ITB 26-04: Mt Vernon Road Multi-Use Trail
This is a competitive sealed bid solicitation issued by the City of Dunwoody, Georgia Department of Public Works for the Mt Vernon Road Multi-Use Trail construction project. The project encompasses adding a pedestrian path along the north side of Mount Vernon Road, relocating extensive overhead and underground public utilities, constructing temporary diversion lanes for water main installation, building new storm drain infrastructure and gravity walls, milling and paving Mount Vernon Road, installing new traffic signal poles and mast arms at the Tilly Mill Road intersection, and placing required signage and pavement markings. Bids were received until 2:00 PM on May 28, 2026, at the City of Dunwoody offices located at 4800 Ashford Dunwoody Road, Dunwoody, Georgia 30338. A pre-bid conference was held on May 14, 2026, at 2:00 PM at the same location, with attendance highly recommended. The question submission deadline was 5:00 PM on May 21, 2026. Award was expected by the third quarter of 2026, with the contractor required to mobilize within ten days of receiving the Notice to Proceed. The contract specifies substantial completion within 1,100 calendar days from the Notice to Proceed and final completion within 60 calendar days thereafter. Bids remain valid through November 24, 2026.
The contractor must submit a five percent (5%) bid bond and will be required to provide one hundred percent (100%) performance and payment bonds upon award. All contractors must be prequalified with the Georgia Department of Transportation and hold current licensure as a general contractor from the State Licensing Board for Residential and General Contractors. The prime contractor must be certified in work classes 205, 209, 310, 441, 550, and 668, with certification in work classes 149, 150, and 500a preferred. The bid schedule includes both a roadway items section and a separate water distribution system section, with the low bid determined by the sum of the base bid and any city-selected alternates. Liquidated damages are assessed at daily rates ranging from $213 to $5,311 per day depending on contract amount, with incentive payments available for early completion up to a maximum of $150,000. The project is funded by the City of Dunwoody, with extensive coordination required among multiple utilities including Georgia Power, Comcast, AT&T, AGL, DeKalb Watershed Management, Colonial Pipeline, and Crown Castle. Work hours are restricted to 7:30 AM to 8:00 PM Monday through Friday, with lane closures prohibited between 7:00 AM to 9:00 AM and 4:00 PM to 6:00 PM on weekdays. All work must comply with Georgia Department of Transportation Standard Specifications and current editions, and contractors must maintain environmental sustainability standards throughout the project.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
THE CITY OF DUNWOODY, GEORGIA
DEPARTMENT OF PUBLIC WORKS
OFFICIAL BID DOCUMENTS
MT VERNON RD MULTI-USE TRAIL
ITB 26-04
BID OPENING DATE:
2:00 PM, May 28, 2026
ITB 26-04
The City of Dunwoody is soliciting competitive sealed bids from qualified contractors for the MT
VERNON RD MULTI-USE TRAIL project for the Department of Public Works.
Bids should be typed or submitted in ink and returned in a sealed container marked on the outside with the ITB number and Company Name. Bids will be received until 2:00 P.M. local time on May 28, 2026 at the City of Dunwoody, 4800 Ashford Dunwoody Rd, Dunwoody, GA 30338. Any bid received after this date and time will not be accepted. Bids will be publicly opened and read at 2:05 P.M. Apparent bid results will be available the following business day on our website www.dunwoodyga.gov.
A Pre-Bid Conference will be held at 2:00 p.m. on Thursday, May 14, 2026 at the City of Dunwoody
City Hall, 4800 Ashford Dunwoody Rd, Dunwoody, GA 30338. The conference will include a review of the Bid Documents, and a question-and-answer period. Attendance at the Pre-Bid Conference is highly recommended. Bidders are expected to be familiar with the Bid Documents and to provide the
City with any questions regarding the Bid Documents at the Pre-Bid conference or by the deadline for questions to be submitted.
Questions regarding bids should be directed to John Gates, Purchasing Manager, at purchasing@dunwoodyga.gov no later than close of business on Thursday, May 21, 2026. Bids are legal and binding upon the bidder when submitted. All bids should be submitted in duplicate.
The written bid documents supersede any verbal or written prior communications between the Parties.
If a contract is awarded, it will be made to the lowest reliable bidder whose base bid proposal shall have met all of the prescribed requirements. The City reserves the right to reject any or all bids, to waive technicalities and to make an award deemed in its best interest. The low bid will be determined based on the sum of the base bid and any alternates selected by the City.
All companies submitting a bid will be notified in writing of award. We look forward to your bid and appreciate your interest in the City of Dunwoody.
John Gates
Purchasing Manager
TABLE OF CONTENTS
SECTION TITLE
0010 Table of Contents
0050 Project Directory
0100 Bid Instructions
0150 Bid Checklist
0200 Bonding and Insurance Requirements
0250 Scope of Work
0300 General Notes
0350 Bid Schedule
0400 Bid Bond
0450 Affidavits
0500 Qualifications Signature and Certification
0550 Statement of Bidders Qualifications and References
0600 Corporate Certificate
0650 Subcontractor Listing
0700 Statement of Equipment
0750 Sample Contract
0800 General Conditions
0850 Special Conditions
0875 Special Provision
1000 Payment Bond
1050 Performance Bond
1100 Maintenance Bond
PROJECT DIRECTORY
Section 0050
The City of Dunwoody, Georgia
ITB 26-04: MT VERNON RD MULTI-USE TRAIL
OWNER The City of Dunwoody, Georgia
4800 Ashford Dunwoody Rd
Dunwoody, GA 30338
(678)-382-6700
Mayor Lynn P. Deutsch
City Manager Eric Linton
Associated Public Works
Department Michael Smith, P.E. Director
Design Southeastern Engineering, Inc (SEI)
Consultant Scott Jordan, P.E.
BID INSTRUCTIONS
SECTION 0100
CITY OF DUNWOODY
DEPARTMENT OF FINANCE AND ADMINISTRATION – PURCHASING DIVISION
GENERAL INSTRUCTIONS FOR BIDDERS
These Instructions will apply unless a particular item is specifically addressed in the solicitation document or not relevant to the particular type of good or service.
1. PREPARATION OF BIDS:
A. Each bidder shall examine the drawings, specifications, schedule and all instructions. Failure to do so will be at the bidder’s risk, as the bidder will be held accountable for their bid response.
B. Each bidder shall furnish all information required by the bid form or document. Each bidder shall sign the bid and print or type his or her name on the schedule. The person signing the bid must initial erasures or other changes. An authorized agent of the company must sign bids.
C. Individuals, firms and businesses seeking an award of a City of Dunwoody contract may not initiate or continue any verbal or written communications regarding a solicitation with any City officer, elected official, employee or other City representative without the permission of Purchasing between the date of the issuance of the solicitation and the date of the final contract award.
Violations will be reviewed by the Purchasing Manager. If determined that such communication has compromised the competitive process, the offer submitted by the individual, firm or business may be disqualified from consideration for award.
2. BID TIME TABLE. The anticipated schedule for the bid process is as follows:
Bid Documents Posted ............................................... Thursday, April 30, 2026
Pre-Bid Conference ..................................................... 2:00 PM, Thursday, May 14, 2026
Deadline for submission of questions ..................... 5:00 PM, Thursday May 21, 2026
Deadline for submission of Bid ............................... 2:00 PM, Thursday, May 28, 2026
Bids Valid Until………………………. ..................... Tuesday November 24, 2026
3. EXPLANATION TO BIDDERS:
Any explanation desired by a bidder regarding the meaning or interpretation of the invitation for bids, drawings, specifications, etc. must be requested by the question cutoff deadline stated in the solicitation in order for a reply to reach all bidders before the close of bid. Any information given to a prospective bidder concerning an invitation for bid will be furnished to all prospective bidders as an addendum to the invitation if such information is necessary or if the lack of such information would be prejudicial to uninformed bidders. The written bid documents supersede any verbal or written communications between Parties. Receipt of addendum should be acknowledged in the bid. Although Purchasing will make every effort to send any addendum to known bidders, it is the bidder’s ultimate responsibility to ensure that they have all applicable addenda prior to bid submittal. This may be accomplished via contact with Purchasing prior to bid submittal.
4. SUBMISSION OF BIDS:
A. Bids shall be enclosed in sealed envelopes, addressed to the City of Dunwoody Purchasing Office with the name of the bidder, the date and hour of opening and the invitation to bid number on the face of the envelope. Telegraphic/faxed bids will not be considered. Any addenda should be enclosed in the sealed envelopes as well.
B. ADD/DEDUCT: Add or deduct amounts indicated on the outside of the envelope are allowed and will be applied to the lump sum amount. Amount shall be clearly stated and should be initialed by an authorized company representative.
C. Samples of items, when required, must be submitted within the time specified and, unless otherwise specified by the City, at no expense to the City. Unless otherwise specified, samples will be returned at the bidder’s request and expense if items are not destroyed by testing.
D. Items offered must meet required specifications and must be of a quality, which will adequately serve the use and purpose for which intended.
E. Full identification of each item bid upon, including brand name, model, catalog number, etc. must be furnished to identify exactly what the bidder is offering. Manufacturer’s literature may be furnished.
F. The bidder must certify that items to be furnished are new and that the quality has not deteriorated so as to impair its usefulness.
G. Unsigned bids will not be considered except in cases where bid is enclosed with other documents, which have been signed. The City will determine this.
H. The City of Dunwoody is exempt from federal excise tax and Georgia sales tax with regard to goods and services purchased directly by the City. Suppliers and contractors are responsible for federal excise tax and sales tax, including taxes for materials incorporated into City construction projects.
Suppliers and contractors should contact the State of Georgia Sales Tax Division for additional information.
I. Information submitted by a bidder in the bidding process shall be subject to disclosure after the public opening in accordance with the Georgia Open Records Act. Each page of proprietary information must be identified. Entire bid may not be deemed proprietary.
5. WITHDRAWAL OF BID DUE TO ERRORS:
A. The Bidder shall give notice in writing of his claim of right to withdraw his bid without penalty due to an error within two (2) business days after the conclusion of the bid opening procedure. Bids may be withdrawn from consideration if the price was substantially lower than the other bids due solely to a mistake therein, provided the bid was submitted in good faith, and the mistake was a clerical mistake as opposed to a judgment mistake, and was actually due to an unintentional arithmetic error or an unintentional omission of a quantity of work, labor or material made directly in the compilation of the bid, which unintentional arithmetic error or unintentional omission can be clearly shown by objective evidence drawn from inspection of original work papers, documents and material used in the preparation of the bid sought to be withdrawn. The bidder’s original work papers shall be the sole acceptable evidence of error and mistake if he elects to withdraw his bid. If a bid is withdrawn under the authority of this provision, the lowest remaining responsive bid shall be deemed to be low bid.
B. No bidder who is permitted to withdraw a bid shall, for compensation, supply any material or labor or perform any subcontract or other work agreement for the person or firm to whom the contract is awarded or otherwise benefit, directly or indirectly, from the performance of the project for which the withdrawn bid was submitted.
C. The Bidder has up to forty-eight (48) hours to notify Purchasing of an obvious clerical error made in calculation of bid in order to withdraw a bid after bid opening. Withdrawal of bid for this reason must be done in writing within the forty-eight (48) hour period. Bidders who fail to request withdrawal of bid by the required forty-eight (48) hours shall automatically forfeit bid bond. Bid may not be withdrawn otherwise.
D. Bid withdrawal is not automatically granted and will be allowed solely at the City of Dunwoody’s discretion.
6. TESTING AND INSPECTION:
Since tests may require several days for completion, the City reserves the right to use a portion of any supplies before the results of the tests are determined. Cost of inspections and tests of any item, which fails to meet the specifications, shall be borne by the bidder.
7. F.O.B. POINT:
Unless otherwise stated in the invitation to bid and any resulting contract, or unless qualified by the bidder, items shall be shipped F.O.B. Destination. The seller shall retain title for the risk of transportation, including the filing for loss or damages. The invoice covering the items is not payable until items are delivered and the contract of carriage has been completed. Unless the F.O.B. clause states otherwise, the seller assumes transportation and related charges either by payment or allowance.
8. PATENT INDEMNITY:
The contractor guarantees to hold the City, its agents, officers or employees harmless from liability of any nature or kind for use of any copyrighted or uncopyrighted composition, secret process, patented or unpatented invention, articles or appliances furnished or used in the performance of the contract, for which the contractor is not the patentee, assignee or licensee.
9. BID BONDS AND PAYMENT AND PERFORMANCE BONDS (IF REQUIRED):
A five percent (5%) bid bond is required for this Bid. The bidder will be required to provide a one hundred percent (100%) performance bond, and a one hundred percent (100%) payment bond, to be furnished to the City of Dunwoody for any awarded bid as required in bid package or document.
Failure to submit appropriate bonding will result in automatic rejection of bid. Bonding company must be authorized to do business in Georgia by the Georgia Insurance Commission, listed in the Department of the Treasury’s publication of companies holding certificates of authority as acceptable surety on Federal bonds and as acceptable reinsuring companies, and have an A.M. Best rating as stated in the insurance requirement of the solicitation.
10. AWARD:
A. Award will be made to the lowest responsive and responsible bidder. The quality of the articles to be supplied, their conformity with the specifications, their suitability to the requirements of the City, and the delivery terms will be taken into consideration in making the award. The City may make such investigations as it deems necessary to determine the ability of the bidder to perform, and the bidder shall furnish to the City all such information and data for this purpose as the City may request. The City reserves the right to reject any bid if the evidence submitted by, or investigation of such bidder fails to satisfy the City that such bidder is properly qualified to carry out the obligations of the contract.
B. The City reserves the right to reject or accept any or all bids and to waive technicalities, informalities and minor irregularities in bids received.
C. The City reserves the right to make an award as deemed in its best interest, which may include awarding a bid to a single bidder or multiple bidders; or to award the whole bid, only part of the bid, or none of the bid to single or multiple bidders, based on its sole discretion of its best interest.
11. DELIVERY FAILURES:
Failure of a contractor to deliver within the time specified or within reasonable time as interpreted by the Purchasing Manager, or failure to make replacement of rejected articles/services when so requested, immediately or as directed by the Purchasing Manager, shall constitute authority for the Purchasing Manager to purchase in the open market articles/services of comparable grade to replace the articles/services rejected or not delivered. On all such purchases, the contractor shall reimburse the City within a reasonable time specified by the Purchasing Manager for any expense incurred in excess of contract prices, or the City shall have the right to deduct such amount from monies owed the defaulting contractor. Alternatively, the City may penalize the contractor one percent (1%) per day for a period of up to ten (10) days for each day that delivery or replacement is late. Should public necessity demand it, the City reserves the right to use or consume articles delivered which are substandard in quality, subject to an adjustment in price to be determined by the Purchasing Manager.
12. CITY FURNISHED PROPERTY:
No material, labor or facilities will be furnished by the City unless so provided in the invitation to bid.
13. REJECTION AND WITHDRAWAL OF BIDS:
Failure to observe any of the instructions or conditions in this invitation to bid may constitute grounds for rejection of bid.
14. CONTRACT:
A. Each bid is received with the understanding that the acceptance in writing by the City of the offer to furnish any or all of the commodities or services described therein shall constitute a contract between the bidder and the City which shall bind the bidder on his part to furnish and deliver the articles quoted at the prices stated in accordance with the conditions of said accepted bid. The City, on its part, may order from such contractor, except for cause beyond reasonable control, and to pay for, at the agreed prices, all articles specified and delivered.
B. It is understood that the bidder has reviewed the contract documents with the understanding that the City of Dunwoody requires that all agreements between the parties must be entered into via this document. If any exceptions are taken to any part, each must be stated in detail and submitted as part of the bid. If no exceptions are stated, it is assumed that the bidder fully agrees to the provisions contained in the “Sample Contract” in its entirety.
C. When the contractor has performed in accordance with the provisions of this agreement, the City of Dunwoody shall pay to the contractor, within thirty (30) days of receipt of any department approved payment request and based upon work completed or service provided pursuant to the contract, the sum so requested, less the retainage stated in this agreement, if any.
15. NON-COLLUSION:
Bidder declares that the bid is not made in connection with any other bidder submitting a bid for the same commodity or commodities, and that the bid is bona fide and is in all respects fair and without collusion or fraud. An affidavit of non-collusion shall be executed by each bidder. Collusion and fraud in bid preparation shall be reported to the State of Georgia Attorney General and the United States Justice Department.
16. DEFAULT:
The contract may be canceled or annulled by the Purchasing Manager in whole or in part by written notice of default to the contractor upon non-performance or violation of contract terms. An award may be made to the next low responsive and responsible bidder, or articles specified may be purchased on the open market similar to those so terminated. In either event, the defaulting contractor (or his surety) shall be liable to the City for costs to the City in excess of the defaulted contract prices; provided, however, that the contractor shall continue the performance of this contract to the extent not terminated under the provisions of this clause. Failure of the contractor to deliver materials or services within the time stipulated on his bid, unless extended in writing by the Purchasing Manager, shall constitute contract default.
17. TERMINATION FOR CAUSE:
The City may terminate this agreement for cause upon ten days prior written notice to the contractor of the contractor’s default in the performance of any term of this agreement. Such termination shall be without prejudice to any of the City’s rights or remedies by law.
18. TERMINATION FOR CONVENIENCE:
The City may terminate this agreement for its convenience at any time upon 30 days written notice to the contractor. In the event of the City’s termination of this agreement for convenience, the contractor will be paid for those services actually performed. Partially completed performance of the agreement will be compensated based upon a signed statement of completion to be submitted by the contractor, which shall itemize each element of performance.
19. DISPUTES:
Except as otherwise provided in the contract documents, any dispute concerning a question of fact arising under the contract which is not disposed of shall be decided after a hearing by the Purchasing Manager, who shall reduce his/her decision to writing and mail or otherwise furnish a copy thereof to the contractor. The decision of the Purchasing Manager shall be final and binding; however, the contractor shall have the right to appeal said decision to a court of competent jurisdiction.
20. SUBSTITUTIONS:
Bidders offering and quoting on substitutions or who are deviating from the attached specifications shall list such deviations on a separate sheet to be submitted with their bid. The absence of such a substitution list shall indicate that the bidder has taken no exception to the specifications contained herein.
21. INELIGIBLE BIDDERS:
The City may choose not to accept the bid of a bidder who is in default on the payment of taxes, licenses or other monies due to the City. Failure to respond to three (3) consecutive times for any given commodity/service may result in removal from the supplier list under that commodity/service.
22. BUSINESS LICENSE:
Each successful bidder shall provide evidence of a valid City of Dunwoody business license if the bidder maintains an office within the City of Dunwoody. Unincorporated, out of City, and out of State bidders are required to provide evidence of a certificate to do business in any town, County or municipality in the State of Georgia, or as otherwise required by City ordinance or resolution.
23. ALTERATIONS OF SOLICITATION AND ASSOCIATED DOCUMENTS:
Alterations of City documents are strictly prohibited and will result in automatic disqualification of the firm’s solicitation response. If there are “exceptions” or comments to any of the solicitation requirements or other language, then the firm may make notes to those areas, but may not materially alter any document language.
24. TAX LIABILITY:
Local and state governmental entities must notify contractors of their use tax liability on public works projects. Under Georgia law, private contractors are responsible for paying a use tax equal to the sales tax rate on material and equipment purchased under a governmental exemption that is incorporated into a government construction project: excluding material and equipment provided for the installation, repair, or expansion of a public water, gas or sewer system when the property is installed for general distribution purposes. To the extent the tangible personal property maintains its character (for example the installation of a kitchen stove), it remains tax-exempt. However, if the installation incorporates the tangible personal property into realty, e.g., the installation of sheetrock, it becomes taxable to the private contractor.
See O.C.G.A. 48-8-3(2) and O.C.G.A. 48-8-63
25. GENERAL CONTRACTORS LICENSE:
All General Contractors must have a current valid license from the State Licensing Board for Residential and General Contractors, unless specifically exempted from holding such license pursuant to Georgia law (O.C.G.A. Section 43-41-17).
26. INDEMNIFICATION:
To the fullest extent permitted by law, the Contractor shall, at his sole cost and expense, indemnify, defend, satisfy all judgments, and hold harmless the City, the engineer, and their agents and employees from and against all claims, damages, actions, judgments, costs, penalties, liabilities, losses and expenses, including, but not limited to, attorney's fees arising out of or resulting from the performance of the work, provided that any such claim, damage, action, judgment, cost, penalty, liability, loss or expense (1) is attributable to bodily injury, sickness, disease, or death, or to injury to or destruction of tangible property (other than the work itself) including the loss of use resulting therefrom, and (2) is caused in whole or in part by any act or omission of the Contractor, any subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, regardless whether such claim is caused in part by a party indemnified hereunder. Such obligation shall not be construed to negate, abridge or otherwise reduce any of the rights or obligations of indemnity which would otherwise exist as to any party or person described in this agreement. In any and all claims against the City, the engineer, or any of their agents or employees by any employee of the Contractor, any subcontractor, anyone directly or indirectly employed by any of them, or anyone for whose acts any of them may be liable, the indemnification obligation contained herein shall not be limited in any way by any limitation on the amount or type of damages, compensation, or benefits payable by or for the Contractor or any subcontractor under Worker's Compensation Acts, disability benefit acts, or other employee benefit acts.
27. ENVIRONMENTAL SUSTAINABILITY
The City of Dunwoody is committed to environmental sustainability. The City believes we have a unique opportunity to further expand our leadership in the area of environmentally preferable purchasing, and through our actions, elicit changes in the marketplace. By further incorporating environmental considerations into public purchasing, the City of Dunwoody will positively impact human health and the environment, remove unnecessary hazards from its operations, reduce costs and liabilities, and improve the environmental quality of the region. As such the City encourages the incorporation of environmental sustainability into proposals.
*DIRECTIONS TO DUNWOODY CITY HALL*
From I-285 take Exit 29 (Ashford-Dunwoody Rd.) and turn North. Turn left on Ashford Gables Drive. The entrance to the parking lot for 4800 Ashford Dunwoody Rd is on the right. The City of Dunwoody offices are on the second floor.
END OF BID INSTRUCTIONS SECTION 0100
SCOPE OF WORK
SECTION 0250
The Mount Vernon Road Multi-Use Trail project work includes adding a pedestrian path along the north side of Mount Vernon Road, extensive overhead and underground public utility re-location, staged temporary construction of diversion lanes to allow for installation of 2 new water mains in the existing eastbound traffic lane, new storm drain and structures, the construction of gravity walls, milling, patching, leveling and paving Mount
Vernon Road. Work also includes new signal poles, mast arms and control cabinet at the Tilly Mill Road intersection, and placement of required signage, thermoplastic pavement markings and RPMs. The contractor shall furnish all materials (unless otherwise noted), equipment, and labor to complete the required construction as described in its entirety to the specifications as directed and the terms of this contract including all incidentals as directed by the City of Dunwoody Director of Public Works or his representative.
Construction plans can be accessed and downloaded at the following link:
2119189_Mt Vernon Road_Final Plans_01-29-26.pdf
Utility Adjustment plans and UAS�s can be accessed / downloaded from the following link:
Mt Vernon Road - Utility Adjustment Plans and UAS's
Unless otherwise specified, the project shall be completed in compliance with the Construction Documents prepared by Southeastern Engineering, Inc
(SEI) dated and stamped 1-28-2026, Georgia Department of Transportation
Standard Specifications and Supplemental Specifications, Current Edition and the bid documents including all appendices and addenda. It is the intent of this contract for each unit price bid to include all labor, materials, equipment, tools, transportation, and supplies as required to complete the work in accordance with the plans, specifications as directed, and the terms of this contract. The contractor is responsible for inspecting the site and for being thoroughly familiar with all bid and contract documents.
https://dunwoodygagov.sharepoint.com/:f:/s/CitizenUploadSite/IgCiGeqlHfcvQae5EiiJ-ixgAWPF7RsErJZnAUEoKsAVUFQ?e=ywuhB1 https://dunwoodygagov.sharepoint.com/:b:/s/CitizenUploadSite/IQAtBfJEfgSESb1irjFRqzWAAYnf5IvOd2yEcg5tOGmHq_Y?e=Wsn1pu
SECTION 0250
Any item which must be removed during the construction work and which is not specifically called for shall be removed by the contractor. The cost shall be included in other unit price bid items. No claims will be considered for extra compensation.
Project Execution Parameters:
Work is expected to be completed as follows:
a. Contractor management of the utility adjustment phase shall begin within 10 calendar days of issuance of the Notice to Proceed.
Responsibilities shall include conducting the Major Project Utility Coordination Meeting with all utilities (Georgia Power, Comcast, AT&T, AGL, DeKalb Watershed Management (DWM), Colonial Pipeline, Flock Camera, Dunwoody ITS, Crown Castle, etc.) in the project limits, weekly communication with ongoing utility relocation to confirm vendor is tracking on schedule and notification of schedule improvement and/or slippage. Escalation, monitoring and enforcement / documentation of the individual utility UASs shall also be the contractor�s responsibility. [Reference also Utility Coordination section below.]
b. Within 10 days of issuance of the NTP, contractor shall initiate clearing all trees in the R/W. Tree removal shall not exceed 30 calendar days.
c. The fill section at Parcel 4 needs to be cleared / graded and fill/ placed / compacted to construct the new shoulder/ slope before AGL can begin relocating the gas main. It is anticipated that the gas main installation needs to occur ahead of wall and path construction on the north shoulder.
d. Contractor Execution Narrative / Sequence of Operations: Furnish a project narrative at time of bid outlining the contractor�s approach and general sequence of operations. This can be presented in outline form and should address:
i. Critical Path activities,
ii. Utility constraints and your plan for addressing / working around said
iii. Staging parameters, TCP and ongoing pedestrian access
iv. Coordination with residents and commercial enterprise(s)
v. Work Zone / Site maintenance and management
vi. Contractor Quality Contral plan
SECTION 0250
DeKalb Watershed Management
Water Service Outages: All water service outages shall be minimized and shall be approved in writing at least 72 hours in advance of the requested outage. A designated DWM representative must be present for the duration of the scheduled outage.
Water Main Construction Requirements: The contractor performing the work should be thoroughly familiar with the installation methods and procedures of DWM. All work shall be in conformance with the requirements of DeKalb County DWM�s Design and Construction Standards Manual current edition.
This document is available for download at:
Dekalb Watershed Management Water and Sewer Design Standards 12-14- 2017.pdf
Contractors performing this work shall be Prequalified or Registered with GDOT under Work Class 670-Water Distribution. The contractor performing this work, along with the superintendent�s contact information and resume, must be provided with the submission of Bid. Contractors self-performing the water distribution shall submit a minimum of 3 projects completed within the last 5 years that included installation of similar scope. If this portion of the work is subcontracted, then the prime contractor shall provide the same information with their subcontractor. Projects submitted must contain a brief narrative of the work performed and references for the acting superintendent and owner�s construction manager.
Prior to close-out, the utility contractor shall furnish survey-grade As-Builts in accordance with DWM requirements. An As-Built Checklist is available for reference within the DWM Design and Construction Standards Manual � Appendix E3.
Utility Coordination https://dunwoodygagov.sharepoint.com/:b:/s/CitizenUploadSite/IQBXmMlVoYQrRr18aYaM8U47AYuUUYfyT4prhsANz7ln7PI?e=FX7AEC
SECTION 0250
The contractor is responsible for calling for utility locates prior to the start of work and throughout the duration of construction in compliance with Georgia Utility Facility Protection Act �GUFPA� procedures for Large Projects. It shall be the contractor's responsibility to coordinate his work, including marking / refresh as required during construction. No claims will be considered for extra compensation.
The contractor shall have a designated representative (WUCS) on staff to coordinate utility relocation work in accordance with the approved work plan and project schedule. [Reference GDOT Supplemental Specifications Section 107 attached in Section 0875 � Special Provisions.] GDOT Utility Accommodation Policy and Standards (2016) shall govern. This designated representative shall be responsible for managing and enforcing the Utility Adjustment Schedules as provided by the affected utilities on this project. The current UASs are attached for reference and contractor planning purposes.
Minimum Contractor Qualifications
The contractor must meet Georgia general contractor licensing requirements and be a Georgia Department of Transportation prequalified contractor. The contractor shall have been a licensed general or utility contractor engaged in construction and successful completion of work of similar character and magnitude for at least five years and shall demonstrate the financial ability to perform the work. The current GDOT Certificate of Qualification letter must be submitted at time of bid.
The Prime Contractor is required to be certified in the following work classes:
205, 209, 310, 441, 550 and 668. In addition to the required work classes, a contractor certified in 149, 150 and 500a is preferred.
Traffic Control
All traffic control shall be provided by the contractor in accordance with
GDOT�s �shelf� Special Provision 150. Assistance from police officers will not be provided by the City. Two-way traffic and driveway access must be maintained throughout
SECTION 0250
the construction of this project unless noted otherwise. Work times and lane closure or restriction times are detailed in Special Conditions Article 2.5
Temporary Traffic Control Zone for Vehicular and Pedestrian Traffic
The ingress and egress of vehicles for private property shall not be hindered by construction activities. Driveways shall be maintained or temporary driveways constructed to allow vehicular access from the right-of-way.
Driveway access shall not exceed the existing or proposed slopes, whichever is higher. Driveways along a pedestrian route shall accommodate safe pedestrian passage.
Pedestrian passage within the project limits shall be accommodated at all times. A pedestrian walkway, consisting of a level, continuous surface (firm, stable and slip resistant), shall be provided throughout the entire length of the project. Crossings shall be planned to occur at a signalized intersection, Where a crossing between signals is necessary, a temporary crosswalk shall be striped and a temporary pedestrian crosswalk system shall be provided.
Access to transit stops shall be maintained.
Barriers and channelizing devices used along a temporary pedestrian route shall be in compliance with the MUTCD. A pedestrian walkway shall not be severed or relocated for non-construction activities, such as parking for construction vehicles and equipment.
Movement by construction vehicles and equipment across designated pedestrian walkways should be minimized. When necessary, construction activities shall be controlled by flaggers. Pedestrian walkways shall be kept free of mud, loose gravel, or other debris. A traffic control plan, including signage, shall be submitted to the Project Manager at least (14) days prior to the anticipated traffic shift.
Traffic Control General Notes for Waterline Construction:
1. During the construction of the proposed water line, two-way traffic will be maintained for most of the project, except as noted. Any deviations from these traffic limits will require city approval before work can commence.
SECTION 0250
a. For the segment from STA 101+83 to STA 103+50: If two 10-foot lanes cannot be maintained, the water line will be constructed with temporary lane closures managed by police and flaggers.
b. For the segment from STA 103+50 to STA 110+00: If two 10-foot lanes cannot be maintained, a detour for eastbound traffic will be implemented as depicted in Figure 1, utilizing a temporary traffic signal at the intersection of
Mount Vernon Place and Tilly Mill Road. The detour duration will not exceed
30 calendar days.
All signage must comply with the current edition of the Manual on Uniform
Traffic Control Devices (MUTCD).
c. For the segment from STA 110+00 to STA 130+46: Two 10-foot lanes must be maintained using temporary pavement as needed.
It is anticipated that temporary barriers (GDOT specifications Section will be needed between the temporary lanes and the water main construction.
Additional barriers may also be needed where fixed objects are close to the edge of the temporary lane.
d. For the segment from STA 130+46 to STA 131+50: If two 10-foot lanes cannot be maintained, the water line will be constructed with temporary lane closures managed by police and flaggers. A temporary detour for Tilly Mill
Road via Mount Vernon Place will be permissible while the water main is installed across the Tilly Mill intersection.
Figure 1
SECTION 0250
2. A traffic control plan detailing the water line construction and including any required signage, signals, and striping must be submitted to the city for approval before any work on the water line construction begins.
3. The Contractor will consider necessary signal head adjustments to accommodate the detour and temporary lanes, any necessary striping, striping eradication, signing and temporary lane shifts of the travel lanes throughout the project. This includes installation and removal of the temporary travel lanes. Cost for construction of the work associated with this work will be paid for under the Traffic Control Bid Item in the WATER DISTRIBUTION Bid Schedule.
4. Construction of any temporary paving will be paid for by the SYD on Pay Item noted on the Water Main bid form. Design of temporary pavement shall follow the
GDOT Pavement Design Manual. Chapter 4 (Pavement Design Procedures) provides design considerations and Section 4.4.4 provides the design criteria for Temporary
SECTION 0250
Pavements. For this project, the contractor should consider a design that will accommodate an AADT of 15,000, with an estimated AADTT of 750.
5. Maintenance of the temporary paving is the responsibility of the Contractor. The
City will notify the Contractor of any deficient areas of temporary paving. If the
Contractor fails to remedy the unsatisfactory maintenance within 48 hours after receipt of such notice, the City may immediately proceed to maintain the Work, and the entire cost of this maintenance will be deducted from monies due or to become due the Contractor under the Contract.
6. For the duration of the project the Contractor will provide three PCMS for use on the project. The PCMS will be deployed to the project 7 days prior to the beginning of work and remain through the duration of the work. Location and messaging will be directed by the City.
7. The contractor shall add, replace, remove, adjust and/or reset existing roadway signs, as necessary, throughout the construction to comply with the
MUTCD. Contractor shall be responsible for adjusting overhead traffic signal heads based on temporary lane shifts during construction.
Schedule
The contractor shall conduct one overall Construction Pre-Construction meeting with the city stakeholders, designated personnel from DeKalb Watershed Management (DWM) and all affected utilities.
The contractor shall submit a CPM/Gantt Chart construction schedule including detail on tasks and subtasks to the city within 14 calendar days following the pre-construction meeting. This schedule must include details / tasks that identify how the contractor proposes to build the project including utility re-location.
a. Contractor shall furnish monthly schedule reports with their monthly pay requests.
b. In the event the contractor falls behind schedule, detailed recovery plans must be submitted with the pay request.
c. Time is of the essence. Failure or delay in completing work on time will result in daily deductions as outlined in Section 108.08 of GDOT�s Standard Specifications.
SECTION 0250
If a Construction Contract is approved by the City, a Notice of Award is expected to be given by the 3rd QTR, 2026.
The contractor shall mobilize within 10 days of receiving notice to proceed.
Work shall be completed within 1100 calendar days following issuance of the
NTP. Once construction begins in an area, the contractor shall work diligently and without delay to complete the work to minimize disruption to the property owners.
Delay in completion of the project results in additional management and testing costs to the City and erosion of public confidence and goodwill. The failure or delay in completing work on time will result in daily deductions
(liquidated damages) as outlined in Special Conditions, Section 850, Article
2.3. For each day or Available Day, as specified, that any work shall remain uncompleted after the contract time specified for the completion of the Work required by the Contract, the sum specified in the Contract will be deducted from any money due the Contractor, not as a penalty, but as liquidated damages; provided however, that due account shall be taken of any adjustment of the contract time for completion of the work previously agreed to by both parties, as may be required from time to time. The amount of such charges is hereby agreed upon as fixed liquidated damages due the City of
Dunwoody after the expiration of the time for completion specified in the contract. The Contractor shall be liable for liquidated damages in excess of the amount due the Contractor on the final payment. These fixed liquidated damages are not established as a penalty but are calculated and agreed upon in advance by the City of Dunwoody and the Contractor due to the uncertainty and impossibility of making a determination as to the actual and consequential damages which are incurred by the City and the general public as a result of the failure on the part of the Contractor to complete The Work on time.
SECTION 0250
Striping
1. Marking tape is permissible for temporary pavement markings on milled surfaces and freshly paved asphalt when traffic remains in the original configuration. Traffic placed in a new traffic configuration shall require temporary paint striping. Temporary marking must be placed, and maintained until permanent marking can be installed, on all pavement areas to be opened to traffic. The pre-marking layout shall be approved by the
City prior to temporary or permanent pavement marking.
2. Interim pavement marking must be installed prior to opening areas to traffic. Traffic configuration changes shall be full pattern pavement markings.
Temporary tape is not permissible on traffic configuration changes. The City of Dunwoody shall approve all striping layout. If the project requires asphalt paving, thermoplastic pavement markings must be installed no sooner than
15 days after paving but no later than 30 days after paving on final surface courses. Should the contractor fail to meet these requirements, the City will remove these items from the contract and deduct from the contract any additional costs incurred by the City to complete the work.
3. Where construction plans indicate 5� striping, 6� shall be used instead.
The pay items for 6� striping are included in the bid schedule.
Miscellaneous:
1. Unless noted otherwise on the plans, existing wood privacy fences, decorative brick walls, etc. shall be protected from damage by construction / utility work. In the event any of these are damaged, the contractor shall replace in kind at contractor expense.
2. Final site stabilization / restoration: Disturbed areas to be stabilized with sod or permanent grassing as noted on the plans or as directed by the city. Place cypress mulch and/or pine straw as directed by the city.
BASE BID
ITEM NO. DESCRIPTION QTY UNIT UNIT
PRICE
EXTENDED
COST
ROADWAY ITEMS
150-1000 TRAFIC CONTROL � MT VERNON RD MULTI-USE
TRAIL
1 LS
205-0210 EXCAVATION � ROCK-SPECIAL PROV (AS
DIRECTED BY CITY ENGINEER)
100 CY
206-0002 BORROW EXCAV, INCL MATL-SPECIAL PROV
(AS DIRECTED BY CITY ENGINEER)
350 CY
207-0203 FOUND BKFL MATL, TP 2 (AS DIRECTED BY
CITY ENGINEER)
175 CY
210-0100 GRADING COMPLETE � MT VERNON RD MULTI-
USE TRAIL
1 LS
310-1101 GR AGGR BASE CRS, INCL MATL-10 IN 3,900 SY
318-3000 AGGR SURF CRS 200 TN
402-1802 RECYCLED ASPHALT CONC PATCHING, INCL
BITUM MATL & H LIME
300 TN
402-1812 RECYCLED ASPH CONC LEVELING, INCL
BITUM MATL & H LIME
125 TN
402-3121 RECYCLED ASPH CONC 25 MM SUPERPAVE, GP
2 ONLY, INCL BITUM MATL & H LIME
336 TN
402-3130 RECYCLED ASPH CONC 12.5 MM SUPERPAVE,
GP 2 ONLY, INCL BITUM MATL & H LIME
1,058 TN
402-3190 RECYCLED ASPH CONC 19 MM SUPERPAVE, GP
1 OR 2, INCL BITUM MATL & H LIME
169 TN
413-0750 BITUM TACK COAT 1439 GAL
432-0206 MILL ASPH CONC PVMT, VARIABLE DEPTH 1300 SY
441-0016 DRIVEWAY CONCRETE, 6 IN TK 122 SY
441-0018 DRIVEWAY CONCRETE, 8 IN TK 177 SY
441-0104 CONC SIDEWALK, 4 IN 1,601 SY
441-0106 CONC SIDEWALK, 6 IN 3,225 SY
441-0108 CONC SIDEWALK, 8 IN 318 SY
441-0754 CONCRETE MEDIAN, 7 1/2 IN, TYPE 7 FACE 46 SY
441-4020 CONC VALLEY GUTTER, 6 IN 234 SY
441-4030 CONC VALLEY GUTTER, 8 IN 40 SY
441-5002 CONC HEADER CURB, 6 IN, TP 2 33 LF
441-5008 CONCRETE HEADER CURB, 6 IN, TP 7 1,516 LF
441-6216 CONC CURB & GUTTER, 8 IN X 24 IN, TP 2 5,777 LF
441-6299
CONC CURB & GUTTER, 8 IN X 24 IN, ROLLED
CURB
35 LF
446-1100
PVMT REINF FABRIC STRIPS, TP 2, 18 INCH
WIDTH
1622 LF
500-3201 CLASS B CONCRETE, RETAINING WALL 155 CY
500-9999 CLASS B CONC, BASE OR PVMT WIDENING 88 CY
515-2020 GALV STEEL PIPE HANDRAIL, 2 IN, ROUND 768 LF
621-6200 CONCRETE SIDE BARRIER, TP 2-S 201 LF
621-6201 CONCRETE SIDE BARRIER, TP 2-SA 59 LF
632-0003
CHANGEABLE MESSAGE SIGN, PORTABLE, TP
3 EA
634-1200 RIGHT OF WAY MARKERS 6 EA
643-8200 BARRIER FENCE (ORANGE), 4 FT 85 LF
900-0526 BOLLARDS 4 EA
999-1000
WOODEN PRIVACY FENCE, 6-FOOT
SHADOWBOX PATTERN STATION 121+17 LT TO
121+48 LT
47 LF
999-1001
DECORATIVE STONE WALL, 3 FOOT, STATION
120+76 LT TO 121+41 LT
65 LF
SIGNING AND MARKING ITEMS
610-9001 REM SIGN 9 EA
611-5551 RESET SIGN 9 EA
636-1033 HWY SIGNS, TP 1 MATL-REFL SHEETING, TP 9 159 SF
636-1036 HWY SIGNS, TP 1 MATL-REFL SHEETING, TP 11 108 SF
636-2070 GALV STEEL POSTS TP 7 387 LF
653-0120
THERMOPLASTIC PVMT MARKING, ARROW,
TP 2 17 EA
653-0130
THERMOPLASTIC PVMT MARKING, ARROW,
TP 3 3 EA
653-1906
THERMOPLASTIC SOLID TRAFFIC STRIPE, 6
IN, WHITE 3,626 LF
653-2602
THERMOPLASTIC SOLID TRAFFIC STRIPE, 6
IN, YELLOW 5,234 LF
653-1504
THERMOPLASTIC SOLID TRAFFIC STRIPE, 12
IN, WHITE 975 LF
653-1704
THERMOPLASTIC SOLID TRAFFIC STRIPE, 24
IN, WHITE 828 LF
653-2611
THERMOPLASTIC SKIP TRAFFIC STRIPE, 6 IN,
WHITE
1,235
GLF
653-3602
THERMOPLASTIC SKIP TRAFFIC STRIPE, 6 IN,
YELLOW
GLF
653-6004 THERMOPLASTIC TRAF STRIPING, WHITE 45 SY
653-6006 THERMOPLASTIC TRAF STRIPING, YELLOW 80 SY
654-1001 RAISED PVMT MARKER, TP 1 110 EA
654-1003 RAISED PVMT MARKER, TP 3 21 EA
659-7015
HOT APPLIED PREFORMED PLASTIC PVMT
MKG, BIKE LANE MARKING, TP P
EA
SITE LIGHTING
682-6222
CONDUIT, NONMETAL, TP 2, 2-INCH (AS
DIRECTED BY THE ENGINEER)
LF
SIGNAL ITEMS
636-1041 HWY SIGNS, TP 2 MATL-REFL SHEETING, TP 9 41 SF
639-3004
STEEL STRAIN POLE, TYPE IV (W/ TANDEM 60' & 60'
MAST ARMS) 1 EA
639-3004 STEEL STRAIN POLE, TYPE IV (W/ 40' MAST ARM) 1 EA
639-3004 STEEL STRAIN POLE, TYPE IV (W/ 45' MAST ARM) 1 EA
647-1000 TRAFFIC SIGNAL INSTALLATION #1 1 LS
682-2145 PULL BOX TYPE 4S 1 EA
682-9950 DIRECTIONAL BORE, 7" 200 LF
687-1000 TRAFFIC SIGNAL TIMING 1 LS
936-4000 CCTV CAMERA SYSTEM, TYPE 1 1 EA
936-8000 TESTING - CCTV 1 EA
937-6000 MICROWAVE RADAR DETECTION ASSEMBLY 5 EA
937-8020 TESTING - MICROWAVE DETECTION SYSTEM 1 LS
ITS ITEMS
647-2160 PULLBOX, PB-6 4 EA
682-6233 CONDUIT, NONMETAL, TP 3, 2-INCH 3,760 LF
682-9950 DIRECTIONAL BORE, 5 IN 1,880 LF
935-1116
OSP FIBER OPTIC CABLE, LOOSE TUBE, SINGLE
MODE, 72 FIBER
2,320
LF
935-3106
FIBER OPTIC CLOSURE, UNDERGROUND, 72
FIBER
EA
935-4010 FIBER OPTIC SPLICE, FUSION 720 EA
DRAINAGE ITEMS
550-3318 SAFETY END SECTION 18 IN, STORM DRAIN, 4:1 SLOPE 1 EA
550-5180 STORM DRAIN PIPE, 18 IN, CLASS III 1,294 LF
550-5183 STORM DRAIN PIPE, 18 IN, CLASS V 43 LF
550-5360 STORM DRAIN PIPE, 36 IN, CLASS III 555 LF
550-5420 STORM DRAIN PIPE, 42 IN, CLASS III 474 LF
550-5480 STORM DRAIN PIPE, 48 IN, CLASS III 109 LF
603-2181 STN DUMPED RIP RAP, TP 3, 18 IN 9 SY
603-7000 PLASTIC FILTER FABRIC 9 SY
611-3000 RECONSTR CATCH BASIN, GROUP 1 2 EA
611-3010 RECONSTR DROP INLET, GROUP 1 1 EA
611-3030 RECONSTR STORM SEW MANHOLE, TYPE 1 1 EA
668-1100 CATCH BASIN, GP 1 9 EA
668-1110 CATCH BASIN, GP 1, ADDL DEPTH 15 LF
668-1200 CATCH BASIN, GP 2 4 EA
668-1205 CATCH BASIN, GP 2, SPCL DES 5 EA
668-1210 CATCH BASIN, GP 2, ADDL DEPTH 12 LF
668-1215 CATCH BASIN, GP 2, ADDL DEPTH, SPCL DES 6 LF
668-2100 DROP INLET, GP 1 5 EA
668-4300 STORM SEWER MANHOLE, TP 1 3 EA
668-4311 STORM SEWER MANHOLE, TP 1, ADDL DEPTH, CL 1 2 LF
668-4312 STORM SEWER MANHOLE, TP 1, ADDL DEPTH, CL 2 11 LF
668-4398 STORM SEWER MANHOLE, TP 1, SPCL DES 1 EA
668-4399
STORM SEWER MANHOLE, TP 1, ADDL DEPTH, CL 1,
SPCL DES 1 LF
668-4400 STORM SEWER MANHOLE, TP 2 1 EA
668-4411 STORM SEWER MANHOLE, TP 2, ADDL DEPTH, CL 1 4 LF
668-4498 STORM SEWER MANHOLE, TP 2, SPCL DES 1 EA
668-4499
STORM SEWER MANHOLE, TP 2, ADDL DEPTH, CL 1,
SPCL DES 2 LF
EROSION CONTROL ITEMS
163-0232 TEMPORARY GRASSING 2 AC
163-0240 MULCH 53 TN
163-0301 CONSTRUCT AND REMOVE CONSTRUCTION EXITS 1 EA
163-0550 CONSTRUCT AND REMOVE INLET SEDIMENT TRAP 39 EA
165-0010 MAINTENANCE OF TEMPORARY SILT FENCE, TYPE A 2,855 LF
165-0101 MAINTENANCE OF CONSTRUCTION EXIT 1 EA
165-0105 MAINTENANCE OF INLET SEDIMENT TRAP 39 EA
165-0310
MAINTENANCE OF CONSTRUCTION EXIT TIRE WASH
AREA (PER EACH)
1 EA
167-1000 WATER QUALITY MONITORING AND SAMPLING 12 EA
167-1500 WATER QUALITY INSPECTIONS 18 MO
171-0010 TEMPORARY SILT FENCE, TYPE A 5,710 LF
700-6910 PERMANENT GRASSING 2 AC
700-7000 AGRICULTURAL LIME 4 TN
700-8000 FERTILIZER MIXED GRADE 2 TN
700-8100 FERTILIZER NITROGEN CONTENT 253 LB
700-9300 SOD 3,779 SYD
702-9025
LANDSCAPE MULCH, AVG. 4.5 INCHES THICK CYPRESS
MULCH (AS DIRECTED BY THE CITY)
250 SYD
999-1002
LONG-NEEDLE PINE STRAW BALES (AS DIRECTED BY
THE CITY)
300 EA
716-2000 EROSION CONTROL MATS, SLOPES 203 SY
BASE BID: $_____________________________________
SUBMITTED BY (CONTRACTOR NAME) _________________________________________________________
WATER DISTRIBUTION BID
ITEM NO. DESCRIPTION QTY UNIT UNIT
PRICE
EXTENDED
COST
150-1000 TRAFFIC CONTROL-WATER DISTRIBUTION SYSTEM 1 LS
205-0210
EXCAVATION � *ROCK-SPECIAL PROVISION*
(AS DIRECTED BY CITY ENGINEER) 700 CY
210-0100 GRADING COMPLETE-WATER DISTRIBUTION SYSTEM 1 LS
500-3101 CLASS A CONCRETE 60 CY
600-0001 FLOWABLE FILL 25 CY
670-1060 WATER MAIN-6 IN *SPECIAL PROVISION* 260 LF
670-1080
WATER MAIN-8 IN *SPECIAL PROVISION*
3,500 LF
670-1160
WATER MAIN-16 IN *SPECIAL PROVISION*
3,030 LF
670-1600
CUT & PLUG EXISTING WATER MAIN *SPECIAL
PROVISION* 12 EA
670-2060 GATE VALVE, 6 IN *SPECIAL PROVISION* 25 EA
670-2080
GATE VALVE, 8 IN *SPECIAL PROVISION*
10 EA
670-2160
GATE VALVE, 16 IN *SPECIAL PROVISION*
6 EA
670-2700
ABANDOMENT OF WATER VALVES *SPECIAL
PROVISION* 11 EA
670-2800 COMBINATION AIR VALVES *SPECIAL PROVISION* 2 EA
670-3066
TAPPING SLEEVES AND VALVE ASSEMBLY, 6 IN X 6 IN
*SPECIAL PROVISION* 5 EA
670-3087
TAPPING SLEEVES AND VALVE ASSEMBLY, 8 IN X 8 IN
*SPECIAL PROVISION* 7 EA
670-3129
TAPPING SLEEVES AND VALVE ASSEMBLY, 16 IN X 16
IN *SPECIAL PROVISION* 1 EA
670-4000 FIRE HYDRANT *SPECIAL PROVISION* 10 EA
670-500 WATER SERVICE LINE…