Performance Work Statement Summary
This is a Performance Work Statement (PWS) for auxiliary machinery work aboard USS Ship (LCC 20), Item No. 0501, categorized as Category "A" with a contract number AWP-N-TBD (MTA) and due date of August 28, 2026. The work requires removal, installation, and crating of two Main Air Ejector and Condenser assemblies located in the Engine Room Upper Level (7-86-0-E). Each unit manufactured by Graham Manufacturing weighs 2,980 lbs with 146 tubes and is fabricated from ASTM B1111 copper alloy.
The contractor must execute the following primary tasks: rig the existing Main Air Ejector and Condenser assembly from the Engine Room to Main Deck; uncrate and rig the new assembly from Main Deck to the Engine Room; assist Ship's Force in conducting hydrostatic testing; rig the new unit onto the foundation; replace and target new piping and flanges for five connection points (Condensate Supply/Return, Gland Seal Steam Exhaust, Intercondenser Drain, and Aftercondenser Drain); crate the old unit using the original shipping crate for international shipment; and install new insulation and lagging per NAVSEA specifications. Piping materials include seamless drawn copper tubing and bronze flanges with silver braze connections, except for the Gland Seal Exhaust line which requires seamless carbon steel piping and carbon steel flanges. Quality assurance requires compliance with General Technical Requirements (GTRs 1-7, 22-24, 28-29), dual-point lifting with fully-rated equipment, NDT Dye Penetrant Testing of all welds, and calibrated load testing of a minimum twelve pad eyes. Ship's Force provides gasket materials and handles all shipping logistics including crane services. The contractor must conduct a site survey to assess rigging challenges and provide all remaining materials, equipment, and labor.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| J-1 Contractor Price Breakdown.xlsx | XLSX spreadsheet | |
| Solicitation - N6817126QN090.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USS Ship
( LCC 20 )
AUXILIARY MACHINERY CONTRACT NO. AWP - N-TBD (MTA)
ITEM NO. 0501 CATEGORY "A" 2026-08-28
LCC-VR AIR EJECTOR & CONDENSER
REMOVAL, INSTALLATION AND CRATE FOR
SHIPMENT
Simpson, Eric H.
0508 - 1
1.0 ABSTRACT
1.1 This work item describes the requirement to:
1.1.1 Rig the installed Main Air Ejector and Condenser assembly from the Engine Room to Main Deck.
1.1.2 Uncrate a new Main Air Ejector and Condenser assembly and rig from Main Deck to the Engine Room.
1.1.3 Under the cognizance of Ship’s Force, assist in conducting a hydrostatic test of the new unit.
1.1.4 Upon satisfactory hydrostatic test, rig onto the foundation in the upper level of the Engine Room.
1.1.5 Target new piping and flanges for the following connections:
1.1.5.1 Condensate Supply
1.1.5.2 Condensate Return
1.1.5.3 Gland Seal Steam Exhaust to Air Ejector Condenser
1.1.5.4 Intercondenser Drain to Loop Seal
1.1.5.5 Aftercondenser Drain to Atmospheric Drains
1.1.6 Using the crate that the new unit arrived in, crate the old unit for international shipment.
1.1.7 Install new insulation and lagging on Air Ejectors and Condenser Assembly and piping as per Ref. 2.1, 2.3 and 2.4.
2.0 REFERENCES
2.1 NAVSEA Technical Manual 0946-LP-014-0010 AIR EJECTOR
2.2 Graham Mfg. (OEM) Dwg. 15520-11 Air Ejector Assembly Drawing
2.3 NAVSEA Dwg 208-2492084 Conds & Air Piping Diagram
2.4 NAVSEA Dwg 514-2492511 Gland Sealing Sys. Diagram
2.5 MSC Drawing No. 845-4458934 Rev. W, Selected Record Drawing (SRD)
General Arrangement
2.6 NSTM 635 Thermal, Fire, and Acoustic Insulation S9086-VH-STM-010
3.0 ITEM LOCATION / DESCRIPTION
3.1 7-86-0-E Engine Room Upper Level
3.1.1 Quantity (Two), Condenser, Main Air Ejector
AUXILIARY MACHINERY CONTRACT NO. AWP - N-TBD (MTA)
ITEM NO. 0501 CATEGORY "A" 2026-08-28
LCC-VR AIR EJECTOR & CONDENSER
REMOVAL, INSTALLATION AND CRATE FOR
SHIPMENT
Simpson, Eric H.
0508 - 2
Mfr: GRAHAM MRG CO INC
Mfr Dwg: C15520-32
Number of Tubes: 146
Size of Tube: 5/8 inch OD x 0.049 inch x 6 feet
Tube Material: ASTM B1111, Copper Alloy
Weight: 2980 lbs.
APL: 730060037
3.2 Piping:
3.2.1 Condensate Supply and Return Piping and Flanges
Material:
Pipe: Seamless Drawn Copper Tubing, 5 inch, 0.065” Min Wall Thickness
Flanges: Bronze, 5 inch
Silver Braze Connection
Quantity: Two (2)
3.2.2 Main Condenser Air Suction
Material:
Pipe: Seamless Drawn Copper Tubing, 4 inch, 0.065” Min Wall Thickness
Flanges: Bronze, 4 inch
Quantity: Two (2)
3.2.3 Gland Seal Exhaust to Aftercondenser
Material:
Pipe: Seamless Carbon Steel, 4 inch, ASTM A106 Gr B
Flange: Carbon Steel, 4 inch, ASTM A-105 Gr II
Quantity: One (1)
3.2.4 Aftercondenser Drain to Atmospheric Drains
Material:
Pipe: Seamless Drawn Copper Tubing, 1”, 0.065 Min Wall Thickness
Flanges: Bronze, 1 inch
Silver Braze Connection
AUXILIARY MACHINERY CONTRACT NO. AWP - N-TBD (MTA)
ITEM NO. 0501 CATEGORY "A" 2026-08-28
LCC-VR AIR EJECTOR & CONDENSER
REMOVAL, INSTALLATION AND CRATE FOR
SHIPMENT
Simpson, Eric H.
0508 - 3
Quantity: One (1)
3.2.5 Intercondenser Drain to Loop Seal
Material:
Pipe: Seamless Drawn Copper Tubing, 1”, 0.065 Min Wall Thickness
Flanges: Bronze, 1 inch
Silver Braze Connection
Quantity: One (1)
3.2.6 1st Stage Suction from Main Condenser
Material:
Pipe: Seamless Drawn Copper Tubing, 4”, 0.065 Min Wall Thickness
Flanges: Bronze, 4 inch
Silver Braze Connection
Quantity: Two (2)
4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES
4.1 Government Furnished Equipment (GFE): Two (2) each Main Air Ejector and
Condenser assemblies listed under 3.1.1.
4.2 Government Furnished Material (GFM):
4.2.1 Gasket Material for the condenser, air ejectors, and piping connections to be provided by Ship’s Force.
4.3 Government Furnished Services (GFS): All Shipping will be the responsibility of MSC to include crane services from ship and shore.
4.4 Government Furnished Information (GFI): None
5.0 NOTES:
5.1 Bidder’s must perform a ship check in order to accurately gauge the significant challenges in performing this statement of work.
5.2 All material, equipment and manpower not specifically stated as GFM shall be provided by the contractor.
AUXILIARY MACHINERY CONTRACT NO. AWP - N-TBD (MTA)
ITEM NO. 0501 CATEGORY "A" 2026-08-28
LCC-VR AIR EJECTOR & CONDENSER
REMOVAL, INSTALLATION AND CRATE FOR
SHIPMENT
Simpson, Eric H.
0508 - 4
6.0 QUALITY ASSURANCE REQUIREMENTS:
6.1 The contractor and all subcontractors, regardless of tier must consult the General Technical Requirements (GTR) to determine the applicability to this work item.
In performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements of all applicable GTRs including but not limited to GTRs 1 through 7, 22, 23, 24, 28 and 29.
6.2 Rigging must be accomplished using equipment rated for the full weight of the components being lifted.
6.2.1 Weight of entire assembly is 2980 lbs. (1351 kg)
6.2.2 Removal of the Air Ejectors and valves is permissible in order to decrease the size and weight of the unit for rigging purposes.
6.2.3 At no time will it be permissible for the unit to be off the deck supported by only one lifting appliance. Unit must be supported by two separate pick points / lifting appliances at all times (No single point of failure is acceptable).
6.2.4 Each lifting appliance must be capable of carrying the full weight of the material being lifted i.e. A 1000 lb. part may not be lifted by two (2) 500
lb. chain falls. Both chain falls will need to be capable of carrying the full load of 1000 lbs.
6.2.5 Each lifting appliance must be capable of covering the entire height of a lift without using two lifting appliances in series (No daisy chaining of lifting appliances. i.e. A chain fall may not be directly connected to another chain fall.
6.2.6 All lifting appliances, to include straps and beam clamps, must be affixed with test tags indicating the rated capacity and test date. If the material is new affixed with rated capacity from the manufacturer this requirement may be waived.
6.2.7 Contractor to provide calibrated dynamometer and / or test weights to test all proposed lift points. For estimating purposes a minimum of twelve (12)
AUXILIARY MACHINERY CONTRACT NO. AWP - N-TBD (MTA)
ITEM NO. 0501 CATEGORY "A" 2026-08-28
LCC-VR AIR EJECTOR & CONDENSER
REMOVAL, INSTALLATION AND CRATE FOR
SHIPMENT
Simpson, Eric H.
0508 - 5 padeyes will require testing. Further test requirements should be submitted to MSC Rep. via CFR.
6.2.8 Lifting appliances shall be connected to pad eyes or structural members using beam clamps. Lifting appliances shall not be applied to pipes or any other non-structural member.
6.2.9 When rigging through Ellison Doors, door and frame must be removed and reinstalled to avoid damage to the door operating mechanism.
6.2.10 For removal of ladder in the rigging path, contract shall provide barriers to cordon off the area to traffic. This to be a physical barrier, Caution Tape will be considered insufficient.
6.2.11 Removed ladders shall be securely stowed on the deck before rigging equipment through the space.
6.2.12 Fasteners
7.0 STATEMENT OF WORK REQUIRED
7.1 Ship’s Force to Lock Out Tag Out steam / condensate piping components.
7.2 Rig the Air Ejector Condenser and associated Air Ejectors from the upper level of the engine room to Main Deck.
NOTE: Suggested rigging path is through the ladder wells on the port side of the engine room and then aft down the port side passageway of 4th deck to the Cargo Elevator. Contractor to verify dimensions and rigging path during Ship Check.
7.3 Place removed Air Ejectors and Condenser on pallets and protect from weather.
7.4 Open crate and remove new Air Ejector and Condenser Assembly.
NOTE: Expect assembly to be in one piece. Air Ejectors and components may be removed from Condenser to facilitate rigging.
NOTE: Care is to be taken when opening the crate as it will be re-used for shipment of old Air Ejector Assembly.
AUXILIARY MACHINERY CONTRACT NO. AWP - N-TBD (MTA)
ITEM NO. 0501 CATEGORY "A" 2026-08-28
LCC-VR AIR EJECTOR & CONDENSER
REMOVAL, INSTALLATION AND CRATE FOR
SHIPMENT
Simpson, Eric H.
0508 - 6
7.5 Rig new Condenser and Air Ejectors to the upper level of the Engine Room following the rigging path used in 7.2.
7.6 Rig new Condenser in position on foundation for targeting of piping outlined in 3.2.
7.6.1 Replace flanges and piping as required to make connections.
7.6.2 For bidding purposes assume each flange and 2 linear feet of piping will require replacement.
NOTE: Flange replacement is to be accomplished on the piping. No work shall be performed on the flanges of the Condenser without written approval from the MSC Rep.
7.6.3 Upon completion of each weld, perform NDT Dye Penetrant Testing in the presence of the MSC Rep. and submit results of the testing to the MSC Rep.
7.7 Assist the ship in accomplishing a hydrostatic test of the following:
7.7.1 Condenser Inter / Aftercondenser
7.7.1.1 Install blanks / pancakes between the flanges of the
Intercondenser Drain to the Loop Seal (one (1) 1 inch flange).
7.7.1.2 Install the First Stage Air Ejector Discharge Valves.
7.7.1.3 Install the Second Stage Air Ejector Suction Valves.
7.7.1.4 Remove the water boxes from both ends of the Condenser Shell
7.7.1.5 Ship’s Force will perform the hydrostatic test between the Inter / Aftercondenser
7.7.2 Upon Satisfactory hydrostatic test of the Inter / Aftercondenser:
7.7.2.1 Restore the remaining Air Ejectors and Associated piping.
NOTE: Ship’s Force will supply all gasket material.
7.7.2.2 Install blanks / pancakes between the flanges of the Gland Seal Exhaust (one (1) 4 inch flange), the Aftercondenser Drain (one
AUXILIARY MACHINERY CONTRACT NO. AWP - N-TBD (MTA)
ITEM NO. 0501 CATEGORY "A" 2026-08-28
LCC-VR AIR EJECTOR & CONDENSER
REMOVAL, INSTALLATION AND CRATE FOR
SHIPMENT
Simpson, Eric H.
0508 - 7
(1) 1 inch flange, and the Gland Exhaust Fan Suction Piping (one (1) 4 inch flange).
7.7.2.3 Ship’s Force will perform hydrostatic test to shell.
7.7.2.4 Upon completion of satisfactory hydrostatic test, restore the water boxes on both ends. Remove the blanks installed in
7.7.1.1 and 7.7.2.2 and install new gaskets.
7.8 Insulate Air Ejectors and Condensers and disturbed piping using Ref. 2.6 for guidance.
8.0 GENERAL REQUIREMENTS: None Additional