SOLE SOURCE JUSTIFICATION - TYPE B A-E SERVICES
Solicitation number
W912JA-18-F-6021-P00003
Issued by

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Control No: ALNG-6005

Justification Review Document for Other Than Full And Open Competition

Program/Equipment: A-E Design Services for the Deployable Parts Storage (FAKZ182356)

Authority: 6.302-1(a)(2)(ii) Only one responsible source and no other supplies or services will satisfy the requirement.

Amount:

Prepared by:

Typed Name: Stephen A. Shanks DSN: 358-9529

Title: Contract Specialist Date:_____________ E-mail: stephen.a.shanks2.civ@mail.mil

Contracting Officer:

Typed Name: William C. Kast DSN: 358-9529

E-mail: william.c.kast.civ@mail.mil Date: _____________

Technical Representative:

Requirements Representative:

Typed Name: Capt Nathan Brock DSN: 358-9403

Title: Base Civil Engineer Date Reviewed: _____________

Reviews: I have reviewed this justification and find it adequate to support other than full and open competition.

Program Manager

Typed Name: Maj Adam W. Sanders DSN: 358-9418

Signature: _____________________________ Date:_________________

Legal Counsel

Typed Name: __________________________ Phone: ___________________

Signature: _____________________________ Date:_________________

Command Advocate for Competition

Typed Name: COL Raymond J. Barnes DSN: 363-2988

Signature: _____________________________ Date:_________________

Justification and Approval for Other Than Full and Open Competition

1. Contracting Activity: USPFO-AL

2. Description of Action: Action requested is to award a contract/modification on a sole source basis to Seay, Seay & Litchfield, PC (SS&L) for architectural design services of the F-35 Deployable Parts Storage (DPS) facility (FAKZ182356) located at the 187th Fighter Wing (FW), Montgomery, Alabama.

3. Description of Supplies/Services:

In September 2018 USPFO-AL and the 187th FW awarded a task order for Type A design services to SS&L to design a new supply complex (FAKZ999088) to be constructed at the 187th FW. In September 2019 a sole source modification was award to continue design services, Type B, to the 100% designed stage. The initial intent of this project was to design the facility to meet current and future mission needs. During the performance of Type B design services it was determined that to meet future mission requirements, to store the deployable parts package for the F-35 aircraft arrival scheduled for FY2023, that changes needed to be made to the supply complex. The change is a 6,000 square foot addition to the west end of the supply complex building which will include fire protection, utilities, and site improvements.

The supply complex is currently programmed for Fiscal Year (FY) 2021 and the Deployable Spare Parts for FY2022 but it is the intent/desire of the 187th FW for these projects to be built concurrently.

Anticipated award amount:

If awarded to SS&L

If awarded to other than SS&L

4. Authority Cited:

6.302-1(a)(2)(ii) Only one responsible source and no other supplies or services will satisfy agency requirements.

(2) When the supplies or services required by the agency are available from only one responsible source, or, for DoD, NASA, and the Coast Guard, from only one or a limited number of responsible sources, and no other type of supplies or services will satisfy agency requirements, full and open competition need not be provided for.

(ii) Supplies may be deemed to be available only from the original source in the case of a follow-on contract for the continued development or production of a major system or highly specialized equipment, including major components thereof, when it is likely that award to any other source would result in-

(A) Substantial duplication of cost to the Government that is not expected to be recovered through competition; or

(B) Unacceptable delays in fulfilling the agency’s requirements.

5. Reason for Authority Cited:

In January 2014, the USPFO-AL issued an indefinite delivery contract to SS&L to perform A-E Services for the Alabama Army and Air National Guard. Since then they have performed all A-E services for the 187th FW, to include creating the Installation Development Plan. SS&L was awarded a task order to perform Type A design services for the construction of a new base supply complex. SS&L completed initial Type A services to the 35% stage. In September 2019 a sole source modification was approved and awarded to SS&L to perform the Type B design services to 100% completion.

In October 2019 NGB A4O contacted the 187FW to see if we would be able to execute an award for design services for the DPS, no later than February 2020. Currently USPFO-AL does not have local A-E IDIQ in place. The initial decision was we would not be able to award the contract within the time constraints. After discussion with the Base Civil Engineer (BCE) it was determined that this should be considered for a modification to the existing task order or a sole source award to the incumbent architects under FAR 6.302-1(a)(2)(ii).

This requirement meets the intent of FAR 6.302-1(a)(2)(ii) in that it is a follow-on contract for the continued development of a highly complex and detailed project. The project calls for additional warehouse/storage space to be added to the planned supply complex, to include tying into planned electrical, plumbing, security and fire protection equipment. Additionally, there is a high probability of increased cost and time delays if this project is not awarded as a sole source.

If a firm other than SS&L was selected additional time would have to be added for re-work/revision to the previously performed Type A services. To date $796,800.00 have been obligated to this design action. Based on awarding as a sole source the Government can expect an immediate savings of and a potential savings, at time of construction, of approximately see table below, for a total potential cost saving of What is more difficult to estimate are the savings in dollars and time that can be gained during construction by having both projects to the 100% designed stage and bid out as a single construction project.

Direct Costs Cost Estimate

Removal of 3,570SF of Metal Wall Panel Installation of 1,404 SF of new exterior composite metal wall panel Installation of 2,166 SF of new interior metal wall panel Removal of 441 SF of brick veneer Mobilizing/Additional Job Trailer Additional Supervision $25/hr. x 2020 hrs.

To pursue this action competitively, under FAR Part 36.6, would add 6 – 12 months for the award of the design services of the DPS. The USPFO-AL is currently working to put a local A- E IDIQ in place, with an anticipated start date of November 2020. To award other than a sole source to SS&L would jeopardize the completion of the design effort in time to include the DPS project into the construction of the supply complex.

6. Efforts to Obtain Competition:

At this time effort to obtain competition has not been performed.

7. Actions to Increase Competition:

No actions have been taken at this time to increase competition. However USPFO-AL has initiated the acquisition process for a new local A&E IDIQ. This acquisition will be competitive, utilizing FAR Part 36.6 procedure. Anticipated award date November 2020.

8. Market Research:

Specific market research for these items have not been performed.

9. Interested Sources:

To date, no other sources have written to express an interest.

10. Other Facts:

A complete POM/PNM shall be accomplished prior to award of the modification/Award.

11. Technical Certification: Include the following statement:

I certify that the supporting data under my cognizance, which are included in the justification are accurate and complete to the best of my knowledge and belief.

Typed Name: Date: Maj. Adam Sanders Date:___________________

Title: Base Civil Engineer Signature: ________________________

12. Requirements Certification: Include the following statement:

I certify that the supporting data under my cognizance, which are included in the justification are accurate and complete to the best of my knowledge and belief.

Typed Name: Mr. Stephen A. Shanks Date:___________________

Title: Base Contracting Officer Signature: ________________________

13. Fair and Reasonable Cost Determination: Price Fair and Reasonable shall be determined in a separate (stand-alone) document. A complete PNM/POM with analysis of labor hours/level of effort shall be performed and submitted, for review and approval, prior to modification award.

Typed Name: Date: William C. Kast Date:___________________

Title: Supervisory Contract Specialist Signature: ________________________

14. Contracting Officer Certification: This certification shall be made by the contracting officer who will sign the contract resulting from this justification and approval. Include the following statement:

I certify that this justification is accurate and complete to the best of my knowledge and belief.

Typed Name: William C. Kast Date:___________________

Title: Supervisory Contract Specialist Signature: ________________________