This statement of work outlines site improvement requirements for the Monongahela National Forest Fenwick Storage Area. The USDA Forest Service seeks a contractor to provide and install wooden utility poles with light fixtures, electrical circuits and outlets, a steel tube gate, chain link fencing and gate, and optional additional stone at the site. The contractor must be a licensed electrician to complete electrical work. Deliverables include mobilization, installation of the steel tube gate, chain link fencing and gate, outdoor lighting and outlets, and lock upgrades. An optional item to provide additional stone is also included. All work must be completed by the period of performance end date in accordance with technical requirements, plans, and specifications. The related federal contract opportunity is solicitation number 12445523Q0128 for Monongahela NF Fenwick Site Improvements issued by the US Department of Agriculture Forest Service.

View the file

Other files for this federal contract opportunity

Other files attached to Monongahela NF Fenwick Site Improvements, newest first.
File Type Posted
Amendment 0001 SF30.pdf PDF
Amendment 0001 Pre Bid Questions and Answers Fenwick Site Improvements.pdf PDF
J4 Fenwick Site Improvements PLANS 071323.pdf PDF
Sol_12445523Q0128.pdf PDF
J5 Vicinity Map.pdf PDF
J1 DBA Wage Determination WV 20230061 Nicholas County WV dated 01272023.pdf PDF
J3 Fenwick Site Improvements Specifications 071323.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work

Project Fenwick Site Improvements

General Information

1.0 Scope of Work

The contract work is to provide and install site improvements at the Fenwick Storage Site on the Monongahela National Forest. See Part 2 of this document for more detailed explanation. The Fenwick Storage Area for the Monongahela National Forest requires further site development and upgrades. The base bid for this project is to provide and install wooden utility poles, attach light fixtures, associated conduit and circuits, GFCI outlets, chain link security fencing, locks, and a steel tube gate. There is an optional item for providing and placing additional stone at the site. The contract work shall include all materials, labor, and incidentals to complete the work described in the contract documents. All work shall comply with applicable laws, codes, and regulations, and shall be in accordance with the contract plans and specifications.

Contractor Requirements

2.0 Technical Requirements / Tasks

The contract work shall include all materials, labor, and incidentals to complete the work described in the contract documents. All works shall comply with applicable laws, codes, and regulations, and shall be in accordance with the contract plans and specifications. Electrical Work Shall be Completed by a WV Licensed Electrician.

Item No. Deliverable Objective Due 0001 Mobilization Mobilize to the Site - 0002 Steel Tube Gate Provide and install a 24’ steel gate made up of 2 – 12’ sections in accordance with the plans and specifications. Posts, locking pin, steel, signs, hardware, concrete, and any other materials and work to fabricate and install the gate are to be provided by the contractor. Once the new gate is installed, the existing 20’10” wide red gate (gate and posts) shall be removed by the contractor and move to an approved storage location on site.

Period Of Performance End Date

0003 Chain Link Fence & Gate Provide and install an 8’ tall chain link fence (25’x45’ area) with a 20’ wide swing gate and approximately 70LF of privacy fabric.

(140LF of Fence Including Gate). The gate shall consist of 2 – 10’ sections. The fence and gate shall comply with the plans and specifications. Stone, concrete, and other items for proper installation are incidental to this item.

Period Of

0004 Outdoor Lighting & Outlets Provide and install 2 utility poles with 1 light fixture each; 2 – 20amp wiring circuits and associated conduit; and 2 GFCI electrical outlets, to be mounted on the utility poles. Stone, concrete, and other items for proper installation are incidental to this item.

Period Of Performance End Date

0005 Lock Upgrades Provide and install 3 – Grade 1 Deadbolt Locks in the existing double doors of the storage building on site (1 lock for each door). The screws on the exterior face of each existing latch mechanism shall be welded in place. Welding, fabrication, painting, and other items of work are incidental to this item.

Period Of

1001 3/4” Crusher Run Provide and place ¾” Crusher Run at the site in a manner approved by the COR in writing. Place stone prior to the installation of the chain link fence if the optional item is awarded. Stone shall be placed in a manner such that site drainage away from the building is not impaired and, in a manner, to prevent ponding of water anywhere on the project site. This stone is separate from the stone incidental to the other items in the SOI.

Period Of

Attachments See Attachments Below.

Figure 1: Front of Storage Building Area To Receive Chain Link Fence, 20’ Gate Chain Link Swing Gate, Outlets, and Lighting.

Figure 2: Rear of Storage Building Area

Figure 3: Existing Breaker Panel

Figure 4: Existing Breaker Panel Close-Up

Figure 5: Existing Exterior of Doors & Latching Mechanism. Machine Screws Holding Latch are to be Welded in Place.

Figure 6: Existing Exterior of Latching Mechanism Close Up. 3 Machine Screws Holding Latch are to be Welded in Place.

Figure 7: Existing Interior Side of Doors & Latching Mechanism.

Figure 8: Close-Up of Interior of Existing Latching Mechanism.

Figure 9: Additional View of Door.

Figure 10: Entrance Area to Install the Steel Tube Gate.

Tube Gate shall be installed where indicated, further up the driveway from the existing gate.

Existing 20’ 10” Gate to be Removed Once Steel Tube Gate is operational.

Project
General Information
1.0 Scope of Work
Contractor Requirements
2.0 Technical Requirements / Tasks