JBER - SOW - Purchase Deutz Engines.pdf
PDF 162 KB Posted
- Attached to
- Deutz Diesel Engine Kits
- Solicitation number
- 25Q0044
About this file
This Statement of Work (SOW) details the purchase of Deutz Diesel engines for the 611th Civil Engineer Squadron at Joint Base Elmendorf-Richardson, scheduled for 9 April 2025. The procurement supports the mandatory ten-year overhaul of the BAK-12 Aircraft Arresting System (AAS) and Mobile Aircraft Arresting System (MAAS). The specific requirements include one Deutz Diesel Tier4i Engine (63.7 HP@2600 RPM, 24 Volt electrical system) with multiple accompanying components such as a LOFA 24 VDC Control Panel, Power Take-Off package, 24 VDC starter and alternator, glow plugs, engine harness, exhaust pipe, and various other specialized parts.
The vendor must perform comprehensive quality assurance (QA) inspections prior to shipment, including verifying engine safety shut-down devices, gauge functionality, throttle operation, D.C. charging system, and engine preheat system. The diesel engine assembly kit must be fully assembled except for the control panel, parts manual, and operators manual, which will be packaged separately. The project is subject to final inspection and approval from 611 CES/CEOFP in the Wide Area Workflow system, with strict requirements for packaging, transportation, and component security during shipment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions Consolidated.docx | DOCX document | |
| Attachment 1-Engine data plate.jpg | JPG image | |
| Solicitation - FA521525Q0044.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF
WORK
Purchase Deutz Diesel Engines
Joint Base Elmendorf- Richardson
611th Civil Engineer
Squadron 9 April 2025
Purchase Deutz Diesel Engines Joint Base Elmendorf-Richardson
1. Scope: This contract is to purchase Deutz Diesel engines.
1.1. Background: The purpose of this requirement is to support the mandatory, ten-year overhaul of the BAK-12 Aircraft Arresting System (AAS) and Mobile Aircraft Arresting System
(MAAS).
2. Requirements: The vendor shall secure engines to the pallet and make sure the oil pan is above the pallet and not touching. All items not attached to the engine shall be secured to prevent movement during transportation.
2.1. General Requirements: The Contractor shall provide all material, equipment, labor, supervision, housing, food, and transportation for new material to and from the job site required to accomplish the requirements of this SOW.
2.2. Specific Requirements:
3.2.1. 1-Deutz Diesel Tier4i Engine with EGR Valve, rated at 63.7 HP@2600 RPM;24 Volt electrical system(P/N:D2011L04i)(Deutz) .
3.2.2. 1-Deutz LOFA 24 VDC Control Panel with internal gauge illumination wiring harness and no external factory harness (P/N: EP250KL7) (Deutz ONLY)
3.2.3. 1- Power Take-Off (PTO) package, HSG size 4; Clutch size 8S (NACD P/N:
999-0521) (Deutz ONLY)
3.2.4 1- 24 VDC Starter (P/N: 4300286) (Deutz ONLY)
3.2.5 1- 24 VDC Alternator (P/N: 4103903) (Deutz ONLY)
3.2.6 1- 24 VDC Shutdown Solenoid (P/N: 4103822) (Deutz ONLY)
3.2.7 2- 24 VDC Glow Plugs (P/N: 1179017) (Deutz ONLY)
3.2.8 1- Engine Harness with integral relay sockets (P/N: 23973) (Stauffer “or Equal”)
3.2.9 1- Exhaust pipe (P/N: 4191392) (Deutz “or Equal”)
3.2.10 1- Guard cooler (P/N: 1732) (Stauffer “or Equal”)
3.2.11 1- Throttle Lever/mounting kit, speed control (P/N: 1548) (Stauffer “or Equal”)
3.2.12 1-Aluminum Vernier throttle cable, 75 Inches long (P/N: 58028) (Stauffer “or Equal”)
3.2.13 1- Truck valve, lube oil drain (P/N: V4104P) (Parker-Hannifin “or Equal”)
3.2.14 1- Adapter, oil drain (P/N: 6-3/8F50G) (Parker-Hannifin “or Equal”)
3.2.15 1- Timing Control Unit (Relay ) (PIN: 4 2l 9 375)(Deutz/Or Equal)
3.2.16 1- Relay, Slave (PIN: 427198l)(Deutz/Or Equal)
3.2.17 1- Wiring Harness for LOFA Panel Gauge illumination (PIN: 801-3305-
17)(Stauffer/Or Equal)
3.2.18 2- Lifting eyes, engine (PIN: 4272053)(Deutz/Or Equal)
3.2. 19 1 Parts manual (PIN: 929EN)(Deutz) and 16Operators/Instruction manual (PIN:
02979934)(Deutz) are also required.
3.3 The vendor will perform the following actions prior to shipment:
• Perform quality assurance (QA) inspection to verify operation and correct indication on control panel for all engine safety shut down devices, such as low oil pressure and high engine temperature.
• Ensure all gauges are functioning properly and calibrated; throttle operates freely with no binding; and D.C. charging system checked.
• Verify engine preheat system is operational through the preheat controller and indicating properly on the engine control panel.
• The diesel engine assembly kit/PTO must be assembled with the exception of the LOF A 24 Volt control panel, the Parts manual, and the Operators/Instruction manual, which will be separate, but still packaged with the engine.
• Loose items will be verified and inventoried for packaging/completeness.
J
4.4.1. Project cannot receive inspector approval in Wide Area Workflow from 611 CES/CEOFP prior to final inspection or receipt.
5. Attachments: NA