This document is an Addendum to an Invitation to Bid (ITB) #24-014 T0069 for the Peachtree Dunwoody Rd and Windsor Pkwy ITS Project. The project is being solicited by a state or local government entity. The addendum addresses questions related to the 51% work performance requirement for the prime contractor, and clarifies that the budget for the project is over $100,000. The bid response is due on October 17, 2023 at 2:00 p.m.
The addendum outlines the definition of "work" and the 51% work performance requirement for the prime contractor, as detailed in Articles 2.2 and 2.5 of the ITB. It states that the prime vendor must have the necessary staff in place if awarded the contract. No further details on the project budget or past project costs of similar magnitude are provided, other than the budget being over $100,000.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 24_014 T0069 Peachtree Dunwoody Rd and Windso.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum Number 1
ITB #24-014 T0069 Peachtree Dunwoody Rd and Windsor Pkwy ITS Project
COMPLETE THIS ADDENDUM, SIGN and SUBMIT with the ITB
RESPONSE DUE DATE: October 17, 2023 2:00 p.m.
To All Prospective Offerors: In reference to the ITB listed above, the following answers to questions, additions, deletions, and changes are hereby incorporated into the ITB:
Q 1: The bid proposal states that a company can utilize subcontractors, but 51% has to be handled internally. Can project management (Project Manager) or other types of work that will be needed that may not be included in the items quote requirements be counted within that 51%? What constitutes
51% of the work performed?
Answer: The prime vendor is responsible for completing 51% of the work to be performed. Articles
2.2 “Work” Defined and 2.5 Work to be Performed by the Prime Contract, lay out the definition of work and the 51% of the value of the project requirement.
Q 2: If I currently do not have employees, will I have a period to hire staff to support this project 51% requirement?
Answer: If awarded at Mayor and Council, the vendor shall have the necessary staff in place.
Q 3: Is there any information you can share on the budget range or even share information on past project cost of similar magnitude?
Answer: The budget is over $100,000.
I hereby acknowledge receipt of Addendum Number 1 for 24-014 T0069 Peachtree Dunwoody Rd and
Windsor Pkwy ITS Project and have incorporated the changes into my response for the above mentioned ITB
COMPANY NAME:
CONTACT PERSON:
ADDRESS:
CITY: _________________________________STATE: ___________ ZIP: ________________________
PHONE: ________________ FAX: _______________
EMAIL ADDRESS: ______________________________________
SIGNATURE: ____________________________________________
DATE: ______________________________________
File details come from the government source that posted it. Updated .