J02 Techincal Specification - 02528 Well Decommissioning.pdf
PDF 182 KB Posted
- Attached to
- Olympic Peninsula Well Decommissioning Federal contract opportunity
- Solicitation number
- 75H70122Q00031
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 75H70122Q00031-A00001.pdf | ||
| J05 WA20220071 06242022 (Kitsap).pdf | ||
| J06 IHS IEE Representation Form_Jan 2022.pdf | ||
| J01 Well Site Location Comprehensive Maps.pdf | ||
| B01 75H70122Q00031.pdf | ||
| J03 WA20220044 06242022 (Clallam).pdf | ||
| J04 WA20220046 06242022 (Grays Harbor).pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JAMESTOWN S'KLALLAM, MAKAH, QUINAULT,
AND SUQUAMISH TRIBES
PO-21-UI1 OLYMPIC PENINSULA WELL DECOMMISSIONING
SECTION 02528 – WELL DECOMMISSIONING Page 1 of 2
SECTION 02528
WELL DECOMMISSIONING
PART 1 - GENERAL
1.01 SUMMARY
A. This section includes the proper decommissioning of wells including well holes (casing), submersible pumps, drop pipe, and submersible cable.
B. This specification should be used as a guide and actual Washington State Standards should be referred to for complete requirements.
1.02 REFERENCES
A. Applicable state codes for the State of Washington.
B. Washington Administrative Code (WAC) Chapter 173-160.
1.03 SUBMITTALS
A. Method of decommissioning
B. Well Sealing (Fill) Material
PART 2 – PRODUCTS
2.01 MATERIALS FOR WELL DECOMMISSIONING
A. Conform to applicable State and local regulations.
PART 3 - EXECUTION
3.01 EXISTING CASED WELLS
A. Remove well pump (if applicable), liner, debris, and obstructions and well drop-pipe from existing wells prior to decommissioning.
1. Well pump, drop pipe, electrical cable, and any other components or materials removed from well shall be disposed of per the Owners instructions.
2. Pull casing or cut casing off 2 feet below ground surface.
3. Perforate or withdraw the casing from the bottom to within five feet of the land surface and pressure seal.
a. Perforations shall be at least four equidistant cuts per row, and one row per foot.
JAMESTOWN S'KLALLAM, MAKAH, QUINAULT,
AND SUQUAMISH TRIBES
PO-21-UI1 OLYMPIC PENINSULA WELL DECOMMISSIONING
SECTION 02528 – WELL DECOMMISSIONING Page 2 of 2
b. Perforations must be sufficient enough to allow neat cement grout or neat cement, or bentonite slurry to migrate outside the casing and effectively prevent the movement of water.
c. Apply enough pressure to force the sealing material through the perforations, filling any voids on the outside of the casing.
4. Fill hole with well fill material to two feet from the surface.
B. Placement of sealing (fill) material.
1. Sealing (fill) material placed below the water level shall be piped directly to the point of application or placed by special means.
2. As the sealing material is placed, the existing well tile may be encapsulated into the seal material.
3. If concrete, neat cement grout, bentonite, bentonite slurry, or neat cement is used to seal below the static water level in the well, the material shall be placed from the bottom up by methods that avoid segregation or dilution of the material.
4. All authorized sealing material placed above the static water level or into the dewatered portion of the well may be hand poured above the static water level, provided the material does not dilute or segregate, and result in a seal free of voids.
5. When decommissioning wells that were originally constructed without casing, unhydrated bentonite chips or pellets may be hand placed, provided it forms a continuous seal.
3.02 RECORDS
A. File well decommissioning reports with designated State agency and provide a copy to the Project Engineer within 30 days.
END OF SECTION