This Invitation to Bid (ITB 27-112) is issued by the City of Salisbury, Maryland Department of Procurement for interior coating work on the Wor-Wic Water Tower. The project involves applying interior coating to the water tower structure. Bids must be submitted electronically through the City's Procurement Portal via Procureware prior to the deadline specified in the Advertisement or ITB. All copies of bid documents, bid security, and required documentation must be submitted electronically; bids received after the specified date and time or through any means other than electronic submission will not be accepted. The City reserves the right to reject any or all bids, award in whole or in part, add or delete quantities, waive informalities or irregularities, and award the contract in its own best interests. The contract will be awarded to the lowest responsive and responsible bidder provided the price is reasonable and does not exceed available funds. The guarantee period will last for two years from the date of Final Acceptance unless otherwise specified.

Bid security in the form of a bid bond, certified check, or cashier's check is required in an amount not less than five percent of the base bid, made payable to the City of Salisbury. The successful contractor must furnish a Performance Bond and Labor and Materials Payment Bond, each in an amount equal to one hundred percent of the contract price. The contractor is required to maintain Commercial General Liability insurance of $1,000,000 per occurrence and $3,000,000 aggregate, Commercial Automobile insurance of $1,000,000 combined single limit, and Workers' Compensation insurance as mandated by Maryland law. The City must be named as an additional insured on the Commercial General Liability policy. Retainage will be withheld at ten percent of the estimated amount with a maximum of five percent of the total contract amount until final acceptance, or the contractor may provide a Maintenance Bond in the amount of five percent of the contract cost. Liquidated damages will be assessed at rates ranging from $100 to $1,000 per calendar day depending on contract value if the contractor fails to achieve Final Acceptance by the deadline.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Invitation to Bid ITB 27-112

Wor-Wic Water Tower Interior Coating

Department of Procurement

125 N. Division St., Room 200, Salisbury, MD 21801

PH: 410-548-3190 FX: 410-548-3192

Salisbury, MD 21801

ITB 27-112 Wor-Wic Water Tower Interior Coating Page 2

TABLE OF CONTENTS

SECTION I: INTRODUCTION

SECTION II: GENERAL CONDITIONS

SECTION III: SPECIAL CONDITIONS

SECTION IV: SCOPE OF WORK

SECTION V: REQUIRED FORMS

SECTION VI: AFFIDAVIT OF DEBTS AND CLAIMS

ATTACHMENTS:

CITY OF SALISBURY BID BOND FORM

CITY OF SALISBURY PERFORMANCE BOND FORM

CITY OF SALISBURY PAYMENT BOND FORM

ATTACHMENT 1: MEASUREMENT AND PAYMENT

ATTACHMENT 2: DIVISIONS 09960-1 THROUGH 09960-7

ITB 27-112 Wor-Wic Tower Interior Coating Page 3

SECTION I: INTRODUCTION

1. FILLING OUT BID FORMS

A. Use only forms supplied by the City of Salisbury (“City”).

B. All blanks on the Bid Document form will be filled in by typewriter or manually in ink.

C. Where so indicated by the makeup of the Bid Document, sums will be expressed in both words and figures, and in the case of a discrepancy between the two, the amount written in words will govern. In event there is a discrepancy between the unit price and the extended totals, the unit prices will govern. In the event of a discrepancy between the figures entered electronically and the information expressed on the Form of Proposal, the Form of Proposal shall prevail.

D. Any interlineations, alteration, or erasure MUST be initialed by the signer of the Bid Document.

E. Each copy of the Bid Document will be signed by the person or persons legally authorized to bind the Contractor to a contract, using the legal name of the signer. A Bid Document submitted by a third party for the Contractor will have a current Power of Attorney attached, certifying the third party’s authority to bind the Contractor.

F. Contractor will supply all information and submittals required by the Bid Documents to constitute a responsive and responsible Bid Document.

G. Any ambiguity in the Bid Document as a result of omission, error, lack of clarity or non-compliance by the Contractor with specifications, instructions, and/or all conditions of bidding will be construed in the light most favorable to the City.

2. QUESTIONS & CLARIFICATIONS

A. Bid Documents are available for inspection and download via our web site, www.salisbury.md; MENU; Procurement Portal; Procureware; Bids. Questions regarding Bid documents or procedures should be referred to Michael Lowe, Senior Buyer, during normal business hours, at 410-548-3192, or via email at mlowe@salisbury.md. Specific questions regarding the solicitation shall be written and can be emailed by the due date and time listed in the solicitation document.

B. The City of Salisbury may conduct a pre-bid or pre-proposal meeting for this solicitation.

These meetings are held to interpret the technical and procurement aspects of the solicitation document. While not mandatory, it is highly encouraged potential respondents attend.

3. SUBMISSION OF BIDS

A. All copies of Bid Documents, the Bid Security, if any, and any other document required shall be submitted electronically through the City’s Procurement Portal via Procureware.

The submittal will be addressed to the Director of Procurement and will be identified with the project name and the Contractor’s name and address.

B. Bid Documents will be electronically submitted prior to the time and date for receipt of bids indicated in the Advertisement or Invitation to Bid, or any extension made by Addendum.

Bid Documents received after the time and date for receipt will be not be accepted. Bid http://www.salisbury.md/ mailto:mlowe@salisbury.md

ITB 27-112 Wor-Wic Tower Interior Coating Page 4 documents delivered by any means other than electronic submittal through the Procureware platform will not be accepted.

C. Contractor will assume full responsibility for taking whatever measures necessary to ensure that the Bid Documents are submitted electronically prior to the local time and date specified. The City will NOT BE RESPONSIBLE for any bid delayed due to technical issues or received after the Bid Document date.

D. Contractors or their authorized agents are expected to fully inform themselves as to the conditions, requirements, and specifications before submitting Bid Documents; failure to do so will be at the Contractor’s own risk.

E. A fully executed Affidavit of Qualification to Bid will be attached to each Bid Document.

G. All Bid Documents will be valid for a minimum of ninety (90) days from the date of opening.

F. For Vendor’s who have previously registered through the Procurement Portal / Procureware, please note that any previous links to the solicitation you may have received by email may have changed. After signing in, please click the link associated with the corresponding solicitation number. Navigate to the “Response” ribbon. On the Response Ribbon you will see “Question Response”. Please upload all documentation for the response here. You will also be asked to enter your figures in for the corresponding bid items. After uploading the documentation and submitting the prices for the bid items click the “Submit Bid” button and follow the prompts. In the event of technical issues, support for Procureware can be reached by emailing support@procureware.com or by phone at 855-535-3233. The City is not responsible for technical issues unresolved prior to the due date and time for the solicitation.

4. OPENING OF BIDS

A. Bid Documents received on time will be opened electronically. An electronic version of the bid tabulation will be posted to the public documents section within the corresponding solicitation.

B. The Contract will be awarded or all Bid Documents will be rejected within ninety (90) days from the date of the Bid Document opening.

5. ACCEPTANCE OR REJECTION OF BIDS

A. Unless otherwise specified, the Contract will be awarded to the lowest RESPONSIBLE and RESPONSIVE Contractor complying with the provisions of the Bid Documents, provided the price is reasonable and does not exceed the funds available, and is in the best interest of the City. The City reserves the right to reject any Bid Document from any Contractor who has previously failed to perform properly in any way or complete on time contracts of a similar nature; or a Bid Document from a Contractor who, investigation shows, is not in a position to perform the Contract; or a Bid Document from any person, firm, or corporation which is in arrears or in default to the City for any debt or contract.

B. In determining a Contractor’s RESPONSIBILITY, the City may consider the following qualifications, in addition to price:

1. Ability, capacity, and skill to provide the commodities or services required within the specified time, including future maintenance and service, and including current financial statement or other evidence of pecuniary resources and necessary facilities;

2. Character, integrity, reputation, experience, and efficiency;

mailto:support@procureware.com

ITB 27-112 Wor-Wic Tower Interior Coating Page 5

3. Quality of past performance on previous or existing contracts, including a list of current and past contracts and other evidence of performance ability;

4. Previous and existing compliance with laws and ordinances relating to contracts with the City and to the Contractor’s employment practices;

5. Evidence of adequate insurance to comply with Contract terms and conditions;

6. Statement of current work load and capacity;

7. Explanation of methods to be used in fulfilling the Contract;

8. The Contractor, if requested, will be prepared to supply evidence of its qualifications, listed above, and its capacity to perform the Services; such evidence to be supplied within a specified time and to the satisfaction of the City.

C. In determining a Contractor’s RESPONSIVENESS, the City will consider whether the Bid Documents conform in all material respects to the City’s Bid Document’s requirements. The City reserves the right to waive any irregularities that may be in its best interest to do so.

D. The City will have the right to reject any and all Bid Documents, where applicable, to accept or award in whole or in part, to add or delete quantities, to waive any informalities or irregularities in the Bid Document received, to reject a Bid Document not accompanied by required Bid Security or other data required by the Bid Documents, and to accept or reject any Bid Document which deviates from specifications when in the best interest of the City. Irrespective of any of the foregoing, the City will have the right to award the Contract in its own best interests.

E. City personal property taxes must be on a current basis. If any such taxes are delinquent, they must be paid before Contract award. Failure to pay will result in the Contract award to another Contractor.

6. AUDIT

A. Successful Contractor agrees to retain all books, records, and other documents relative to the awarded Contract for five (5) years after final payment, or until audited. The City, its authorized agents, and/or State auditors will have full access to and the right to examine any of said materials during said period.

7. ASSIGNMENT

A. Successful Contractor will not assign, transfer or subject the Contract, or its rights, title interests or obligations therein without City’s prior written approval.

B. Violation of the terms of this paragraph will constitute a breach of Contract. All rights, title, interest and obligations of the Successful Contractor will thereupon cease and terminate.

8. CONTRACT AWARD

A. A written award in the form of a Purchase Order or other contract document will result in a binding Contract without further action by either party. If the Contractor fails or refuses to sign and deliver the Contract and the required surety bonds and insurance documentation, the City will retain, as partial damages for such failure or refusal, the Bid Security of such defaulting Contractor. The Contract will be executed and signed by the successful Contractor within fifteen (15) working days of receipt of the Contract.

ITB 27-112 Wor-Wic Tower Interior Coating Page 6

B. Bids and contracts issued by the City will bind Contractors to applicable conditions and requirements herein set forth, unless otherwise specified in the Bid Documents, and are subject to all Federal, State, and Municipal laws, rules, regulations, and limitations.

9. WORK NOT INCLUDED IN CONTRACT

A. If a price is requested in the Bid Documents for furnishing of a crew, tools, equipment, materials, rental, etc., to perform related Work not included in the Bid Documents, these items will be for contingency purposes only. Bids for this Work in no way guarantees Contractor award of any related Work not included in, and outside the scope of, the Contract. The City reserves the right to contract with any Contractor for non-inclusive work.

10. MODIFICATION OR WITHDRAWAL OF BID

A. A Bid Document may not be modified, withdrawn, or cancelled by the Contractor during the stipulated time period following the time and date designated for the receipt of Bid Documents and each Contractor so agrees in submitting a Bid Document.

11. DEFAULT

A. The Contract may be cancelled or annulled by the City in whole or in part by written notice of default to the Contractor upon non-performance, violation of Contract Terms, delivery failure, bankruptcy or insolvency, or the making of an assignment for the benefit of creditors. An award may then be made to the next low Contractor, or when time is of the essence, similar commodities and/or service may be purchased on the open market. In either event, the defaulting Contractor (or its surety) will be liable to the City for cost to the City in excess of the defaulted Contract price.

12. COLLUSION/FINANCIAL BENEFIT

A. The Contractor certifies that its Bid Document is made without any previous understanding, agreement, or connection with any person, firm, or corporation making a Bid Document for the same project; without prior knowledge of competitive prices; and is in all respects fair, without outside control, collusion, fraud, or otherwise illegal action.

B. Upon signing the Bid Document, Contractor certifies that no member of the governing body of the City, or members of his/her immediate family, including spouse, parents or children, or any other officer or employee of the City, or any member or employee of a Commission, Board, or Corporation controlled or appointed by the Mayor or Council has received or has been promised, directly or indirectly, any financial benefit, related to this Contract.

13. MATERIAL QUALIFICATIONS

A. A sample of material to be supplied under this Contract may be requested by the City to be provided prior to the Contract award. All materials will be new, standard production, unless otherwise approved by the City.

14. UNBALANCED & CONDITIONAL BIDS

A. UNBALANCED BIDS –

1. “Unbalanced bid” is a Bid Document which includes a number of items or alternates to be added or deleted, on which a Contractor quotes higher prices on items expected

ITB 27-112 Wor-Wic Tower Interior Coating Page 7 to be ordered in higher quantities than those used for Bid Document evaluation, and/or low prices on items the Contractor believes will be ordered in smaller quantities.

2. “Mathematically unbalanced bid” is a Bid Document in which each item does not carry its share or proportion of the cost of work plus profit, or one in which there are nominal prices for some work and higher prices for other work.

3. Contractors are cautioned not to unbalance their bids. The City reserves the right to reject any Bid Document that is decisively unbalanced.

B. CONDITIONAL BIDS –

1. When a Contractor unilaterally imposes a condition that the bid is an “all or none” offer, i.e., that any acceptance of the Bid Document must include all items offered. Such a condition affords the Contractor an inequitable advantage and contradicts the City’s right to accept any item or group of items in the Bid Document.

2. When a Bid Document is conditioned upon receiving the award of both the contract in question and another contract, such tying together of Bid Documents provides an undue competitive advantage and will not be accepted.

15. SUB-CONTRACTORS

A. The Contractor may be required to submit a list of sub-contractors proposed to be used in accomplishing the Work. Use of sub-contractors may be subject to approval by the City.

16. TAX EXEMPTION

A. The City is exempt from Federal Excise Taxes, Maryland Sales and Use Taxes, and Transportation Taxes. This exemption cannot be used by Contractors doing business with the City. Contractors are responsible for State Sales Tax of real property furnished and installed or constructed for the City.

17. EQUAL EMPLOYMENT OPPORTUNITY AND NON-DISCRIMINATION

A. All Contractors are subject to and must comply with the provisions of the City’s EEO policy and applicable State and Federal anti-discrimination laws. The City encourages equal employment opportunity to businesses owned and controlled by minorities and women.

B. The successful Contractor will not discriminate against any employee or applicant for employment or any member of the public because of race, color, creed, religion, national origin, sex, sexual preference, disability, marital status, age; or otherwise commit an unfair employment practice. Contractor further agrees that this non-discriminatory agreement will be incorporated by the Contractor in all contracts entered into with suppliers of commodities and services, contractors and subcontractors, and all labor organizations furnishing skilled, unskilled, and craft union skilled labor, or who may perform any such labor or services in connection with this Contract.

18. INDEMNITY

A. The awarded Contractor agrees to indemnify, defend, and hold harmless the City and its officers, employees, and agents from any and all liability, loss, cost, damage, and expense (including reasonable attorney’s fees and court costs) resulting from, arising out of, or incurred by reason of any claims, actions, or suits based upon or alleging bodily injury, including death, or property damage rising out of or resulting from the Contractor’s operations under this Contract, whether such operations be by itself or by any

ITB 27-112 Wor-Wic Tower Interior Coating Page 8 subcontractor or by anyone directly or indirectly employed by either party.

B. Contractor further agrees to furnish adequate protection against damages to all Work and to repair damages of any kind, to the building or equipment, due to Contractor’s own Work or to the Work of other Contractors for which the awarded Contractor is responsible.

19. CONTRACTOR STATUS

A. The Contractor will be responsible to the City for acts and omissions of their employees, subcontractors, their agents and employees, and other persons performing portions of the Work for this Contract or other arrangement with the Contractor. It is understood that the relationship of Contractor to the City will be that of an “independent contractor”. Nothing contained herein or inferable will be deemed or construed to (1) make the Contractor the agent, servant, or employee of the City, or (2) create any partnership, joint venture, or other association between the City and the Contractor.

20. APPLICABLE LAWS

A. Contractor will observe and comply with all applicable Federal, State, and local laws and regulations in the performance of the Work. This Contract will be construed and interpreted in accordance with the laws of the State of Maryland and all questions of performance hereunder will be determined in accordance with such laws.

21. APPROVED SUBSTITUTE

A. Approved substitute pertains to material and/or equipment which must meet the quality and the design requirements as specified. Any mention of product names or Contractors in the specifications is for the purpose of establishing a standard of quality and/or design and is not intended to limit competition.

B. When an item is identified in the Bid Documents by a manufacturer’s name or catalog number, it is understood that the Contractor proposes to furnish the material and/or equipment so identified and as specified by the City UNLESS the Contractor specifically proposes an alternate.

C. In bidding on a proposed alternate, the Contractor will clearly state in writing on the Bid Document exactly what is proposed to be furnished, and forward with the bid a complete description of the proposed alternate, including brand, model number, drawings, performance and test data, references and any other information necessary for a complete evaluation of the proposed alternate by the City.

D. Contractor will include a statement setting forth any changes in other materials, equipment, or other Work which would be required by incorporation of the proposed alternate. The burden of proof of the merit of the proposed alternate is upon the Contractor.

E. The City’s decision to approve or disapprove a proposed alternate will be final and will be made in the City’s best judgment and interests.

F. Bid Document submittals will conform to these requirements for bid ALTERNATES and, where applicable, will include, but not necessarily be limited to, the following information:

1. Exceptions to these specifications along with justification for each exception;

2. Manufacturer and manufacturer’s type designation;

3. Manufacturer’s catalog data confirming conformance to specified requirements;

4. Overall dimensional data including drawings, sketches, and photographs;

ITB 27-112 Wor-Wic Tower Interior Coating Page 9

5. Performance data developed for the specific application;

6. Parts list noting materials of construction;

7. Complete list of locations where the manufacturer has supplied this equipment.

a. The list will include the name and address of the respective owner, date of installation, and contact person and telephone number of the person who has knowledge of the equipment performance.

22. FORCE ACCOUNT WORK

A. When the Contractor will perform extra Work for which there is no quantity and price included in the Contract, as a result of changes, alterations, deductions, and/or additions to the Contract, such work will be done in accordance with the specifications and only by an authorized written Change Order by the City. The extra work will be paid for on Force Account basis. All work done on a Force Account basis will be paid for in the following manner:

1. Application of unit prices stated in the Contract or subsequently agreed upon;

2. Lump-sum price agreed to by both the City and the Contractor;

3. When there are no applicable unit prices in the Contract, and when the City and the Contractor cannot reach an agreement, the City will require the Contractor to do such work on a Force Account basis to be compensated in conformance with the following:

a. Labor. For all labor and for foreman in direct charge of the specific project, the City and Contractor will agree on the labor rates before any Force Account work is begun. The number of laborers and foreman employed in the Work will be subject to regulation by the City’s Engineer; and will be agreed on in advance of the Work.

The Contractor will receive as shown on its weekly payroll the basic hourly wage, overtime, and fringe benefits paid in case to the employee for each and every hour that said labor and foremen are actually engaged in such Work, to which cost will be added an amount equal to fifteen percent (15%) of the sum thereof. The Contractor’s superintendent’s or office personnel’s time will not be allowed. To substantiate labor cost for the Force Account, the Contractor will be required to submit copies of certified payrolls showing name, classification, date, daily hours, total hours, rate, and extension for each laborer and foreman.

b. Materials. For materials accepted by the City’s Engineer and used, the Contractor will receive the actual cost of such materials delivered for the Work, including transportation charges paid by the Contractor (exclusive of machinery rentals as hereinafter set forth), to which the cost of fifteen percent (15%) may be added. To substantiate materials and transportation costs, original receipted invoices will be submitted. If, however, the materials used in the force account Work are not specifically purchased for such Work but are taken from the Contractor’s stock, then in lieu of the original invoices, the statements will contain or be accompanied by an affidavit from the Contractor which will certify that such materials were taken from the Contractor’s stock, that the quantity claimed was actually used and that the price and transportation of the material as claimed represent actual costs. The City reserves the right to furnish such materials as it deems appropriate, and the Contractor will have no claim for any costs, overhead, or profit on such materials.

c. Materials and Supplies not incorporated in the Work. For materials and supplies

ITB 27-112 Wor-Wic Tower Interior Coating Page 10 expended in the performance of the Work (excluding those required for rented equipment), and approved by the City’s Engineer and/or Director of Procurement, the Contractor will receive the actual cost of such materials and supplies used. The Contractor will receive a reasonable allowance for materials used but not expended in the performance of the Work. These costs will be substantiated as defined in (Equipment Section) below.

d. Equipment. For any machinery or special equipment, other than small tools, including fuel and lubricants, plus transportation costs, the use of which has been authorized by the City’s Engineer, the Contractor will receive rental rates as agreed to in writing before the Work is begun, for the actual time that such equipment is in operation on the Work, to which the sum of fifteen percent (15%) may be added. In addition to the above, the actual transportation costs for one move in and one move out may be allowed. When the City is obligated to pay for idle equipment, the allowance will be seventy-five percent (75%) of the agreed upon equipment rental rate. To compute hourly rates, use eight hours a day, forty hours per week and one-hundred and seventy-six hours per month. For the purpose of definition, equipment with a new cost of one thousand dollars ($1,000) or less will be considered small tools. No overhead and profit will be allowed on such equipment. For all equipment utilized on Force Account Work, the hourly rate for each piece of equipment and attachments will be paid at the Rental Rate Blue Book for Construction Equipment monthly rate for the make and model. The Contractor will furnish to the City’s Engineer serial numbers and year of manufacture for all pieces of equipment used on Force Account Work. Rental rates will be given without operator labor costs which will be paid under Labor (as noted above).

e. Rental Equipment. In cases where a piece of equipment to be used is rented or leased by the Contractor from a third party exclusively for Force Account Work, the actual invoiced amount will be paid when such rates are reasonably in line with established rental rates for the equipment in question and approved by the City’s Engineer.

f. Moving Equipment. When it is necessary to obtain equipment from sources beyond the project limits, exclusively for Force Account Work, the cost of transferring the equipment to the site of the Work and return will be allowed as an additional expense. Where the move requires the use of a hauling unit, the move-in allowance will be limited to the rental rate, as computed in subparagraph (Rental Equipment) above, for the hauling unit plus operator’s wages. In the event that the equipment is transferred under its own power, the moving allowance will be limited to one half the hourly rental rate, as computed in subparagraph (Rental Equipment) above, plus operator’s wages. In the event that the move-out is to a different location, payment will in no instance exceed the amount of the move-in. Move-in allowance will not be made for equipment brought to the project for Force Account Work which is subsequently retained in the project and utilized for Contract items or related Work.

g. Standby Time. Standby rates will apply, with the City Engineer’s approval, when a piece of equipment is required to remain on the project on standby status.

Standby rates will be 50 percent (50%) of the normal base rates without the operating expenses. Standby rates will not exceed 8 hours per day and will not be

ITB 27-112 Wor-Wic Tower Interior Coating Page 11 allowed for Saturday, Sunday, holidays, days the City may be closed due to weather or other Acts of God, i.e. Force Majeure. When a unit works for a portion of a day and is on standby for a portion, the total time allowed will not exceed 8 hours for that day. Equipment that is required to be on the project to transport personnel or materials will be paid the rental rate for that portion of the day being utilized with the remainder being standby. No compensation will be allowed for equipment that is inoperable due to breakdown.

h. Subcontracting. For extra Work performed by subcontractors the Contractor will receive the rate billed to him by the subcontractor for each and every hour that said subcontractor is actually engaged in such Work. This amount shall be equal to five percent (5%) of the sum for the extra work, or five hundred dollars ($500), whichever sum is higher. To substantiate labor cost for the Force Account, the Contractor will be required to submit copies of certified payrolls showing name, classification, date, daily hours, total hours, rate, and extension for each laborer and foreman. No other overhead and profit may be taken by the Contractor for additional subcontractor Work.

i. Compensation. The compensation as herein provided will be received by the Contractor as payment in full for extra Work done on a “Force Account basis”. At the end of each day, the Contractor’s representative and the City’s Engineer will prepare a Force Account daily record, signed by both parties, which daily report will be the true record of the Force Account Work done.

j. Partial Payment. Upon completion of the Work the Contractor may request partial payment for Force Account Work prior to submitting final documentation.

Partial payment will be limited to 50% of the estimated amount for the Work accomplished until all documentation has been received and approved.

k. Miscellaneous. No additional allowance will be made for the General Superintendence of the project and related transportation, the use of small tools, or other costs for which no specific allowance is herein provided.

l. For extra Work, as defined in this section, the Contractor will be reimbursed for its expenditures for Workmen’s Compensation Insurance, Public Liability Insurance, Social Security taxes and Unemployment Compensation covering the workers actually engaged upon such extra Work. No percentage will be added to such payments, but the Contractor will receive only the actual amount of money expended for such expenditures. Such payments will be based on the prevailing standard insurance rates supported by receipted vouchers from the insurance Contractors and upon the actual amount of taxes paid for Social Security and Unemployment Compensation as evidenced by proper documents furnished by the Contractor.

m. If change involves merely a credit, the Contract price will be reduced by the amount it would have cost the Contractor if the omitted item or Work had not been eliminated, including overhead and profit; however, the Contractor and the subcontractor will be allowed to retain a sum not in excess of three percent (3%) for handling. If the deletion affects the allocated project construction workdays, the City may initiate a proportionate reduction.

n. If a change involves an extra credit and a credit, both sums will be shown and the two sums balanced to determine the adjusted total cost or credit.

ITB 27-112 Wor-Wic Tower Interior Coating Page 12

o. NO allowance to the Contractor will be made or allowed for loss of anticipated profits on account of any changes in the Work.

23. SUSPENSION OR TERMINATION FOR CONVENIENCE

A. The City Director of Procurement, unilaterally, will have the right, at any time by written notice, for its convenience, to suspend, delay or interrupt the work for such time as may be determined by the City to be necessary or desirable up to ninety (90) days, unless a longer time is agreed upon in writing by both parties; and thereafter, to require resumption of the whole or any part of the work without invalidating the provisions of this contract.

B. The City’s Director of Procurement, unilaterally, will have the right, at any time by written notice, for his/her convenience, to terminate the work in whole or in part.

C. Any notice issued pursuant to Sections 23.A and/or 23.B above will state the extent and effective date of such notice, and except as otherwise directed, the Contractor will stop work on the date of receipt of the Notice of Termination or other date specified in the notice; place no further orders or subcontracts for materials, services, or facilities, except as necessary for the completion of such portion of the work not terminated. The Contractor, within thirty (30) days of the Notice of Termination, will submit a final invoice reflecting services actually furnished pursuant to this Agreement to the satisfaction of the City and for which no previous invoice was submitted to the City.

D. In the event of a termination, pursuant to Section 23.B above, the City will pay the Contractor’s expenses verified by final invoice as set forth in this section for the following:

1. Completed and acceptable work executed in accordance with the Contract Documents prior to the effective date of termination, including fair and reasonable sums for overhead and profit for such work.

2. Expenses sustained prior to the effective date of termination in performing services and furnishing labor, materials, or equipment as required by the Contract Documents in connection with uncompleted work, plus fair and reasonable sums for overhead and profit.

E. The Contractor will not be paid on account of loss of anticipated profits or revenues or for work not completed prior to the date of termination of the Contract.

No adjustment will be made under this section for any suspension, delay, or interruption to the extent (1) that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or (2) for which an equitable adjustment is provided for excluded under any provision of this Contract.

24. ADDENDUM

A. No oral statements of any person will modify or otherwise affect or interpret the meaning of the Contract Drawings, the Specifications, or the Terms, Conditions, or other portions of the Bid Documents. All modifications and every request for any interpretation must be addressed to the Director of Procurement, City of Salisbury, 125 N. Division Street, Room 104, Salisbury, Maryland 21801, and to be given consideration, must be received at the above address at least seven (7) days prior to the date fixed for the Bid Document opening.

B. Any and all interpretations, corrections, revisions, and amendments will be issued by the Procurement Division to all holders of Bid Documents in the form of written addenda.

Contractors are cautioned that any oral statements made by any City employee that

ITB 27-112 Wor-Wic Tower Interior Coating Page 13 materially change any portion of the Bid Documents will not be relied upon unless subsequently ratified by a formal written amendment to the Bid Document.

C. All addenda will be issued so as to be received at least five (5) days prior to the time set for receipt of Bid Documents, and will become part of the Bid Document and will be acknowledged in the Bid Document. Failure of any Contractor to receive any such addenda will not relieve said Contractor from any obligation under its Bid Document as submitted.

D. Contractors are cautioned to refrain from including in their Bid Document any substitutions which are not confirmed by written addenda. To find out whether the City intends to issue an amendment reflecting an oral statement made by any employee, contact Michael Lowe, Director of Procurement, at 410-548-3190, during normal business hours.

E. The Director of Procurement reserves the right to postpone the Bid Document opening for any major changes occurring in the 5-day interim which would otherwise necessitate an addendum.

25. DEBARMENT

A. By submitting this bid/proposal, the bidder/proposer warrants and certifies that he is eligible to submit a bid/proposal because he is not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from participation in a transaction by any Federal, State, or local department or agency.

26. BID SECURITY

A. Each bid shall be accompanied by a bid bond, in a form and by a surety company approved by the City of Salisbury. The bond must be in an amount not less than five percent (5%) of the base bid(s). Certified or cashier’s checks are acceptable in lieu of bid bond, subject to the same conditions. Bonds and checks shall be made payable to the CITY OF SALISBURY. Vendors shall utilize the bond forms attached to this bid document.

B. Return of Bid Security:

1. All but the lowest three bidders’ bid security shall be returned as soon as the bid prices have been checked and compared.

2. At award of contract, the remaining two unsuccessful bidders’ bid security will be returned.

3. The bid security will be returned to the successful bidder upon execution of the Contract and Performance Bond.

27. PERFORMANCE BOND and PAYMENT BOND

A. The Contractor or to whom the contract is awarded shall furnish a Performance Bond and a Labor and Materials Payment Bond in a form and by a surety company approved by the City of Salisbury. The amount of the bond shall be one hundred percent (100%) of the contract price. Bonds shall be made payable to the City of Salisbury. Vendors shall utilize the Bond Forms attached to this bid document.

28. INSURANCE REQUIREMENTS

A. Unless otherwise required by Special Conditions for this agreement the Contractor will be required to purchase and maintain during the life of the Agreement the following types and amounts of insurance (at minimum).

ITB 27-112 Wor-Wic Tower Interior Coating Page 14

1. Commercial General Liability: $1,000,000 (One million dollars) per occurrence $3,000,000 (Three million dollars) aggregate for bodily injury and property damage.

2. Commercial Automobile: $1,000,000 (One million dollars) combined single limit per accident for bodily injury and property damage. Include hired, non-ownership coverage and owned vehicle coverage if company owns a vehicle.

3. As mandated by the Code of the State of Maryland and Employer’s Liability the Contractor will be required to provide Worker’s Compensation insurance.

4. The Contractor will provide the City with certificates of insurance evidencing the coverage’s required above. Such certificates will provide that the City be given at least thirty (30) days prior written notice of cancellation of, intention to not renew, or material change in such coverage. Contractor must provide certificates of insurance before commencing Work in conjunction with this Agreement.

a. Failure to provide and continue in force such insurance as required above, will be deemed a material breach of the Agreement, will cause the Contractor to be in DEFAULT, and will operate as an immediate termination thereof. The City reserves the right to require higher limits on any Agreement. A 30-day notice in writing of cancellation or non-renewal will be furnished by certified mail to the Director of Procurement at the address listed in solicitation. The Contractor agrees to be responsible for, indemnify, defend, and hold harmless the City, its officers, agents, and employees from the payment of all sums of money by reason of any claim against them arising out of any and all occurrences resulting in bodily or mental injury or property damage that may happen in connection with and during the performance of the Agreement including, but not limited to, claims under the Worker’s Compensation Act

b. ON THE COMMERCIAL GENERAL LIABILITY POLICY THE CITY MUST BE NAMED AS

ADDITIONAL INSURED AND THE INSURANCE CERTIFICATE FURNISHED TO THE CITY

WILL INDICATE SUCH COVERAGE.

c. THE PROVIDING OF ANY INSURANCE REQUIRED HEREIN DOES NOT RELIEVE THE

CONTRACTOR OF ANY OF THE RESPONSIBILITIES OR OBLIGATIONS ASSUMED BY THE

CONTRACTOR IN THIS AGREEMENT, OR FOR WHICH THE CONTRACTOR MAY BE

LIABLE BY LAW OR OTHERWISE.

END OF SECTION

ITB 27-112 Wor-Wic Tower Interior Coating Page 15

SECTION II: GENERAL CONDITIONS

1. OUTLINE SPECIFICATIONS

A. Some sections of the Contract specifications have been written in outline form to facilitate reading and locating information. Only key words, product designations and phrases have been used. Contractors will resolve any questions arising from the outline form specifications prior to submitting a Bid Document. By its Bid Document submission, the Contractor agrees to accept the City Engineer’s interpretation of the specifications in case of discrepancy or misunderstanding.

2. LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC

A. Definition of Contractor - hereinafter “Contractor” will refer to any Contractor currently under contract with the City, or any Contractor or person performing construction to City utilities, roadways, etc. or other appurtenances owned and/or maintained by the City, for which no contract has been awarded by the City.

B. Responsibility for Damage Claims - Contractor will indemnify and save harmless the City and all its representatives from all damage resulting from the construction or non-compliance with any law, ordinance, regulation or by-law in effect.

C. Contractor is responsible for public safety.

D. Contractor is responsible for preservation of all public and private property, trees, monuments, highway signs, markers, fences, curbs and appurtenances.

E. Contractor is responsible for storm water drainage, management and soil erosion control relating to the completion of the Work.

F. “Engineer” or “Inspector” shall be the authorized representative(s) of Salisbury Department of Infrastructure and Development (DID).

3. PROSECUTION OF CONTRACT & LIQUIDATED DAMAGES

A. Contract time may be accrued using working days or calendar days. Calendar days will be used unless designated as working days elsewhere in the contract.

B. Determination of working day will be any normal calendar day when the weather or soil conditions are suitable for work for five (5) hours. All such days claimed not to be suitable for work for five (5) hours shall be reported in writing immediately to the City, whose representative shall either approve such claim or reject the claim that the day was not suitable for work as described and required.

C. Saturdays, Sundays, and legal Holidays will not be considered a working day unless it is used as a productive work day (See Section 20), but are considered Calendar days for the purpose of assessing liquidated damages.

D. Calendar days will begin at start of construction or “Notice to Proceed” date and will be continuous until Final Acceptance. Final Acceptance means acceptance of the Project by the City as evidenced by its signature upon a final payment Certification. The final payment Certification shall be signed only after the City has assured itself by tests, inspections, or otherwise that all of the provisions of the Contract have been carried out as required.

E. Time extensions may be granted, in writing, when it can be shown that the Contractor has been unavoidably detained in completing the Work and achieving Final Acceptance.

F. Time is an essential element of the contract and it is important that the work be vigorously prosecuted until completion.

ITB 27-112 Wor-Wic Tower Interior Coating Page 16

1. The City and Contractor acknowledge and agree that the City will incur damages, including, but not limited to loss of goodwill, detrimental impact on economic development, diversion of internal staff resources, and negative impact on the health, safety and general welfare of the public if the Contractor does not meet the time requirements contained in the contract and obtain Final Acceptance for the project as required. The parties further acknowledge and agree that the damages the City might reasonably be anticipated to incur and accrue as a result of such lack of compliance are difficult to ascertain and prove with precision.

2. Therefore, upon a determination by the City that the Contractor failed to meet the Final Acceptance deadline, after any extended time period adjustment credits have been applied, the Contractor agrees to pay liquidated damages to the City at the rates set forth below for each calendar day the Work is not complete beyond the date of Final Acceptance. The Contractor expressly agrees that the City may withhold payment on any invoices as a set-off against liquidated damages owed.

The Contractor further agrees that for each violation and delay, the agreed upon liquidated damages are reasonably proximate to the loss the City is anticipated to incur as a result of the delay of completion of the project.

Amount of Contract Liquidated Damages per Day Less than $10,000 $100.00 $10,000 or less than $100,000 $250.00 $100,000 or less than $500,000 $750.00 $500,000 or more $1,000.00

4. CONTROL OF MATERIAL

A. Source of supply subject to approval of the City Engineer.

B. City Engineer may require samples of materials.

C. Only materials conforming to these specifications will be approved.

D. Manufacturers and suppliers listed in these specifications or on the City construction standard drawings are pre-approved for the convenience of the Contractor.

E. Plans prepared by agencies other than the City’s Department of Infrastructure and Development will require approval of materials and/or approved substitutes by the City Engineer or representative.

F. Approved substitutes will conform to City Contract specifications and meet requirements as stated in the Approved Substitute section of Instructions to Contractors or “Approved Substitute” on record at the City’s Department of Infrastructure and Development or use the “Construction and Material Specifications for Utility and Roadway Construction” manual where applicable.

G. All rejected materials, damaged in shipment or otherwise not conforming to the specifications or samples, will be removed immediately from the vicinity of the Work.

5. PAYMENT REQUESTS

A. Partial (periodic) payments

1. Made approximately each month in an amount equal to the estimated amount less any Retainage.

ITB 27-112 Wor-Wic Tower Interior Coating Page 17

2. The City Engineer will make out the monthly estimate based on estimated quantities submitted in writing by the Contractor, and agreed upon by the City.

B. Final Payment

1. Final payment will not be made until Final Acceptance is issued.

2. Retainage amounts will be withheld (unless replaced by a Maintenance Bond) until final acceptance of Work at the end of the guarantee period.

3. Maintenance bond will be in the amount of 5% of the total Contract amount.

4. At completion of the guarantee period, a final inspection will be made by the City Engineer.

5. Any items of non-acceptance will be listed on a “Final Punch List” for the Contractor.

Items on this Final Punch List must be corrected or completed before final acceptance can be made.

6. Items on the “Final Punch List” not completed by the Contractor will be done by the City, or the City will cause the Work to be done.

7. The cost of any Work required by the “Final Punch List” not done by the Contractor will be charged to the Contractor’s retainage account or maintenance bond.

C. Retainage Payment

1. Retainage payment will be made upon conditional acceptance and receipt of a maintenance bond.

2. If no maintenance bond is provided, the Retainage amount will not be paid until a satisfactory final inspection is performed and final acceptance is issued.

3. Any unused portion of the Retainage account will be returned to the Contractor after all repairs have been made.

4. Unless otherwise specified in the Contract, Retainage will be withheld on all Contracts.

5. Retainage will be made at 10% of the estimated amount with the maximum retainage being 5% of the total Contract amount.

D. Payment for Stored Materials

1. In making estimates of the value of the Work done and materials incorporated in the Work, the Contractor may, subject to the approval of the City or as required by law, include in the current estimates the delivered cost, as modified below, of equipment and non-perishable materials which have been tested for adequacy and which have been delivered to the site or other such location approved by the City and adequately protected from fire, theft, vandalism, the effect of the elements, and any damage whatsoever, or similarly placed in approved storage facilities adjacent thereto. Such materials and equipment will at all times be available for inspection by the City Engineer and the City. No progress payment will be made for said material and equipment until each of the following conditions has been fulfilled:

a. The Contractor will furnish to the City Engineer invoices establishing the value of said materials and equipment with an indication of the amount the Contractor requests the City to pay for said materials and equipment. Such invoices will be furnished at least ten days in advance of the date of preparation of monthly estimates as established by the City Engineer;

b. The City Engineer will inspect said material and equipment and recommend payment therefore;

ITB 27-112 Wor-Wic Tower Interior Coating Page 18

c. The Contractor will furnish the to the City fire insurance policies, as provided in this Contract and with the broad form extended coverage endorsement, for said material and equipment in an amount equal to one hundred percent of the value thereof and which policies will be maintained, at the sole cost and expense of the Contractor, until said material and equipment has been incorporated into the Work;

d. Within sixty (60) days of the submission to the City of any progress payment, including payment for said materials and equipment, or within thirty days of the date of payment to the Contractor by the City, whichever is longer, the Contractor will furnish to the City Engineer satisfactory evidence that the funds included in the progress payment for said materials and equipment have been paid to Contractors supplying such items. Satisfactory evidence will be: a cancelled check in the correct amount and including identification of the invoice or invoices paid; a letter or telegram, from the Contractor and signed by his properly authorized employee, stating the amounts and invoices that have been paid; or a receipted invoice;

e. Should the above evidence of payment not be furnished, the City Engineer will recommend the deduction of any funds included in previous estimates for such materials and equipment for which said evidence has not been furnished from the current estimate or subsequent current estimates;

f. Any payment made for materials and equipment delivered will not relieve the Contractor of any responsibility for furnishing all the necessary equipment and materials required for prosecution of the Work in the same manner as if such payments had not been made.

6. INSPECTION

A. Competent inspectors will be supplied by the City.

B. The City Engineer will be notified by the Contractor at least three (3) days prior to starting new work.

C. Inspectors will have access to all Work at all times. The Inspector’s duty is to ascertain all Work being performed in accordance with specifications.

D. Contractor has final responsibility for acceptability of finished Work.

E. Contractor will consult with City Engineer concerning:

1. Method of Work;

2. Equipment to be used;

3. Point of beginning Work.

F. The City Inspector will not act as…