DEPARTMENT OF THE AIR FORCE
OKLAHOMA CITY AIR LOGISTICS COMPLEX (OC-ALC)
TINKER AIR FORCE BASE OKLAHOMA
Statement of Requirement / Item Description
76 AMXG/565 AMXS request the purchase of the following item (s):
· Fabricate two (2) "B-52 Engine Nose Cowl FOD Removal Fixture" per drawing X201961718.
· The first article shall be made as a prototype.
· The second article shall be fabricated only after Engineering has validated and verified (val/ver) the first article and made any necessary changes to the design of the fixture.
· The second article shall be fabricated only after Engineering has validated and verified (val/ver) the first article and made any necessary changes to the design of the fixture. An updated drawing will be furnished to the contractor if changes are made.
· The second article shall be delivered no more than sixty (60) days after Engineering has val/ver the first. Engineering shall val/ver the first article within thirty (30) days after delivery.
· Deliver fully assembled or the contractor shall fully assemble the fixtures upon delivery on-site.
· All substitutions or deviations from drawing must be approved by Technical POC (Engineering).
· Delivery shall be directly to Building 2121, addressed to the 565th AMXS Tool Crib.
· Contractor must have access to all standards or specifications referenced in the drawing X201961718.
· For the purposes of the correction of fabrication errors and/or discussion of design changes, the contractor shall be available for no more than three (3) on-site visits of one business day or less.
· Any operations manuals, technical information, instruction guidance, etc. included with Consumer Off-The-Shelf (COTS) items on the fixtures shall be furnished by the contractor to Engineering.
· All welders must be AWS Certified Welders (CW) with at least 5 years’ experience.
· Parts which include Geometric Dimensions and Tolerance (GD&T / GDT) must be fabricated by personnel who have received formal GD&T training with experience machining GD&T parts.
· Components which re-quire electrical wiring must be inspected by a licensed electrician. Contractor must have access to all standards or specifications referenced in the drawing X201961718.
image1.wmf