This is an Invitation to Bid and Instructions to Bidders document issued by The Winter Construction Company on behalf of Atlanta Public Schools for the Miscellaneous Bundle project, a Construction Management at Risk (CMAR) services engagement. The project encompasses four school facilities: Sarah Smith Elementary School (370 Old Ivy Rd NE), Parkside Elementary School (685 Mercer Street SE), Midtown High School (929 Charles Allen Dr NE), and Walden Athletic Complex (320 Irwin Street NW), all located in Atlanta, Georgia. The scope includes a seating package for Parkside Elementary drainage solution, storage renovation to Midtown High School auxiliary gym, structural remediation to Sarah Smith Elementary School, and netting installation for Walden Athletic Complex. Interested bidders must submit lump sum proposals on a per-location basis using the Construction Manager's Proposal Form in BuildingConnected by 5:00 PM on February 27, 2026. A virtual pre-bid meeting is scheduled for 10:00 AM on February 12, 2026 via Microsoft Teams, and an on-site open house will be held at 1:00 PM on February at Winter Construction's offices (5616 Peachtree Road, Suite 100, Atlanta, GA 30341). Bids will not be accepted after the deadline, and each bid is binding for sixty days following the bid date. Construction plans were prepared by Thrasher Comeau Architecture and are dated between October 5, 2025 and January 12, 2026.
Bid bonds and performance and payment bonds are not required for this procurement. All bidders must be prequalified as a subcontractor of The Winter Construction Company prior to award, with prequalification requests submitted through the company's online portal. Subcontractors are required to comply with all federal, state, and local laws, including the Georgia Security and Immigration Compliance Act (O.C.G.A. 13-10-90), and must maintain insurance coverage in accordance with contract documents. The Construction Manager reserves the right to accept or reject any or all bids and to waive technicalities. Work is subject to a fast-track schedule with time being of the essence, and subcontractors must attend periodic project coordination meetings and comply with a zero-tolerance policy regarding interactions with students and school staff. Additionally, subcontractors are prohibited from bringing weapons, alcohol, or controlled substances onto campus, must maintain a full-time competent supervisor on site, and are responsible for all mobilization, temporary facilities (except temporary toilets), daily and final cleanup, and site restoration. Contact for bidding inquiries is Philip Williamson, Preconstruction Manager, at pwilliamson@winter-construction.com or 470-603-1530.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ITB Advertisement _ APS Misc Bundle _ Feb 202.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION TO BID
Atlanta Public Schools Miscellaneous Bundle
Bid Date and Time: February 27, 2026 at 5:00 PM
The Winter Construction Company (“TWCC”) invites qualified bidders to submit lump sum bids for the seating package associated with the Atlanta Public Schools Miscellaneous Bundle project.
Site Addresses:
Sarah Smith Elementary School: 370 Old Ivy Rd NE, Atlanta, GA 30342
Parkside Elementary School: 685 Mercer Street SE, Atlanta, GA 30312
Midtown High School: 929 Charles Allen Dr NE, Atlanta, GA 30309
Walden Athletic Complex: 320 Irwin Street NW, Atlanta, GA 30312
Proposals are due no later than 5:00 PM on February 27, 2026, in BuildingConnected
Bids must be submitted on the Construction Manager’s Proposal Form
Bids must be submitted per the requirements of the Instructions to Bidders, Requirements for All
Bid Packages, and the appropriate Bid Package Scope of Work.
BIDS WILL NOT BE ACCEPTED AFTER 5:00 PM on February 27, 2026
No determination will be made as to the most responsive bidder until a thorough evaluation has been conducted by the Construction Manager and the Owner. Additional information may be requested of responsive bidders and may be used to help select the most qualified bidder. The
Construction Manager and Owner reserve the right to accept or reject any or all bids and to waive technicalities.
List of Bidding Documents
1. Invitation to Bid
2. Instruction to Bidders titled Atlanta Public Schools Miscellaneous Bundle prepared by
TWCC
3. Bid Proposal Form
4. Construction Plans titled Parkside Elementary Drainage Solution dated 01-12-2026 and prepared by Thrasher Comeau Architecture
5. Construction Plans titled Storage Renovation to Midtown High School Auxillary Gym dated Jan. 5, 2026 and prepared by Thrasher Comeau Architecture
6. Construction Plans titled Structural Remediation to Sarah Smith Elementary Schooled dated Oct. 5, 2025 and produced by Thrasher Comeau Architecture
7. Construction Plans titled Netting For Walden Athletic Complex dated Oct. 5, 2025 and produced by Thrasher Comeau Architecture
8. All addenda and clarifications issued prior to bid date and time
All bidders must be prequalified as a subcontractor of Winter Construction prior to subcontract award. Click on this link to submit a request to prequalify:
http://www.wintercompanies.com/AppCenter/91PreQual/PrequalRequest.aspx. An Invitation to prequalify will be sent via TradeTapp/Building Connected once we receive your request.
5616 PEACHTREE ROAD, SUITE 100 | ATLANTA, GEORGIA 30341
http://www.wintercompanies.com/AppCenter/91PreQual/PrequalRequest.aspx
Winter Construction manages all aspects of the bidding process in Building Connected.
Information regarding bid packages and requests to access bid documents should be directed to:
Philip Williamson, Preconstruction Manager: pwilliamson@winter-construction.com, 470-603-1530
Brik Ethridge, Project Manager: bethridge@winter-construction.com, 470-747-9463
A Virtual Pre-Bid Meeting will be held 10:00 AM on February 12, 2026
Microsoft Teams
Join: https://teams.microsoft.com/meet/21441049550730?p=0HNCjfUYU47LkWZFl0
Meeting ID: 214 410 495 507 30
Passcode: 5sw2fh2L
An On-Site Open House will be held at Winter Construction, address below, at 1:00 PM on
February.
Open House Location: 5616 Peachtree Road, Suite 100, Atlanta, GA 30341
We strongly encourage all Minority-Owned, Women-Owned, and Veteran-Owned subcontractors to attend our virtual pre-bid meeting and participate in the bidding process. If you are unfamiliar with Winter Construction or the CMAR process, we will gladly answer any questions you may have and assist you in the process during the meeting.
END OF INVITATION TO BID
mailto:pwilliamson@winter-construction.com mailto:bethridge@winter-construction.com https://teams.microsoft.com/meet/21441049550730?p=0HNCjfUYU47LkWZFl0
INSTRUCTIONS TO BIDDERS
Atlanta Public Schools Miscellaneous Bundle
Bid Date and Time: February 27, 2026 at 5:00 PM
Project Information
Project Name: Atlanta Public Schools Miscellaneous Bundle
Locations:
Sarah Smith Elementary School: 370 Old Ivy Road NE, Atlanta, GA 30342
Parkside Elementary School: 685 Mercer Street SE, Atlanta. GA 30312
Midtown High School: 929 Charles Allen Dr NE, Atlanta, GA 30309
Walden Athletic Complex: 320 Irwin St NE, Atlanta, GA 30312
Construction Manager (CM): The Winter Construction Company
5616 Peachtree Road, Suite 100
Atlanta, GA 30341
404-588-3300 (Office)
404-588-0572 (Fax)
Owner: Atlanta Public Schools
130 Trinity Ave, SW
Atlanta, GA 30303
Architect: Thrasher Comeau Architecture
301 E. Church St
Monroe, GA 30655
Bid Date, Time & Location July 5, 2024, 5:00 PM in Building Connected
Bids to be submitted no later than 5:00 PM on February 27, 2026 in Building Connected. Refer to instructions below.
Instructions to Package Bidders:
1. Bids: Bids must be submitted in Building Connected on the Construction Manager’s Proposal
Form along with Bid Bond if required. Bids must be submitted per the requirements of the
Instructions to Bidders, Requirements for All Bid Packages, and the appropriate Bid Package
Scope of Work.
Bidders may also submit via email to pwilliamson@winter-construction.com and must have the word “Bid” and the “Project Name” in the subject bar.
All quotes must be received no later than to 5:00 PM. BIDS WILL NOT BE
ACCEPTED AFTER 5:00 PM.
Bid forms must be completed in their entirety and ensure that lump sum pricing is provided on a per location basis. Bidders are to specify the Base Bid amount in both words and figures. In the event of a discrepancy between these amounts, the amount written in words shall govern.
Bidders submitting bids on more than one package must do so individually in the form and manner described above.
Each bid may not be withdrawn for a period of sixty (60) days after the bid date.
2. Documents: Bid Documents are available as shown in the Invitation to Bid. The Bidding
Documents will become part of the Contract Documents at award.
3. Addenda/Clarification: It is each Bidder’s responsibility to include all addendum(a) and clarification(s) issued prior to bid date and time.
4. Communication & Interpretations: All communication concerning the Project during the bidding process should be submitted to Philip Williamson, Preconstruction Manager, via email to pwilliamson@winter-construction.com. Interpretation of the meaning or intent of the documents will be issued by written addendum(a), clarification(s), or both. No oral interpretations will be made. It is the Bidder’s responsibility to check the project web pages and plan holder sites for the issuance of addendum(a) and clarification(s) on the project, and to include the same in its bid.
5. Bid Security: Bid Bonds are required for the following Packages: Not Required. The Bid Bond must be executed by a surety company licensed to do business in the State of Georgia and listed in the Department of Treasury Circular 570, latest revision, and on a form acceptable to the
Construction Manager. Said Bid Bond must be accompanied by a Certificate of Power of
Attorney demonstrating that the party executing the bond is authorized to do so by the surety company.
6. Performance and Payment Bonds: Not Required.
7. Award of Bid Packages: The Construction Manager reserves the right to award Bid Packages on whatever basis is in the interest of the Construction Manager and the Owner, and to accept or mailto:%20pwilliamson@winter-construction.com.
reject any or all bids and to waive technicalities and informalities. Attaching qualification(s) or exception(s) to the CM bid form will be considered non-responsive and the bid will be rejected.
8. Form of Agreement: The form of Agreement will be the Construction Manager’s standard subcontract form. This subcontract is available for review upon written request.
9. Insurance Requirements: Subcontractors are required to purchase and maintain insurance coverage in accordance with the Contract Documents, but in no case less than that required by law and the sample Certificate of Liability Insurance attached as Exhibit 1 to these Instructions to Bidders.
10. Progress Payment: Construction Manager will pay the Subcontractor for the performance of its work after payment is received from the Owner, subject to additions and deductions for changes as provided in the Contract Documents and deductions, set offs, retainage, damages, and/or abatements of the Owner. Unless specified otherwise, requests for progress payments are to be submitted monthly no later than the 25th day of the month on the Construction
Manager’s standard “Subcontractor Application for Payment” form, including any supporting documentation required by the Construction Manager.
11. Final Payment: Final payment will be made when the work described in the subcontract is fully completed and performed in accordance with the Contract Documents, and upon written acceptance from the Architect and Owner, and Contractor has received payment for such work from the Owner.
12. Georgia Security and Immigration Compliance Act (O.C.G.A. § 13-10-90): Subcontractors are required to be in full compliance with all applicable state and federal security and immigration laws as a condition to bid and perform work on this project. Evidence of this compliance will be required as a condition of award.
General Package Requirements:
1. By submitting a proposal, the Bidder warrants that it has fully examined the Bid Documents and conducted a thorough inspection of the site and is fully informed as to the nature of the work and all conditions relating to its completion. Further, Subcontractor warrants that all special precautions required to complete the work and ensure existing items to remain are protected are included in its pricing.
2. Subcontractor shall be bound to the Construction Manager by the terms of the Contract
Documents and the subcontract, and assume toward the Construction Manager all obligations and responsibilities that the Construction Manager, by those documents, assumes toward the
Owner, as applicable to the subcontract.
3. Subcontractor shall: (1) comply with all federal, state, and local laws and ordinances applicable to the building(s) or structure(s); (2) comply with and give adequate notices relating to the work and its inspections to the proper authorities; and (3) secure and pay for all necessary licenses, permits, and fees required to carry on the work as described in the Contract Documents.
4. Subcontractor shall comply with all federal, state, and local tax laws, social security laws, unemployment compensation laws, and workmen's compensation laws applicable to the performance of the subcontracted work.
5. Subcontractor shall not discriminate against any employee or applicant for employment because of race, creed, color, or national origin.
6. Subcontractor shall comply with federal, state, and local regulations concerning pollution and contamination, and shall be responsible for all penalties, fees, and clean-up expense(s) resulting from improper handling of or exposure to materials deemed to be hazardous in any way and related to the Subcontractor’s scope of work.
7. After award, and upon receipt of the subcontract documents, Subcontractor agrees to execute and return the Construction Manager’s subcontract, including all supporting documentation required, within two (2) days. A copy of Construction Manager’s standard subcontract is attached as Exhibit 2 to these Instructions to Bidders. Further, the Subcontractor agrees to commence work when requested and in accordance with the project schedule.
8. Unless specifically stated otherwise in the body of the subcontract, all shop drawings, brochures, samples, and other submittals required by the Contract Documents and the
Construction Manager for the work must be submitted for review within two (2) weeks after receipt of the subcontract.
9. Unless specifically stated otherwise in the body of the subcontract, all close-out documents, O&M Manuals, and other submittals required by the Contract Documents and the
Construction Manager for the work must be submitted for review within two (2) weeks after notice from Construction Manager.
10. By submitting its Bid, the Bidder acknowledges that time is of the essence regarding progress of the work and agrees to adhere to the progress schedule, which will be continuously updated by
Construction Manager. This is a fast-track project.
11. Bidder agrees to meet and consult with the Construction Manager concerning value engineering options, cost analysis, scheduling, and coordination required on the project prior to and after award as necessary.
12. Subcontractor shall comply with all statutory and contractual safety requirements applicable to its work or initiated by the Construction Manager and shall report within 24 hours to the
Construction Manager any injury to the Subcontractor's employees at the project site.
13. Compliance with the Construction Manager’s safety plan is a requirement of the work.
14. Subcontractor will not sub-let, assign, or transfer the subcontract, or any part thereof, or assign any payment, to another party or other parties without the written consent of the
Construction Manager.
15. Subcontractor shall include all mobilizations necessary to complete the work in accordance with the CM’s schedule.
16. Subcontractor is required to attend, and participate in, periodic project progress, coordination, and Owner’s meetings as requested by the Construction Manager. These meetings shall be attended by a representative of Subcontractor authorized to make any required decisions on behalf of Subcontractor.
17. Upon request, Subcontractor will furnish periodic progress reports of the work, including the progress, transportation, and delivery of materials and equipment that may be in the course of preparation or manufacture.
18. Subcontractor agrees to schedule and coordinate its work so as not to conflict or interfere with the work of others.
19. Subcontractor agrees that all work shall be done subject to the final approval of the
Construction Manager, Architect, and Owner, or their authorized agents, and that their decision shall be final, if within the terms of the Contract Documents.
20. Subcontractor shall guarantee its work against all defects of material(s), workmanship, or both as called for in the Contract Documents, or if no guarantee is called for, then for a period of one year from the date of partial or total acceptance of the Subcontractor's work by the Construction Manager, Architect, and Owner.
General Package Code of Conduct Requirements:
1. Bidder agrees to comply with all local, state, and federal requirements for conducting work on a public-school campus.
2. Subcontractors, including their employees and agents for whom they are legally responsible, are strictly forbidden from interacting or communicating with any student, faculty, staff, parent, or pedestrian on the school campus at any time. The Construction Manager will follow a ZERO
TOLERANCE POLICY in this regard. Any person(s) found in violation of this policy will be permanently removed from the site and subject to any applicable legal ramifications.
3. Subcontractors, including their employees and agents for whom they are legally responsible, are strictly forbidden from bringing weapons, alcohol, or controlled substances onto the school campus, including those areas designated as “Drug Free/Weapon Free” by the applicable Board of Education, at any time. Any person(s) found in violation of this policy will be permanently removed from the site and subject to any applicable legal ramifications.
4. Subcontractor shall always exercise extreme caution during its work on site.
5. Construction personnel must be readily identifiable from non-construction personnel while on site. Attire shall conform to OSHA requirements and be appropriate for a public-school campus.
6. Construction personnel must follow school system policy regarding the use of tobacco while on campus.
7. Swearing is unprofessional and should not take place in the presence of any student, faculty, staff member, parent, Owner representative, or other person on campus sensitive to the same.
8. The site shall be kept clean of all food debris. Any person(s) witnessed littering will subject his or her associated company to cleanup expenses. Once construction reaches the point deemed appropriate by Construction Manager, food and drinks will no longer be allowed in the building.
General Package Work Requirements:
1. Subcontractor shall have a full-time, competent supervisor, who is acceptable to Construction
Manager, on site at all times. This supervisor will not be replaced without the consent of
Construction Manager.
2. At no time will work interrupt school activities or utilities. In the event of a conflict, the school schedule will prevail, and construction activities will alter or cease as needed.
3. The following temporary facilities and services will be available on site for the use of all trade contractors: temporary toilets. All other temporary facilities, utilities, dumpsters, equipment, etc.
required by Subcontractor to complete its scope of work shall be furnished and paid for in full by Subcontractor.
4. For purposes of this Work, “hazardous substance” shall mean any contaminant, waste, substance, or other material that poses a risk of violating any local, state, or federal law, regulation, or ordinance, or is deemed environmentally hazardous, toxic, or harmful by any local, state, or federal environmental protection or other agency, including, without limitation, asbestos, polychlorinated biphenyls, petroleum products, flammable explosives, radioactive materials, and infectious substances. Subcontractor shall not bring any hazardous substance to the jobsite and hereby agrees to fully defend, indemnify, and hold Construction Manager and
Owner harmless from and against any and all liability, claims, losses, penalties, costs, expenses, damages, and causes of action suffered or incurred by Construction Manager, Owner, or both, resulting in any manner whatsoever, directly or indirectly, from the presence of any hazardous substance as a result of the actions of Subcontractor. If Subcontractor encounters any material on the jobsite reasonably believed to be a hazardous substance, Subcontractor shall immediately notify Construction Manager. Subcontractor shall not disturb material believed to be a hazardous substance.
5. Subcontractor shall take all precautions necessary to protect its work and that of other trades at all times. Any work, finished or otherwise, damaged by the Subcontractor shall be corrected immediately by the Subcontractor at its own expense.
6. Subcontractor is responsible for always keeping the building and premises clean of debris arising out of its work, including removal of the same from the site. This includes both daily and final clean-up. Burn barrels are prohibited on the site.
7. Testing is by the Owner. Subcontractor is responsible for the cost of re-testing of non-conforming work.
8. Damaged fireproofing or insulation shall be replaced at the expense of the Subcontractor responsible for the damage.
9. Subcontractor is responsible for replacing or restoring any exterior area(s) it disturbs.
10. Subcontractor shall be responsible for all sleeves, fire-safing, and fire-caulking at all wall and roof penetrations, if any, made in conjunction with its work.
END OF INSTRUCTIONS TO BIDDERS