jefferson parish - Bid Event _214.pdf

PDF 764 KB Posted

Attached to
Landscape Maintenance Within the Right-of-way on Severn Avenue from Veterans Boulevard to W. Esplanade Avenue
Solicitation number
214
Issued by
Jefferson Parish, Louisiana

About this file

This is a Bid Event specification document issued by the Jefferson Parish Department of Public Works—Parkways Department for landscape maintenance services within the Severn Avenue right-of-way in Louisiana. The scope of work encompasses a two-year contract for grass cutting, edging, blowing, sweeping, litter removal, mulching, and herbicide spraying operations across the east and west rights-of-way and center median between Veterans Boulevard and W. Esplanade Avenue. Work activities include turf mowing and maintenance, irrigation system maintenance, chemical applications, tree trimming, and mulch placement. The site quantities include approximately 6 Muskogee Crape Myrtle trees, 240 Eagleston Holly trees, 1,500 six-inch annual color plants, and 85,000 square feet of Palisades Zoysia turf. A non-mandatory pre-bid conference was scheduled for 10:00 a.m. on October 30, 2026, at the Jefferson Parish Purchasing Department in Gretna, Louisiana. Monthly maintenance invoicing will occur over twenty-four equal payments throughout the two-year contract term, with work scheduled Monday through Friday from 7:00 a.m. to 4:00 p.m., excluding weekends and legal holidays without prior approval.

Bidders must provide monthly pricing for maintenance work and separately price incidental items including shrub replacement, sod repair, irrigation component replacement, and chemical applications. An electronic bid bond of five percent (5%) of the total bid price is required at submission, along with performance and payment bonds of $150,000 each at contract execution. All bidders must possess a Louisiana State Contractor's License with classification for Specialty: Landscape, Grading and Beautification, and the apparent low bidder must submit within ten calendar days copies of required Louisiana Department of Agriculture & Forestry licenses including State Landscape Horticulturist License, Ground Owner Operator License, Category 6 Right-of-Way & Industrial Certification, Category 3 Turf and Ornamental Certification, and Arborist License. The contractor must carry Pollution Insurance with minimum limits of $1,000,000 per incident and $2,000,000 aggregate, with fines, penalties, cleanup costs, and broad form coverage included. Liquidated damages of $200 per day may be assessed for tasks not completed within specified timeframes, such as mulch placement within seven calendar days. Jefferson Parish maintains the right to cancel the contract at any time and reserves the authority to adjust products, methods, and application rates without creating additional financial obligations for the contractor.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEVERN AVENUE LANDSCAPE MAINTENANCE

FOR THE JEFFERSON PARISH

DEPARTMENT OF PUBLIC WORKS – PARKWAYS DEPARTMENT

NON-MANDATORY PRE-BID CONFERENCE

All prospective bidders are invited to attend this non-mandatory pre-bid conference, which will be held at 10:00 a.m.

on October 30, 2026, in the Jefferson Parish Purchasing Department, located at the General Government Building, 200 Derbigny St., Suite 4400, Gretna, LA 70053.

PRE-BID INSPECTION OF THE SITE

The site is easily accessible, at any time, for any bidder. Representatives from Jefferson Parish will not attend any pre-bid site inspections.

BONDS:

• Bid Bond – An electronic bid bond in the amount of five percent (5%) of the total bid price is due with the bid submission.

• Performance Bond - A performance bond in the amount of $150,000.00 is required at the signing of the formal contract. The proposer acknowledges and agrees that the Performance Bond may be forfeited for the successful proposer’s failure to fully and faithfully perform its obligations in accordance with the negotiated and executed agreement.

• Payment Bond - A payment bond in the amount of $150,000.00 is required at the signing of the formal contract.

The proposer acknowledges and agrees that the Payment Bond shall act as security for the true and faithful payment in full of all subcontractors and persons performing labor, services, materials, machinery, and fixtures in connection with the work, and may be subject to forfeiture in the event the successful proposer fails to fully and faithfully satisfy any and all payment obligations.

LICENSING

Bidders shall be properly licensed in accordance with LA-R.S. 37:2150-2163 and must possess a Louisiana State Contractor’s License with the classification of SPECIALTY: LANDSCAPE, GRADING AND BEAUTIFICATION (The license number is required to be on the electronic envelope and failure to do so will result in automatic rejection and your bid will not be read aloud in accordance with public bid law).

The apparent low bidder shall, within ten (10) calendar days of bid opening, submit copies of the front and back (as applicable) of all Agriculture & Forestry licenses and certifications (listed below) required for performance of the work to the Parkways Department. Such documentation is not required at the time of bid submission; however, failure of the apparent low bidder to timely provide the required documentation within the ten (10) day period shall render the bid non-responsive and subject to rejection.

Bidders shall possess the following licenses and certifications:

• Louisiana Department of Agriculture & Forestry State Landscape Horticulturalist License;

• Louisiana Department of Agriculture & Forestry Ground Owner Operator License;

• Louisiana Department of Agriculture & Forestry Category 6: Right-of-Way & Industrial Certification;

• Louisiana Department of Agriculture & Forestry Category 3: Turf and Ornamental Certification;

• Louisiana Department of Agriculture & Forestry Arborist License.

All required licenses shall be issued in the name of the company submitting the bid and performing the work. Any license held in an individual capacity, including but not limited to a Landscape Horticulturalist License, must reflect the bidding company as the individual’s place of business in the records of the Louisiana Department of Agriculture & Forestry.

Bid Event #214

SP - Page 1 of 18

The prime contractor shall independently possess all licenses required to perform the scope of work and may not rely upon a subcontractor’s license to satisfy licensing requirements for work constituting more than fifty-one percent (51%) of the total contract value. Subcontractors shall hold all licenses and certifications applicable to the specific portion of work they perform, but such licenses shall not substitute for the prime contractor’s required licensure

All required licenses and certifications shall remain valid and in good standing for the duration of the contract. In the event of any change in an individually held license (e.g., Landscape Horticulturalist), written notice of such change shall be provided to Jefferson Parish prior to continuation of work.

The Contractor bears sole responsibility for compliance with all applicable federal, state, and local laws, rules, and regulations governing required licensure and certification.

A written list of all proposed subcontractors shall be submitted to Jefferson Parish Parkways Department for approval prior to contract execution. No subcontracted work shall commence until written approval is obtained. By way of example only, mulch placement may be subcontracted to a properly licensed Landscape Horticulturalist, and chemical application may be subcontracted to a duly licensed applicator holding the appropriate category certification.

INSURANCE

In addition to Jefferson Parish’s standard insurance requirements, the Contractor shall possess Pollution Insurance with the following coverages:

• Covering losses caused by pollution conditions that arise from the operations of CONTRACTOR;

• Minimum acceptable limits: $1,000,000 per incident; and $2,000,000 aggregate;

• Broad Form Named Insured endorsement;

• Fines, penalties and punitive damages to be included;

• Clean up costs to be included;

• Additional Insured endorsement in favor of Parish of Jefferson, its Districts, Departments, Agencies and

Employees under the direction of the Parish President and the Parish Council, and should stipulate that the insurance afforded CONTRACTOR shall be primary insurance and that any insurance carried by the Owner shall be excess and not contributing insurance;

• A Waiver of Transfer of Rights of Recovery Against Others to Us endorsement in favor of Parish of Jefferson, its Districts, Departments, Agencies and Employees under the direction of the Parish President and the Parish Council;

• If claims-made coverage is accepted, the retroactive date, if any, must precede the commencement of the performance of the Contract; and

• Any retrospective date applicable to coverage will be maintained or an extended discovery period will be exercised for a period of three (3) years, beginning when this Contract is completed or terminated.

SCOPE OF WORK

The Jefferson Parish Department of Public Works – Parkways (Parkways Department) is soliciting qualified Contractors for a two (2) year contract for grass cutting, edging, blowing, sweeping, litter removal, mulching and herbicide spraying operations to be performed within the Severn Avenue right-of-way between Veterans Boulevard and W. Esplanade Avenue. The site shall include the east and west rights-of-way and the center median. The scope of work shall include all tasks and items listed within these specifications. This shall include, but not be limited to, turf mowing and maintenance, irrigation system maintenance, chemical applications, trimming and mulch placement. All bid item pricing shall include all equipment, incidentals, licenses, insurance, labor, fuel and transportation to complete the work. The Contractor shall refer to Resolution No. 136353, as amended, which provides a uniform set of “General Conditions and Agreement for all contractors engaged in performing work or services for the Parish of Jefferson”.

SP - Page 2 of 18

PERIOD OF AGREEMENT

The term of the contract shall be for two (2) years.

INVOICING

Bid pricing shall be provided on a monthly basis for the maintenance work outlined in these specifications. The Contractor shall submit an invoice once per month based on the unit pricing, for a total of twenty-four (24) equal payments for the life of the contract. Any approved incidental work shall be invoiced separately from the monthly maintenance cost and can be submitted any time after the work is accepted as complete by Parkways. There is no guaranteed quantity of any incidental bid items to be used for this contract. All bid items shall include all associated costs related to the item such as labor, material, equipment, fuel, insurance and related incidentals.

LIQUIDATED DAMAGES

Liquidated damages may be assessed for missed and/or unsatisfactory work. The liquidated damages amount set forth in these specifications is intended to represent a reasonable estimate of the damages anticipated to result from delay or non-performance. At the time of contracting, actual damages may be difficult to calculate with certainty; therefore, the stated amount reflects a good-faith effort to approximate likely costs and impacts associated with such delay. The liquidated damages provision is not intended to operate as a penalty. The amount established bears a reasonable relationship to the anticipated harm and is included solely to compensate for damages that are otherwise uncertain or impracticable to quantify in advance.

Some scheduled maintenance items within the required specifications must be completed within a designated time frame. These schedules are important to the overall appearance of the Site. Once a certain task begins, the Contractor will have a set number of calendar days to complete the task to the satisfaction of the Jefferson Parish Parkways Department. As designated within certain tasks, liquidated damages may be assessed in an amount of $200.00 per calendar day for each day that the task remains incomplete. For example, mulch placement must be complete within seven (7) calendar days. If the Contractor takes nine (9) calendar days to complete the task, he may be penalized up to $400.00 for the delayed completion.

MANUFACTURERS

Wherever a brand name, make, manufacturer, model or catalog number is specified, it is used only to denote the quality standard of the product desired and does not restrict bides to that brand or manufacturer. Such references are intended solely to convey the general style, type, character and minimum quality of the product required. Equivalent products may be acceptable if, in the Parish’s sole discretion, they meet all specifications and project needs. Required documentation for proposed equivalents shall be submitted in accordance with these specifications.

Any prospective bidders wishing to submit as-equal products shall do so during the bid process. Products shall be reviewed and approved or denied by the Parkways Department during the bid process. As-equal products submitted after the bid process shall not be considered by the Parkways Department.

PART I QUALIFICATIONS

MINIMUM REQUIREMENTS

All bidders must have the knowledge, resources and capabilities to meet the expectations of this contract. The successful bidder shall not put an undue hardship on Jefferson Parish staff due to a lack of experience with work of a similar scope and scale.

SAFETY STANDARDS

The Contractor shall be responsible for implementing all safety measures to perform the work. No lane closures may take without prior approval from the Jefferson Parish Parkways Department.

SP - Page 3 of 18

MINIMUM EQUIPMENT

The Contractor shall determine the equipment that is to be used. The bid shall include equipment, operators, fuel, maintenance and transportation. All equipment shall be in a good state of operation and shall be maintained to work and perform the tasks it was designed for in an expedient time frame. Continual breakdown, repairs or work stoppage due to equipment failure will not be permitted. Any damage that occurs to the Site related to faulty equipment shall be repaired immediately at the Contractor’s expense. All equipment required to complete the associated tasks shall be furnished upon request. The following information shall be included: type, make, model, manufacturer and quantity.

PART II DEFINITIONS

DEBRIS

Only debris such as grass clippings, dirt, or any other natural rubbish created, as a direct result the Contractor’s performance will be considered to be debris. Under no circumstances shall the debris from the maintenance work be allowed to remain overnight in any one area.

TRASH

Any non-organic or manmade debris that is not part of or obstructs the area to be maintained by the Contractor, is considered to be trash and will be removed prior to the start of any maintenance work. Trash considered too large to be removed by hand or which requires specialized equipment to remove, shall be reported to the Jefferson Parish Parkways Department as soon as possible so that the obstruction can be removed. The Contractor shall be responsible for establishing the most efficient method of trash removal. Shredding of trash by mowers will not be permitted.

MEDIAN

The entire area between the back of curb of opposing multiple travel lanes. For example: A boulevard has two one-direction lanes traveling north and two one-direction lanes traveling south. The lanes are divided by an area 50’ wide as measured from the back of curb of the north bound lanes to the back of curb of the southbound lanes. This 50’ area is the median.

REPAIR / REPLACEMENT

A list of common incidental repair items is included with this bid. All bidders shall price the incidental items on the bid form for the possibility of providing and installing the items during the life of the contract. There is no minimum or maximum quantity of each item that may be required during the contract. Each item, if required during the contract, will be invoiced in addition to the monthly invoice. All items will require prior approval from Jefferson Parish before being purchased and installed. Whenever possible, the contractor shall supply the same manufacturer and product number of any incidental items he repairs/replaces. All incidentals item pricing shall include all freight, taxes, labor, tools and supplies to properly install each item.

Any additional repair and or replacement not included on the incidental line items sheet, including all associated labor, delivery charges and taxes, shall be approved by Jefferson Parish prior to that repair taking place. The Contractor shall provide a written description of the work to be performed and included all pricing for approval by Jefferson Parish prior to performing the work.

INCIDENTAL WORK

In addition to the items specified, a common incidental material list (bid form) is attached to these specifications. All bidders shall price each line item on the form for the possibility of providing and installing the items during the life of the contract. There is no minimum or maximum quantity of each item that may be required during the contract. Each item, if required during the contract, will be invoiced in addition to the regular monthly invoice. All items will require prior approval from the Jefferson Parish Parkways Department before being purchased and/or installed.

Any additional repair and/or replacement not included on the incidental line items sheet, including all associated labor, delivery charges and taxes, shall be approved by the Director of the Jefferson Parish Parkways Department prior to the

SP - Page 4 of 18 work taking place. The Contractor shall provide a written proposal including a description of the proposed work and an itemized cost breakdown for approval prior to performing the work.

ASSOCIATED COSTS

It is the Contractor’s responsibility to maintain the Site to the highest standard. However, the Contractor is not responsible for any replacement costs, or labor that exceeds the work outlined in this document.

MAINTENANCE REPORTS

A monthly maintenance report shall be required by the Jefferson Parish Parkways Department to be kept and submitted with monthly invoices. These reports are records used for tracking and quality assurance purposes. The Contractor is required to notify Jefferson Parish within 24 hours of any problems and/or restrictions that would prevent him from performing his duties. The Contractor shall provide his own maintenance report form. In addition, the Contractor shall be required to turn in a chemical spray report with every invoice documenting all chemical applications, included routine non-selective herbicide applications.

INSPECTIONS

Frequent inspections of area of work performed shall be made by Jefferson Parish personnel to determine the acceptance of the work performed. In the event the work is considered unacceptable, the Contractor will be directed to immediately employ any and all methods or means to bring the area up to an acceptable level within three (3) calendar days of notice, without any extra cost to Jefferson Parish. The discovery of any fraudulent activities associated with this contract during the inspection process will be grounds for immediate contract termination without further compensation. In addition, such circumstances may initiate possible legal ramifications for the Contractor.

TRAFFIC CONTROL AND SIGNS

The Contractor shall provide all necessary barricades, signs, lights and warning devices or any other item necessary in order to properly move traffic around or through his operations. Set up, removal and maintenance of all traffic control equipment shall be by the Contractor. Slow moving vehicle signs and flashing lights shall be installed on all moving equipment that will use the public rights-of-way for movement of equipment. In the event that a lane of traffic will need to be closed, the Contractor shall provide sufficient notification to the Jefferson Parish Traffic Engineer of necessity to close any portion of the roadway carrying vehicles or pedestrians. The Contractor will request final approval of such closings from the Department of Public Works, Traffic Engineering Division, at least ten (10) working days in advance.

The Contractor shall be responsible for providing safe and expedient movement of traffic through the work Site. The Contractor must have in place prior to work, a method of recording, responding and repairing legitimately broken glass, windshields or any other kind of damage experienced due to the work being performed.

The Louisiana State Manual for Uniform Traffic Control shall be strictly enforced.

WORK PERIODS

No work shall be done between 6:00 p.m. and 7:00 a.m., or on Saturdays, Sundays, or legal holidays without permission from Jefferson Parish. However, emergency work may be done without prior permission. In the event that the Contractor wishes to work weekends, holidays or outside the allowed times of the local governing bodies, he must secure permission from Jefferson Parish, and provide at least 72 hours notification of his intentions. The Contractor must also be aware of any local event(s) that may affect his scheduled maintenance operations.

UTILITY SERVICE INTERRUPT

In the event of interruption of public or private utility service or general damage to public or private properties as a result of accidental breakage or any other actions by the Contractor, he shall immediately notify the proper authority and/or property owner and shall fully cooperate with said authority or owner until the service is restored to its previous capacity. All costs associated with the notification and repair shall be paid for by the Contractor.

SP - Page 5 of 18

ONGOING CONTRACTS

It is possible that other Contractors may be working within close proximity to the Site. The Contractor shall coordinate his work with any other Contractors working in or around the locations. Should a conflict occur, a Parish representative will make all final decisions.

NUISANCE CONTROL

The Contractor shall include in his bid the control of dust, noise and odors created by his operations. All controls shall be completed in order that nuisances are minimized and occur within the standards of all governing bodies.

TRANSFERRING CONTRACTS

Transfer of this contract shall not be allowed under any circumstances unless an amendment is passed by the Jefferson Parish council.

PART III LANDSCAPE MAINTENACE PROGRAMS AND FREQUENCIES

DEBRIS AND TRASH

Any non-organic or manmade debris that is not part of or obstructs the area to be maintained by the successful bidders is considered to be trash and will be removed prior to the start of any work. The successful bidder shall be responsible for establishing the most efficient method of trash removal. Shredding of trash by mowers and equipment will not be permitted. It shall not be permissible for the Contractor to utilize any right-of-way trash can(s) for disposal of debris or trash. All debris and trash shall be picked up and completely removed from the site by the Contractor.

REPAIR AND REPLACEMENT

A list of common incidental repair items is included with this bid. All bidders shall price the incidental items on the bid form for the possibility of providing and installing the items during the life of the contract. There is no minimum or maximum quantity of each item that may be required during the contract. The prices provided with the bid will be used in determining the low bidder, but will not determine the overall contract price. All items on the incidental contract will require prior approval before ordering and/or installing. A purchase order shall be issued by the Parkways Department prior to work beginning. Failure to receive a purchase order prior to work beginning may be cause for non-payment of the invoice for services. Whenever possible, the successful bidder shall supply the same manufacturer and product number of any incidental items repaired or replaces. All as-equal products must receive prior approval, in writing, from the Parkways Department. All incidentals item pricing shall include all freight, taxes, labor, tools, any additional soil and/or mulch (plant material), and all supplies needed properly install each item.

EQUIPMENT REQUIREMENTS

The successful bidder shall determine the proper equipment needed to perform all work listed in this contract. The bid shall include equipment, insurance, operators, fuel, maintenance and transportation. All equipment shall be in a good state of operation and shall be maintained to work and perform the tasks it was designed for in an expedient time frame. Continual breakdown, repairs or work stoppage due to equipment failure will not be permitted. Any damage that occurs to the Site related to faulty equipment shall be repaired immediately at the contractor’s expense.

WORK COMPLIANCE

The proposed work must comply with OSHA, DOT, Jefferson Parish and any other applicable agency requirements and regulations regarding this variety of work. The Contractor shall be responsible for any damage to the site as a result of his operations. This includes, but is not limited to, damage to steel landscape edge, damage to irrigation system components and ruts within turf areas.

EXPERIENCE

The Contractor must have the resources and capabilities to meet the expectations of this contract. Failure to provide satisfactory work and/or inability to provide the required services in a timely manner may result in termination of this contract.

SP - Page 6 of 18

SAFETY

The contractor shall be responsible for ensuring that his operations are performed in a safe manner. This includes, but is not limited to, pedestrian and vehicular access, equipment operation and employee and site safety. All work shall conform to the latest guidelines of OSHA, Louisiana DOTD, Jefferson Parish and any other applicable agency. The Contractor shall maintain a professional work zone at all times. The use of drugs or alcohol is prohibited while working on parish property.

Confrontation with citizens and/or Jefferson Parish personnel will not be tolerated. Soliciting and performing private work while working for Jefferson Parish is prohibited. Failure to maintain a professional work zone, or fraudulent activities, may result in the termination of the contract and possible legal ramifications.

MAINTENANCE REPORTS

Within two working days of completing any scheduled service, the Contractor shall complete and e-mail a copy of his maintenance report and/or spray records to the Parkways Department. A list of e-mail addresses will be provided to the Contractor at “Pre-construction Conference”.

INSPECTIONS

Frequent inspections of the work area shall be made by Jefferson Parish personnel to determine the acceptance of the work performed. In the event the work is considered unacceptable, the successful bidder will be directed to immediately employ any and all methods or means to bring the area up to an acceptable level within three (3) calendar days of the notification from Jefferson Parish. There will be no additional charges to Jefferson Parish by the Contractor for mending unacceptable work. The discovery of any fraudulent activities associated with this contract during the inspection process will be grounds for immediate contract termination without further compensation. One time per month, a required walkthrough of the Site shall take place with a Parkways Department representative and the Contractor’s site superintendent. These meetings shall generally take place during the first week of each month.

DAMAGES

The successful bidder shall be responsible for providing safe and expedient movement of traffic through the Site. The successful bidder must have in place prior to starting any work, a method of recording, responding and repairing legitimately broken glass, windshields or any other kind of damage experienced due to the work being performed. Any damage reported to the Parkways Department relating to this work will be directed to the Contractor for remediation.

GRASS CUTTING CYCLE FREQUENCY

The entire site shall have the grass cut at the following frequency: March 1 through October 31 shall require one (1) cut per every seven (7) days or once every week for a total of thirty-five (35) cuts per year during this time frame.

November 1 through February 28 (or 29) shall require one (1) cut per every fourteen (14) days or once every two (2) weeks for a total of eight (8) cuts per year during this time frame. A total of forty-three (43) cuts shall be required per year. Unless weather delays occur, the Contractor shall perform his grass cutting cycles to occur on Thursdays and/or Fridays of each scheduled week of maintenance.

GRASS CUTTING AND LANDSCAPING

The following activities shall be performed for each required grass cutting cycle:

GRASS CUTTING

All litter, trash and/or debris shall be removed prior to grass cutting. The turf areas of the site shall be maintained at a cut height between 1-1/2 inches and 2 inches of grass blade exposure.

Grass cutting shall be performed in a manner to leave the site with a smooth, level cut on the turf, conforming to the existing grade. No gouging, scalping or similar actions shall be permitted. Grass cutting may be accomplished by utilizing ride-on or push mowing units. In constricted areas where a push type mower will not fit, a weed eater shall be allowed. It is the successful bidder’s responsibility to determine the exact type of equipment to be used.

SP - Page 7 of 18

WEED EATING

Grass areas around all existing fixed features, including but not limited to, signs, landscape curbs, light poles, fire hydrants, drains, manholes and utilities may be cut using a mechanical trimmer. Spraying of chemicals will not be allowed around any hard surface. Weed eating these areas shall be cut to an approximate height of 1 inch of grass blade exposure with no more than a 24-inch diameter cutting path around all objects. Weed eating will not be allowed around any trees or plant material where damage may occur to the bark or the trunk of the plant or tree. Spraying shall only be allowed within a 12-inch diameter around properly mulched trees for the purpose of weed control.

EDGING

At all locations, where grass areas meet surface paving whether it be concrete, asphalt or some other paving type, the grass shall be edged utilizing a mechanical blade edger. Herbicides may not be used to control grass growth where grass and a paved surface meet. Edging equipment shall be such that a clean, sharp line along the hard surface/grass interface shall remain upon completion of edging. A minimum depth of 1 inch shall remain along and below the top of all hard surface upon completion of edging in order to retard the continued growth of the grass. Edging shall be performed with a stick or walk behind edger with a metal or equivalent blade only.

Mechanical weed eaters shall not be used for edging. The frequency of edging shall be the same as mowing such that no part of the grass growth shall extend over the adjacent hard surface.

WEED CONTROL

Weed control shall be performed as needed whereas no weeds are visible within the designated site. Weed control and spraying shall be performed by a licensed and qualified applicator in such a manner as to leave clean lines around all areas that will be affected. Spraying around trees will be a twelve (12) inch diameter from trunk of tree and be covered by mulch. Spraying around other obstructions such as signs, fire hydrants, light poles and the like will not be allowed. Precautions should be taken to avoid chemical drift by not spraying when wind is in excess of five (5) miles per hour. Weeds in all cracks and joints in all paved surfaces including streets, curbs/gutters, parking areas and walkways shall only be removed by spraying. Spraying will not be allowed where a hard surface meets the edge of lawn. Spot spraying of weeds inside of beds areas will be allowed as long as proper precaution is taken when applying the non-selective herbicide. Any damage to the plant material as a result of spot spraying may lead to disallowance of future applications by the successful bidder. Hand weed removal shall occur, as needed, at each grass cutting. Hand weed removal will be limited primarily to garden and planted bed areas. A pre-emergent and post emergent herbicide program will be implemented as part of these specifications, but hand weed removal may be required periodically. Any removed weeds must be properly disposed of offsite.

SWEEPING

In order to keep grass, leaves, smoking paraphernalia butts and other debris and trash from collecting and building up in the location of maintenance, the successful bidder will be required to sweep the areas affected by the work. These areas shall include all turf, bed areas, concrete, asphalt and curbs/gutters. Sweeping shall be performed immediately after each complete grass cutting cycle. The Successful bidder shall not be allowed to blow grass clippings, dirt and debris into the street or drain inlets.

MULCH PLACEMENT

All garden beds and around all trees shall receive bailed pine straw mulch in order to keep a minimum four (4) inch thick layer at all times. All bailed pine straw mulch shall be refreshed every six (6) months. Mulch applications shall take place during the first week of May and the first week of November. The Contractor shall have seven (7) calendar days from the first of each month to complete the mulch installation. Failure to complete the mulch installation within the

SP - Page 8 of 18 allowed timeframe may result in liquidated damages (see LIQUIDATED DAMAGES). Only mulch free of debris and trash shall be permitted. All bale strings and ties shall be removed from the site. Mulch for tree rings outside of the landscape beds shall be 36” in diameter from the trunk of the tree. Mulch shall be set down level and not in a pyramidal fashion around base of tree. Annual color beds shall receive cut pine straw (bag) mulch installed at a minimum depth of four (4) inches immediately after each annual color installation (see ANNUAL COLOR REPLACEMENT).

ANNUAL COLOR REPLACEMENT

The Contractor shall be responsible for the turn-key planting of all annuals. Successful Bidder shall take one (1) soil sample per year (the Parkways Department will determine the date and location(s) of this sample). Soil amendments, if required, will be specified by the Parkways Department and furnished and installed by the successful bidder as an incidental item. The annuals shall be removed and replaced during the first week of the following months: April, July, and December. The Contractor shall have seven (7) calendar days from the first of each month to complete the annual color removal and installation. Failure to complete the annual color removal and installation within the allowed timeframe may result in liquidated damages (see LIQUIDATED DAMAGES). It will be the Contractor’s responsibility to deliver, store and install the annual color. The Parkways Department will select the type of annual and flower color(s) prior to the order being placed. It shall be the Contractor’s responsibility to notify the Parkways Department prior to placing his annual color order so that the Parkways Department can provide the type of annual and flower color(s). The successful bidder shall supply and install approximately (1,500) 6-inch annual plants at each replacement.

The successful bidder shall be responsible for ensuring the irrigation system is in proper operating condition before and after annual color installation. The successful bidder is responsible for all insect control, disease control, and fertilization of annuals. Any annuals that die due to lack of water, insects, disease or the like shall be replaced by the Contractor at no charge to the Parkways Department. Any anticipated treatment and/or fertilization program(s) for annual color installation shall receive prior approval by the Parkways Department before planting. Annual color beds shall receive cut pine straw (bag) mulch installed at a minimum depth of four (4) inches immediately after each annual color installation.

DEAD PLANT REPLACEMENT

Replacement of plants, not including trees, located within the maintenance site is required to be performed by the successful bidder. The timely replacement is critical to the overall look of the site. The successful bidder must notify the Parkways Department upon the discovery of dead plant material. The prolonged existence of dead plant material will not be allowed. The Parkways Department shall approve all proposed plant replacement as notified by the Contractor.

All plant replacement costs shall be paid as per the contract’s incidental replacement list provided by the successful bidder. The replacement plants size shall match surrounding plant material of the same species. When pricing the incidental cost of replacing dead plants, flowers, trees, etc., the successful bidder shall include in their price all materials, freight, labor, soil, mulch, and incidentals in the cost of the replacement. Once any plant replacement work is complete, and inspected by the Parkways Department, the Contractor shall submit the replacement costs with that month’s invoice.

AUTOMATIC IRRIGATION

The maintenance and repair of the existing irrigation system shall be a requirement of this contract.

The irrigation system shall be inspected and documented on a monthly basis for proper operation. The Contractor shall be required to run a test of the irrigation system within the first week of each month (excluding November, December, January and February). The Contractor shall provide the Parkways Department with a report documenting any deficiencies within the system and include a proposal for repair based on the incidental replacement list. Failure to perform the monthly irrigation system inspection and provide the Parkways Department with the corresponding report within the provided time frame may result in the assessment of liquidated damages (see LIQUIDATED DAMAGES). The irrigation system provides separated zone irrigation for all turf, bed and annual planting areas. The system also includes

SP - Page 9 of 18 master valves at each water meter (2 meters for the system). It shall be the successful bidder’s responsibility to ensure all components of these irrigation systems are operational at all times.

These tasks include, but may not be limited to, replacement of heads/nozzles, broken water lines and valves; adjustment of the controller, heads, valves and zone water durations and frequencies. All irrigation repair costs shall be as per all pricing listed on the incidental list provided by the successful bidder and shall be performed within two (2) workings days of the issue being discovered by the successful bidder and/or the Owner. The successful bidder shall receive a separate purchase order prior to any work being performed. Any adjustment of the controller and/or aiming irrigation heads is not considered an incidental item and shall be included in the base bid price. It is the successful bidder’s responsibility to ensure the irrigation system is in proper working order prior to annual color replacement and/or the application of any chemicals as outlined in these specifications. Failure to ensure proper operation of the system may result in harm to the landscape materials. Any damage to the landscape that occurs because of improper watering shall be repaired at the successful bidder’s expense. The successful bidder is also responsible for setting the controller accordingly (before and after) to coincide with each annual color replacement and all chemical applications.

TREE TRIMMING

All holly and crape myrtle trees within the Site shall be properly trimmed in accordance with standard practices. Holly and crape myrtle trees shall be pruned (shaped) a minimum of two times per year. The first pruning shall occur during the first week of March and the second pruning shall occur during the first week of July. Failure to complete tree trimming within the provided time frame may result in the assessment of liquidated damages (see LIQUIDATED DAMAGES). When overhanging the sidewalk, trees with low hanging branches shall be trimmed to a height of seven (7) feet above the sidewalk, where applicable. At no time shall trees obstruct the sidewalk. All dead or broken branches from all trees shall be trimmed as soon as it is noticed. This includes damage caused by wind and or cold (excludes named storms). This contract does not require any trimming of existing oak trees within the Site. No topping of trees will be allowed. Any growth extending six (6) inches beyond the main trunk of the tree, and within five (5) feet of the ground level, is considered to be sucker growth that must be removed. The Contractor shall notify the Parkways Department of the discovery of any declining or dead tree within the Site. Field input from the Jefferson Parish arborist and/or the Jefferson Parish horticulturist will assist with any questions the successful bidder may have regarding tree trimming. After named storm events, and at the request of the Parkways Department, the successful bidder shall assess all damage and submit a quote for the trimming and/or removal of trees within the Site.

SHRUB PRUNING

All shrubs shall be trimmed or pruned to have a massing effect. The massing effect shall be achieved by regular pruning and shaping of the shrubs so they are natural in shape, but maintain a massing effect. Shrubs shall be pruned after blooming each season to promote new growth. This may entail removing an entire limb, branch or frond, and may require removal of a part of a limb, branch or frond.

Ornamental grasses shall be cut back one (1) per year in February or March, just as the ornamental grass begins to push new growth. Pruning shall take place such that the ornamental grass is reduced to a uniform height of roughly 6”. All clippings shall be removed from the site. At each visit, the successful bidder shall remove all invasive and/or poisonous vines from the property. Shrub pruning due to excessive wind and or cold (excluding named storms) may be required, and is considered part of this contract. Field input from the Jefferson Parish horticulturist will assist with any questions the successful bidder may have regarding shrub pruning. Pruning and trimming shall occur on an as-needed basis, but no less than four (4) times per year. After named storm events, and at the request of the Parkways Department, the successful bidder shall assess all damage and submit a quote for the trimming and/or removal of shrubs within the Site.

SP - Page 10 of 18

CHEMICAL APPLICATION SCHEDULE

JANUARY

• Bed pre-emergent (App 1)

MARCH

• Bed fertilization

• Bed pest control (App 1)

• Bed fungicide (App 1)

APRIL

• Turf fertilization (App 1)

• Turf pre-emergent (App 1)

• Turf post-emergent (App 1)

MAY

• Bed pre-emergent (App 2)

• Turf pest control

• Bed pest control (App 2)

• Turf post-emergent (App 2)

JULY

• Turf post-emergent (App 3)

AUGUST

• Turf fertilization (App 2)

SEPTEMBER

• Bed fungicide (App 2)

• Bed pre-emerge (App 3)

NOVEMBER

• Turf pre-emergent (App 2)

• Turf post-emergent (App 4)

Note:

Please refer to the body of these specifications for details on all required chemicals, rates and additional details

SP - Page 11 of 18

FERTILIZATION (TURF)

Liquid turf fertilizer shall be applied two (2) times per year. Liquid turf fertilizer shall be applied during the first weeks of April and August. Failure to complete turf fertilization within the provided time frame may result in the assessment of liquidated damages (see Section 12).

Products:

RegalGrow™ Harness® 30-0-0 liquid fertilizer @ 44 ounces of product per 1,000 square feet of turf (per application).

PLUS

RegalGrow™ 0-18-20 with Shamrock® liquid fertilizer @ 44 ounces of product per 1,000 square feet of turf (per application).

Important: These products are to be applied with a (2) to (1) ratio. A minimum (2) parts water and (1) part product. Products shall be tank mixed together for each application.

FERTILIZATION (LANDSCAPE BEDS)

An 8–12-month slow feed slow-release bed fertilizer shall be applied to all beds in the first week of March each year of the contract. Failure to complete landscape bed fertilization within the provided time frame may result in the assessment of liquidated damages (see LIQUIDATED DAMAGES).

PRE-EMERGENT HERBICIDE (TURF)

Barricade® 65WG or liquid formulation turf pre-emerge shall be applied two (2) times per year. The first application shall take place in April and second application in November. The Parkways Department will communicate the exact time frame for application with the Contractor depending on the trending weather conditions. Once an agreed upon date is determined, the Contractor shall have one (1) week to make the application(s). If the application is not made within the agreed upon time frame, liquidated damages may be assed (see Section 12). The manufacturer’s maximum rate shall be split between the two applications.

PRE-EMERGENT HERBICIDE (LANDSCAPE BEDS)

Three (3) Prodiamine pre-emergent applications are required each year. Apply Syngenta Barricade® 4FL pre-emergent herbicide @ 16 ounces of product per acre (per application). The first application shall occur in January*. The second application shall occur in May* and the third application shall occur in September*. Two (2) Isoxaben pre-emergent applications are required each year. Apply Dow Gallery® 75 Dry Flowable @ 1.0 pound of product per acre (per application). The first application shall occur in January* and the second application shall occur in September*. One (1) Pennant Magnum® S-metolachlor pre-emergent herbicide application is required each year. Apply in accordance with the manufacturer’s recommended rates (as approved by Jefferson Parish). The application shall take place in May*.

Do not spray over the top of ornamental grasses with this application.

*When multiple products are scheduled during the same month, the products shall be tank mixed together for each application.

SP - Page 12 of 18

PEST CONTROL (TURF AND LANDSCAPE BEDS)

Granular Topchoice® insecticide shall be applied in all turf and bed areas during the first week of May each year. Failure to complete pest control within the provided time frame may result in the assessment of liquidated damages (see LIQUIDATED DAMAGES).

PEST CONTROL (LANDSCAPE BEDS ONLY)

Granular Merit™ 0.5G shall be applied to all planting beds during the first week of March of each year.

Failure to complete pest control within the provided time frame may result in the assessment of liquidated damages (see LIQUIDATED DAMAGES).

FUNGICIDE (LANDSCAPE BEDS)

BASF Pagent® Intrinsic® fungicide shall be applied to all planting beds two (2) times per year. The first application shall be in March and the second application shall be in September. The Parkways Department will communicate the exact time frame for application with the Contractor depending on the trending weather conditions. Once an agreed upon date is determined, the Contractor shall have one (1) week to make the application(s). If the application is not made within the agreed upon time frame, liquidated damages may be assed (see LIQUIDATED DAMAGES).

POST EMERGENT HERBICIDE (TURF)

Turf areas shall be kept free of weeds at all times. A post emerge system shall be implemented and applied four (4) times per year to prevent grassy weeds, broadleaf and nutsedge. The first application shall be applied with the turf pre-emerge application as directed by the Parkways Department in April.

PBI Gordon SpeedZone® Southern EW broadleaf herbicide shall be applied as per the manufacturer’s specifications. The second application shall be applied as directed by the Parkways Department early to mid-May. Bayer Tribute® Total shall be applied as per the manufacturer’s specifications. The third application shall be applied as directed by the Parkways Department in late July. Bayer Tribute® Total plus Valent Outrider® shall be applied as per the manufacturer’s specifications. The fourth application shall be applied with the turf pre-emerge application as directed by the Parkways Department in November. PBI Gordon SpeedZone® Southern EW broadleaf herbicide plus Valent Outrider® shall be applied as per the manufacturer’s specifications. The exact rates per application shall be determined by the Parkways Department with the expectation that each product shall be applied to total the manufacturer’s maximum rate for the year. The Parkways Department will communicate the exact time frame for application with the Contractor depending on the trending weather conditions. Once an agreed upon date is determined, the Contractor shall have one (1) week to make the application(s). If the application is not made within the agreed upon time frame, liquidated damages may be assed (see

LIQUIDATED DAMAGES).

POST EMERGENT HERBICIDE (LANDSCAPE BEDS, AS NEEDED)

The Successful Bidder shall be responsible for keeping the beds and hardscape areas free of weeds at all times. In the event any weeds break through the pre-emerge and are too abundant for hand removal, the successful bidder shall implement a post emerge program. All landscape bed post emerge products and rates shall be submitted for approval to the Parkways Department prior to application.

SP - Page 13 of 18

Note:

At the discretion of Jefferson Parish, products, methods and application rates may be adjusted due to cultural changes or plant needs. Any changes in these specifications will not create additional financial obligations for the successful bidder. All chemical applications shall be measured per the manufacturer recommended rate of application.

NOTIFICATIONS

The successful bidder shall prove the Parkways Department with a monthly schedule of anticipated activities.

WORKING HOURS

The work that is to be performed can be scheduled during normal working hours Monday thru Friday, 7:00 a.m. thru 4:00 p.m.

CONTRACT TERMS

The terms of this contract shall be for two years, expiring at midnight on the day immediately preceding the second anniversary thereof. Jefferson Parish reserves the right to cancel this contract at any time.

SAFETY PRECAUTIONS

Safety precautions must be exercised at all times to safeguard the welfare and safety of citizens, parish employees and outside Contractors while any work is being performed.

PRE-CONSTRUCTION CONFERENCE AND NOTICE TO PROCEED

A “Pre-construction Conference” shall be held between the successful bidder and Jefferson Parish prior to any work commencing.

No work shall be performed until the successful bidder receives a written “Notice to Proceed” to begin work from the Parkways Department.

SP - Page 14 of 18

ATTACHMENT “A”

INCIDENTAL SHRUB REPLACEMENT

Incidental shrub replacement shall include:

• Removing and disposing of unhealthy and/or dead shrubs.

• Providing and installing various variety of shrubs as replacement material.

• All provided shrubs must match the adjacent material in variety, size and appearance.

• Provide and install as needed fill to properly grade the area of work.

• Provide and install much in order for the repair to match the adjacent plant material.

All existing drainage slopes shall be maintained. A turnkey price per shrub per gallon size of plant material shall be provided.

INCIDENTAL SOD REPAIR

Incidental sod repair shall include:

• Straight line cutting out of existing turf areas.

• Grubbing all non-native materials.

• Adding pump sand as needed to bring newly installed sod to the same elevation as surround turf area.

• Providing and installing Class A Palisades Zoysia sod (squares).

Pump sand shall be feathered in joints of new turf to create a smooth transition. Additional excavation may be required in order for new turf to meet the elevation of existing turf. All existing drainage slopes shall be maintained. A turnkey price per square yard shall be provided.

INCIDENTAL IRRIGATION VALVE REPLACEMENT

Incidental irrigation valve replacement shall include:

• Removing and disposing of the broken valve.

• Providing and installing a new valve of the same size and manufacturer.

• Flushing and testing the system once the replacement is complete.

A turnkey price per valve (size dependent) shall be provided.

INCIDENTAL IRRIGATION POP-UP SPRAY BODY REPLACEMENT

Incidental irrigation pop-up spray body replacement shall include:

• Removing and disposing of the broken pop-up spray body.

• Providing and installing a new pop-up spray body of the same size and manufacturer.

• Salvaging and re-installing the existing nozzle from the old spray body to the new spray body.

• Flushing and testing the system once the replacement is complete.

A turnkey price per pop-up spray body (size dependent) shall be provided.

INCIDENTAL IRRIGATION NOZZLE REPLACEMENT

Incidental irrigation nozzle replacement shall…