This document is a proposed progress schedule template for the National Technology and Development Program fence project being carried out by the USDA Forest Service Region 2 in San Dimas, California under solicitation number 12970223Q0075. The template outlines a schedule for 30% completion increments on an unspecified number of fence squares to be constructed over a determined number of contract days. The contractor is required to complete the contract time block with the total number of days and days per square. Progress will then be charted at 20%, 40%, 60%, 80% and 100% completion against the proposed schedule and actual progress must be reported to the Contracting Officer's Representative if it falls behind. The schedule is submitted by the contractor and subject to approval by the Contracting Officer's Representative and Contracting Officer.

Text of this file

USDA Forest Service R2-FS-6300-7 (Rev 2/81)) MS Word 2000

PROPOSED PROGRESS SCHEDULE

PROJECT

National Technology and Development Program (NTDP) San Dimas, CA Fence Project

UNIT

NTDP (San Dimas)

CONTRACT NO.

CONTRACT TIME

Compute Time Per Square as follows:

Total Time ( ) days = ( ) days per square Item of Work

% Completion Days Contract Time

INSTRUCTIONS

SUBMITTED BY:

REVIEWED AND APPROVED:

CONTRACTOR

1 Complete CONTRACT TIM block above to determine days per square

2 Insert contract days in brackets at 20%, 40%, etc.

3 Show line through each square for work planned. Please do not block in solid.

4. Submit ONE copy to C.O.R.

Contractor Contracting Officer’s Representative

Date C.O.R.

REVIEWED

1 Approve schedule or submit to C.O. with comments

2 Chart actual progress against proposed progress

3 Advise C.O. when progress falls behind By

4 Distribute as follows: Original to C.O. copies to Contractor, C.O.R. Forest

Date Contracting Officer

Date

GPO 830-257

Other files for this federal contract opportunity

Other files attached to NTDP (San Dimas) Fence Project, newest first.
File Type Posted
J2_Appendix A- Scope of Work.pdf PDF
J5_Project Map.pdf PDF
12970223Q0075.pdf PDF
J4_Appendix C- Standard Plans.pdf PDF
J9_DesignationofReps.doc DOC document
J10_BiobasedStatementLetter.docx DOCX document
J1_Statement of Work.docx DOCX document
J3_Appendix B- Alternate Scope of Work.pdf PDF
J6_Davis-Bacon Act WD CA20230022.pdf PDF
J7_Schedule of Items.xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .