This memorandum documents a sole source justification for an acquisition under the simplified acquisition threshold. The U.S. Navy requires a BREAKER, MDS-C25 3 POLES, 2500 AMPS from DRS Naval Power Systems Inc, the original equipment manufacturer, with proprietary rights to the drawings. The breaker feeds critical ship equipment and continued use of the damaged existing breaker risks loss of 50% of forward house power. Delivery is needed by 4 October 2024 to replace the breaker before that risk materializes. Only DRS Naval Power Systems Inc can provide the breaker, technical data, and support to properly maintain this critical equipment.
The solicitation requests a quote for the breaker by 21 February 2024 for delivery to USS JOHN L. CANLEY by 20 September 2024. The sole source procurement is from DRS Naval Power Systems Inc to acquire the proprietary OEM part for a mission critical ship system. The Department of the Navy Military Sealift Command will issue a firm-fixed price purchase order for this sole source acquisition under the simplified acquisition threshold.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0001.docx | DOCX document | |
| RFQ 24Q0146 Breaker - Canley.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 Ver 2.0 (01 July 2018)
Date: 5 FEB 2024
MEMORANDUM
Subj: USE OF OTHER THAN FULL AND OPEN COMPETITION FOR AN ACQUISITION UNDER
THE SIMPLIFIED ACQUISITION THRESHOLD
Ref: (a) USNS JOHN CANLEY (ESB-6) PR Number(s): N4098B4018A407
I. BACKGROUND:
1. In considering the references, FAR 13.106-1(b)(1)(i) states for purchases not exceeding the simplified acquisition threshold, Contacting Officers may solicit from one source if the Contracting Officer determines that, under the circumstances of the contract action, only one source is reasonably available (e.g., urgency, exclusive licensing, brand-name, or industrial mobilization).
2. As required by FAR 13.106-3(b) (3) (i), this memorandum explains the absence of competition for this acquisition because only one source will be solicited for this requirement (or for a portion of the requirement) and the requirement is not expected to exceed the simplified acquisition threshold.
II. DESCRIPTION OF ITEM OR SERVICE:
1. Provide a description of the item or service required, to include
BREAKER, MDS-C25 3 POLES, 2500 AMPS
a) The name of the required source or brand name:
DRS NAVAL POWER SYSTEMS INC
b) The required delivery date/period of performance and:
4 OCT 2024
c) Its intended use:
MISSION MODULE SERVICE POWER STATION 1 CKT BKR
2. List the source(s) or known vendor(s) who are able to provide the above described item or service.
17TH MACHINERY LLC
III. THE DETERMINATION FOR USE OF OTHER THAN FULL AND OPEN COMPETITION IS BASED
ON THE FOLLOWING (select all that apply):
A. _X_ Only one responsible source (select all that apply):
2 Ver 2.0 (01 July 2018)
1. X RESTRICTIVE RIGHTS: the source has established proprietary rights, limited rights in data, patent rights, copyrights, or secret processes in the item or service.
a. Explain what is subject to the restrictive rights:
DRS NAVAL POWER SYSTEMS INC OWNS PROPRIETARY RIGHTS TO THE
DRAWINGS OF THE MATERIAL.
b. If drawings are included, who is identified as “owning” the drawings.
2. _N/A___ EXCLUSIVE LICENSING AGREEMENTS: The item or service is only available from the Original Equipment Manufacturer (OEM), or there is ONLY ONE authorized distributor or technical representative for the OEM.
a. Identify the OEM and explain the circumstances surrounding why the item or service is only available from the OEM.
b. __ Identify the distributor / authorized technical representative for the item or service.
Provide evidence of the exclusive licensing agreement as an attachment to this document.
(NOTE: If there is more than one distributor / authorized technical representative, then use Part B – Brand Name.)
3. __X__ OTHER REASON:
a. ____ CRITICAL SHIP EQUIPMENT: The required item is critical ship equipment, the failure of which poses a hazard to the ship, the crew or the environment.
i. SMS Procedure Number:
Fire Detection System equipment is included on the list of critical equipment fo the ESB class under Damage Control Equipment section
b. __X__ STANDARIZATION / BRAND NAME: Per MSCs standardization initiative, only the specified make/model of the equipment/parts will satisfy the Government’s needs for additional units or replacement items.
i. Identify Make / Model Number(s):
DRS NAVAL POWER SYSTEMS INC / MFR ID- MDSC253WEA-
2552ANAA6YNNNAX
ii. Identify other vessels with this Make / Model:
3 Ver 2.0 (01 July 2018)
N/A
c. _____ FORM, FIT, and FUNCTION: Item is direct replacement parts / components for existing equipment and must be compatible in terms of form, fit, and function with existing equipment / configurations.
i. Identify Make / Model of existing equipment:
ii. Describe how the equipment must be compatible with the existing configuration.
d. _N/A__ OTHER: Other reasons not identified above: MSC does not have manufacturing and technical information required to evaluate and determine whether non-OEM components and replacement parts offered are equivalent to the OEM components and replacement parts. The OEM rep has access to provide parts and technical data / drawings from the original manufacturer, as required to properly repair and maintain the equipment.
4. _ _X__ UNUSUAL AND COMPELLING URGENCY: The supplies or services are of such unusual and compelling urgency that the Government would be seriously injured unless the agency is permitted to limit the number of sources from which it solicits. Urgent requirements are supplies or services that will result in work stoppage, or are mission critical and the routine processing time would injure the Government. The determination that the procurement for the above is an urgent and compelling requirement is based on the following:
a. Date on which the requirement was identified: 18 JAN 2024
b. Required delivery date / Period of Performance: 4 OCT 2024
c. If the difference between a. and b. is more than one week, explain the delay in submitting the requirement.
DELAYED DUE TO TECHNICAL RESEARCH.
d. Estimated production lead-time: 30 WEEKS
e. Explanation of why delivery / commencement of services by the date required is needed: (explain the impact to the mission, any special circumstances or conditions, etc.)
4 Ver 2.0 (01 July 2018)
CB 36 does not fully rack into the switchboard, which has led to high resistance charring on the ends of the associated switchboard stabs. This breaker feeds P400B and downstream panels. Continued use of this damaged breaker and associated cassette is high risk and may lead to a loss of 50% of forward house power.
f. CASREP Number: __N/A__