This is a Justification and Approval (J&A) enclosure document that identifies the specific repair and maintenance work items required for the USS EMORY S. LAND during a Regularly Scheduled Overhaul and Modernization (ROH) in Fiscal Year 2026. The document lists 26 distinct work packages numbered from 006 through 088, encompassing comprehensive shipboard repairs across multiple systems and structural components. The work includes critical mechanical systems repairs such as circulation pump and motor repair, chill water pump motor crating, and boiler stack cleaning and inspection; piping system replacements including firemain valves, fuel piping risers, shore steam dick riser piping, and fuel oil pipes; structural steel repairs to ship components including deck repairs, stiffener repairs, laundry steel repair, and waterside sill and stiffeners; and various preservation and replacement work on ventilation systems, plumbing, fixed handrails, and echo sounder water heater equipment.
The associated federal contract opportunity is solicitation N3220526C1223P00006 issued by the Department of the Navy Military Sealift Command, which represents a limited or sole source justification procurement. The contract was awarded on February 13, 2026, to an unknown vendor for an undetermined amount. This J&A enclosure serves as the supporting documentation justifying the specific scope of work and requirements for this overhaul and modernization initiative for the USS EMORY S. LAND.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N10426C1223P00006_Redacted.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P00006
| Enclosure to J&A No. N10426C1232P00002 | |
| CCO | WI |
| 001 | WI 0031 |
| 006 | WI 538 - NR3 SSTG Circulation Pump and Motor Repair |
| 012 | WI 0035 - Damage Control Locker |
| 047 | Chill Water Pump Motor Crating |
| 053 | Mooring Station No. 5 and No.6 Repair |
| 054 | Mooring Station Number One Repair (CoC 788) |
| 055 | Boiler Stacks and Combustion Intake Clean and Inspect |
| 056 | AS-CCSI-AC MOTOR AND VENT FAN REWIND |
| 057 | Firemain Valves Replace |
| 058 | Fuel Piping Riser Replace |
| 059 | Shore Steam Dick Riser Piping |
| 060 | Fuel Oil Pipe Replace |
| 074 | Vent Plenum and BHD Repair |
| 075 | WTD SILL AND STIFFENERS REPAIR |
| 076 | SHIPS LAUNDRY STEEL REPAIR |
| 077 | J-BAR AND DAVIT REPAIR |
| 078 | PASSAGE WAY DECK REPAIR |
| 079 | 02 LEVEL PORT DECK REPAIRS |
| 080 | PASSAGE WAY DECK REPAIR |
| 081 | UNDER DECK STIFFENER |
| 082 | FAN ROOM PRESERVATION |
| 083 | VENT PIPE AND PLUMBING REPLACE |
| 084 | FIXED HANDRAIL REPLACE |
| 088 | ECHO SOUNDER WATER HEATER PRESERVATION |