Itemized Pricing 23Q0180.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
USS MAKIN ISLAND (LHD-8) CIS PUMP AND MOTOR
Solicitation number
N5523623Q0180
Issued by

About this file

This itemized pricing spreadsheet outlines the requirements for an overhaul of the NR-4 reverse osmosis unit motor onboard the USS Makin Island. The Navy seeks a contractor to remove, transport, overhaul, shop test, deliver, and reinstall the motor under solicitation number N5523623Q0180. Key tasks include rigging and crane support to remove the existing motor from building 3278 to the contractor's shop, performing an overhaul in accordance with standard item 009-113 including installing new parts, conducting a shop operational test, rigging and installing the overhauled motor back onto its foundation in compartment 6-81-0-E, and preparing and painting the motor. The pricing spreadsheet provides a milestone schedule and notes clarifying standard overhaul procedures and points of contact.

View the file

Other files

File Type Posted
23Q0180_SF18.pdf PDF
N5523623Q0180_RFC.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Itimized Pricing
CONTRACT:PUMP AND MOTOR
CONTRACTOR:TBD
PURCHASE ORDER:TBD
SHIP:USS MAKIN ISLAND (LHD-8)
LOCATION:NAVY REGION SOUTHWEST
ITEM NO CLINDESCRIPTIONQUANTITYUNITUNIT PRICEAMOUNT
0001COMMERCIAL INDUSTRIAL SERVICES (CIS) PUMPS AND MOTORS CONTRACT IS TO PROVIDE LABOR, RIGGING SERVICES, CRANE, TRANSPORTATION, EQUIPMENT, AND MATERIALS FOR THE REMOVAL, OVERHAUL, REASSEMBLY, SHOP TEST, DELIVERY AND INSTALLATION ONTO THE EXISTING FOUNDATION OF THE NR-4 REVERSE OSMOSIS UNIT MOTOR ONBOARD THE USS MAKIN ISLAND (LHD-8).1LOT$0.00
PROVIDE LABOR, SERVICES, EQUIPMENT AND MATERIALS FOR THE RIGGING (OFFLOAD AND ONLOAD), CRANE SUPPORT, FORKLIFT AND TRANSPORTATION OF THE NR-4 REVERSE OSMOSIS UNIT MOTOR FROM SWRMC BUILDING 3278 TO THE SHOP FOR OVERHAUL AND DELIVER AND RIG THE OVERHAULED REVERSE OSMOSIS UNIT MOTOR ONTO THE EXISTING FOUNDATION IN COMPARTMENT 6-81-0-E IN ACCORDANCE WITH THE REQUIREMENTS OF THE CONTRACT AND THE STATEMENT OF WORK (SEE NOTE-4 )
PROVIDE LABOR, SERVICES, EQUIPMENT, AND MATERIALS TO ACCOMPLISH THE OVERHAUL OF THE NR-4 REVERSE OSMOSIS UNIT MOTOR IN ACCORDANCE WITH NAVSEA STANDARD ITEM 009-113 TO INCLUDE THE INSTALLATION OF NEW BEARINGS, THERMISTORS, SEALS, O-RINGS, GASKETS, FITTINGS, LOCK WASHERS, LOCKNUTS, FLEXIBLE CONNECTORS, FLEXIBLE CONDUIT AND GROUND STRAPS IN ACCORDANCE WITH THE REQUIREMENTS OF THE CONTRACT AND THE STATEMENT OF WORK
PROVIDE LABOR, SERVICES, EQUIPMENT AND MATERIALS FOR THE SHOP OPERATIONAL TEST OF THE OVERHAULED REVERSE OSMOSIS UNIT MOTOR
PROVIDE LABOR, SERVICES, EQUIPMENT AND MATERIALS FOR THE RIGGING ( INSTALL ONLY) AND INSTALLATION OF NR-4 REVERSE OSMOSIS UNIT MOTOR ONTO THE FOUNDATION AFTER OVERHAUL
PROVIDE LABOR, SERVICES, EQUIPMENT AND MATERIALS FOR THE PREPARATION AND PAINTING OF THE REVERSE OSMOSIS UNIT MOTOR IN ACCORDANCE WITH NAVSEA STANDARD ITEMS 009-32
PROVIDE LABOR (40 HOURS), SERVICES, EQUIPMENT, AND MATERIALS FOR THE MACHINING HOURS (IF REQUIRED) ASSOCIATED WITH ENSURING SPECIFICATIONS IN ACCORDANCE WITH THE REQUIREMENTS OF THE CONTRACT AND THE STATEMENT OF WORK

(SEE NOTE 3)

NET AMT $0.00

MILESTONE EVENT
1. Purchase Order Start Date13-Jul-23
2. Remove and transport to shop13-14-Jul-23
3. Overhaul and Shop Test14-Jul to 11-Aug-23
4. Delivery to ship and install11-14-Aug-23
5. Purchase Order End Date14-Aug-23
NOTES:
1. In the event the requirements stated in the SOW has changed from NAVSEA Standard Item 009-113 to 009-33 or 009-17 as a result of the disassembly inspection, the Contractor shall submit one legible copy, in hard copy or approved transferrable media, of a CFR listing the recommendations of repair requirements to the SBS. The change in scope will require the Contractor to submit a revised estimated cost towards the performance of the new repair recommendation.
2. Refer to Technical Manual S9531-C5-MMA-010, Technical Manual for Reverse Osmosis Desalination Unit for detailed procedures on the overhaul of the NR-4 Reverse Osmosis Unit Motor to include shop operational testing.
3. If machining hours are required, submit CFR to the SUPERVISOR with the result of UNSAT measurement not conforming in accordance with the Technical Manual S9531-C5-MMA-010, Technical Manual for Reverse Osmosis Desalination Unit
4. Remove existing disassembled NR-4 RO Pump Motor from the SWRMC Building 3278 (POC Todd Stubblefield @ (619) 372-0043). Collect all associated motor parts and rig and transport NR-4 RO Pump Unit Motor to the contractor shop for overhaul. Rig and install the overhauled NR-4 Reverse Osmosis Unit Motor onto the existing foundation in compartment 6-81-0-E (POC ENCS Rodriguez) upon completion of overhaul.

Sheet2

Sheet3

File details come from the government source that posted it. Updated .