J02 Measurement and Payment.pdf

PDF 110 KB Posted

Attached to
Warm Springs Individual Onsite System Replacement
Solicitation number
75H70121Q00018
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Measurement and Payment- Peggy Williams 8205 County Line Rd. Warm Springs, OR

MEASUREMENT AND PAYMENT

1. MOBILIZATION & DEMOBILIZATION

Payment for transportation of equipment, material, and personnel to and from the job site location (regardless of trips required), required permits for water and sewer, and all other necessary items to complete the work.

Mobilization & demobilization 1 LS $

2. TWO WAY CLEANOUT

Payment for two way cleanouts shall be made at the contract unit price for the sizes listed based on the number of cleanouts installed. Compensation shall include payment for the excavation, backfilling and compaction; all pipe and fittings, and all other items for a complete and operational installation.

Two Way Cleanout 1 LS $

3. 4” SOLID SEWER PIPE

Payment for 4” solid sewer pipe shall be made at the contract unit price per linear feet of 4” solid sewer pipe installed. Compensation shall include payment for the excavation, backfilling and compaction; all pipe and fittings; connection of the solid sewer pipe to the existing sewer line;

testing; and all other necessary items for a complete and operational installation.

4” Solid sewer pipe 30 LF $

4. 1500 GALLON CONCRETE SEPTIC TANK W/ PUMP CHAMBER

Payment for septic tanks with pump chamber and riser lids shall be made at the contract unit price for the sizes listed based on the number of septic tanks installed. Compensation shall include payment for excavation, backfilling and compaction; septic tank, baffles, access risers, effluent filter, inspection ports as required, and all other necessary items for a complete and operational installation.

1500 gallon Septic Tank 1 LS $

5. BIOTUBE EFFLUENT PUMPING PACKAGE

Payment for Biotube effluent pumping package shall be made at the contract unit price.

Compensation shall include payment for all equipment, labor, and materials to install an effluent pump package in the pump chamber; Biotube vault, 10-gpm effluent pump, floats and controls, discharge assembly with flow control, and all other necessary items for a complete and operational installation.

Biotube Effluent Pumping Package 1 LS $

6. ELECTRICAL & ALARM PANEL/DEMAND DOSED CONTROLS

Payment for electrical and alarm panel for demand based controls shall be made at the contract unit price. Compensation shall include payment for all equipment, labor, and materials to extend electrical power to the pump package, exterior mounting of control panel, excavation, backfilling, Measurement and Payment- Peggy Williams 8205 County Line Rd. Warm Springs, OR and compaction to install conduit for underground power, electrical wiring and connections, internal splice box, installation of overcurrent circuit protection, and all other necessary items for a complete and operational installation. The contract price assumes that an empty circuit breaker slot for 120 V power is readily available for use.

1500 gallon Septic Tank 1 LS $

7. TRANSPORT PIPE

Payment for transport pipe and connections from the dosing chamber to the drainfield distribution box shall be made at the contract unit price per linear feet of transport pipe installed.

Compensation shall include payment for the excavation, backfilling and compaction; all pipe and fittings; connections and all other necessary items for a complete and operational installation.

Transport Pipe 260 LF $

8. CONVENTIONAL GRAVEL DRAINFIELD

Payment for conventional gravel drainfield shall be made at the contract unit price based on the number of linear feet installed. EZ Flow or chambered systems are not acceptable. Compensation shall include payment for system layout/staking, excavation and backfill; drainfield units and fittings, connections, clean drain gravel, drainfield filter fabric, and all other necessary items for a complete and operational installation.

Conventional Gravel Drainfield 360 LF $

9. INSPECTION PORT

Payment for inspection ports to be installed shall be made at the contract unit price based on the number of inspection ports installed. Compensation shall include payment for inspection port material, and all other necessary items for a complete and operational installation.

Inspection port 4 EA $

10. DISTRIBUTION BOX

Payment for distribution boxes to be installed shall be made at the contract unit price based on the number of distribution boxes installed. Compensation shall include payment for distribution box material, locking cover, and all other necessary items for a complete and operational installation.

Distribution box 1 EA $

11. ABANDON EXISTING SEPTIC TANK

Payment for abandonment of existing septic tanks shall be made at the contract unit price for the sizes listed based on the number of septic tanks abandoned. Compensation shall include payment for excavation, breaking into the tank, pumping the tank, disposal of liquids and solids, filling the tank with borrow material, compaction, restoring the ground surface, and all other necessary items for a complete abandonment.

Abandon Existing Septic Tank 1 EA $

File details come from the government source that posted it. Updated .