This Justification and Approval (J&A) document supports a sole-source procurement by the General Services Administration (GSA) for Sonobuoy Storage Racks for the United States Naval Air Systems Command (NAVAIR). The contract is with Arnprior Aerospace Portland, Inc. for 34 total storage racks (17 right-side and 17 left-side) specifically designed for the P-8A Poseidon maritime patrol aircraft, with a total estimated task order value of $2,666,769.00.

The sole-source justification is based on Arnprior being the exclusive designer, developer, and manufacturer of these storage racks, which are critical to P-8A aircraft production. Market research, including a seven-day Notice of Intent posted on SAM.gov in October 2024, confirmed no alternative sources. The procurement will be conducted under simplified acquisition procedures, using an Open Market Purchase Order, with staggered delivery per the production schedule. The contract aims to maintain mission-critical rates for the Department of the Navy's P-8A Poseidon fleet, with the government determining the pricing to be fair and reasonable through multiple price analysis techniques.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0002 Sonobuoy Storage Rack - Left

The total estimated value of the contract is $2,666,769.00.

4. AN IDENTIFICATION OF THE STATUTORY AUTHORITY PERMITTING OTHER

THAN FULL AND OPEN COMPETITION

This acquisition will be conducted under 10 U.S.C. 3204(a)(4) and the authority of FAR 13.106- 1(b)(2), soliciting from a single source, and in accordance with FAR 13.5 Simplified Procedures for Certain Commercial Products and Commercial Services, which allows the use of simplified acquisition procedures for the purchase of commercial products and services in amounts greater than the simplified acquisition threshold but not exceeding $7,500,000. The Sonobuoy Storage Racks meet the definition of a commercial product in accordance with FAR 2.101 as this is an item generally available for the public in the commercial marketplace.

For sole source purchases exceeding the simplified acquisition threshold, the requirements at FAR 13.501(a) apply. The need for a sole source requirement is justified in writing utilizing the format at FAR 6.303-2 properly modified to reflect that the procedures at FAR 13.5 were used in accordance with 41 U.S.C. 1901. This justification will be approved at the levels specified in accordance with FAR 13.501(a)(2)(ii) and posted to SAM.gov within fourteen (14) days of contract award in accordance with FAR 13.501(a)(1)(iii).

QUALIFICATIONS OR THE NATURE OF THE ACQUISITION REQUIRES USE OF THE

AUTHORITY CITED

The P-8A Poseidon aircraft, modified from the , is the ds the responsibility of maintaining, repairing, and implementing new aircraft capabilities to the P- 8A fleet for operational use. Arnprior is the sole designer, developer, and manufacturer of the Sonobuoy Storage Racks for use in the P-8A. The acquisition of the Sonobuoy Storage Racks is intended to enhance their P-8A Poseidon aircraft fleet to effectively maintain and repair their fleet for operational use. Arnprior will be delivering parts identified in Section 3 of this document.

Arnprior understands and is prepared to meet the critical role of providing these parts to maintain Mission Critical Rates for the Department of the Navy assets.

The United States Naval Air Systems Command (NAVAIR) PMA 290 has a fully implemented and funded Foreign Military Sales (FMS) Letter of Offer and Acceptance (LOA) for the and the for the supply of P-8A Poseidon Sonobuoy Storage Racks.

The LOA formalizes and articulates a comprehensive proposal detailing the terms, and conditions, and specifics of the agreement between the U.S. Government, .

Also, the LOA serves as a clear and structured vehicle to present an official offer for the procurement of Sonobuoy Storage Racks. The LOA also establishes a transparent framework between Governments on arrangements such as price, quantity, and delivery for the Sonobuoy Storage Racks thereby ensuring accountability by all involved stakeholders.

Awarding any other source would disrupt ongoing P-8A production by delaying the delivery of qualified and properly integrated Sonobuoy Storage Racks to the P-8A production line.

Furthermore, award to any other source would invalidate the established and mutually consented

The timeline to compete and qualify a second source to fulfill the P-8A production weapons system requirements is estimated to be approximately three years.

6. A DESCRIPTION OF EFFORTS MADE TO ENSURE THAT OFFERS ARE

SOLICITED FROM AS MANY POTENTIAL SOURCES AS IS PRACTICABLE,

INCLUDING WHETHER A NOTICE WAS OR WILL BE PUBLICIZED AS

REQUIRED BY SUBPART 5.2 AND, IF NOT, WHICH EXCEPTION

UNDER 5.202 APPLIES DESCRIPTION OF EFFORTS TO ENSURE THAT OFFERS

ARE SOLICITED FROM AS MANY POTENTIAL SOURCES AS PRACTICABLE,

INCLUDING IF A NOTICE WILL BE PUBLICIZED AS REQUIRED BY SUBPART 5.2

The market research conducted by the Contracting Officer and information submitted by the customer for review indicates that only one (1) source is available. Additionally, the Contracting Officer posted a notice of proposed contract action on October 17, 2024, to SAM.gov, in which the Government intends to solicit and negotiate with only one (1) source; and no response was received. The notice was open for seven (7) days.

7. A DETERMINATION BY THE CONTRACTING OFFICER THAT THE ANTICIPATED

COST TO THE GOVERNMENT WILL BE FAIR AND REASONABLE

Because this requirement is being sole sourced, the Government will be utilizing at least two (2) price analysis techniques outlined in FAR 13.106-3(a)(2) by which to determine pricing submitted by Arnprior to be fair and reasonable. These techniques include, but are not limited to the following:

Market research

Comparison of the proposed price with prices found reasonable on previous purchases

Comparison to an independent Government estimate

8. A DESCRIPTION OF THE MARKET RESEARCH CONDUCTED (SEE PART 10) AND THE

RESULTS OR A STATEMENT OF THE REASON MARKET RESEARCH WAS NOT

CONDUCTED

Market research was conducted in accordance with FAR Part 10 to determine the availability of provided by the Client, a Notice of Intent (NOI) to negotiate with one source was posted on SAM.gov on October 17, 2024, for a period of seven (7) calendar days to ascertain industry interest in the requirement. The NOI closed on October 24, 2024 and no responses were

Date

Competition Advocate GSA General Supplies & Services