ITB-2024-11_Milton_Force_Main_Interconnect_Materials_Phase_II_&_III_-_Addendum_1.pdf
PDF 224 KB Posted
- Solicitation number
- ITB-2024-11
- Issued by
- Florida
About this file
This document is Addendum #1 for RFP 2024.11 issued by the City of Milton Purchasing Department in Florida, addressing the Milton Force Main Interconnect Materials Phase 2 & 3 procurement. The addendum provides a series of seven questions and answers related to material specifications for the project, with each response consistently directing bidders to meet Pace Water System Inc. specifications. Specific inquiries cover domestic material requirements, ductile iron pipe coating, steel casing wall thickness and coating, ARI model selections, and submission procedures.
The addendum requires proposers to acknowledge receipt of the amendment by signing and submitting it with their proposal package. All submittals must be delivered to the City of Milton Purchasing Department at 6738 Dixon Street, Milton, FL 32570. The document emphasizes that proposers should make necessary adjustments to their estimates based on the addendum and that each proposal is expected to be submitted with full knowledge of all modifications and supplemental data specified. No specific pricing details, funding sources, or contract term lengths are provided in this addendum.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ITB-2024-11_Milton_Force_Main_Interconnect_Materials_Phase_II_&_III.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Milton Purchasing Department
P.O. Box 909 ● 6738 Dixon Street ● Milton, Florida 32572 ● (850) 983-5480 ● miltonfl.org
RFP 2024.11 Milton Force Main Interconnect Materials Phase 2 & 3
ADDENDUM #1 – Questions & Answers posted October 16, 2024
Question #1 Do all of the materials need to be Domestic?
Answer #1 All materials must meet Pace Water System Inc. specifications.
Question #2 Ductile Iron Pipe and Fittings is standard asphalt coated on the OD, is that acceptable? If not, what OD coating do you require?
Answer #2 All materials must meet Pace Water System Inc. specifications.
Question #3 What wall thickness are you requiring on the 24” steel casing?
Answer #3 All materials must meet Pace Water System Inc. specifications.
Question #4 Is the 24” casing bare or coated?
Answer #4 All materials must meet Pace Water System Inc. specifications.
Question #5 You have several ARI models listed, which one are you requiring?
Answer #5 All materials must meet Pace Water System Inc. specifications.
Question #6 Is ARV needed detail?
Answer #6 All materials must meet Pace Water System Inc. specifications.
Question #7 Does the City of Milton provide a method for vendors to submit their sealed responses electronically for the project referenced in the subject?
Answer #7 All Submittals should be delivered to: City of Milton, Purchasing Department, 6738 Dixon Street Milton, FL 32570.
End of Addendum #1
The information given in this addendum is in addition to or supersedes conflicting information in the request for proposal and is hereby made a part of the request.
Proposers are hereby notified that they shall make any necessary adjustments to their estimates because of this Amendment. It will be construed that each proposal is submitted with full knowledge of all modifications and supplemental data specified herein.
PROPOSERS MUST SIGN THE AMENDMENT AND SUBMIT IT WITH THEIR PROPOSAL.
ACKNOWLEDGEMENT:
I hereby certify that I have received the above addendum:
Signature Date
THIS ACKNOWLEDGEMENT MUST BE RETURNED
WITH PROPOSAL PACKAGE.