Lee County Jail/Courthouse Waste Pipe Replacement Phase II
This is a construction project manual and bidding package for Lee County Government of North Carolina, prepared by Dewberry Engineers Inc., for the replacement of waste pipe systems at the Lee County Jail/Courthouse facility located at 1400 S. Horner Blvd., Sanford, North Carolina. The base bid scope includes removal and replacement of existing cast-iron waste and vent piping in inmate cell pods A and B, replacement of piping in the common utility chase serving public fixtures in those cell pods, and addition of a floor sink and lint interceptor in laundry room 1018. Alternate 1 encompasses approximately 16 linear feet of cast-iron waste piping replacement below the ground floor slab in the men's locker room, replacement of three tank toilets with flush valve toilets, and provision of new domestic water lines. Alternate 2 includes approximately 50 linear feet of waste piping replacement below the ground floor slab between offices. The mandatory pre-bid meeting is scheduled for 10:00 AM on December 10, 2026, at the project site. Sealed bids must be submitted in two complete bid packages to Lee County Government at 115 Chatham Street, Suite 301, Sanford, NC 27330, by 2:00 PM on January 7, 2027. Base bid work must be completed within 120 calendar days from the notice to proceed, with cell pod work limited to 30 calendar days per pod with no concurrent vacating of both pods. Alternate 1 extends the schedule by 15 calendar days, and Alternate 2 extends an additional 30 calendar days.
The contractor must submit a bid bond equal to five percent of the gross bid amount, along with performance and payment bonds in the full contract amount. Liquidated damages are assessed at $1,000 per day for work exceeding the contract completion date. The contractor must provide a $30,000 lump sum allowance for unforeseen conditions, with unused allowance returned to the owner. General liability insurance with minimum limits of $2,000,000 per project and $1,000,000 per occurrence, workers' compensation insurance as required by North Carolina law, and automobile liability coverage with $1,000,000 combined single limits are required. The contractor must maintain a 120-minute maximum response time from their closest office to the project site and comply with E-Verify requirements. All bidders must be properly licensed under North Carolina state law, and the owner reserves the right to award to the lowest responsive and responsible bidder or reject any or all bids.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Construction Documents
Project Manual
Lee County
Jail/Courthouse Waste Pipe Replacement Phase II
Bid Number: 4262-02-27
Dewberry Project #: 50164439
November 6, 2026
ELECTRONIC BID SUBMISSIONS
WILL NOT BE CONSIDERED
SUBMITTED TO:
Lee County Government Ryan Faulk General Services Director 805 South Fifth Street Sanford, NC 27330 919.718.4622
SUBMITTED B Y :
Dewberry Engineers Inc.
2610 Wycliff Road Suite 410 Raleigh, NC 27601 NC License No.: F-0929 919.881.9939
Docusign Envelope ID: C8049794-8E73-884D-835E-4C0EA9AC8EEB
Dewberry Engineers Inc. Table of Contents Lee County Jail/Courthouse Waste Pipe Replacement Phase II 00 01 02 - 1
DEI# 50195182
TABLE OF CONTENTS
Division 00 – Procurement and Contracting Requirements
00 01 07 Seals Page 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 41 13 Bid Form 00 43 13 Bid Bond Form 00 52 13 Standard Form of Agreement 00 54 13 General Conditions of the Contract for Construction Exhibit A Dispute Resolution 00 61 13 Performance and Payment Bond Forms 00 62 43 Sexual Offender Registry Check Certification Form 00 62 76.13 State/County Sales/Use Tax Forms 00 63 55 Change Proposal Form 00 65 36 Contractor’s Warranty 00 65 37 Asbestos Free Warranty
Division 01 – General Requirements
01 10 00 Summary of Work 01 21 00 Allowances 01 22 00 Unit Prices 01 23 00 Alternate Bid Items 01 25 00 Substitution Procedures 01 26 00 Contract Modification Procedures 01 29 00 Payment Procedures 01 31 00 Project Management and Coordination 01 32 00 Construction Progress Documentation 01 33 00 Submittal Procedures 01 40 00 Quality Procedures 01 50 00 Temporary Facilities and Controls 01 60 00 Product Requirements 01 73 00 Execution 01 74 00 Warranties 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures 01 78 39 Project Record Documents 01 79 00 Demonstration and Training
Division 03 – Concrete
03 30 00 Cast-in-Place Concrete
Dewberry Engineers Inc. Table of Contents Lee County Jail/Courthouse Waste Pipe Replacement Phase II 00 01 02 - 2
Division 22 – Plumbing 22 01 00 Plumbing General Requirements 22 01 05 Plumbing Submittal Requirements 22 05 23 Plumbing Piping Valves 22 05 29 Plumbing Hangers and Supports 22 05 32 Plumbing Firestopping 22 07 19 Plumbing Insulation 22 11 16 Domestic Water Piping 22 13 16 Sanitary Waste and Vent Piping 22 13 19 Sanitary Waste and Vent Piping Specialties 22 13 23 Sanitary Waste Interceptors 22 40 00 Commercial Plumbing Fixtures
Dewberry Engineers Inc. Seals Page Lee County Jail/Courthouse Waste Pipe Replacement Phase II 00 01 07 - 1
SECTION 00 01 07 – SEALS PAGE
1.1 DESIGN PROFESSIONALS OF RECORD
STRUCTURAL
ENGINEER
Andrew R. Pacifico North Carolina Professional Engineer License # 054437
PLUMBING
ENGINEER
Christopher Cain Cook North Carolina Professional Engineer License # 039771
END OF SECTION 00 01 07
11/5/2026
11/5/2026
Dewberry Engineers Inc. Advertisement for Bids Lee County Jail/Courthouse Waste Pipe Replacement Phase II 00 11 13 - 1
SECTION 00 11 13
ADVERTISEMENT FOR BIDS
PROJECT INFORMATION
Project Name: Lee County Jail/Courthouse Waste Pipe Replacement Phase II Bid Number: 4262-02-27 Project Address: 1400 S. Horner Blvd., Sanford, NC 27330 Owner: Lee County Government of North Carolina
BIDS
Sealed bids for the project will be received from bidders by the Owner at 115 Chatham Street, Suite 301, Sanford, NC 27330 until 2:00 PM on January 7, 2027, at which time they will be opened and read.
Please note that, as stated in Section 00 21 13 Instruction to Bidders, two complete bid packages must be submitted – if only one bid package is submitted the bid will be rejected. Both bid packages may be in one sealed envelope. Indicate bid number 4262-02-27 on the outside of the envelope(s).
PROJECT DOCUMENTS
Electronic project documents may be obtained from the Engineer, Dewberry Engineers, 2610 Wycliff Road, Suite 410, Raleigh, NC 27607, at no cost.
Please contact Bill Hamilton with Dewberry Engineers at whamilton@dewberry.com or 984.833.4832
BIDDING REQUIREMENTS
All bidders are hereby notified that they shall be properly licensed under the state laws governing their trades.
Refer to Section 00 21 13 "Instructions to Bidders" for bid security and bonding requirements.
Submit questions to Dewberry Engineers in writing to the email address listed above no later than seven (7) days prior to the opening of bids.
PRE-BID MEETING
A Pre-Bid Meeting will be held at 10:00 AM on December 10, 2026 at 1400 S. Horner Blvd., Sanford, NC 27330, meeting in the brick courtyard between the jail and courthouse buildings.
Attendance in-person is mandatory.
END OF SECTION
Dewberry Engineers Inc. Instructions to Bidders Lee County Jail/Courthouse Waste Pipe Replacement Phase II 00 21 13 - 1
SECTION 00 21 13
INSTRUCTIONS TO BIDDERS
DEFINITIONS
A. The Bidding Documents consist of the Advertisement or Invitation to Bid, Instructions to Bidders, Bid Form, and other sample bidding and contract forms.
B. The proposed Contract Documents consist of the Form of Agreement between the Owner and Contractor, Conditions of the Contract (General, Supplementary, and other Conditions), Drawings, Specifications and Addenda issued prior to execution of the Contract.
C. Definitions set forth in Section 00 54 13 "General Conditions of the Contract" for Construction or in other Contract Documents are applicable to the Bidding Documents.
D. Addenda are written or graphic instruments issued by the Engineer prior to the execution of the Contract which modify or interpret the Bidding Documents by additions, deletions, clarifications, or corrections.
E. A Bid is a complete and properly executed proposal to do the Work for the sums stipulated therein, submitted in accordance with the Bidding Documents.
F. The Base Bid is the sum stated in the Bid for which the Bidder offers to perform the Work described in the Bidding Documents as the base, to which Work may be added or from which Work may be deleted for sums stated in Alternate Bids.
G. A Bidder is a person or entity who submits a Bid and who meets the requirements set forth in the Bidding Documents.
BIDS
A. Submit Section 00 41 13 "Bid Form" along with required enclosures in a sealed envelope, with the Bidder's name, license number, and project name written on the outside; place this sealed envelope in another envelope and deliver to the Owner at the address specified in Section 00 11 13 "Advertisement for Bids". Please note that two complete bid packages must be submitted - if only one bid package is submitted the bid will be rejected. Both bid packages may be in one sealed envelope.
B. Bids will be received until the date and time specified in Section 00 11 13 "Advertisement for Bids", at which time they will be publicly opened and read.
C. Please note that, two complete bid packages must be submitted – if only one bid package is submitted the bid will be rejected. Both bid packages may be in one sealed envelope."
D. Fill in and sign the bid form correctly. Bids that show any omission, alterations of form, additions not called for, conditional Bids, or any irregularities of any kind may be rejected. If erasures are necessary and appear on the forms, each such erasure must be initialed by the person signing the proposal. Bid Bond shall be signed by the Bidder and notarized.
E. Bids that are non-responsive or fail to follow the Instructions to Bidders may be rejected.
Lee County Jail/Courthouse Waste Pipe Replacement Phase II 00 21 13 - 2
F. No bid may be withdrawn after receipt of Bids for a period of sixty (60) days.
ACCEPTANCE OF BID (AWARD)
A. It is the Owner's intention to award a contract for work under this project to the lowest responsive, responsible Bidder; however, in the interest of suitability to the Owner's need and/or economy, equipment, materials and furnishings other than the lowest in price may be selected.
B. The Owner reserves the right to reject any or all Bids, to accept any bid submitted, to waive any formalities, and to negotiate with the low Bidder or Bidders any changes considered necessary or desirable. The Owner reserves the right to reject any Bid when such rejection is in the interest of the Owner to reject the bid of the bidder who has previously failed to perform or to complete on time Contracts of a similar nature; and to reject the bid of a bidder who is not, in the opinion of the Engineer, in a position to perform the Contract.
C. The Owner shall have the right to accept Alternates in any order or combination, unless otherwise specifically provided in the Bidding Documents, and to determine the low Bidder on the basis of the sum of the Base Bid and Alternates accepted. Alternates may be accepted at any time during the bid holding period.
PRE-BID MEETING
A. Refer to Section 00 11 13 "Advertisement for Bids" for the date, time, and location of the mandatory Pre-Bid Meeting.
B. A Pre-Bid Meeting will be held for purposes of considering questions posed by Bidders. All interpretations and corrections to Contract Documents deriving from this meeting will be documented via Addendum.
DISQUALIFICATION
A. The Owner reserves the right to disqualify Bids, before or after opening, upon evidence of collusion with intent to defraud or commit other illegal practices upon the part of the Bidder.
CONTRACTOR'S LICENSE
A. All Bidders must have proper licenses for contractors as required by State Law. The Bidder's license number shall be listed on the bid form and on the outside of the inner sealed envelope in which the bid is submitted.
CONFLICT OF INTEREST
A. Bidders must disclose in writing with their bid the name of any owner, officer, director, or agent who is also an employee of the Owner.
B. Bidders must disclose in writing with their bid the name of any employee of the Owner who owns, directly or indirectly, an interest of five percent (5%) or more in the Bidder’s firm or any of its branches or subsidiaries.
Lee County Jail/Courthouse Waste Pipe Replacement Phase II 00 21 13 - 3
C. By submitting a bid, the Bidder certifies that there is no relationship between the Bidder and any person or entity which is, or gives the appearance of, a conflict of interest related to this project.
NON-DISCRIMINATION
A. The Bidder shall not discriminate against any individuals and will take proactive measures to assure compliance with all Federal and State requirements concerning fair employment, employment of people with disabilities, and concerning the treatment of all employees without regard to discrimination based upon age, race, color, religion, sex, national origin, or disability.
INTERPRETATION OF DRAWINGS AND SPECIFICATIONS
A. Examine Drawings and Specifications and all Addenda or other revisions thereto and thoroughly familiarize himself with the detailed requirements thereof prior to submitting a proposal.
B. Should a Bidder find discrepancies or ambiguities in, or omissions from the Specifications and Drawings bound herein, or should be in doubt as to their meaning, notify the Engineer in writing immediately. Engineer will issue an interpretation in the form of an addendum. This addendum will be forwarded to all Bidders of record.
C. Addenda will be issued no later than seven days prior to the date for receipt of Bids except an Addendum withdrawing the request for Bids or one which includes postponement of the date for receipt of Bids.
D. Act promptly and allow sufficient time for a reply to be provided before the date established for submission of Bids.
E. Acknowledge receipt of all addenda on the Bid Form.
F. No oral interpretations will be made to any Bidder as to the meaning or intent of the Contract Documents or be effective to modify any of the provisions of the Contract Documents.
SUBSTITUTIONS
A. References are made to certain specific products solely to denote the quality standard of the desired product and are not intended to restrict Bidders to a specific brand, make, manufacturer, or name. These products have been noted to assist in establishing material types and acceptable products. Equivalent products will be considered acceptable provided that the approval of the specific product has been given in writing by the Engineer.
B. Written requests for substitution of equivalent products from prime bidders will be considered if received by the Engineer ten (10) calendar days prior to the bid opening.
C. Identify the product or the fabrication or installation method to be replaced in each request.
Include related specification sections and drawing number.
D. Provide complete documentation on both the product specified and the proposed substitution
Lee County Jail/Courthouse Waste Pipe Replacement Phase II 00 21 13 - 4 including the following information as appropriate:
1. Comparison of specified and proposed substitute product data, fabrication drawings, and installation procedures.
2. Samples where applicable or requested.
3. Detailed comparison of significant qualities of the proposed substitution with those of the work specified.
4. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by the Owner and separate Contractors that will become necessary to accommodate the proposed substitution.
E. Certification by the Bidder or manufacturer that the substitution proposed is equal-to or better in every respect to that required by the Contract Documents, and that it will perform equal or superior to product specified in the application indicated. The Bidder waives any right to additional payment or time, which may subsequently become necessary because of the failure of the substitution to perform adequately.
F. Engineer's Action: The Engineer may request additional information or documentation necessary for evaluation of the request. The Engineer will notify the Bidders of acceptance of the proposed substitution by means of an addendum to the bid documents. If the proposed substitute is accepted through an addendum use the product specified by name. Engineer's Substitution Approval during bidding and subsequent addendums does not void the Bidder's responsibility to submit the required shop drawings and comply with the other contract documents and requirements.
SITE INVESTIGATION
A. Examine and thoroughly familiarize itself with existing conditions including applicable laws, ordinances, rules and regulations that will affect the work prior to submitting a proposal. Visit the site, examine the grounds and existing buildings, utilities and roads and ascertain by any reasonable means conditions that will in any manner affect its work. Ask the Engineer for any additional information that he deems necessary for it to be fully informed as to exactly what is to be expected prior to submitting a proposal. The drawings have been prepared on the basis of surveys and inspections of the site and physical conditions at the site. This, however, does not relieve the Bidder of the necessity for fully informing itself as to the existing physical conditions. Each shall carefully examine the existing conditions as compared to the Contract Documents.
B. Secure on-site measurements for quantities upon which proposal is based and has observe existing conditions and limitations.
BID SECURITY
A. In lieu thereof, each bid may be accompanied by a deposit of cash or a certified check drawn on a bank or trust company insured by the Federal Deposit Insurance Corporation in an amount equal to not less than five percent (5%) of the gross amount of the bid.
B. If the successful Bidder fails to execute the contract within 10 days after award, the above deposit will be retained by the Owner on the bid bond executed on liquidated damages.
Lee County Jail/Courthouse Waste Pipe Replacement Phase II 00 21 13 - 5
PERFORMANCE BOND AND LABOR AND MATERIALS PAYMENT BOND
A. A Performance Bond and Payment Bond in the amount of the contract is required. Include the cost of providing Performance Bond and Payment Bond in the Base Bid.
B. Deliver the required bonds to the Owner not later than three days following the date of execution of the Contract. If the Work is to be commenced prior thereto in response to a letter of intent, prior to commencement of the Work, submit evidence satisfactory to the Owner that such bonds will be furnished and delivered in accordance with this Section.
C. Unless otherwise provided, write bonds on the forms referenced in Section 00 61 13 "Performance and Payment Bond Forms". Write both bonds in the amount of the Contract Sum.
D. Date bonds on the date of the Contract.
E. Issued by sureties and executed by an attorney-in-fact, on behalf of the surety, who are authorized to do business in the State of North Carolina.
F. Affix thereto a certified and current copy of the power of attorney.
PRIME CONTRACT
A. Perform all work under the single prime contract.
PERMITS, FEES AND TAXES
A. Secure and pay the costs of licenses, permits and fees for inspections required by City, County and/or State authorities; Social Security and other applicable Local, State and Federal Government taxes, and sales taxes. Include such costs in its bid.
SUBCONTRACTORS
A. Names of subcontractors must be listed on Section 00 41 13 "Bid Form". The Bidder shall identify work by the general, subcontractor or not applicable for each trade; utilize parenthesis (_) blanks to list trades not provided in the table. Do not list suppliers. All blanks must be filled in. Failure to do so may result in bid being declared non-responsive. If there is more than one subcontractor per trade identified below, list all. If no subcontractors are to be utilized, indicate by signing at the appropriate place at the bottom of the table.
B. A Bidder whose bid is accepted shall not substitute any person as subcontractor in the place of the subcontractor listed in the original bid, except
1. if the listed subcontractor's bid is later determined by the successful Bidder to be nonresponsible or nonresponsive or the listed subcontractor refuses to enter into a contract for the complete performance of the bid work, or
2. with the approval of the awarding authority, the Owner, for good cause shown by the successful Bidder.
C. The terms, conditions, and requirements of each contract between the successful Bidder and a
Lee County Jail/Courthouse Waste Pipe Replacement Phase II 00 21 13 - 6 subcontractor performing work under a subdivision or branch of work listed in this subsection shall incorporate by reference the terms, conditions, and requirements of the contract between the contractor and the Owner.
FORM OF AGREEMENT
A. The form of agreement to be entered into shall be the sample contained in Section 00 52 13 "Standard Form of Agreement" between Owner and Contractor, as revised.
B. The form of agreement to be entered into is an Owner's Purchase Order.
CONTRACTOR QUALIFICATIONS
A. Bids will be accepted from Bidders who are regularly engaged in, and licensed to perform, the work they are bidding, which represents a significant portion of their total volume and who perform this work with workers regularly employed on their direct payrolls. Before a bid is considered for award, the Bidder may be requested by the Engineer to submit a statement of facts in detail as to its previous experience in performing similar or comparable work and of its business and technical organization and financial resources available to be used in contemplated work. The Bidder may also be required to submit a statement of facts in detail on his proposed subcontractors as to their previous experience and past performance in performing similar work or comparable work.
B. Bidders shall be required to submit with their bid the following:
1. Evidence that submitting firm can provide a 120 minutes response time from their closest office to the Project site. Response time is subject to Owner verification.
Dewberry Engineers Inc. Bid Form Lee County Jail/Courthouse Waste Pipe Replacement Phase II 00 41 13 - 1
SECTION 00 41 13
BID FORM
To: Lee County Government of North Carolina 115 Chatham Street, Suite 301, Sanford, NC 27330
Project: Lee County Jail/Courthouse Waste Pipe Replacement Phase II 1400 S. Horner Blvd, Sanford, NC 27330
Date:
Bidder:
Address:
Phone: Email:
North Carolina License No.:
Classification:
Limitation:
SCOPE OF WORK
Provide all necessary labor, material, equipment, supervision, etc. for waste pipe improvements within designated areas of the Lee County Jail/Courthouse building. Base bid includes removal and replacement of existing cast-iron waste and vent piping in inmate cell pods “A” and “B”, removal and replacement of existing cast-iron waste and vent piping in the common utility chase serving public fixtures in inmate cell pods “A” and “B”, and addition of a floor sink and lint interceptor in laundry room 1018. Alternate 1 includes removal and replacement of approximately sixteen (16) linear feet (to be verified by Contractor) of existing cast-iron waste piping below the ground floor slab in men's locker room 1035, replacement of two (2) existing tank toilets in men's locker room 1035 and one tank toilet in women's locker room 1058 with flush valve toilets, and providing new domestic water lines to the new toilets. Alternate 2 includes removal and replacement of approximately fifty (50) linear feet (to be verified by Contractor) of existing cast-iron waste piping below the ground floor slab between offices 1038 and 1061.
We are in receipt of Addendum __________1__________2__________3__________4_________5
The undersigned, as bidder, proposes and agrees if this bid is accepted to contract with Lee County Government through the furnishing of all materials, equipment, and labor necessary to complete the construction of the work described in these documents in full and complete accordance with plans, specifications, and contract documents, and to the full and entire satisfaction of Lee County Government for the sum of:
BASE BID:
Lee County Jail/Courthouse Waste Pipe Replacement Phase II 00 41 13 - 2
Alternate # Description Add or Deduct
(to Base Bid) Alternate Bid Price (Enter $ Value)
Accepted (OWNER
INITIALS INDICATES
ACCEPTANCE OF
ALTERNATE)
Alternate No. 1: Sheriff’s Office Men’s Locker Room
Alternate No. 2: Sheriff’s Office Admin, Lobby, Offices, and Men’s/Women’s Toilet Rooms
ALLOWANCES: $30,000.00 (Lump Sum) allowance for unforeseen conditions.
UNIT PRICES:
Unit Price No. 1: Remove and replace non-load bearing interior partition walls.
Unit Price ($) /SF
SCHEDULE OF COMPLETION:
The undersigned understands that time is of the essence and agrees to the Contract Time and liquidated damages as indicated in General Conditions of the Contract for Construction and Supplementary Conditions apply to this Work. The undersigned hereby agrees to commence work on this project within fourteen (14) days following receipt of an Executed Agreement between Owner and Contractor. Date of commencement will be established in a Notice to Proceed issued to Contractor.
Work under the Base Bid shall be completed within 120 calendar days from the date of commencement.
Work in cell pods “A” and “B” which requires the pods to be vacated by inmates shall be completed in no more than 30 calendar days per cell pod. At no time shall work requiring inmates to vacate cell pods “A” and “B” occur concurrently.
Work under Alternate 1 shall extend the Base Bid project schedule by 15 calendar days from the date of commencement.
Work under Alternate 2 shall extend the Alternate 1 project schedule by 30 calendar days from the date of commencement.
Applicable liquidated damages shall be stated in the contract agreement and general conditions.
SUBCONTRACTORS:
If subcontractors are to be utilized, the Bidder shall fill out all blanks on the list below. All subcontractors shall be listed. The Bidder shall identify work by the general, subcontractor or not applicable for each trade;
utilize parenthesis (_) to list trades not provided. Do not list suppliers. All blanks must be filled in. Failure to do so may result in bid being declared non-responsive. If there is more than one subcontractor per trade
Lee County Jail/Courthouse Waste Pipe Replacement Phase II 00 41 13 - 3 identified below, list all. If no subcontractors are to be utilized, indicate by signing at the appropriate place at the bottom of the table.
Trade Company License # General ( )
Waste Disposal
Utility Locate
Other ( )
Other ( )
We do not plan to use subcontract forces
ENCLOSURES:
Provide the following enclosures with submitted bid:
A. Bid Bond
B. Section 00 52 13 “Standard Form of Agreement”
Lee County Jail/Courthouse Waste Pipe Replacement Phase II 00 41 13 - 4
Respectfully submitted this day of , .
Company:
Printed Name:
Signature:
Title:
(State)
County of
I, , a Notary Public for County, (State), do hereby certify that personally appeared before me this day and acknowledged the due execution of the foregoing instrument.
Witness my hand and official seal, this day of , 20 .
(OFFICIAL SEAL)
Notary Public
My commission expires , 20 .
Dewberry Engineers Inc. Bid Bond Form Lee County Jail/Courthouse Waste Pipe Replacement Phase II 00 43 13 - 1
BID BOND
KNOW ALL MEN BY THESE PRESENTS, That we, (Bidder's Name)
,of (Street Address) (City, State, Zip) hereinafter called the Principal, and
(Surety's Name) a corporation organized and existing under the Laws of the State of ____________________, and authorized to transact business in the State of North Carolina, as Surety, hereinafter called Surety, are held and firmly bound unto Lee County Government, as Owner, hereinafter called Obligee, in the Penal sum of five percent (5%) of the amount bid, good and lawful money of the United States of America, for the payment of which the Principal and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents. This bid bond is submitted in lieu of submitting cash, a cashier’s check, or a certified check pursuant to G.S.143-129.
The Condition of this Obligation is such, that, WHEREAS the Principal has submitted a proposal to the Obligee on a contract for the construction of (Contract Name and Number)
NOW THEREFORE, if the Obligee shall accept the bid of the Principal and the Principal shall enter into a contract with the Obligee in accordance with the terms of such bid, and give such bond or bonds as may be specified in the Bidding or Contract Documents with good and sufficient surety for the faithful performance of such construction for the prompt payment of labor and material furnished in the prosecution thereof, or in the event of the failure of the Principal to enter such contract and give such bond or bonds, if the Principal shall pay to the Obligee the difference not to exceed the penalty hereof between the amount specified in said bid and such larger amount for which the Obligee may in good faith contract with another party to perform the Work covered by said bid, then this obligation shall be null and void; otherwise to remain in full force and effect.
Dewberry Engineers Inc. Bid Bond Form Lee County Jail/Courthouse Waste Pipe Replacement Phase II 00 43 13 - 2
In witness whereof, we have hereunto set our signatures and seal this __________ day of ___________________, 20______, all pursuant to due authorization.
(Seal) Principal
Surety
Attorney-in-Fact in accordance with the attached Power of Attorney
STATE OF )
) ss:
COUNTY OF )
I, ____________________________, a Notary Public in and for the State and County aforesaid, do hereby certify that _________________________________, and
____________________________, whose names are signed to the foregoing bond, this day personally appeared before me in my State and County aforesaid and acknowledged the same.
Given under my hand and seal this ____________ day of ______________, 20______.
Notary Public
My Commission expires:
End of Section B-2
Contract Agreement Between and Lee County Government
THIS AGREEMENT, made the day of month 202 by and between . (hereinafter referred to as the “Contractor”) and Lee County Government (hereinafter referred to as the “Owner”) agree as follows:
1. Scope of Work: The Contractor shall furnish and deliver all of the materials, and perform all of the work in the manner and form as provided by the enumerated plans, specifications and documents, which are attached hereto and made a part thereof as if fully contained herein: advertisement, Instructions to Bidders, General Conditions, Supplementary General Conditions, specifications, accepted proposals, contract, performance bond, payment bond, power of attorney, worker’s compensation, public liability, Exhibit A – Lee County Dispute Resolution Policy, any and all addendums, and all drawings.
2. The Contractor shall commence work to be performed under this agreement on a date to be specified in a written order of the Owner and shall fully complete all work hereunder within consecutive calendar days from said date. For each day in excess thereof, liquidated damages shall be $1,000.00 per day. The Contractor, as one of the considerations for the awarding of this contract, shall furnish to the Owner a construction schedule setting forth the project broken down by various divisions of the work and by the calendar days, as described in the General Conditions.
3. The Owner agrees to pay to the Contractor for the faithful performance of this agreement, subject to additions and deductions as provided in the specifications or proposal, in lawful money in the amount of $ .
4. Alternates. Alternates, if any, included in the Contract Sum are as follows:
Item Price
Alternate Bid Item No. 1 $
Sheriff’s office men’s locker room.
Alternate Bid Item No. 2 $ Sheriff’s office admin, lobby, offices, and men’s/women’s toilet rooms.
5. Allowances. Allowances, if any, included in the Contract Sum are as follows:
Base bid shall include a Lump Sum allowance of $30,000.00 to be used for unforeseen conditions as directed by Lee County. Unused allowance shall be returned to the Owner at the end of the project.
6. Unit Prices. Unit prices, if any, are as follows:
Unit Price No. 1: Remove and replace non-load bearing interior partition walls.
Unit Price ($) /SF
7. Liquidated Damages. Liquidated damages will be $1,000.00 per day, after the date specified for substantial completion.
8. Binding Dispute Resolution. For any claim subject to, but not resolved by mediation, the method of binding dispute resolution shall be litigation in a court of competent jurisdiction.
9. The Owner’s Representative is:
Lisa Minter, County Manager 408 Summit Drive Sanford, NC 27330 lminter@leecountync.gov
The Contractor’s Representative is:
10. It if further mutually agreed between the Parties that if at any time after the execution of this agreement and the surety bonds hereto attached for its faithful performance, the Owner shall deem the surety or sureties upon such bonds to be unsatisfactory, or if, for any reason, such bonds cease to be adequate to cover the performance of the Work, the Contractor, at its own expense, within five (5) days after the receipt of notice from the Owner so to do, furnish an additional bond or bonds in such form and amount, and with such surety or sureties as shall be satisfactory to the Owner. In such event, no further payment to the Contractor shall be deemed to be due under this agreement, until such new or additional security for the faithful performance of the Work shall be furnished in a manner and form satisfactory to the Owner.
11. Compliance with E-Verify requirements: The Contractor and any of its subcontractors must comply with the requirements of Article 2 of Chapter 64 of the North Carolina General Statutes, if applicable, which requires certain employers to verify the work authorization of each newly hired employee through the federal E-Verify program operated by the United States Department of Homeland Security and other federal agencies.
12. Divestment from companies that boycott Israel: Contractor certifies that (a) it is not identified on the Israel Boycott List or any other list created by the NC State Treasurer pursuant to N.C.G.S. 147—86.80 et al and (b) it will not take any action causing it to appear on any such list during the term of the contract agreement.
13. Iran Divestment Act Certification. The Contractor certifies that the Contractor is not listed on the Final Divestment List created by the State Treasurer pursuant to N.C.G.S.
147-86.58 (the Final Divestment List) and the Contractor will not utilize any subcontractors performing work under this Contract which is listed on the Final Divestment List. The Final Divestment List can be found on the State Treasurer’s website at the address and should be updated every 180 days.
14. Non-Discrimination in Employment. The Contractor will not discriminate again any employee or applicant for employment because of age, sex, race, creed, national origin or disability. In the event Contractor is determined by the final order of an appropriate agency or court to be in violation of this provision or any non-discrimination provision of federal, state or local law, this Contract may be suspended or terminated, in whole or in part by the County. In addition, the Contractor may be declared ineligible for further contracts with the County.
15. Drug-Free Workplace. During the performance of this agreement, the Contractor agrees to (i) provide a drug-free workplace for its employees; (ii) post in conspicuous places, available to employees and applicants for employment, a statement notifying employees of the unlawful manufacture, sale, distribution, dispensation, possession, or use of a controlled substance or marijuana is prohibited in its workplace and specifying the actions that will be taken against employees for violations of such prohibitions, (iii) state in all solicitations or advertisements for employees placed by or on its behalf that it maintains a drug-free workplace; (iv) include the provisions of the foregoing clauses in every subcontract or purchase order of over $10,000.00 so that the provisions will be binding upon each subcontractor or vendor.
16. Non-Appropriation Clause. Contractor acknowledges that Lee County is a governmental entity, and the contract validity is based upon the availability of public funding under the authority of its statutory mandate. In the event that public funds are unavailable and not appropriated for the performance of Lee County’s obligations under this contract, then this contract shall automatically expire without penalty to Lee County thirty (30) days after written notice to Contractor of the unavailability and non-appropriation of public funds. It is expressly agreed that Lee County shall not activate this non-appropriation provision for its convenience or to circumvent the requirements of this contract, but only as an emergency fiscal measure during a substantial fiscal crisis, which affects generally its governmental operations. In the event of a change in the Lee County’s statutory authority, mandate and mandated functions, by state and federal legislative or regulatory action, which adversely affects Lee County’s authority to continue its obligations under this contract, then this contract shall automatically terminate without penalty to Lee County upon written notice to Contractor of such limitation or change in Lee County’s legal authority.
17. No Pledge of Taxing Authority. No deficiency judgment may be rendered against Lee County or any agency of Lee County in any action for breach of a contractual obligation under this contract. The taxing power of the Lee County is not pledged directly or indirectly to secure any monies due under this contract.
18. Gov Ops. Contractor acknowledges that by contracting with Lee County and receiving public funds, they may be subject to potential examination, evaluation and investigation, including access to buildings and documents and compelled testimony, by the Joint Legislative Commission on Governmental Operations under Section 27.10(b) of North Carolina S.L. 2023-134. Contractor acknowledges that Lee County has no control over the Commission and its activities.
19. This agreement becomes effective upon the last signature of both parties.
IN WITNESS WHEREOF, the Parties hereto have executed this agreement on this the day of , .
CONTRACTOR / FIRM
By:
Witness:
Date: _
LEE COUNTY GOVERNMENT
By:
Witness:
Date: _
Initial Here:
GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION
Table of Contents
ARTICLE 1. DEFINITIONS
ARTICLE 2. CORRELATION, INTERPRETATION AND INTENT OF CONTRACT
DOCUMENTS
ARTICLE 3. FAMILIARITY WITH WORK, CONDITIONS AND LAWS
ARTICLE 4. BONDS
ARTICLE 5. INSURANCE AND INDEMNITY
ARTICLE 6. OTHER DOCUMENTS AND SUBMITTALS
ARTICLE 7. CONTRACTOR
ARTICLE 8. OWNER
ARTICLE 9. CONSTRUCTION MANAGER
ARTICLE 10. DESIGNER
ARTICLE 11. CONTRACT TIME
ARTICLE 12. CHANGES IN THE WORK
ARTICLE 13. CHANGE OF THE CONTRACT PRICE
ARTICLE 14. UNFORESEEN CONDITIONS
ARTICLE 15. CORRECTION OF WORK BEFORE FINAL PAYMENT
ARTICLE 16. CORRECTION OF WORK AFTER SUBSTANTIAL COMPLETION;
WARRANTIES AND GUARANTIES
ARTICLE 17. OWNER’S RIGHT TO DO WORK
ARTICLE 18. PARTIAL PAYMENTS
ARTICLE 19. FINAL PAYMENT
ARTICLE 20. CONTRACTOR, SUBCONTRACTOR AND SUPPLIER AFFIDAVIT
ARTICLE 21. ASSIGNMENTS AND SUBCONTRACTS
ARTICLE 22. MEASUREMENTS
ARTICLE 23. CONTRACTOR AND SUBCONTRACTOR RELATIONSHIPS
ARTICLE 24. USE OF PREMISES
ARTICLE 25. DISPUTE RESOLUTION
ARTICLE 26. TAXES
ARTICLE 27. OPERATION OF OWNER’S FACILITIES
ARTICLE 29. TERMINATION OR SUSPENSION BY THE OWNER FOR CAUSE
ARTICLE 29. TERMINATION OR SUSPENSION BY THE OWNER FOR CONVENIENCE
ARTICLE 1. DEFINITIONS
1.1 Agreement- the Contract Agreement, these general conditions, and any supplementary conditions, advertisement, instructions to bidders, specifications, drawings, bonds, addendums, drawings.
1.2 Beneficial Occupancy- the point at which the Project can be occupied by the Owner for its intended purpose, upon achievement of Substantial Completion, as defined in 1.35.
1.3 Change Order- a written order to the Contractor signed by the Owner and the Designer authorizing an addition, deletion, or revision in the Work and/or an adjustment in the Contract Price and/or the Contract Time issued after execution of the Contract Agreement.
1.4 Completion Date- those dates identified as completion dates in the Contract Construction
Schedule or elsewhere in the Contract Documents.
1.5 Contract Agreement- the document executed by the Contractor and Owner to formally memorialize their consent to the terms of the Agreement.
1.6 Construction Change Directive- a written order to the Contractor signed by the Owner and the Designer directing an addition, deletion, or revision in the Work after execution of the Contract Agreement, in circumstances when the parties have been unable to agree on an adjustment to the Contract Price or the Contract Time, but the Owner requests that the Contractor proceed with said Work subject to adjustment of the Contract Price and/or Contract Time under the procedures described herein.
1.7 Construction Manager- the person or firm designated as the Construction Manger in the
Contract Documents, or their authorized representatives. The Construction Manager, as referred to herein, will be referred to hereinafter as if each were of the singular number, masculine gender.
1.8 Contract Construction Schedule- that schedule identified as the Contract Construction
Schedule.
1.9 Contract Documents- all of the documents that make up the Agreement, plus the Drawings and Specifications that describe the scope of the work, plus allowable modifications to the contract documents.
1.10 Contract Price- the total monies payable to the Contractor under the Contract Documents.
1.11 Contract Time- the number of calendar days stated in, or computed from, the Contract Documents for the completion of the Work, or any portion thereof. Time of completion is of the essence. The time used and referred to on the Project will be that time which is observed in Sanford, Lee County, North Carolina, being Eastern Daylight Savings Time, Eastern Standard Time, or other as designated by the Designer.
1.12 Contractor- the Contractor shall be that party identified in the Agreement.
1.13 Days- unless otherwise indicated, the term “days” shall mean consecutive calendar days.
1.14 Daylight Hours- the hours or portion of hours between sunrise and sunset local time.
1.15 Designer- the person or firm designated as the Designer, in the Contract Documents, or their authorized representatives. The Designer(s), as referred to herein, shall mean architect, landscape architect, and/or engineer. They will be referred to hereinafter as if each were of the singular number, masculine gender.
1.16 Drawings- the drawings are the graphic and pictorial portions of the Contract Documents, wherever located and whenever issued, showing the design, location, and dimensions of the Work, and generally including plans, elevations, sections, details, schedules and diagrams. A list of the Drawings is contained in the Supplemental General Conditions.
1.17 Field Order- a written order issued by the Designer which clarifies or interprets the
Contract Documents or orders minor changes in the Work in accordance with the Contract Documents.
1.18 Final Completion- the point at which the Contractor has, as determined by the Designer, completed the Work, with the exception of guaranty and warranty obligations, and becomes entitled, upon the recommendation of the Designer and determination by the Owner, to final payment.
1.19 Liquidated Damages- An amount, as stated in the Contract Agreement, reasonably estimated in advance to cover the consequential damages associated with the Owner’s economic loss in not being able to use the Project for its intended purposes at the end of the contract’s completion date as amended by change order, if any, by reason of failure of the contractor(s) to complete the work within the time specified.
1.20 Modification- a written amendment to the Contract Documents signed by the Owner and the Contractor and identified therein as such, or a Change Order, or a Construction Change Directive, or a Field Order.
1.21 Notice to Proceed- see Article 11.3.
1.22 Owner- the Owner is the person designated as such in the Agreement.
1.23 Owner’s Authorized Representative- a person or persons, employed by the Owner and designated from time to time by written notice to the Contractor to administer the Contract Documents, and to observe and monitor the Work on behalf of the Owner with authority and responsibility as herein specified.
1.24 Notice- the term “notice” or “written notice” as used herein shall mean and include all written notices, demands, instructions and claims, approvals and disapprovals furnished by the Owner or the Designer to obtain compliance with the requirements of the Contract Documents as well as all written notices, demands, instructions and claims furnished by the Contractor as required by the Contract Documents. Where notice is required under the terms of the Contract Documents, written notice shall always be required, and oral or “constructive” notice shall be insufficient and ineffective as notice unless specifically allowed by the Supplementary Conditions or a Modification to the Agreement. Written notice shall be deemed to have been duly served on the date that it is delivered in person to the individual or to a member of the firm, to an officer of the corporation for whom it is intended, to an authorized representative of such individual, firm, or corporation, or on the date that it is mailed by registered or certified mail, return receipt requested, addressed to the last business address of such individual, firm, or corporation. Written notice may also be given by facsimile transmission, provided that proof of delivery is obtained. In the case of delivery in person, such delivery shall not be effective unless and until a written and signed receipt showing the date and time of deliver is obtained.
1.25 Project- the total construction of which the Work performed under the Contract
Documents may be the whole or a part.
1.26 Project Expediter- As used herein, is an entity stated in the Contract Documents, designated to effectively facilitate scheduling and coordination of Work activities. For the purpose of a single prime contract, the single prime contractor is designated as the Project Expediter.
1.27 Project Manager- that person designated by the Contractor who shall be in general charge of the Work and its performance.
1.28 Request for Information- a written communication from the Contractor to the Designer for any interpretation of, or information needed, required, or desired under the Contract Documents. The Owner reserves the right to determine the reasonable format and contents required for a Request for Information. In any Request for Information, the Contractor shall state a reasonable date by which a response is necessary in order to avoid delay in progress of the Work and shall make such request sufficiently in advance of such date as to avoid any such delay.
1.29 Request for Payment- document approved by Owner, which is to be used by the
Contractor in requesting progress payments and which is to include a Schedule of Values as required by the Contract Documents and an affidavit of the Contractor that progress payments theretofore received from the Owner on account of the Work have been applied by the Contractor to discharge in full all the Contractor's obligations incurred in connection with Work covered by all prior applications for payment.
1.30 Superintendent- that person designated by the Contractor who has day-to-day responsibility for the prosecution of the Work and the obtaining of proper materials and equipment, and adequate labor.
1.31 Schedule of Values- any breakdown of the Contract Price which may be required by the
Contract Documents and designated as such.
1.32 Specifications- the portion of the Contract Documents consisting generally of the written requirements for materials, equipment, construction systems, standards, and workmanship for the Work and performance of related services.
1.33 Subcontractor- a person, firm, or corporation who has entered into a direct contract with the Contractor to perform any of the Work of the Project.
1.34 Submittal- shop drawings, product data, samples, and other documents required by the Contract Documents to be submitted by the Contractor to the Designer.
1.35 Substantial Completion- the point at which the Work, and Work by other Contractors on or in connection with the Project, as determined by the Designer, is sufficiently complete in accordance with the Contract Documents that it can be beneficially occupied by the Owner, and the Work can be utilized by the Owner for its intended use, and all necessary permits and permissions for Beneficial Occupancy and utilization having been obtained by the Contractor. All operations and maintenance manuals, Owner training, and as-built drawings must be submitted prior to Substantial Completion being achieved.
1.36 Work- the construction and services required by the Contract Documents, including all labor, materials, equipment, and services provided or to be provided by the Contractor to fulfill the Contractor’s obligations.
ARTICLE 2. CORRELATION, INTERPRETATION AND INTENT OF CONTRACT
DOCUMENTS
2.1 It is the intent of the Specifications and Drawings and other Contract Documents to describe a complete Project in accordance with the Contract Documents.
2.2 The Contract Documents are complementary; what is called for by one is as binding as if called for by all. If the Contractor finds a conflict, error or discrepancy in the Contract Documents, the Contractor shall notify the Designer in writing before proceeding with the Work affected thereby. In resolving such conflicts, errors and discrepancies, the Contract Documents shall be given preference in the following order: Contract Agreement, Modifications, Addenda, Supplemental Conditions, General Conditions, Specifications, and Drawings. Figure dimensions on Drawings shall govern over scale dimensions, and detailed Drawings shall govern over general Drawings. Any Work that may reasonably be inferred from the Contract Documents as being required to produce the intended result shall be supplied whether or not it is specifically called for. Work, materials or equipment described in words which, so applied, have a well known technical trade meaning shall be deemed to refer to such meaning and to incorporate any recognized standards which are a part of such meaning.
2.3 Miscellaneous items, accessories and work which are not specifically mentioned, but which are essential to produce a complete and properly operating installation, or useable structure or plant providing the indicated function shall be furnished and installed without change in the Contract Price. Such miscellaneous items and accessories shall be of the same quality standards, including material, style, finish, strength, class, weight and other applicable characteristics, as specified for the major component of which the miscellaneous item or accessory is an essential part, and shall be approved by the Designer before installation. This requirement is not intended to include major components not covered by or inferable from the Contract Documents.
2.4 The Work of all trades under the Contract Documents shall be coordinated by the Contractor in such a manner as to obtain the best workmanship possible for the entire Project and all components of the Work shall be installed or erected in accordance with the best practices of the particular trade.
2.5 The Contractor shall fully complete the Work and shall be responsible for all of the Work under the Contract Documents to which the Construction Agreement applies. If the Contractor is prevented from doing so by any limitation of the Contract Documents, the Contractor shall immediately give notice thereof to the Designer and the Owner in writing before proceeding with the construction in the area where the problem or limitation exists.
2.6 Standard specifications or manufacturers' literature, when referenced, shall be of the latest revision or printing unless otherwise stated and is intended to establish…