This document is a Scope of Work (SOW) for the Florida Department of Juvenile Justice (DJJ) Bureau of Information Technology, seeking a vendor to develop a comprehensive Business Impact Analysis (BIA) and Disaster Recovery Plan (DRP). The project aims to identify mission-critical functions, assess potential business interruption impacts, and establish an actionable recovery framework to ensure operational continuity. The contract term runs from August 1, 2025, to February 28, 2026, with work to be performed at the DJJ Office of Administration in Tallahassee. The vendor will be responsible for conducting stakeholder interviews, mapping critical dependencies, developing recovery strategies, and creating a detailed Disaster Recovery Plan aligned with state and federal cybersecurity standards, including NIST Cybersecurity Framework 2.0 and Florida Cybersecurity Standards.

The project requires the selected vendor to produce multiple deliverables, including a stakeholder interview summary, critical function inventory, impact analysis report, draft and final disaster recovery plans, and training materials. The project is funded through state appropriations and is contingent on legislative budget approval. Key compliance requirements include adhering to CJIS, HIPAA, and state law regulations, with strict data handling protocols involving encrypted data storage, secure systems, and non-disclosure agreements for all project personnel. The total project will involve comprehensive analysis of DJJ's IT systems, with a focus on maintaining continuous access to case management systems while protecting sensitive juvenile records and ensuring organizational resilience against potential disruptions.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Juvenile Justice Bureau of Information Technology Business Impact Analysis (BIA) and Disaster Recovery Plan (DRP) Development Scope of Work

May 9, 2025

HISTORY:

The State Department of Juvenile Justice (DJJ) plays a critical role in ensuring public safety and youth rehabilitation through secure detention, community-based services, education, and counseling. Given the sensitive nature of juvenile records, The Department of Juvenile Justice (DJJ) is essential for maintaining public safety and promoting youth rehabilitation, which is achieved through secure detention facilities, community-based services, education, and counseling. Due to the sensitive nature of juvenile records, DJJ must have continuous access to case management systems while adhering to legal data protection requirements. Therefore, DJJ requires a thorough Business Impact Analysis (BIA) and a Disaster Recovery Plan (DRP). Uninterrupted access to case management systems and the legal requirements for data protection, DJJ requires a comprehensive Business Impact Analysis (BIA) and Disaster Recovery Plan (DRP).

PROJECT OVERVIEW:

The Department of Juvenile Justice (“the Department”) is seeking proposals from qualified vendors to conduct a comprehensive Business Impact Analysis (BIA) and develop a robust Disaster Recovery Plan (DRP). This engagement aims to identify and prioritize mission-critical functions, assess the potential impacts of business interruptions, and establish an actionable recovery framework that ensures operational continuity following a disruption.

SCOPE:

This scope of work is for the vendor to perform the following: 1) Identify critical business operations and their dependencies. 2) Determine the impact of various disruption scenarios. 3) Establish Recovery Time Objectives (RTOs) and Recovery Point Objectives (RPOs). 4) Develop a Disaster Recovery Plan (DRP) that aligns with regulatory requirements. 5) Ensure compliance with cybersecurity and business continuity policies. 6) Recommend and document recovery strategies and plans for IT systems. 7) Validate the feasibility of the DRP through simulation or testing. These efforts aim to enhance organizational resilience, identify critical functions, and prepare response strategies for potential disruptions while protecting the agency's and customers' interests. The BIA and DRP should align with the requirements specified in Chapters 60GG-2.001 through 60GG-2.006, F.A.C., known as the State of Florida Cybersecurity Standards (SFCS). (Current chapter 60GG-2001(1)(a), F.A.C). , NIST Cybersecurity Framework (CSF) 2.0 (February 2024)

TERM:

This scope of work will begin on 8/1/2025 or the date the purchase order is issued, whichever is later. It will end at midnight, Eastern Time on February 28, 2026. The State of Florida’s performance and obligation to pay under this purchase order and any subsequent renewal is contingent upon annual appropriation by the Legislature and satisfactory performance of the Contractor.

LOCATION OF WORK:

The worksite for this scope of work is the following location (s):

Department of Juvenile Justice, Office of Administration, Bureau of Technology 2737 Centerview Drive Tallahassee, Fl 32399

CONTRACTOR RESPONSIBILITIES/DELIVERABLES:

A. Business Impact Analysis (BIA)

1.Stakeholder Engagement – Conduct interviews, surveys, and workshops with key
personnel across all departments.
2.Critical Function Identification – Identify mission-critical business processes,
applications, systems, and personnel.
3.Dependency Mapping – Assess and document internal and external interdependencies.
4.Impact Analysis – Evaluate potential impacts across multiple dimensions (e.g.,
operational, financial, legal, regulatory, reputational).
5.Recovery Objectives – Establish and document RTOs and RPOs for all critical functions.
6.Prioritization – Develop a prioritization matrix for systems and functions based on
criticality.

B. Disaster Recovery Plan (DRP)

1.DR Strategy Development – Define technical and operational strategies for recovery
of IT systems, applications, data, and infrastructure.
2.Role Definition and Escalation – Outline roles, responsibilities, escalation procedures,
and communication plans.
3.DRP Documentation – Develop a detailed, modular DRP aligned with industry standards
(e.g., NIST SP 800-34, ISO/IEC 22301)
4.Gap Analysis – Evaluate existing DR practices and capabilities; identify areas

requiring improvement.

5. Testing and Validation – Facilitate at least one tabletop exercise or recovery simulation.

6. Final Plan Package – Deliver a complete DRP, including review protocols and update schedules.

C. Deliverable Table

Deliverable
Description
Due Date (Tentative)
Project Kickoff Meeting
Initial meeting to establish

scope, schedule, and communication protocols Week 1

Stakeholder Interview Summary
Documentation of all initial

stakeholder input Week 2–3

Critical Function Inventory
List of all critical processes

and systems Week 4-6

Business Impact Analysis Report
Detailed report with impact

assessments, RTO/RPO, and prioritization Week 7-9

Disaster Recovery Strategy Draft
Proposed DR strategies and

architecture Week 10-12

Disaster Recovery Plan (Draft)
Full draft of DRP with documented roles, procedures, and dependencies
Week 13-15
Tabletop Exercise
Facilitated simulation with lessons learned summary
Week 16-18
Training and Awareness Materials
PowerPoints, handouts, and job aids for staff
Week 19-21
Final Disaster Recovery Plan
Final version of DRP with incorporated feedback
Week 22- 24
DRP Maintenance Plan
Guidelines for review/update cycles and ownership
Week 25 - 26

Roles and Responsibilities Client Responsibilities:

· Provide access to key personnel, documentation, and systems.

· Review and approve deliverables in a timely manner.

· Maintain compliance with all CJIS, HIPAA, and state laws.

Consultant Responsibilities:

· Conduct all activities outlined in the scope.

· Maintain confidentiality and data security.

· Deliver high-quality, actionable reports and plans.

· Maintain compliance with all CJIS, HIPAA, and state laws.

Assumptions and Constraints

· Stakeholders will be available for scheduled interviews.

· DR test scope limited to one simulation unless otherwise specified.

· All work will be performed within the continental United States (CONUS).

· The Vendor will have appropriate security clearances if required (e.g., Public Trust, Secret).

· Client will provide access to facilities, documentation, and personnel as needed.

· Any significant changes to scope, resources, or timeline will require a formal Change Order.

Acceptance Criteria

· Final BIA and DRP are approved by Chief Information Officer.

· Deliverables meet the requirements set in this SOW.

· Project completed within agreed-upon timeline and budget.

· DRP must include specific recovery instructions.

· Final approval from DJJ IT and Legal.

Records Retention and Disposal

At the conclusion of the project, the vendor will return or securely destroy all client data and project materials that are not required to be retained by law or contractual obligation. Data destruction will be conducted in accordance with NIST SP 800-88 standards (Media Sanitization Guidelines).

Confidentiality Agreement

All the vendor personnel assigned to the project will sign non-disclosure agreements (NDAs) and undergo agency-required training in information handling procedures prior to accessing sensitive agency data.

Data Handling Requirements

All data collected during the engagement will be encrypted during transit and at rest, utilizing FIPS 140-2 validated encryption modules. The data will be stored on secure systems that are authorized under the applicable Authority to Operate (ATO) standards.

Standards and Compliance

Fla. Stat. ch. 252Fla. Stat. ch. 186CJIS Security PolicyISO/TEC 22301
Fla. Stat. ch. 282Fla. Stat. ch. 119NIST SP 800-34 Rev. 1ISO/IEC 27001
Fla. Stat. ch. 501State COOP RequirementsNIST SP 800-53HIPAA Rules
ITILGDPRFlorida Digital Standards 60GG-2

DATA SECURITY AND CONFIDENTIALITY TASK:

The Contractor, its employees, subcontractors, and agents must comply at all times with all Department data security procedures and policies in performing this scope of work, as specified in the Data Security and Confidentiality document attached to the purchase order.

File details come from the government source that posted it. Updated .