ITB_CC20260901final60reel.pdf
PDF 2 MB Posted
- Attached to
- Bay County - Reels To Reefs
- Solicitation number
- CC202609-01
- Issued by
- Bay County, Florida
About this file
This Invitation to Bid (ITB) document pertains to Bay County, Florida, in collaboration with the Bay County Artificial Reef Association (BCARA) and Oceaneering, for the deployment of industrial cable reels as part of the Reels to Reefs project. The scope of work involves deploying 60 reels across 14 different patch reef locations offshore of Bay County. The reels consist of two size categories: 24 reels measuring approximately 9.8 feet in diameter by 7.6 feet in width, weighing 4,060 pounds each, and 36 reels measuring 8.3 feet in diameter by 6.6 feet in width, weighing 2,760 pounds each. Respondents must account for a critical deadline requiring all reels to be deployed or removed from the storage site and transported to an alternate location no later than November 17, 2026, and must incorporate this deadline into their proposed pricing and work schedule. Detailed material specifications, permit area information, and deployment site location details are provided in Section II.2 of the ITB.
The Reels to Reefs project is funded through the Coastal Corridor Project, a state-funded initiative implemented by the Fish & Wildlife Foundation of Florida through direct appropriation by the Florida Legislature. The project is administered via a grant contract with the Florida Fish and Wildlife Conservation Commission (FWC). The ITB invites qualified contractors to submit bids for the offshore deployment services, with all pricing and scheduling proposals due to reflect the November 17, 2026 deadline constraint.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ITAITBCC20260901.pdf | ||
| 20261013__Bid_Response_Tabulation.pdf | ||
| Addendum_No120261007.pdf | ||
| FWC-25118_CoastalCorridorGrant_EXECUTED.pdf | ||
| PERMITLAARS_AB.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FISH & WILDLIFE FOUNDATION OF FLORIDA
INVITATION TO BID
ITB # CC202609-01
COASTAL CORRIDOR PROJECT – ARTIFICIAL REEF DEPLOYMENT:
Reels To Reefs
RESPONDENT ACKNOWLEDGEMENT FORM
Purpose: The intent of this ITB is to seek a qualified contractor to deploy artificial reef structures within designated corridors in the state of Florida, per the specifications contained herein, in accordance with FWC Contract No. 25118 and Chapter 287, Florida Statutes. Only responsive and responsible Respondents will be considered for award of this ITB.
Responsive: To be responsive, a response must constitute a definite, firm, unqualified and unconditional offer to meet all the material terms of this ITB. Material terms are those that could affect the price, quantity, quality, or delivery. Also included as material terms are those which are clearly identified in this ITB and which, for reasons of policy, must be complied with at risk of response rejection for non-responsiveness.
Non-Responsive: Any submission that does not comply with this ITB in any way, does not contain all the properly signed forms, supplements or deviates from the ITB requirements or has an incomplete Cost Sheet may be considered nonresponsive at the discretion of Fish & Wildlife Foundation of Florida, Inc.
(hereinafter “Foundation”).
Responsible Companies: The Foundation shall only consider responsible companies. Responsible companies are those that have, in the sole judgment of the Foundation, the financial ability, experience, resources, skills, capability, reliability and business integrity necessary to perform the requirements of the contract. The Foundation may also consider references and quality to determine the responsibility of the Respondent. The Foundation reserves the right to use any information, whether supplied through the Respondent’s submission or otherwise obtained, in determining responsibility.
Rejection of Reponses: The Foundation reserves the right to reject any and all responses and to waive any minor irregularity in the submissions received in response to this ITB. The Foundation reserves the right to consider all information, whether submitted or otherwise, to determine responsiveness and responsibility and to reject responses accordingly.
Name of Business: _____________________________________________________________________________________________
Contact Person Name: __________________________________________________________________________________________
Business Address: _____________________________________________________________________________________________
City: ________________________________ State: ___________________________________ Zip code:_______________________
Phone:________________________________ Fax:___________________________ Email:__________________________________
Federal Employer Identification Number:_________________ Respondent Unique Entity Identifier Number (UEI) __________________
I certify that this ITB response is submitted without prior understanding, agreement, or connection with any corporation, firm, or person submitting a response for the same goods and services and is in all respects fair and without collusion or fraud. I agree to abide by all conditions of this ITB and certify that I am authorized to sign this acknowledgement for the Respondent.
Authorized Signature (Manual): ___________________________________________________________________________________
Authorized Signature Name (Typed) and Title: ______________________________________________
Date: ___________________________________
CALENDAR OF EVENTS
ITB # CC202609-01
FWC Contract No. #25118
For technical assistance with VendorLink, contact support@evendorlink.com
SCHEDULE DUE DATE METHOD
ITB Advertised 9/30/2026 Posted on the VendorLink Bid Details Page:
https://www.myvendorlink.com
Deadline for Questions
Must be received
NO LATER THAN:
11:59PM ET on 10/6/2026
See Deadline for Questions Clause
Anticipated date for Responses to Written Questions 10/7/2026
Posted on the VendorLink Bid Details Page:
https://www.myvendorlink.com
SEALED RESPONSE DUE
Must be received
NO LATER THAN:
11:59PM ET on 10/12/2026
Submitted through VendorLink Bid Details Page:
Submissions are due BEFORE the date and time of the public opening.
Public Response Opening 10/13/2026
Public Opening Location:
via teleconference or virtual platform, with instructions to be provided to all Respondents prior to opening
Anticipated Date of Intended Award 10/16/2026 Posted on the VendorLink Bid Details Page:
I. PURPOSE
The purpose of this Invitation to Bid is to seek a qualified contractor for the deployment of industrial cable reels offshore of Bay County, Florida. The scope consists of deployment of 60 reels at 14 different patch reef locations. Reels range in size from approximately 9.8 feet in diameter by 7.6 feet in width, weighing 4,060 pounds each (n = 24) to 8.3 feet in diameter by 6.6 feet in width, weighing 2,760 pounds each (n = 36). These materials are available through a collaborative effort with the Bay County Artificial Reef Association (BCARA) and Oceaneering.
This individual project is funded through the Coastal Corridor Project, a state-funded initiative implemented by the Fish & Wildlife Foundation of Florida via direct appropriation by the Florida Legislature, and administered via grant contract with the Florida Fish and Wildlife Conservation Commission (FWC).
Detailed material, permit area, and deployment site location information, and intended site design criteria are available in Section II.2 of this ITB.
II. SCOPE OF WORK
1 DEFINITIONS
1.1 “Artificial reef”, “habitat structure”, and “habitat support structure” means one or more manufactured or natural objects intentionally placed on the bottom in predominantly marine waters to provide conditions believed to be favorable in sustaining, or enhancing the spawning, breeding, feeding, or growth to maturity of Florida’s managed reef associated fish species as well as to increase the productivity of other reef community resources which support fisheries. Included in this definition are artificial reefs developed with one or more of the following additional objectives:
enhancement of fishing and diving opportunities, fisheries research, and fisheries conservation/preservation purposes.
1.2 “Permitted area” means an area with discrete boundaries inside of which one or more artificial reefs may be located and for which all required permits and authorizations have been obtained. These permits and authorizations include: artificial reef permits issued by the Florida Department of Environmental Protection and/or the Army Corps of Engineers and other permits, licenses, or authorizations required by any governing body.
1.3 “Staging area” means a land-based holding area for artificial reef material where such material is stored and prepared for transportation to an approved artificial reef site.
1.4 “Foundation” refers to the Fish & Wildlife Foundation of Florida, Inc.
1.5 “FWC Contract No. 25118” or “#25118” refers to the grant contract, administered by the Florida Fish and Wildlife Conservation Commission (FWC), for the Foundation to implement the state-funded Coastal Corridor initiative.
1.6 “Fully burdened per unit cost” is the total cost per unit to acquire/fabricate, transport, and deploy. This includes but is not limited to ground transportation/loading, staging/storage of reef materials, labor, vessel costs, administration and mobilization fees.
2 PROJECT LOCATION AND DESCRIPTION
2.1 Material Staging Location:
1798 Hannah Drive, Panama City, FL 32401 or adjacent properties.
Due to limited storage capacity, all reels must be deployed or transported to an alternate off-site location by November 17, 2026.
Available Material Loading Facility:
Respondents are not obligated to use the material loading facility described below. However, the Bay County Artificial Reef Association (BCARA) has established a partnership with the Port of Panama City and SSA Gulf to facilitate drayage and loading of materials.
Port of Panama City, 1 Seaport Dr., Panama City, FL 32401
If the selected contractor choses to load at the Port of Panama City, they shall be responsible for any costs related to facility access and loading. BCARA has received a rate of $365.00/straight time hour and an overtime differential of $240.70/hour that selected contractors are eligible for pursuant to this project.
Rates include stevedoring license, qualified labor, supervision, forklifts, trucks with trailers, and proper gear to handle reels. Overtime will apply when working past 1800 on Monday – Friday, all weekend hours, and working holidays.
Labor callout times are 0700, 0800, 1000, and 1800. Meal breaks are 1200-1300.
Labor will be scheduled the day prior to commencing operations before 1700.
Labor guarantee time is typically 4-hour minimum except 0700 start times, which is a 5-hour minimum. If labor is called back after a meal break, there is a 2-hour minimum.
Neither the Foundation nor BCARA shall be responsible for changes in rates and/or availability.
Reef Locations:
Seven patch reefs shall be created in Bay County’s Large Area Artificial Reef Site (LAARS) A, and seven patch reefs shall be created in Bay County LAARS-B.
Table 2 provides the number and size of reels to be deployed at each individual patch reef, patch reef location details and the distance of each patch reef from St.
Andrews Bay Entrance Buoy 4.
These locations are authorized as artificial reef permit areas by the U.S. Army Corp of Engineers.
Table 1. ArƟficial Reef Permit Area SpecificaƟons
Permit Holder
Permit Area
ACOE Permit ACOE Permit
Expiration
Required Navigational
Clearance (ft)
Bay County
BOCC
LAARS-A SAJ-1993-00660
(SP-LSL)
1/12/2027* 50
LAARS-B
* Permit renewal in review
Table 2. Individual Patch Reef LocaƟons.
Reef
ID
# and Size of Reels
Latitude Longitude Chart Depth
(ft)
Distance (nm) from St.
Andrews Bay Entrance
Permit Area
LAC3 4S 30.014556 -85.876524 93.7 9.26 LAARS-A
LAC1 4S 30.017951 -85.881862 93.5 9.35 LAARS-A
LAC11 4L 30.013560 -85.880770 93.6 9.47 LAARS-A
LAC6 4S 30.010119 -85.880181 96.5 9.58 LAARS-A
LA3 4S 29.988167 -85.860033 95.4 9.79 LAARS-A
LA8 4S 29.958250 -85.860000 105.3 11.24 LAARS-A
LA6 4S 29.967833 -85.904417 107.3 12.24 LAARS-A
LB18 4L 29.929817 -85.967633 127.4 16.19 LAARS-B
LB15 4L 29.885267 -85.958917 125 17.82 LAARS-B
LB23 3L; 1S 29.825117 -85.881883 118.9 18.83 LAARS-B
LB24 4L 29.816383 -85.927517 125.2 20.33 LAARS-B
LB11 5S 29.760850 -85.909183 128.5 22.93 LAARS-B
LB10 4L 29.766333 -85.957183 134.8 23.71 LAARS-B
LB17 5S 29.737883 -85.978917 140 25.74 LAARS-B
* Size: S = 8.3ft dia. reel and L = 9.8ft dia. Reel
2.2 Project-specific material standards:
2.2.1 The selected contractor shall be responsible for all costs and logistics related to accessing available material, transportation and loading, and materials deployment. The Foundation and/or BCARA shall facilitate coordination with the Port of Panama City and SSA Gulf as needed.
2.2.2 For all material deployments, the contractor shall use at least a two-point anchoring system or a method capable of maintaining position with minimal movement (± 50ft) to ensure materials are consolidated to the best extent possible on the seafloor.
2.2.3 Representative photos of materials at staging location:
3 MINIMUM MATERIALS REQUIREMENTS
All materials must comply with any State and/or Federal permit requirements and project-specific material standards discussed in Section 2.2. In addition:
3.1 All artificial reef materials shall be clean and free from dirt, asphalt, creosote, petroleum, or other hydrocarbons and toxic residues, loose free-floating material or other deleterious substances.
3.2 The Contractor agrees to allow the Foundation and/or FWC to conduct on-site inspections of the staging sites as well as artificial reef materials before, during, and after the deployment.
4 LOADING AND TRANSPORTATION REQUIREMENTS
4.1 The Contractor will provide all personnel, equipment, and materials necessary to complete work under this Contract including vessels, vehicles, and protective equipment. The Contractor will be responsible for each job site at all times during work covered by this scope of work.
4.2 The Contractor is required to obtain and have present on each job site all active local, state, and federal licenses, certifications, and permits required to fulfill each aspect of work under this Contract.
4.3 The Contractor is responsible for all costs and liabilities associated with moving the reef material from its current location to any other location for storage or deployment, and deploying the habitat support structure.
4.4 Unless otherwise approved in writing in advance, the following general requirements are to be followed:
a) Artificial reef materials will be loaded using a suitable means of conveyance for transportation to a staging area site and loading onto a barge or other suitable vessel for offshore transportation to the designated artificial reef site.
Offshore transportation shall be provided by a sufficiently powered transport or towing vessel, and shall include the necessary personnel and equipment to safely transport and deploy the reef material. Reef material loaded on to the transporting vessel must be properly secured in compliance with Coast Guard standards to allow for its safe transport to the reef deployment site.
b) The Contractor is responsible for ensuring the FWC Artificial Reef Cargo Manifest form is maintained onboard the vessel at all times during transport of materials, pursuant to Chapter 379.249, F.S. The Foundation will provide printed or electronic copies of the form prior to each deployment.
c) For each load of artificial reef materials, the Contractor shall inventory all of the material, calculate the tonnage (either using before and after barge draft calculations, trucking receipts, or the known weights of individual pieces or reef materials), and take a representative photograph of the artificial reef material on the barge or other deployment vessel immediately prior to deployment.
d) The Contractor upon request agrees to provide to the Foundation Project Director an updated inventory report that accurately describes the staging area materials recommended for artificial reef utilization. The inventory report will include a brief narrative of the material stockpile, pictures, and estimated weight of individual reef material.
e) The Foundation reserves the right to stop or delay work for non-compliance with the Purchase Order specifications or if site conditions become unacceptable.
5 DEPLOYMENT AND MATERIAL PLACEMENT REQUIREMENTS
5.1 Unless described in further detail in Section 2.2, the Contractor shall be responsible for ensuring the transport vessel is effectively moored through double anchoring, spudded down, dynamically positioned, or otherwise held securely in place with minimal movement (+/-50 feet) to ensure accurate placement of the materials on the bottom. The Contractor will confirm deployment locations with the Foundation in advance of deployment, and will use a secondary method to confirm proper positioning of the deployment vessel. Secondary methods include either onboard-radar detection, or a handheld GPS, to monitor the GPS location of the deployment vessel throughout the course of the deployment. Material must be arranged to provide habitat complexity as well as provide sand bottom forage area opportunities.
Individual reef materials should not be widely scattered.
5.2 The Contractor is responsible for ensuring that any machinery used to move and deploy the reef materials should be sufficiently powered/maneuverable and capably operated to ensure timely, effective and safe off-loading of materials. The tug or transport vessel shall meet all U.S. Coast Guard certification and safety requirements, be equipped with a working, accurate Global Positioning System (GPS) unit and other marine electronics including a working VHF radio. Effective and reliable communications shall exist at all times between the transport vessel, and the designated Foundation observer on site.
5.3 Deployment operations will only be initiated when sea height in the operations area is no greater than two to three feet as forecast by the nearest NOAA weather office.
Either FWC’s observer, the Foundation's observer or the subcontractor’s vessel captain reserves the right to suspend off-loading operations if positioning and other deployment objectives, including safety of personnel and equipment, are not being met.
5.4 All special and standard conditions described in the Army Corps of Engineers Permits for the selected reef site(s) must be met.
5.5 The minimum vertical clearance shall be maintained above the highest point of the reef material in the permitted site (in accordance with the special conditions of the US Army Corps of Engineers permit).
5.6 The Contractor shall have on site current nautical charts of the deployment area, with the permitted site indicated on the chart. The proposed patch reef coordinates and the corner coordinates of the reef site will also be in possession of the Contractor when on site.
5.7 The Foundation’s Project Director or designated official observer shall oversee temporary marking of reef deployment location boundaries in advance of artificial reef materials deployment. The Contractor shall comply with boundary requirements or any necessary modifications by the Project Director or official observer prior to deployment of materials.
5.8 The Foundation’s Project Director or designated official observer shall remain onsite during the entire deployment phase.
5.9 The Contractor shall be prepared to remove any floating debris that might occur during deployment. Having boat hooks, dip nets, and other equipment on board to enable efficient collection of unanticipated floating debris is strongly encouraged. The Contractor shall be responsible for ensuring that any floating debris discovered during deployment operations (e.g., wood, floating line, aluminum cans, plastic bottles, or other floating materials) shall be collected and transported back to land for proper disposal.
5.10 The Contractor shall be responsible for removal of, or coordination of removal with the Foundation’s designated deployment observer, any lifting lines or straps used to lower reef materials to the seafloor.
5.11 The Contractor shall be responsible for all costs and liabilities associated with deploying artificial reef materials. This shall include compliance with all federal, state, or local requirements or permit conditions governing transportation and deployment of artificial reef materials.
6 DOCUMENTATION TO BE COLLECTED AND PROVIDED BY CONTRACTOR
6.1 The Contractor shall provide a detailed description of all material intended to be deployed as an artificial reef, including type, quantity, and dimensions and individual weight of various sizes of materials to be deployed at the beginning of each project.
All materials must be prepared for visual inspection no later than 16 days prior to intended deployment activities.
6.2 The Contractor shall provide written notice no later than 36 hours prior to scheduled departure for deployments, and continuous notifications as the deployment date approaches. This notification alone shall not be misconstrued as adequate communication between the Contractor and Foundation Project Director during other phases of the project.
6.3 The Contractor shall provide a post-deployment description of all materials deployed as an artificial reef. This must include an accurate material tonnage; a detailed description of type, quantity, dimensions and individual weights of various sizes of materials deployed; highest recorded relief (distance of materials above seafloor) of the site; and accurate GPS coordinates of individual reefs created. Post-deployment information must be provided no more than 72 hours following an individual deployment day unless otherwise approved in writing by the Foundation.
7 DOCUMENTATION TO BE COLLECTED AND PROVIDED BY FOUNDATION
7.1 Unless otherwise provided in this scope of work, within 30 days following contract award, the Foundation Project Director shall provide the Contractor with a specific list of coordinates for each of the proposed reef locations. In the event minor modifications to any coordinates provided in this scope are necessary to ensure permit compliance, the Foundation Project Director shall provide updated coordinates prior to departure for deployment activities.
7.2 The Foundation Project Director shall provide a copy of artificial reef permit conditions to the Contractor. The Contractor is responsible for compliance of all permit conditions, including the general and special conditions specified in any permits issued by the Department of the Army, Corps of Engineers and/or the Florida Department of Environmental Protection.
7.3 The Foundation Project Director shall provide the Contractor with a copy of the FWC
Artificial Reef Cargo Manifest form and the Contractor is responsible for ensuring this form is maintained onboard the vessel at all times during transport of materials, pursuant to Chapter 379.249, F.S.
8 PROJECT COORDINATION & MINIMUM REPORTING EXPECTATIONS
8.1 The Contractor will be responsible for having periodic project update meetings with the Foundation Project Director. These meeting should occur at intervals of a minimum of once a month and the Contractor should provide an update of work performed to date, and schedule that describes remaining work necessary and when the anticipated deployment will take place. The Foundation may create a “punch list” of remediation items that must be addressed prior to deployment. These meeting may be available through virtual means (TEAMS, Skype, Zoom, etc.), on the phone, or in-person discussions with the Project Director and Contractor.
8.2 Recognizing that weather and other considerations may delay deployment operations, the Contractor must regularly communicate with the Foundation Project Director regarding any delays in work required under the Agreement and reasons for such delays, as well as when deployment efforts are scheduled to continue.
8.3 Upon request, the Contractor will convey all necessary information to the Foundation to support coordination with local, state, and federal agencies as required.
8.4 The Contractor shall notify the Foundation Project Director at least thirty (30) days prior to project (artificial reef deployment) commencement to coordinate pre-deployment matters. The Contractor shall provide timely updates leading up to the day of deployment to allow coordination of observers and notification applicable permitting/regulatory agencies, with no less than 36 hours’ notice of intent to deploy being provided. Any additional coordination will be identified by the Project Director.
9 CALENDAR OF PROJECT EVENTS
9.1 Notwithstanding timelines indicated in Section 2.1, the deployments related to the this ITB must be completed prior to December 31, 2026. No compensation will be made for any work completed prior to issuance of a Purchase Order pursuant to this ITB or after this date unless agreed upon in writing in advance.
10 PAYMENT REQUESTS
10.1 The amounts on the Cost Sheet submitted by the Contractor (Exhibit III) shall be used as the maximum ceiling rates for the work completed by the Contractor for all work done, including all cost associated with the fabrication/acquisition, loading, transportation, and deployment of the artificial reef.
10.2 Invoices shall include the following information, at a minimum:.
a. Purchase Order Number,
b. Contractor’s federal employer identification number,
c. Contractor’s invoice date,
d. Contractor’s invoice number,
e. Contractor’s address,
f. Date(s) of service (date Contractor began the project work and date all
Contractor work ended; or dates of service which the invoiced amount applies),
g. Type, quantity, and per unit cost of habitat support structure deployed,
h. Photos of the habitat support structure on the barge or other deployment vessel immediately prior to deployment
i. Completed Final Deployment Details form, in full, for each habitat support structure deployed (Exhibit X - Attachment E)
10.3 Unless otherwise approved by the Foundation, invoices shall be submitted upon the successful completion of each project. At the Foundation’s discretion, partial payment may be authorized when requested by the contractor prior to execution of the Purchase Order. In such cases, the Foundation shall establish a partial payment schedule based on satisfactory completion of defined performance milestones, deliverables, or other measurable progress as determined by the Foundation.
11 LIABILITY AND RESPONSIBILITY FOR REEF MATERIALS
11.1 Upon initiation of the handling and movement of these artificial reefs by the contractor, all liability, risk of loss and responsibility for the safe handling, storage, transportation and deployment of the materials shall be the responsibility of the contractor. This liability, assumption of risk and responsibility shall remain with the contractor until the material are deployed at the permitted reef site in accordance with the specification of this Agreement.
12 FINANCIAL CONSEQUENCES
12.1 Materials deployed outside of permit area boundaries or above minimum navigational clearance requirements indicated in this Scope MUST be removed by the CONTRACTOR prior to any payment.
13 DELIVERABLES
13.1 The following service(s) or service tasks are identified as deliverables for the purpose of this Agreement:
a) Deployment of materials as set forth in this Scope of Work.
b) Submission of a completed Final Deployment Details form to Foundation’s
Project Director.
III. BID EVALUATION AND MANDATORY REQUIREMENTS
General evaluation criteria include the following:
1. The Foundation reserves the right to accept or reject any or all responses received and reserves the right to make an award without further discussion of the responses submitted. Therefore, responses should be initially submitted as outlined in the Mandatory Responsiveness Requirements for Response Submission section.
2. Non-responsive responses shall include, but are not limited to, those that:
a. are irregular or are not in conformance with the requirements and instructions contained herein;
b. fail to utilize or complete prescribed forms; or
c. have improper or undated signatures.
3. The Foundation may waive minor irregularities in the responses received that are merely a matter of form and not substance, and the corrections of which are not prejudicial to other respondents.
A NON-RESPONSIVE RESPONSE WILL NOT BE CONSIDERED.
The Respondent must submit the following information with their response. Failure to provide the required information is considered sufficient cause for the Foundation to reject the bid.
TAB A. Respondent Acknowledgment Form (Mandatory) The Respondent shall complete and submit the Respondent Acknowledgment Form (page
1) in its entirety and return the form as part of the ITB response or the response shall be deemed nonresponsive.
TAB B. References (Mandatory) — Exhibit I The Respondent shall complete and submit the References form enclosed herein, to provide a minimum of three (3) references for similar projects completed. Current contact names, phone numbers and email addresses shall be given. This information shall be provided on the Reference Form, enclosed herein, and submitted with the response. The References form shall be completed in its entirety and returned as part of the ITB response or the response shall be deemed non-responsive.
TAB C. Experience (Mandatory) — Exhibit II The Respondent shall provide a chronological list (starting with most recent experience first) of the Respondent’s prior and relevant experience to include any previous work performing acquisition and deployment of artificial reef structures. The list shall include a description of the services provided; and, the location, duration, and cost of the project. The Respondent must provide evidence of a minimum of 3 past experiences performing artificial reef deployment projects as provided herein. The Experience form shall be completed in its entirety, and returned, as part of the ITB response or the response shall be deemed non-responsive.
TAB D. Project Plan (Mandatory) Respondents shall develop a detailed project plan for the transportation and deployment of materials described in Section II.2 of this ITB. The project plan should align with the Calendar of Project Events stated in Section 9. The bidder must submit the following information with their bid response. Bidders may provide additional evidence to support responses. Failure to provide the required information is considered sufficient cause for rejection of their bid by the Foundation.
Schedule of Operation Provide the total number of:
a) Days to transport from and/or load materials on to deployment vessel,
b) Days to deploy material, and;
c) Individual trips necessary to complete deployment
Material Transport/Deployment Methodology Respondents shall provide a brief narrative to:
(a) Describe step-by-step tasks of loading, moving, transporting, handling and deploying materials to the seafloor. Proven methods are preferred.
(b) Describe proposed anchoring or method to accurately deploy materials at the designated GPS coordinates. Methods which achieve greatest accuracy are preferred.
(c) Describe how coordination with the Foundation Project Director will be maintained during each phase of the operation.
If a subcontractor will be used, provide a clear description of operational roles and expectations for the primary and subcontractors.
Deployment Resources Respondent’s shall provide a description of resources available to adequately and safely conduct artificial reef deployment operations pursuant to this bid. Resources should be commensurate with those necessary to deploy reef materials indicated in the Scope of Work. If a subcontractor will be used, then the Respondent must identify any applicable Deployment Resources owned or operated by the proposed subcontractor.
(a) Staging site: If materials will be moved to a different staging site, provide a location and hours of operation where the units will be available for inspection at least fourteen (14) days prior to deployment. Sites must be accessible by the Foundation and/or permitting agency staff upon request.
(b) Provide a list of vessels and equipment available to facilitate deployment of materials in offshore waters. For each vessel, the Respondent must provide the following information:
i. Vessel identification, home port, and owner/operator
ii. Vessel type description: barge, tug, crane barge, support vessel, etc.
iii. Vessel specifications: Length overall, beam, and draft (loaded), maximum payload/load capacity if applicable
iv. Applicable Federal, State, or local vessel certifications/exemptions. (Note:
it is the responsibility of the contractor to ensure all required certifications are current for operation in the planned deployment areas)
(c) The GPS specifications and methods to be used to deploy materials at the target locations and the anticipated deployment accuracy in relation to target coordinates.
Equipment redundancy and installations with the least offset distances are preferred.
TAB E. Cost Sheet (Mandatory) — Exhibit III On the pages provided as Exhibit III, the Respondent shall provide its costs for the goods/services requested in this solicitation. Costs must be “fully burden” costs which shall include all costs necessary to provide the goods and services listed including, but not limited to, employee pay, benefit costs, insurance, travel and incidental expenses, fuel, vehicles, materials, supplies, PPE, disposal, and any other costs necessary for the Contractor to meet project specifications. This information shall be returned as part of the ITB response or the response shall be deemed non-responsive.
TAB F. List of Proposed Subcontractors (Mandatory) – Exhibit IV On the pages provided as Exhibit IV, the Respondent shall provide a list of all proposed subcontractors. The Respondent must submit this form regardless of whether he/she is proposing to use subcontractors. Indicate “N/A” on the form if no subcontractor will be used*. This information shall be returned as part of the ITB response or the response shall be deemed non-responsive.
* Respondents should list SSA Marine, Inc. as a proposed subcontractor if anticipating their services described in Scope of Work Section 2.1.
SSA Marine, Inc.
Florida Division of Corporations Registration # F24000006032
FEIN: 91-2038445
IV. GENERAL CONDITIONS
The Foundation’s mission is to provide assistance, funding, and promotional support to contribute to the health and well-being of Florida's fish and wildlife resources and their habitats. The Coastal Corridor Project (“the Project”) is a State-funded initiative implemented by the Foundation via a five-year, $15 million direct appropriation by the Florida Legislature, and administered via grant contract with Florida Fish and Wildlife Conservation Commission (“FWC”). The goal of the Costal Corridor Project is to deploy artificial habitat structures along Florida’s coastal counties to create a diversified and resilient network of habitats that enhance marine biodiversity, support reef-dependent species, and generate socio-economic benefits to the State of Florida and Floridians.
This ITB seeks to establish an agreement with a qualified marine contractor able to transport and deploy materials as nearshore/offshore artificial reefs throughout coastal counties of Florida, in accordance with local, state and federal regulations as well as best management practices for deploying artificial reefs.
The Foundation reserves the right to reject any proposal, withdraw all or part of this agreement at any time, waive any formalities, or re-advertise for these services. A Respondent submitting a response shall be registered in the VendorLink system and, where required, the Sunbiz system prior to the ITB opening. Business entities which must be on file with Sunbiz include the following foreign and domestic entities: Corporations for and not for profit, Limited Liability Companies (LLC), Limited Partnerships (LP) including Limited Liability Limited Partnerships (LLLP), and organizations doing business under a fictitious name (DBA). A Respondent may not be considered for an award if not registered in the VendorLink and Sunbiz system. The Respondent’s registration address and federal employer identification (FEID) number should match the Respondent’s address and FEID number listed on the Respondent Acknowledgment form (page 1).
Certified Minority-owned, Woman-owned and Service-Disabled Veteran Business Enterprises, as certified by the State of Florida Office of Supplier Diversity, are encouraged by the Foundation to participate in the proposal process.
Response from Respondent shall include all necessary equipment to complete the job. The Respondent is required to supply all specified documentation when submitting a response for this project.
Please note:
The terms “Contract,” “Agreement” and “Purchase Order” are used interchangeably in the document.
The terms “Commodities” and “Goods” are used interchangeably in the document.
TERMS AND CONDITIONS
PUR 1000 and PUR1001 are hereby incorporated by reference. PUR1000 and PUR1001 can be found at the Department of Management Services website at the following link:
https://www.dms.myflorida.com/business_operations/state_purchasing/state_agency_resources/ statepurc hasing pur_forms The following terms and conditions take precedence over the PUR1001 and PUR1000 forms where applicable. “Customer” means the Fish & Wildlife Foundation of Florida, Inc. (also referred to as the “Foundation” in this ITB). Any reference to the Customer as “agency” or
“governmental entity” is hereby changed to the Foundation as a non-governmental and not-for-profit organization. Moreover, any terms in PUR 1000 or 1001 that expressly identify or refer to Customer as exclusively an agency of the executive branch of the State of Florida or a governmental entity of the State of Florida are not applicable to this RFP. The risk of loss terms in PUR 1000, Section 5(h) are modified to align with the terms of FWC Agreement #25118, such that Contractor bears all risk of loss until artificial reef materials are deployed at the permitted reef site in accordance with the specifications of this ITB and the resulting Purchase Order. The payment terms in PUR 1000, Section 7(b) are replaced with the payment terms specified in this ITB. The Transaction Fee in PUR 1000, Section 7(d) only applies to the extent this ITB requires use of the MyFloridaMarketPlace eProcurement system. The Customer’s set off rights in PUR 1000, Section 7(h) apply to liabilities or other obligations of the Contractor or its affiliates to the Foundation. The Insurance Requirements in PUR 1000, Section 8(e) are as stated in Exhibit V – Attachment C. In addition to the exceptions stated in the last sentence of the first paragraph of the Limitation of Liability terms in PUR 1000, Section 8(g), Contractor’s gross negligence or intentional misconduct are also excepted from the Limitation of Liability terms. Subpart (2) of the last paragraph of the Limitation of Liability terms in PUR 1000, Section 8(g) is hereby replaced with the following: “or 2) in the event the damage is not related to the Customer’s failure to comply with the payment provisions of the Contract, the total amount paid under the Contract to Contractor as of the accrual of damages.” PUR 1000, Section 12 is hereby deleted in its entirety. Any award by the Foundation under this ITB to a Respondent shall be final and not subject to further challenge or protest. The following sentence in PUR 1001, Section 13 is deleted: “Any person who is adversely affected by the decision shall file with the Buyer a notice of protest within 72 hours after the electronic posting.” In addition, PUR 1001, Section 20 is deleted in its entirety. Section 4 of Exhibit V-Attachment B (Purchase Order Terms and Conditions) is subject to the insurance requirements as stated in Exhibit V – Attachment C to this ITB. All references in PUR 1001 to MyFloridaMarketPlace are replaced with VendorLink, as identified above in this RFP.
The Foundation objects to and shall not consider any additional terms or conditions submitted by a Respondent or Contractor, including any appearing in documents attached as part of a Respondent’s response. In signing and submitting its response, a Respondent agrees that any additional terms or conditions, whether submitted intentionally or inadvertently, shall have no force or effect. Failure to comply with terms and conditions, including those specifying information that must be submitted with a response, shall be grounds for rejecting a response.
The terms and conditions of Exhibit V-Attachment B, Purchase Order Terms and Conditions, are hereby incorporated into this solicitation. The terms of FWC Agreement #25118 take precedence over Exhibit V-Attachment B. Any contract resulting from this solicitation will include the terms and conditions of this solicitation and the terms and conditions contained in FWC Agreement #25118, attached as Exhibit VI.
TERM
The agreement between the Foundation and selected Contractor will be effective upon issuance of a Purchase Order. All work must be completed by the completion date identified in the Scope of Work of this ITB.
If circumstances constituting Force Majeure have occurred, or if anything occurs beyond the Contractor’s control, the Contractor may request in writing an extension of Completion Date. The Foundation Project Director will review the extension request and if they determine it is justified, will forward to the Foundation for procurement review and approval/disapproval.
SUBCONTRACTS
Subcontracting is permitted pursuant to the Terms and Conditions of the Contract.. A list of subcontractors and their qualifications shall be included with proposal submissions. The Foundation reserves the right to reject any proposal if subcontractors are deemed to not be qualified to perform subcontracted services. The Subcontractor Minority Status Report (Attachment D to Exhibit V) shall be submitted with each invoice for payment. The List of Subcontractors (Exhibit IV) shall be included with this ITB submission.
NON-MANDATORY PRE-PROPOSAL CONFERENCE CALL
A non-mandatory pre-proposal conference call will be held on the date and time specified in the Calendar of Events (Page 3). The purpose of the pre-proposal conference call is to discuss the contents of this ITB and to accept verbal questions from Respondents concerning the project. The Foundation will make a reasonable effort to answer verbal questions asked during the pre-proposal conference call, however, Respondents should clearly understand that verbal discussions held at the pre-proposal conference call shall not be binding on the Foundation, and the Foundation will only issue an official written response to verbal questions subsequently submitted in writing in accordance with the Deadline for Questions clause below.
DEADLINE FOR QUESTIONS
Any questions from Respondents that require an official Foundation answer concerning this project shall be submitted electronically through VendorLink (https://www.myvendorlink.com). Questions must be received no later than the date and time specified in the Calendar of Events (Page 3). It is the responsibility of the Respondent to confirm receipt of questions if needed.
If questions are received, an addendum will be issued and shall be posted on the VendorLink Bid Details webpage (https://www.myvendorlink.com).
LIMITATION ON RESPONDENT CONTACT DURING SOLICITATION PERIOD
Respondents to this solicitation or persons acting on their behalf may not contact, between the release of the solicitation and the end of the 72-hour period following the Foundation posting the notice of intended award, (note the 72-hour posting period excludes Saturdays, Sundays, and federal holidays) any employee or officer of the Foundation concerning any aspect of this solicitation, except in electronically through VendorLink (https://www.myvendorlink.com). Violation of this provision may be grounds for rejecting a response.
VERBAL INSTRUCTION PROCEDURE
Respondents may not consider any verbal instructions as binding upon the Foundation. No negotiations, discussions, or actions shall be initiated or executed by the Respondent as a result of any discussion with any Foundation employee. Only those communications from the Foundation that are in writing may be considered as a duly authorized expression on behalf of the Foundation.
ADDENDUMS
If the Foundation finds it necessary to supplement, modify or interpret any portion of the specifications or documents or answer any Respondent questions during the solicitation period, an addendum shall be posted on the Vendor Information Portal website. Each Respondent is responsible for monitoring the VendorLink Bid Details website (https://www.myvendorlink.com) for new or changing information relative to this procurement. The Foundation bears no responsibility for any delays, or resulting impacts, associated with a Respondent’s failure to obtain the information made available through the Vendor Information Portal.
ECONOMY OF PRESENTATION
Each response shall be prepared simply and economically, providing a straightforward, concise response to each requirement of this ITB. Elaborate binding, colored displays, and promotional materials are not required. However, examples of services provided may be included as attachments to the response. Emphasis in each response must be on completeness and clarity of content. To expedite the evaluation of responses, it is essential that Respondents follow the format and instructions contained herein. All costs associated with preparing a response to this ITB is the sole responsibility of the Respondent. Respondent shall use no less than 12 point Times New Roman font or its equivalent.
RESPONDENT ACKNOWLEDGMENT
For this response to be considered responsive, the Respondent Acknowledgement Form (page
1) must be completed in its entirety, signed by the Respondent and returned as part of the response.
Otherwise the response will be deemed non-responsive. By affixing your signature to the Respondent Acknowledgement Form, the Respondent hereby states that the Respondent has read all response specifications and conditions and agrees to all terms, conditions, provisions, specifications, and is currently licensed to do business within the State of Florida, if required by State or Federal Law, for the services or commodities the Respondent will provide the Foundation under these response specifications.
CONFIDENTIALITY/PUBLIC RECORDS LAW
Respondents are cautioned that Florida law generously defines what constitutes a public record and grants broad rights of public access to those records (e.g., section 119.07, F.S.). If a Respondent considers any portion of the documents, data or records submitted in their Response to this solicitation to be confidential, proprietary, trade secret or otherwise not subject to disclosure pursuant to Chapter 119, F.S., the Florida Constitution or other authority, the Respondent must mark the document as “Confidential.” The Respondent shall also provide the Foundation with a separate PDF redacted copy of its Response and briefly describe in writing the grounds and specific legal citations for claiming exemption from public records law. This redacted copy shall contain the Foundation’s solicitation name, number and the Respondent’s name on the cover and shall be clearly titled “Redacted Copy.” The Redacted Copy should only redact those portions of material that the Respondent claims is confidential, proprietary, trade secret or otherwise not subject to public disclosure pursuant to Chapter 119, F.S., the Florida Constitution or other authority. If after the notice of intended decision or thirty
(30) days after response opening, whichever is earlier, the Foundation receives a public record request related to the solicitation, the Foundation will provide the Redacted Copy to the requestor. If the Respondent fails to properly indicate any material enclosed in their Response is confidential, the Foundation is authorized to produce documents, data or records in their entirety as submitted to the Foundation in answer to a public records request. The Foundation will endeavor to provide notice to the Respondent of all public records requests received related to documents provided by the Respondent that were marked pursuant to this paragraph. In no event shall the Respondent hold the Foundation or any of its employees or agents liable for disclosing, or otherwise failing to protect the confidentiality of information submitted in response to this solicitation.
SUBMISSION INSTRUCTIONS
The Contractor shall submit the response by uploading the complete response to VendorLink.
THE FOUNDATION IS NOT RESPONSIBLE FOR LATE SUBMISSIONS DUE TO
COMPLICATIONS RELATED TO THE UPLOADING OF THE RESPONSE.
SOLICITATION PUBLIC OPENING
The public opening of this ITB will be conducted at the date, time and method specified in the Calendar of Events (Page 2). RESPONSES RECEIVED AFTER THE SPECIFIED DATE
AND TIME WILL BE REJECTED.
Any person with a qualified disability shall not be denied equal access and effective communication regarding any response documents or the attendance at any related meeting or response opening. If accommodations are needed because of a disability, please contact procurement@wildlifeflorida.org at least three (3) workdays prior to the opening.
SELECTION AND EVALUATION OF RESPONSES
The Foundation shall award this bid to the lowest, responsive and responsible vendor. The Foundation has the right to reject bids, which would result in an award, which is financially disadvantageous to the Foundation.
POSTING OF RESPONSE TABULATION
Response Tabulation, with recommended award(s), will be posted electronically and may be viewed at https://www.myvendorlink.com.
Awarded Respondents are instructed not to proceed until a Purchase Order, Formal Written Contract, Notice to Proceed, or some other form of written notice is given to the Contractor by the Foundation. A company or person who proceeds, or incurs expenses, prior to receiving a Purchase Order, Formal Written Contract, Notice to Proceed, or some other form of written notice from the Foundation does so without a contract and at their own risk.
Sealed responses, proposals, or replies received by the Foundation pursuant to a competitive solicitation are exempt from Section 119.07(1) and Section 24(a), Art. I of the State Constitution until such time as the Foundation provides notice of an intended decision or until thirty (30) days after opening the responses, proposals, or final replies, whichever is earlier.
CONTRACT & NOTICE TO PROCEED
The successful Respondent’s response and all purchase orders issued pursuant to the response shall form the contract between the parties. In the event there is any disagreement between the documents, the parties shall refer first to the Request for Proposal then to Contractor’s response.
The Foundation reserves the right to revise the Purchase Order as necessary to meet the requirements of this ITB.
No work shall begin on any project until the Foundation has authorized a Purchase Order for a specific project and the Contractor has emailed the designated Foundation Project Director confirming receipt of the Purchase Order.
SCOPE CHANGES AFTER CONTRACT EXECUTION
The Foundation shall provide written notice to the successful Contractor thirty (30) days in advance of any Foundation required changes to the technical specifications and/or scope of service that affect the successful Contractor’s ability to provide the service as specified herein. Any changes that are other than purely administrative changes will require a change order.
LIQUIDATED DAMAGES
If the Contractor fails to complete the work or the conditions of the Purchase Order and/or Change Orders by…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .