
Pricing is determined through a predetermined formula applying RS Means unit prices multiplied by quantities and contractor adjustment factors, with non-priced items (NPP) supported by competitive quotes and limited overhead and profit markups. The contract is designated as a total small business set-aside in NAICS code 236220 (Commercial and Institutional Building Construction). Key contractor requirements include maintaining a Program Manager with 15 years of construction experience and PMI certification, a Project Manager with 10 years of JOC experience capable of managing projects valued $5,000 to $1.5 million, a Superintendent with equivalent qualifications, a Level 1 Site Safety Health Officer meeting OSHA 30-hour requirements, and a Quality Control Manager with daily site inspection responsibilities. All contractor personnel must be U.S.-born citizens or possess valid work authorization, obtain Top-Secret security clearances for on-site personnel, complete limited background investigations, and comply with Marine Corps Base Quantico and FBI security protocols including badging and access requirements. The contractor must provide quality control, health and safety, environmental, and security programs at no additional cost to the Government as part of the coefficient; maintain comprehensive documentation including as-built drawings and daily reports; comply with applicable federal, state, and local codes including OSHA, EM 385-1-1, and FBI Quantico Campus Design Standards; and adhere to Davis-Bacon wage determinations for Prince William County, Virginia. All work is subject to a one-year warranty against defects in materials and workmanship following final Government acceptance.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FEDERAL BUREAU OF INVESTIGATION
Statement of Work for
Quantico Job Order Contract
Facilities & Logistics Services Division Real Property Management Section
November 23, 2026
FBI Complex at Quantico Quantico, Virginia
C-2
C.1 INTRODUCTION
The FBI requires continued Job Order Contract (JOC) services to support the FBI Complex at Quantico.
The FBI necessitates JOC services to support construction, alteration, and repair of industrial, commercial, office, and utility projects at various FBI facilities at Quantico, Virginia. The FBI needs project management, planning, estimating, labor, transportation, materials, equipment, tools, supervision, minimal drawings, and other associated tasks necessary to fulfill the construction requirements of each JOC Task Order (TO). The JOC is a single-award Indefinite Quantity, Indefinite Delivery (IDIQ) contract vehicle composed of one base and four option year periods. During any given period, the FBI may issue any number of task orders up to the ceiling of the IDIQ for construction requirements within the scope of this Statement of Work (SOW).
RS Means will be used as the basis for price for JOC task orders. A cost coefficient will be applied to the unit price of Pre-Priced Items (PPI) defined in RS Means. If negotiation or price clarification is required for a task order, the Government will focus on whether the contractor used the right task, quantities, assumptions, labor, Non Pre-Priced (NPP) support, and schedule to make sure the overall task-order price is complete and reasonable.
Pre-Priced Item (PPI) pricing for each PPI in the Task Order is determined by applying the RS Means Complete Online Full Library unit pricing, including the RS Means Location Factor adjustment, and the Contractor’s applicable PPI coefficient and multipliers, if applicable. The Government may review the proposed tasks, quantities, assumptions, labor, NPP support, schedule, and other elements necessary to determine whether the overall Task Order price is complete and reasonable.
Non-Pre-Priced Item (NPP) means a necessary, but incidental, part of a job or project ordered or to be ordered under a JOC that is not susceptible to unit pricing used in the Complete Online Full Library Unit Price Book incorporated in the JOC. Non-pre-priced items are defined as construction materials, services, and work not listed by the RS Means Complete Online Full Library UPB. Non-Pre-Priced Items of work are expected to be infrequent and included in projects by exception . The Government will not consider an item as non-pre-priced if the materials or services are listed in the RS Means Complete Online Full Library UPB or the non-pre-priced item has been established as a pre-priced item by prior modification. It is the Government’s preference that, whenever practicable, PPI be identified as the closest RS Means match to any NPP item included in a proposal to serve as a point of reference, with the Contractor explaining any assumptions, availabilities, product modifications, or project constraints that necessitate the use of NPP and the basis for the price charged to the Government.
Bidders will bid two adjustment factors to be applied to the unit prices: one adjustment factor for performing work during standard working hours (see Section C.4.1) and a second adjustment factor for performing work during nonstandard working hours (see Section C.4.2). These adjustment factors apply to every Pre-priced task in the RS Means Complete Online Full Library. Bidders will also bid a Non-Pre-priced adjustment factor to be applied to Non-Pre-priced work.
This contract provides for a 1-year Base Period and up to four (1-year) Option Periods. The Period of Performance of each Task Order is independent of the Period of Performance of the IDIQ. All terms and conditions of the IDIQ contract apply to each TO, unless specifically waived or superseded
As projects are assigned, the Contractor will attend Joint Scope Meetings with the Government to review and discuss the proposed work. The Government will prepare a Task Order SOW and issue a Task Order Request for Proposal (TORP) to the Contractor. The Contractor will then prepare a TO proposal including a price proposal, construction schedule, list of proposed subcontractors, and other requested documentation.
The value of the price proposal shall be determined by calculating the total price for each Pre-priced task using the following formula:
Pre-priced Task Price = RSMeans Unit Price × Quantity × Applicable Adjustment Factor
C-3
If the TO proposal is found to be complete and accurate, the Government may issue a TO to the Contractor without further discussion or negotiation However, the Government may request clarification, revision, or negotiation if necessary before TO award.
A TO will reference the SOW and set forth the TO completion time and price. Depending on the size and scope of the TO, progress payments may be available and will be identified in the TO. The final invoice must include the required Substantial Completion documentation before final payment.
C.2 CONTRACTOR COEFFICIENT
For the life of the contract, in each TO, the Contractor shall provide certain labor, equipment, materials, and rentals/fees that are considered field overhead and therefore part of the Contractor’s coefficient.
These requirements and responsibilities are identified throughout this Statement of Work (SOW). Note that where notification of a coefficient requirement/responsibility is stated, all associated subparagraphs are also applicable as part of the coefficient. Other coefficient statements within these subparagraphs refer to additional requirement/responsibilities. A consolidated, but not exhaustive, list of applicable coefficient requirements/responsibilities is provided in Technical Exhibit (TE)-1, “Applicable Contractor Coefficient Requirements and Responsibilities.”
Costs included in the Contractor's coefficient shall not be separately charged, directly or indirectly, through pre-priced line items, non-pre-priced work, supplemental proposals, or other task order pricing mechanisms, except where expressly authorized by this contract.
C.3 APPLICABLE CODES, REGULATIONS, AND STANDARDS
If there is a conflict between applicable codes, regulations, standards, or these contract specifications, the most stringent requirement shall govern when the conflict can be resolved on that basis. If the conflict cannot be resolved by applying the most stringent requirement, the Contractor shall notify the Contracting Officer before proceeding with the affected work. The Government will provide direction, in coordination with the applicable Authority Having Jurisdiction (AHJ), as necessary.
The most current versions of the FBI at Quantico Complex Design Guide, Quantico Construction Standards Volumes 1 and 2, and the Unified Facilities Criteria 3-580 shall be used in the preparation and execution of all work under this contract.
Publications listed within this document form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
C.3.1 CODE OF FEDERAL REGULATIONS (CFR)
C.3.1.1 OCCUPATIONAL, SAFETY AND HEALTH ADMINISTRATION (OSHA )
Both the Occupation, Safety and Health Administration (OSHA) General Industry Safety and Health Standards (29 Code of Federal Regulations [CFR] 1910), Publication V2206, OSHA Construction 3 Industry Standards (29 CFR 1926) and EM 385-1-1 are applicable. One source of these regulations is OSHA Publication 2207, which includes a combination of both Parts 1910 and 1926 as they relate to construction safety and health. They are for sale by the Superintendent of Documents, US Government Publishing Office, Washington, DC 20402.
C.3.1.2 US ARMY CORPS OF ENGINEERS (USACE) ENGINEERING MANUAL (EM) 385 1-1
EM 385-1-1 is the U.S. Army Corps of Engineers (USACE) Safety and Occupational Health Requirements Manual. The Contractor shall comply with the applicable requirements of the edition identified in this contract.
https://www.osha.gov/ https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf https://www.gpo.gov/ https://www.gpo.gov/ https://www.osha.gov/ https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf https://www.osha.gov/ https://www.osha.gov/ https://www.osha.gov/laws-regs/regulations/standardnumber/1910 https://www.osha.gov/general-industry https://www.osha.gov/general-industry https://www.osha.gov/
C-4
C.3.1.3 FED-STD-313F SAFETY DATA SHEETS (SDS)
The Contractor shall prepare and submit a copy of all required Safety Data Sheets (SDS) to the FBI for each TO issued against this contract.
Use of Asbestos Containing Material or any Class 1 ozone depleting chemical compounds are prohibited, Department of the Army (DA) Circular 40-83-4.
Hazardous Materials refer to hazardous and toxic materials/substances included in Subparts H and Z of 29 CFR 1910 and to others as additionally defined in FED-STD-313F and EM 385 1-1 Chapter 6 (Hazardous or Toxic Agents and Environments).
The most common hazardous materials include asbestos, lead-based paint, polychlorinated biphenyls (PCB), explosives, and radioactive material, among others. The most likely products to contain asbestos are sprayed-on fireproofing, insulation, boiler lagging, pipe coverings, vinyl floor tile and/or its associated materials. The Contractor shall adhere to regulations and standards IAW the USEPA Clean Air Act (CAA), USEPA Toxic Substances Control Act, USEPA National Emission Standards for Hazardous Air Pollutants (NESHAP), and USEPA 40 CFR 763 Subpart I.
C.4 WORK TYPES
C.4.1 STANDARD WORK
Standard work hours are defined as the period from 6:00 a.m. to 6:00 p.m. EST, Monday through Friday, excluding Federal holidays. All work shall be performed during this period unless otherwise authorized by the Contracting Officer (CO) and approved at least 48 hours in advance unless otherwise specified in the TO. Access to work sites may be restricted to this period due to mission requirements.
C.4.2 NONSTANDARD WORK
Nonstandard work is defined as the period outside of Standard Work, Section C.4.1. The nonstandard coefficient may be used to account for loss of productivity while working in secure areas, for TOs to be accomplished on weekends and during nonstandard hours only, and to accelerate a TO to include multiple shifts both during standard hours and nonstandard hours. The use of the nonstandard coefficient shall be based on the Government's identification of work requiring nonstandard hours and shall not be at the Contractor's discretion. Only work specified by the CO, prior to issuance of a TO, or subsequent modification that identifies work requiring nonstandard work hours, shall be multiplied by the nonstandard coefficient. The Contractor shall not unreasonably delay or refuse accelerated performance.
C.4.3 MINIMAL DESIGN
The Government will require a conventional design developed up to 35% stage for renovation and repair projects (project dependent). If the design requires the services of a registered architect or engineer, it is outside the parameters of minimum design and outside the scope of this JOC. Stamped drawings by a registered Architect or Engineer shall not be ordered as Non-Pre-priced tasks and will be procured by the Government under a separate contract vehicle. The Government shall only provide basic concept design, sketches, and/or drawing(s) information for a specific work requirement. The Contractor must demonstrate design capabilities of providing quality, cost effective minimal design for multiple TOs simultaneously, which shall comply with Government requirements and all applicable building codes and governing authorities. The Contractor will be provided with the Government’s initial concept design and SOW for each TO. The Contractor shall then be responsible for further development of the Government’s concept design to a point where the Contractor’s designs/drawings clearly indicate the proposed method of accomplishing the work, as well as the description, size, and location of all proposed elements of the work. The Contractor’s design must fully comply with the Government’s concept design requirements as https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf https://www.osha.gov/laws-regs/regulations/standardnumber/1910 https://www.osha.gov/laws-regs/regulations/standardnumber/1910 https://quicksearch.dla.mil/qsDocDetails.aspx?ident_number=53769
C-5 well as all governing codes, Unified Facilities Guide Specification, and the FBI Quantico Campus Design Guide and FBI Quantico Construction Standards Guide, which will be provided at award in a portable document format (PDF). The Contractor is expected to use recognized industry standard practices in determining proposed design materials and methods unless the Government specifies otherwise.
The Contractor shall be responsible for verifying existing field conditions, dimensions, measurements, site constraints, and constructability of the proposed work prior to submitting a TO proposal. The Contractor shall exercise due diligence in identifying potential conflicts, omissions, discrepancies, or conditions that may affect the design, cost, schedule, or successful execution of the work. Any discrepancies between Government-provided information and actual field conditions, or any identified constructability concerns, shall be promptly brought to the Government's attention in writing for clarification and resolution before proceeding with the affected work. The Contractor shall not proceed with work involving unresolved discrepancies without direction from the Contracting Officer (CO).
Failure to perform reasonable field verification or timely notify the Government of identifiable discrepancies shall not, by itself, constitute grounds for additional compensation or schedule extensions, subject to the applicable contract clauses.
C.5 CONTRACTOR PERSONNEL/PROGRAMS/EQUIPMENT MATERIALS AND SERVICES
The Contractor shall not employ persons for work on this contract if such employee is identified to the Contractor by the CO as a potential threat to health, safety, security, general well-being, or operational missions of the installation and its population. Where reading, understanding, and discussing safety and environmental warnings are an integral part of a contract employee's duties, that employee will be able to understand, read, write, and speak English (speaking skills are not required where a Contractor employee is hearing impaired). FBI property requires all workers to be US-born Citizens. Work in support of the FBI that is not performed strictly on FBI property must comply with Quantico’s personnel requirements and any applicable trust and security requirements imposed by the FBI.
C.5.1 PERSONNEL
C.5.1.1 PROGRAM MANAGER (PGM)
The Program Manager shall have a minimum of 15 years of construction related services and either superintendence or senior construction management experience. They must possess a program management certification from an accredited source with a program as rigorous as Program Management Institute (PMI). The PMI programs require at least 2,500 contract hours prior to receiving the Program Manager certifications plus extensive courses of study. The Program Manager for the JOC shall have positive past performance overseeing multiple projects of varying complexity with successful completion of those projects on time and within budget. The Program Manager shall have the ability to commit the Contractor, respond to all the various types of service support for the JOC and not delay proposal responses to the Government. The Program Manager shall coordinate all Contractor personnel and tasks and facilitate any required conflict resolution measures.
C.5.1.2 Project Manager (PM)
The Project Manager (PM) shall have a minimum of 10 years’ experience in JOC-type tasks and be able to handle multiple job orders simultaneously while maintaining cost, schedule, and risk levels in accordance with industry and Government standards. The PM shall be a qualified individual with relevant project management training to manage projects in the value range of $5,000 to $1.5 million and shall be capable of standing in for the Program Manager (PgM) for short periods not to exceed 2 weeks.
The PM shall respond to a standard TO within 48 hours and within 2 hours for an Emergency TO.
The on-site Project Manager shall have and maintain a Top-Secret Clearance.
https://www.pmi.org/ https://www.pmi.org/ https://www.wbdg.org/dod/ufgs
C-6
C.5.1.3 SUPERINTENDENT
The Superintendent shall have a minimum of 10 years’ experience in JOC type tasks, be able to handle multiple job orders simultaneously, maintain cost, schedule, and risk levels IAW industry and Governmental standards. The Superintendent shall be experienced in multi-skill trade integration for project completion and communicate project status to the PM and the Government. The Superintendent shall have some project management training with completion certifications to handle projects in the value of $5,000 to $1.5M and be ready to stand in for the PM for short periods of time (not to exceed 2 weeks).
The on-site Superintendent shall have and maintain a Top-Secret Clearance.
C.5.1.4 SAFETY OFFICER (SO)/LEVEL 1 SITE SAFETY HEALTH OFFICER (SSHO)
As outlined in the USACE Safety and Health Requirements Manual (EM 385-1-1) the Level 1 Site Safety Health Officer (SSHO) shall:
Be a full-time responsibility.
The SSHO shall be present at the project site, located so they have full mobility and reasonable access to all major work operations during the shift.
Report to a senior corporate safety official, senior PM, or corporate official.
Per EM 385-1-1, all Level 1 SSHOs must receive OSHA 30-hour general industry or construction safety training. Training may be web-based if permitted by OSHA. In lieu of formal OSHA-30 training, SOH training covering the subjects of the OSHA 30-hour course and this Statement of Work (SOW) may be accepted by the CO in coordination with the local SSHO having jurisdiction over the work. The local SSHO will evaluate the proposed equivalent training for applicability to the contract SOW being performed. In addition, the SSHO is required to have proof of employment for one of the following:
Five years of cumulative construction industry safety experience in the last 10 years in supervising/managing or implementing a Safety, Occupational, and Health (SOH) program on projects similar in industry type, size, and complexity as the project described in the contract scope of work.
If the SSHO has a safety-related degree, third-party, nationally accredited (e.g., American National Standards Institute [ANSI], National Commission for Certifying Agencies [NCCA], or Council on Engineering and Scientific Specialty Boards [CESB]) SOH-related certification or designation requiring a minimum of 3 years of experience to obtain, only 3 years of experience are needed.
The SSHO shall maintain competency through 24 hours of documented formal, or online safety and health related coursework within the past 5 years. The initial SOH training (OSHA 30-hour) does not meet the 24-hour competency training requirement. Hours spent as an instructor for SOH related training (e.g., teaching an OSHA 10- or 30-hour class, or a 4-hour fall protection end user training) can be considered for hours spent training, however each course can only be used for hours once. For example, instructing a 4-hour fall protection end user course training three times a year only counts for 4 hours of training.
For projects with multiple shifts, an Alternate SSHO as identified in the Activity Hazard Analysis (AHA) will be assigned to ensure SSHO coverage for the project at all times work activities are being conducted.
Note that the Alternate SSHO must meet the same requirements and assume the responsibilities of the project SSHO. Responsibilities of the SSHO are located in EM 385-1-1 Chapter 2-4.b. The Alternate SSHO is referenced in EM 385-1-1 Chapter 2-4.9 Note that if additional SSHO(s) are used on a project site or required due to contract requirements, multiple shifts, etc. the alternate SSHO(s) must abide by the same roles and responsibilities and assist the primary SSHO in the performance of the duties outlined above. Definitions for Alternate SSHO and SSHO can be found in EM 385-1-1 Chapter 2.
https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf https://www.osha.gov/training/outreach https://www.osha.gov/training/outreach https://www.cesb.org/ https://www.cesb.org/ https://assess.com/ncca-accreditation/ https://www.ansi.org/ https://www.ansi.org/ https://www.osha.gov/training/outreach https://www.osha.gov/training/outreach https://www.osha.gov/ https://www.osha.gov/training/outreach https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf
C-7
Per, EM 385-1-1, if the Level 1 SSHO must be off-site for a period longer than 24 hours/one day, an additional/alternate Level 1 SSHO must be at the site of work to fulfill the same roles and responsibilities when work is performed.
The Contractor’s project management team, with the assistance of the SSHO, is responsible for managing, communicating, implementing, and enforcing compliance with the Contractor's Accident Prevention Program (APP) and other accepted safety and health submittals.
Per EM 385-1-1 Chapter 2-4.b(3), the SSHO shall conduct daily inspections according to EM 385-1-1 Chapter 2-5.b, “Contractor SOH Inspections,” and maintain an SOH deficiency tracking system according to EM 385-1-1 Chapter 2-8.f(3), “Deficiency Log and Hazard Tracking System.”
The SSHO is responsible for the daily inspection of the jobsite to identify key issues that may affect the safety of the Contractors and Government employees. These duties include, but are not limited to:
Attending all pre-construction conferences, tail-gate meetings, and pre-work meetings, to include preparatory meetings and periodic in-progress meetings.
Conducting ongoing evaluations of the APP throughout the life of the project to ensure it is current and site-specific.
Maintaining applicable safety reference material at the site of work including SDS, APP, manufacturer instructions, etc.
Ensuring all project personnel comply with SOH requirements.
Providing and keeping a record of site safety orientation and indoctrination training for all project personnel, including subcontractors.
Reviewing daily logs documenting compliance with OSHA and other governing laws and regulations.
Reporting and investigating all accidents and near misses.
C.5.1.5 QUALITY CONTROL MANAGER (QCM)
The Contractor shall provide a Quality Control Manager (QCM) to provide quality control during active Task Orders (TOs). The QCM shall maintain frequent inspections and be present at the project site as required by the size, complexity, and risk of the work. The TO SOW shall identify any specific inspection frequency required. If the TO SOW does not specify a frequency, the QCM shall perform at least one site visit each workday while work is active. The QCM shall ensure compliance with safety requirements and verify that work and materials in place or stored on site conform to the approved construction drawings, shop drawings, and material submittals. The QCM shall submit daily field notes recording activities at each project site, prepare and coordinate material submittal sheets and shop drawing submittals, and prepare quality control reports.
C.5.1.6 ESTIMATOR
The Estimator shall have a minimum of 10 years’ experience with 4 years of TO estimating or TO type contracting experience. It is a requirement that the Estimator must sign off on all proposals prior to review by the Government.
C.5.1.7 SUBCONTRACTORS
The PM shall have the ability to manage and control multiple subcontractors at multiple work sites. The Contractor shall schedule all jobs and adequately staff all construction sites to ensure all projects are completed as efficiently as possible and that no site is left idle for more than 7 calendar days. The PM shall provide to the CO a completed Statement and Acknowledgement Form (SF 1413) within 7 calendar days after any subcontractor award regardless of tier (IAW FAR 52.222-11). Subcontractors shall be https://www.acquisition.gov/far/52.222-11 https://www.gsa.gov/reference/forms/statement-and-acknowledgment https://www.osha.gov/ https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf
C-8 selected from within a 30-mile radius of FBI at Quantico. If the required subcontracting trade/specialty cannot be obtained within the 30-mile radius the Contractor shall locate and submit a subcontractor to the Government for approval.
The PM shall be responsible for the oversight, coordination, and performance of all subcontractors, regardless of tier, and shall proactively monitor subcontractor progress, staffing, scheduling, quality, safety, security, and compliance with applicable contract requirements. The PM shall promptly address performance deficiencies, coordination conflicts, and other subcontractor issues to prevent delays, rework, or disruption to Government operations. The Contractor remains fully responsible for the performance, actions, and omissions of its subcontractors and shall not transfer that responsibility to the Government. Subcontractor performance issues, staffing shortages, or coordination failures shall not relieve the Contractor of its contractual obligations.
C.5.2 PROFESSIONAL, TECHNICIAN, AND CRAFTSMAN QUALIFICATIONS
The PM shall ensure all employees, including subcontractor employees, have valid licensing/certifications to accomplish applicable contract requirements before starting work under this Contract. Additionally, the PM shall ensure all employees are compliant with all Federal, State, and Local regulations and environmental requirements or laws, are qualified, competent, and capable of handling all assigned tasks.
All work performed under this contract shall be completed by a professionally licensed contractor specializing in the field of work to be performed. The following qualifications are not all inclusive.
C.5.2.1 TECHNICAL COMPETENCE
All PMs, QCMs and Project Superintendents shall have the minimum years of experience performing in that function as stated above, and all nonprofessional and/or technician project managers shall have relevant experience in the discipline they are designing.
C.6 PROGRAMS
C.6.1 QUALITY CONTROL PROGRAM
All labor, equipment, materials, and rentals/fees required to provide the Quality Control Program shall be at no additional cost to the Government and are considered field overhead, therefore part of the Contractor’s coefficient.
C.6.1.1 QUALITY CONTROL PLAN (QCP)
In compliance with the FAR 52.246-4 the Contractor shall provide a Quality Control Plan (QCP) with their proposal that contains, at a minimum, the items listed in Section C.6.2. The QCP shall become a compliance document for all work accomplished under all TOs. Any subsequent modifications shall be submitted to the CO for acceptance before implementation.
C.6.2 MINIMUM REQUIREMENTS
C.6.2.1 INSPECTION SYSTEM
The Contractor shall provide a description of the inspection system that covers all tasks and services required to perform work on each TO. The description shall include specifics as to the areas to be inspected on a scheduled and unscheduled basis, frequency of inspections, submission of a quality control inspection schedule, and the title and organizational placement of the inspectors. Additionally, control procedures for any Government provided keys or lock combinations shall be included.
https://www.acquisition.gov/far/52.246-4
C-9
C.6.2.2 IDENTIFICATION AND PREVENTION METHODS
The Contractor shall provide a description of the methods to be used for identifying discrepancies, eliminating negative trends, and preventing defects in the quality of work performed.
C.6.2.3 DOCUMENTATION
The Contractor shall provide a description of the records kept to document inspections and corrective, or preventive actions taken. The records of inspections shall be maintained and made available to the Government throughout the contract performance period and for the period after contract completion until final settlement of any claims under this contract. At a minimum, daily Superintendent production reports and all QCM inspections must be performed and documented within the system of records. Copies of inspection reports and daily reports for all active projects shall be supplied to the CO and COR on a weekly basis.
C.6.2.4 DRAWINGS
The Contractor shall maintain “As-Built” record drawings during the progress of the job to serve as a record of all changes and corrections from the original layout on the drawings. Locations of all sub-surface utility lines shall be detailed on the record drawings. To ensure all buried or hidden items may be determined in the future, the drawings shall show their location using offset dimensions to two permanent fixtures or landmarks. This marking method shall be used to locate the end of each run and all changes in direction. Valves, splice boxes, and similar appurtenances shall be located by dimensioning along the utility run from a known reference point. The average depth of the item shall be recorded. Final “As- Built” record drawings shall be stored in the system of record and submitted to the CO and COR upon project completion in both hard copy and on CD. Failure to maintain record drawings may result in retention from progress payments, and notation on the performance evaluation of record. Shop drawings shall be submitted for projects (particularly fire alarms/sprinkler plans) with a “red marked” version to be submitted to the COR for final approval.
C.6.2.5 MATERIALS
The Contractor shall provide material lists to include trade names, brand names, model number, and ratings (if appropriate) for all materials necessary for a complete job. Material submittals shall be provided for all proposed materials in the form of cut sheets. No materials shall be installed without prior written approval of the CO or the COR. Any materials installed without prior approval shall be removed and replaced at no cost to the Government if deemed unacceptable. All Operations and Maintenance (O&M) manuals and product warranty information shall be delivered to the COR electronically at the completion of each TO.
C.6.2.6 AUTHORITY HAVING JURISDICTION (AHJ)
The Contractor shall follow the “Authority Having Jurisdiction” (AHJ) for fire alarm and sprinkler requirements when modifying existing spaces within a building. Project designs shall be submitted for AHJ review at least 15 business days before TO approval.
C.6.2.7 PROGRAM OF REQUIREMENTS (POR)
Projects occurring in existing FBI facilities and/or on the FBI Campus. The Contractor shall obtain the Program of Requirements (POR), if applicable, from the Owner and ensure design and construction compliance with the POR. The Contractor shall ensure design and construction within existing FBI facilities are compliant with the most recent published version of the FBI at Quantico Campus Design Guide.
C-10
C.6.2.8 DESIGNS
The Contractor shall have at least one hardcopy full set of 100% or IFC designs on the project site while work is being performed. The size shall be no less than Arch D (24″ x 36″).
C.6.2.9 CONCEPTUAL DESIGN
Conceptual design effort is defined as the capability to provide shop drawings and preliminary specifications of the type routinely developed in commercial practice and/or as provided and supplemented by industry. This includes pre-engineered building manufacturers, major heating ventilating and air conditioning (HVAC) equipment suppliers, fire suppression system suppliers, etc.
C.6.3 HEALTH AND SAFETY PROGRAMS
All labor, equipment, materials, and rentals/fees required to provide the Health and Safety Programs shall be at no additional cost to the Government and are considered field overhead, therefore part of the Contractor’s coefficient.
C.6.3.1 NON-COMPLIANCE ACTIONS
The CO will notify the Contractor of any non-compliance of health or safety requirements, and the required action to be taken (notification delivered to the Contractor representative at the worksite shall be deemed sufficient). The Contractor shall take immediate corrective action to rectify all violations. If the Contractor fails, or refuses to promptly comply, the CO may issue a Stop Work Order ceasing all, or part of the work for a stop work order issued for non-compliance actions, until satisfactory corrective action has been taken. The Contractor shall not claim costs, damages, or time extensions due to Stop Work Orders based on non-compliance with health or safety requirements.
C.6.3.2 US ARMY CORPS OF ENGINEERS MANUAL, EM 385-1-1 , SAFETY AND HEALTH
REQUIREMENTS MANUAL
The Contractor shall comply with all pertinent provisions of the most current version of the USACE Manual, EM 385-1-1, Safety and Health Requirements Manual. The Contractor (including subcontractors) is responsible for compliance with the provisions of this manual.
C.6.3.3 ACCIDENT PREVENTION PLAN (APP)
Per EM 385-1-1, an Accident Prevention Plan (APP) is “a written site-specific SOH plan that documents project, contract, and job-specific potential hazards in the workplace, and the company policies, controls, and work practices that will be used to minimize those hazards.” The APP must be developed by a CP (Competent Person(s)) and reviewed and approved by the prime contractor and corporate safety official.
Upon contractor approval, the plan must be submitted to the CO or COR for review and acceptance prior to the performance of any work. No contract work can begin without a CO or COR accepted APP. APPs must include the following:
(1) The APP must be written in English and articulate the specific work, work process, equipment, and materials to be used, hazards pertaining to the contract work, and the control measures that will be implemented. Follow the mandatory ENG Form 6293 (Accident Prevention Plan Worksheet).
(2) It is understood that at the time of APP submission, there may be unknown portions of the work.
Include all known information in the APP prior to the start of work. Project-specific information that is yet to be known (for example, subcontractors to be used, type of fall protection to be used at a certain point in time, specific cranes or other load handling equipment (LHE) to be brought at the site of work, must be added and submitted prior to each preparatory phase/meeting, along with the appropriate AHAs.
(See EM 385-1-1 referenced Engineer Forms.)
https://www.nae.usace.army.mil/Portals/74/docs/Contracting/2024/APP-24Q0097.pdf?ver=VRDdnNX4Y_s7CrKoxKGLXA%3D%3D https://www.publications.usace.army.mil/USACE-Publications/Engineer-Forms/ https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf
C-11
(3) The SSHO must conduct on-going evaluations and updates of the APP throughout the life of the project to ensure it is up to date and site specific. Changes, revisions, and updates to the APP must be reviewed and approved by the contractor and submitted to the CO or COR for acceptance.
Include measures to be taken to control potential hazards associated with materials, services, or equipment provided by vendors, contractors, subcontractors, etc.
Address any unusual or unique aspects or hazards of the project or activity.
(4) The completed APP (reviewed and approved by the contractor and accepted by the CO or COR) must always be available on site of the work and be accessible to all employees. At minimum, a copy of the most current APP EM 385-1-1 must be posted on the SOH bulletin board, or a notice posted on the board stating the location of the plan.
C.6.3.4 EMERGENCY PLANS.
Emergency plans ensure employee safety in case of fire, inclement weather, or other emergencies at the project location must be prepared, in writing, and reviewed with all affected employees. Emergency plans must be tested to ensure their effectiveness.
(1) Plans must include evacuation procedures, routes, and rally points; the identification of critical plant operations and procedures for employees who operate critical plant operations (for example, gas line shut down, electrical systems, etc.); employee accountability following evacuation; rescue and medical duties; means of reporting emergencies; and points of contact.
(2) Onsite emergency planning must be coordinated with off-site emergency support. Documentation of specific onsite emergency services is also required and can include written agreements, memoranda for record, telephone conversation logs, etc. The contractor must offer an onsite orientation of the project and associated hazards to the emergency services provider.
(3) Emergency alert systems must be developed, tested, and used to alert all persons likely to be affected by existing or imminent disasters and to alert and summon emergency responders.
(4) Emergency telephone numbers and reporting instructions for ambulance, physician, hospital, fire, and police must be clearly communicated to all employees and posted at the site of work.
(5) Employees working alone in remote locations must be provided with an effective means of emergency communications (for example, cellular phone, two-way radios, land-line telephones, remote employee tracking devices/GPS, or other).
The selected communications must be readily available (easily within the immediate reach) of the employee and be tested prior to the start of work to verify effective operation at the site of work.
Develop an employee check-in/check-out communication process to ensure employee safety.
C-12
C.6.3.5 ACTIVITY HAZARD ANALYSIS (AHA)
Risk management is a business process that requires planning to ensure risk is reduced to an acceptable level prior to performing work activities. Risk management provides consistent and systematic identification and communication of risks, consequences, and potential actions to mitigate those risks.
Unidentified and unmanaged hazards and their associated risks impede successful missions, undermine readiness, decrease morale, and deplete resources. A properly documented risk assessment serves as evidence that leadership decision-making was based on sound judgment and reasonable principles.
Leadership and management at every level must exercise risk management. Risk management must be integrated into all phases of work to ensure risk decisions are made at the appropriate level, no unnecessary risk is taken, and the process is applied consciously. Effective risk management requires the following steps.
(1) Identify all potential hazards associated with the task prior to work.
(2) Assess identified hazards to determine probability and potential severity of occurrence (that is, risk).
(3) Develop adequate controls to mitigate hazard and reduce probability and risk.
(4) Implement controls to ensure all workers know, understand, and implement required controls to reduce risk.
(5) Continuously supervise and evaluate controls to ensure they are fully implemented, adequate, and effective at reducing risk. When needed, stop work to make corrections, modify, or add more controls, to ensure risk is managed. Note. There are many tools to aid with risk management implementation. One of these tools is the AHA.
Hazard Mitigation. Analysis of hazards and implementation of control measures is a vital element to the risk management process and reducing the residual risk to an acceptable level. Use the following hierarchy of controls, listed from most effective to decreasing effectiveness, to identify control measures to be implemented to eliminate or control hazards to an acceptable level: (2-6.b) EM 385-1-1 Note. There may be some situations or activities when more than one control measure or level of controls may need to be implemented to adequately control the hazard(s) to an acceptable level.
(1) Elimination/Substitution. Elimination/substitution involves removing the hazard from the work area. This may be accomplished by modifying structures, changing work processes, or substituting equipment so that persons are not exposed to the hazard(s).
(2) Engineering Controls. Engineering controls isolate or separate the hazard(s) from the general work area and personnel exposure. A common engineering control is physical barriers that prevent contact/exposure to the hazard(s) (for example, guardrails, machine guards, containment).
(3) Administrative Controls. Administrative controls involve work practices or procedures to govern/control the way persons work so that hazardous situations or conditions can be avoided. A common example of an administrative control is training, in that persons are trained in proper procedures so that they do not subject themselves or others to hazards.
(4) PPE. PPE is equipment worn or used by persons performing work with hazards to minimize the effects of exposure to the hazard(s). PPE includes hard hats, safety glasses, safety shoes, hearing protection, respirators, etc. (See chapter 5) Note. PPE should not be used as the only protection against a hazard. It should only be used after attempt has been made to implement higher level controls, or as a subsequent control to provide an additional layer of protection.
C-13
Risk Acceptance. Acceptance of risk is a serious matter; therefore, the appropriate level of leadership must accept the overall residual risk associated with a task before its commencement. Residual risk must be communicated and accepted by the proper authority before beginning the activity. Note: The proper authority may be different in each scenario and is based on the scope of work, hazards, and associated risk.
Activities that require an AHA must not begin until the AHA with the identified RAC has been reviewed, accepted, and signed by the proper approval authority.
Prime contractors must establish an internal process that outlines appropriate acceptance authority based on each level of residual risk. The risk acceptance process and acceptance authority personnel must be included in the APP. Note. USACE does not accept contractor risk. EM 385-1-1.
C.6.3.6 AHA MINIMUM REQUIREMENTS
AHAs must be prepared and documented for all field, laboratory, industrial, and maintenance activities performed. Before beginning each work activity, task, or DFOW, an initial AHA must be prepared to ensure minimum safety requirements are adequately addressed. In developing the AHA for a particular activity, the writer(s) (that is, CPs) should draw upon the expertise (for example, knowledge, skills, and experience) of the employees, supervisors, and SOH personnel. Additional AHA requirements may be found in other applicable chapters of this manual. See paragraph 6 of each chapter of this manual. Note.
JSAs, JHAs, or similar Risk Management assessment tools are considered equivalent to, and acceptable substitutes for AHAs as long as the data collected is the same as that required by the AHA.
AHAs must be provided to and reviewed by all involved employees prior to starting the task. Each employee must document their review with a signature on the AHA or an additional signature sheet.
Provide copies of signed AHAs to the CO or COR upon request.
AHAs must be readily available onsite (for example, office trailer) and accessible onsite by all employees for a period of 12 months, or for contracted work, the length of the contract. Workers/crews must have in their possession the current AHA that reflects current site conditions, personnel, equipment, control measures, etc. while the work is being performed.
AHAs must include the following:
Identify the activity/task/DFOW name, contractor name and contract number, project location, date of AHA development, name, and title of AHA preparer, and name and title of AHA acceptance authority.
Define the steps to be performed for the activity/task/DFOW and the work sequences (for example, site conditions, materials, personnel) needed. Job steps should be detailed so that the reader clearly understands how that job will be accomplished (for example, how the part will be installed or removed, anticipated voltages, quantities of chemicals utilized, equipment utilized to accomplish the task, heights being accessed or trenched).
List all potential hazards associated with each specific job step.
List all controls required to mitigate hazards according to paragraph 2-6.a. If one layer of control cannot fully eliminate or reduce hazards to an acceptable level, put additional controls in place to reduce risk to an acceptable level (that is, low or medium where possible).
Assign a RAC to each job step, to identify the residual risk that remains after controls have been applied.
Assign an overall RAC to the AHA. The overall RAC must not be lower than the highest job step RAC on the AHA.
C-14
C.6.3.6.1 Identify the equipment needed, training requirements needed of involved personnel, and any inspection requirements necessary for the activity/task/DFOW. Employer will designate, in writing (for example, certification, company letter) any required CP(s) and QP(s) by name for a particular activity (for example, excavation, confined space, scaffolding, fall protection, lead removal, asbestos abatement, other activities as specified by OSHA and this manual), and provide proof of competency/qualification.
C.6.3.6.2 Activities that require an AHA must not begin until the AHA with RAC has been reviewed and accepted by the proper acceptance authority. Note. Contractors must submit their accepted AHAs to the CO or COR for review and acceptance to ensure contractual requirements are met.
C.6.3.6.3 Updates to the AHA. The AHA must be modified as necessary to address changing site conditions, operations, or change of CPs or QPs.
If the initial RAC increases due to a change made to the AHA, resubmit the AHA for acceptance prior to the start of work.
Changes or updates to an AHA that do not increase the RAC are not required to be resubmitted for acceptance.
If the AHA needs to be revised, work should not resume until revision is complete and provided to and reviewed by all involved employees prior to starting the task.
If the work has been stopped due to safety non-compliance with this manual, APP, AHA, etc.
and the AHA needs to be revised, work should not resume until revision is complete and accepted and employees have re-reviewed. Note. For a non-mandatory formatted outline of an AHA, see ENG Form 6206.
C.6.3.7 RECORDS/NOTIFICATION
The Contractor shall maintain accurate records and notify the CO in the prescribed manner of, all exposure data, accidents resulting in death, traumatic injury, occupational disease, and damage to property, materials, supplies, and equipment incident to work performed under this contract.
C.6.4 ENVIRONMENTAL PROGRAMS
Prior to becoming what is now known as the Federal Bureau of Investigation (FBI) Quantico, the land generally east of the Lunga Reservoir was used for military training. Specifically, the FBI Academy land is located in the firing fans of what were multiple military artillery and mortar ranges between approximately 1943 and the mid-1950s. This means the land where the FBI Quantico is located is known or suspected to contain material(s) that potentially presents an explosive hazardous risk. Munitions and Explosives of Concern (MEC) and Material Potentially Presenting an Explosives Hazard (MPPEH) have been found within the described areas of the areas of the proposed work.
The Contractor is required during any excavation and/or ground disturbing activities in the UXO-33 area where the possibility of a UXO exists, or may be encountered, to provide a UXO qualified technician on-site during all groundbreaking activities to provide UXO support as required.
C.6.4.1 REQUIREMENTS FOR CONSTRUCTION STORMWATER MANAGEMENT
For any proposed construction/ alteration actions performed on FBI-Quantico properties, the following requirements must be met prior to project implementation.
The Contractor is to meet the standards for any land disturbance subject to Chesapeake Bay Preservation Act (CBPA) requirements. Contractor will consult with the FBI’s Environmental Program Manager through the FBI’s project manager for specific requirements for the project.
https://www.osha.gov/
C-15
The Contractor shall perform, track, participate, implement, and comply with stormwater pollution prevention minimum control measures, protocols, and best management practices (BMPs) and ensure that water quality standards are not violated in accordance with FBI Quantico Complex’s MS4 General Permit VPDES Number VAR040105 and 9 VAC 25-890 – Discharges of Stormwater from Small MS4s.
The Contractor shall support FBI’s low impact design/development (LID) techniques to restore predevelopment hydrology to the maximum extent technically feasible for both new and renovation construction projects regardless of size and shall adhere to designs and guidance found in the contract documents and plans concerning LID for storm water management. LID practices include but are not limited to restoring predevelopment hydrology to the maximum extent technically feasible; promoting natural removal of pollutants such as nutrients, oil, grease, and sediments from storm water; managing rainfall at the point where it falls; and meeting the requirements of the MS4 permit.
The Contractor shall coordinate with FBI Environmental Office to schedule inspections and shall provide timely corrective actions for noted…