Invitation for Bid - Railroad Quiet Zone.pdf

PDF 668 KB Posted

Attached to
RFP Railroad Quiet Zone Improvements
Solicitation number
2026-04
Issued by
Cochise County, Arizona

About this file

Summary

This is an Invitation for Sealed Bids issued by the City of Willcox, Arizona for Railroad Quiet Zone Improvements at the Maley Avenue railroad crossing (Solicitation No. 2026-04). The project requires a qualified contractor to furnish all necessary labor, materials, equipment, supervision, and incidental services to complete roadway and median improvements including removal and replacement of concrete median improvements, asphalt pavement grinding, pavement marking removal, fog sealing, construction of concrete curbs, installation of stamped concrete median surfaces, railroad pavement markings, traffic striping, raised pavement markers, and railroad warning signage. The scope of work encompasses eleven line items with quantities ranging from 2 each (sign assemblies) to 353 linear feet (yellow curb painting), with work to be performed in accordance with approved civil engineering plans, Arizona Department of Transportation specifications, and the Manual on Uniform Traffic Control Devices. The bid closing date and time is Tuesday, December 8, 2026 at 8:00 AM Arizona time. A non-mandatory pre-bid meeting is scheduled for Monday, November 30, 2026 at 10:00 AM Arizona time. Sealed bids must be physically delivered to City Hall at 101 South Railroad Avenue, Suite B, Willcox, Arizona 85643. Bidders are encouraged to conduct site visits prior to submission, and questions must be submitted to the Public Works Director at least ten calendar days prior to the closing date. The bid shall remain valid and irrevocable for ninety days after the closing date. Award will be made to the lowest responsible and responsive bidder whose bid conforms to all material requirements and is most advantageous to the City.

The contract will be awarded based on firm fixed pricing for two lump-sum bid items: the Construction Scope of Work and Union Pacific Railroad Maintenance Consent Letter compliance and coordination. All costs must include necessary labor, materials, equipment, traffic control, supervision, applicable taxes, and incidental expenses. The City will pay Net 30 after receipt of invoice. Transaction privilege and use tax shall be separately identified, with out-of-state vendors subject to Arizona use tax at 5.6% remitted directly by the City, and the City is exempt from Federal Excise Taxes. No price increases will be approved except as expressly provided in the contract. A critical requirement involves compliance with Union Pacific Railroad's Maintenance Consent Letter (Exhibit D), which mandates forty-five days advance notification, completion of a Contractor Endorsement, railroad-approved third-party flagging services for all work on railroad property, mandatory Union Pacific Property Access Training for all personnel, and adherence to railroad safety restrictions including prohibition of counterflow traffic operations. The contractor is responsible for all railroad coordination costs and scheduling requirements, with contractor-responsible delays not constituting grounds for additional compensation or contract extension. The contract is governed by the City of Willcox Standard Terms and Conditions, which include comprehensive indemnification requirements, warranty provisions for one year following final acceptance, compliance with federal and Arizona employment and immigration laws, and dispute resolution procedures in Coconino County, Arizona.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CITY OF WILLCOX

INVITATION FOR SEALED BIDS

SOLICITATION FOR: Railroad Quiet Zone Improvements

SOLICIATION No: 2026-04

CLOSING DATE AND TIME: Tuesday, December 8, 2026 AT 8:00 AM (Arizona time)

INFORMATION: The Solicitation and all related materials and any addenda may be downloaded from the City website, https://willcox.az.gov/bids

SECTION 1 - INSTRUCTIONS

1. OFFER SUBMISSION, DUE DATE, AND TIME: Submissions must be received by the Bid Due date indicated above and must be in a sealed package marked with the solicitation number, along with the name and address of the company making the submission. The submittal must be delivered to the following address:

City of Willcox Attention: Crystal Hadfield 101 South Railroad Ave Ste. B Willcox, Arizona 85643

At the closing date and time sealed bids will be opened and read aloud in the Willcox City Hall. Bidders or their representatives may be present at the bid opening. Electronic copies of bids shall not be accepted. Bids must be in the actual possession of the City of Willcox on or prior to the exact date and time indicated above.

2. QUESTIONS: Offerors must carefully read the entire Invitation to Bid package. There will be a pre-bid meeting. Any questions must be received by the Public Works Director via email rlinton@willcox.az.gov at least ten (10) calendar days prior to the Closing Date and Time.

Any correspondence related to an Invitation to Bid should refer to the appropriate Invitation for Bid number, page, and paragraph number. The City will not be responsible if you adjust your bid based on any verbal statements made by employees or officers of the City, particularly if such statements conflict with the Solicitation. You may request the Buyer to issue an addendum to the Solicitation. Any changes to this Invitation for Bid will be in the form of a published addendum.

3. PRE-BID MEETING: A Pre-Bid Meeting has been scheduled for this solicitation on Monday, November 30, 2026, 10:00 am Arizona time and will be held virtually. This non-mandatory pre-bid meeting will be the City of Willcox City Hall at 101 S Railroad Ave, Willcox, AZ.

4. ADDENDUM: The City will issue any interpretation or correction of the Solicitation only by written addendum at least ten (10) days prior to closing and will be posted on the City website https://willcox.az.gov/bids. Before your submission, check the site for any addenda or other materials that may have been issued affecting the bid. PLEASE MAKE SURE TO AKNOWLEDGE ALL ADDENDA ITEMS ON THE BID FORMS. Failure to acknowledge ANY https://willcox.az.gov/bids mailto:rlinton@willcox.az.gov addenda issued may deem the contractor non-responsive once the solicitation has closed.

5. LATE BIDS: Late bids will not be accepted and will be returned unopened.

6. WITHDRAWAL OF BID: At any time prior to the specified bid due date and time, a bidder may withdraw a bid. A withdrawal must be signed by the bidder’s authorized representative and submitted to the Buyer by hand delivery or mail.

7. AMENDMENT OF BID: Amendments to or withdrawal of bids received later than the time and date set for the bid opening will not be considered.

8. DUE DILIGENCE: It is your responsibility to examine the entire Solicitation prior to completing your offer. It is the Bidder’s responsibility to ensure that all line items on the Bid Form are completed according to what the Bidder desires to bid on. Any blank areas will be considered as a “no-Bid” or as non-responsive.

9. SITE VISIT: Bidders are encouraged to review the job sites prior to submitting their Bid. Bidder shall be responsible for having examined the job sites, compared them with the descriptions and specifications of the Bid. No allowance shall subsequently be made on behalf of Bidder on account of an error or negligence on its part for failing to become sufficiently familiar with the conditions of the job sites or surrounding areas.

10. FORMAT OF BID: The bid packet will include the entire solicitation packet with all forms and information requested completed, a copy of each addendum initialed, and any attachments necessary to explain exceptions or confidential information.

11. EXCEPTIONS: You may request changes to the form of contract or any terms and conditions as part of your bid. The City reserves the right to reject, accept or further negotiate Exceptions.

(Use the Exceptions form)

12. BID ACCEPTANCE PERIOD: A bid made in response to this Solicitation shall be valid and irrevocable for ninety (90) days after the Closing Date and Time.

13. IMPROPER CONTACT WITH CITY EMPLOYEES: All Bidders submitting a bid (including the firm’s employees, representatives, agents, lobbyists, attorneys, and subcontractors) will refrain from direct or indirect contact for the purpose of influencing or creating bias in the evaluation/selection process with any person who may play a part in the evaluation/selection process. This includes but is not limited to the evaluation committee, City Council Members, City Manager, Assistant City Manager(s), Deputy City Manager(s), Department Directors, or other staff (“City Staff”). This policy is intended to create a level playing field for all potential firms, assure that contract decisions are made in public, and to protect the integrity of the selection process. A Bidder may be disqualified if the Bidder: (a) contacts a quorum of the Council or contributes to an open meeting law violation; (b) offers political support or gratuities in exchange for approval or support of Bidder’s Bid; (c) obtains information from City Staff not available to other Bidders which may result in an unfair advantage in the competitive procurement process and fails to notify Senior Procurement Specialist of this fact within 48 hours thereafter; or (d) engages in any other egregious conduct.

14. BRAND NAMES: If the Solicitation refers to a specific manufacturer, brand, make or catalog designation, this means the City is seeking materials with the same or equal character, quality, performance, or features. If a Bidder is submitting an offer to furnish materials with a different manufacturer, brand, make or catalog designation, then the Bidder shall submit complete data and information with respect to the materials being offered and how it differs from the specific manufacturer, brand, make, or catalog designation referenced in the Solicitation. If a Bidder does not provide data and information, then the Bidder shall be deemed to be making a bid to provide the exact material referenced in the Solicitation. The

City reserves the right to determine what an approved equal is.

FINANCIAL AND TAX CONSIDERATIONS FOR BID

15. BASE BUILDING PRICE: Provide a firm fixed price bid for the described materials including delivery and taxes.

16. UNIT PRICES: Please check all math prior to submittal of the Bid. If the Bid unit prices do not correspond with the multiplied subtotal or total, the unit price shall prevail.

17. ALL CHARGES: The bid should separately list all delivery/freight charges, taxes, and any other applicable fees. Delivery charges are considered non-taxable when separately stated.

Freight charges are not considered delivery and are taxable.

18. PAYMENT: Specify on the bid documents your required schedule for deposit and payments.

19. TRANSACTION PRIVILEGE (SALES)/USE TAX: State and local transaction privilege or use tax, as required, shall be indicated as a separate item on the bid. If the Bidder is an out-of-state vendor, the City will remit the Arizona Use Tax (5.6%) directly to the State of Arizona.

20. FEDERAL EXCISE TAXES: The City is exempt from Federal Excise Tax, including the Federal Transportation Tax.

EVALUATION OF BID AND CONTRACT AWARD

21. STANDARD TERMS AND CONDITIONS: The City of Willcox Standard Terms and Conditions are attached to the Contract as Exhibit A. The Standard Terms and Conditions are an explicit part of the Solicitation and any resulting Contract with the City.

22. RESERVATION OF RIGHTS: The City expressly reserves the right to reject any and all bids, or any part thereof. The City reserves the right to waive any clerical error or nonmaterial defect in the bid when it is deemed to be in the City's best interest. The City reserves the right to cancel or reissue a Solicitation.

23. OFFER TO CONTRACT: A response to an Invitation for Bid is an offer to contract with the City based upon the terms, conditions and specifications contained in the City’s Invitation for Bid and the written amendments thereto, if any. Bids do not become contracts unless and until they are accepted by the City. The contract has its inception in the award document, eliminating a formal signing of a separate contract. For that reason, all of the terms and conditions of the procurement contract are contained in the Invitation for Bid; unless modified by a Solicitation Amendment or a Contract Amendment.

BID MOST ADVANTAGEOUS TO THE CITY: The City will award a contract to the lowest responsible and responsive bidder whose bid conforms in all material respects to the requirements and criteria set forth in the Invitation for Bid and whose bid is the most satisfactory and advantageous to the City. The City will be the sole judge as to the acceptability of the products and/or services offered.

A “responsible bidder” or offeror is defined as a person/business who has the capability to perform the contract requirements and the integrity and reliability that will assure good faith performance. A responsive bidder" means a person/business who submits a bid that conforms in all material respects to the invitation for bids. Any single factor or combination of factors may be grounds for determination of non-responsibility or non-responsive as determined by the City.

24. PARTIAL AWARD: The City reserves the right to make multiple awards by product or installation, or as a total, whichever is deemed in the best interest to the City.

25. RESERVATION OF RIGHTS: The City reserves the right to reject any Bids, or any part thereof. The City reserves the right to waive any clerical error or nonmaterial defect in the Bid when it is deemed to be in the City's best interest. The City reserves the right to cancel or reissue a Solicitation.

26. EVALUATION PROCESS: The City will review each bid to determine if it is responsive and responsible. A bid tabulation will be created showing the pricing offered by each Bidder. The low bid/offer will be determined using the solicitation bid form.

27. REQUESTS FOR ADDITIONAL INFORMATION: After the Closing Date and Time, the City may request you to provide additional information related to your bid. Failure to provide this information within five (5) business days after communication of the request by the City will be grounds for the City to reject a bid, and/or to declare the bid as non-responsive or non-responsible.

28. NOTICE OF PROPOSED CONTRACT AWARD OR RECOMMENDATION: All Bidders will receive an email notifying them of the City’s proposed contract award or recommendation to reject all bids. This notice will be posted as part of the agenda for the regular meeting of the City Council, on the City website. The agenda is typically posted at least one (1) week prior to the Council Meeting.

29. PUBLIC RECORDS: Bids received by the City are available for public inspection after a contract has been awarded, subject to any confidentiality restrictions.

30. PROTESTS: Companies wishing to protest a disqualification, or a procurement outcome may file a protest pursuant to the Arizona Administrative Code, Sections R2-7-A901 through A911. Protests must be filed with the City of Willcox Finance Director either within 14 days of the Notice of Intent to Award or 10 days after the procurement file is made available for public inspection, whichever is later.

SECTION 2: SCOPE OF WORK SPECIFICATIONS

Railroad Quiet Zone Improvements

PROJECT OVERVIEW

The City of Willcox is soliciting Bids from qualified contractors to furnish all necessary labor, materials, equipment, supervision, and incidental services to complete roadway and median improvements associated with establishing a railroad Quiet Zone at the Maley Avenue railroad crossing.

Railroad Crossing Location:

Southeasterly of Railroad Ave and Maley St; Milepost 1074.75

Willcox, Arizona 85643

City Hall Hours of Operation:

Monday through Thursday

7:30 am to 5:00 pm

The City's objective includes removal and replacement of concrete median improvements, asphalt pavement grinding, pavement marking removal, fog sealing, construction of concrete curbs, installation of stamped concrete median surfaces, railroad pavement markings, traffic striping, raised pavement markers, and railroad warning signage.

All improvements shall be constructed in accordance with the approved civil engineering plans

(attached), applicable Arizona Department of Transportation (ADOT) Standard Specifications and Drawings, the Manual on Uniform Traffic Control Devices (MUTCD), and City of Willcox requirements.

SCOPE OF WORK

The selected contractor shall furnish the labor, equipment, machinery, and services necessary to crush, pulverize, process, and, when necessary, screen the City's existing stockpiled material into usable aggregate base.

Materials may include but are not limited to: Asphalt pavement, base material, and asphalt millings; Concrete; and traffic control.

A. Removal of Existing Curb and Stamped Concrete

Remove existing concrete curb and stamped concrete at the designated median radius locations.

• Sawcut and remove designated concrete improvements.

• Remove concrete from contraction joint to contraction joint.

• Protect adjacent concrete and pavement scheduled to remain.

• Dispose of removed materials at an approved disposal location.

• Prepare the area for construction of replacement concrete improvements.

Plan Quantity: 16 square feet.

B. Asphalt Pavement Grinding

Grind existing asphalt pavement where pavement elevations have risen above the existing concrete gutter flow line.

Work shall include:

• Grind asphalt pavement to restore a minimum 6-inch exposed curb height.

• Extend grinding a minimum of 1 foot from the edge of existing concrete.

• Maintain positive drainage along the gutter.

• Avoid creating depressions or areas of standing water (birdbaths).

• Provide smooth pavement transitions to adjacent roadway surfaces.

Plan Quantity: 66 linear feet.

C. Existing Pavement Marking Removal and Fog Sealing

The contractor shall remove existing pavement striping within the designated project limits using an abrasive blasting method (air or water) in accordance with ADOT Specification 701-3.06.

Following removal, the contractor shall apply a fog seal over the full asphalt pavement width, curb to curb, extending longitudinally from the beginning to the end of the designated treatment area.

Quantity: Lump Sum.

D. Construction of Concrete Median Curb

Construct new 6-inch-high Type A single concrete curb in accordance with ADOT Standard

Drawing C-05.10.

Work shall include:

• Establish required curb alignment and elevations.

• Extend median curbs to within 10 feet, measured from the curb face to the centerline of the railroad tracks, as indicated on the plans.

• Maintain a 6-inch curb height above the existing asphalt.

• Match the width and direction of existing median improvements.

• Provide necessary forming, concrete placement, finishing, and curing.

Plan Quantity: 11 linear feet.

E. Concrete Median Improvements

Construct new concrete median surface improvements to match the existing median configuration.

• Install 4-inch-thick concrete within the designated median areas.

• Place concrete flush with the top of the new curb.

• Match adjacent median grades and elevations.

• Provide appropriate surface finishing and curing.

• Use Class A concrete with a minimum specified compressive strength of 3,000 psi.

Plan Quantity: 44 square feet.

F. Railroad Crossing Pavement Symbols

Install railroad crossing pavement symbols in accordance with ADOT Standard Drawing M-5.

• Provide two railroad crossing pavement symbols.

• Center the symbols on the existing railroad tracks as shown on the plans.

• Use reflective pavement marking materials meeting applicable ADOT and MUTCD requirements.

Plan Quantity: 2 each.

G. Railroad Crossing Stop Bars

Install 24-inch-wide white reflective stop bars at the locations identified on the construction plans.

• Locate stop bars 8 feet upstream from the nearest railroad grade crossing flashers.

• Install markings perpendicular to the direction of traffic as indicated.

• Coordinate final placement with existing railroad warning equipment.

Plan Quantity: 147 linear feet.

H. Yellow Curb Painting and Raised Pavement Markers

Paint designated median curbs yellow and install raised pavement markers.

• Prepare concrete curb surfaces before painting.

• Apply reflective yellow traffic paint.

• Install four Type D raised pavement markers at each designated radius.

• Comply with ADOT Standard Drawing M-1.

Plan Quantities:

• Yellow curb painting: 353 linear feet.

• Type D raised pavement markers: 16 each.

I. Yellow Pavement Striping

Install 6-inch-wide yellow reflective pavement striping along the median improvements.

• Locate striping 2 feet from the median as shown on the plans.

• Maintain consistent alignment and stripe width.

• Match the configuration indicated on the civil plans.

• Comply with applicable ADOT and MUTCD standards.

Plan Quantity: 310 linear feet.

J. Railroad Warning Sign Installation

Furnish and install railroad warning signage as shown on the construction plans.

• Install W10-1 Railroad Crossing advance warning signs.

• Install W10-9P "NO TRAIN HORN" supplemental plaques.

• Provide signposts, mounting hardware, foundations, and associated installation materials as required.

• Locate and orient signs in accordance with the approved plans and applicable ADOT and

MUTCD standards.

Plan Quantity: 2 sign assemblies, consisting of W10-1 signs with W10-9P supplemental plaques.

3. Construction Quantity and Bid Schedule

The following quantities are taken directly from the October 2026 civil construction plan.

Item Description Quantity Unit

1 Remove existing striping and apply fog seal 1 LS

2 Remove existing curb and stamped concrete 16 SF

3 Asphalt pavement grinding 66 LF

4 Construct 6-inch Type A concrete curb 11 LF

5 Construct 4-inch concrete median surface 44 SF

6 Railroad crossing pavement symbols 2 EA

7 24-inch white railroad stop bars 147 LF

8 Paint median curb yellow 353 LF

9 Type D raised pavement markers 16 EA

10 6-inch yellow pavement striping 310 LF

11 W10-1 and W10-9P sign assemblies 2 EA

LS = Lump Sum; SF = Square Feet; LF = Linear Feet; EA = Each.

4. Traffic Control and Railroad Coordination

The contractor shall provide all necessary traffic control, warning devices, temporary signage, barricades, and other protective measures necessary to perform the work safely.

Traffic control shall be coordinated with the City of Willcox and shall comply with the approved construction traffic control plan and applicable MUTCD requirements.

The contractor shall:

1. Maintain safe vehicular access through or around the construction area as approved by the City.

2. Coordinate work activities near the railroad crossing with the City and railroad operator.

3. Protect existing railroad crossing gates, flashers, signal equipment, tracks, and concrete crossing panels.

4. Obtain any required railroad access authorization before performing work within railroad-controlled property.

5. Maintain access for emergency vehicles.

6. Remove temporary traffic control devices following completion of the improvements.

5. General Construction Requirements

All work shall conform to the following requirements:

• All curb removal and replacement shall extend from contraction joint to contraction joint.

• Concrete shall be Class A, 3,000 psi, as specified on the plans.

• Median curb extensions shall maintain the required 6-inch curb height and terminate at the distances indicated on the approved plans.

• Pavement markings and traffic paint shall be reflective and conform to the MUTCD and

ADOT Construction Manual, Chapter 7, as specified.

• The contractor shall protect existing improvements and repair any damage caused by construction activities.

• Construction debris and excess materials shall be removed from the project site.

• Final improvements shall be inspected and accepted by the City of Willcox.

6. Project Completion and Acceptance

Upon completion of construction, the contractor shall:

1. Remove all debris, surplus materials, and temporary construction equipment.

2. Restore disturbed pavement and adjacent areas.

3. Verify that concrete median heights, curb alignment, and pavement drainage meet the approved plans.

4. Verify proper placement of railroad symbols, stop bars, striping, raised pavement markers, and signage.

5. Coordinate a final inspection with the City of Willcox.

6. Correct deficiencies identified during final inspection before project acceptance.

7. Items to Clarify Before Issuing the Bid

The civil construction plan establishes the principal construction quantities and technical requirements. However, I recommend clarifying the following items in the City's bid documents.

Item Recommended clarification

Fog seal Define exact beginning and ending station limits and total treatment area in square yards.

Stamped concrete Confirm whether replacement concrete is required to match the existing stamped pattern and color.

Curb replacement Require contraction-joint-to-contraction-joint removal and replacement, as expressly indicated on the plans.

Traffic control Establish whether traffic control will be paid as a separate lump-sum bid item.

Railroad coordination

Identify the party responsible for railroad permits, flagging, and associated costs.

Pavement grinding Clarify the grinding width and required pavement transition.

Concrete median Confirm the finish required for the 44 square feet of concrete median surface.

Signs Confirm final sign locations, mounting heights, and post specifications.

Important distinction: These clarifications are recommended additions to the procurement documents. They should not be interpreted as requirements already established by the civil plans.

Recommendation

For the City of Willcox, I recommend using the above scope as the technical basis for the

Request for Bids, with the approved civil construction and traffic control plans incorporated by reference.

The construction bid schedule should include the 11 quantified items identified on the plans, with a separate lump-sum traffic control item if the City wishes to track that cost independently.

This will allow contractors to submit comparable bids while maintaining the engineer's specified construction quantities and requirements.

8. Union Pacific Railroad Maintenance Consent Letter – Exhibit D

The City of Willcox has received a Maintenance Consent Letter from Union Pacific Railroad

Company authorizing the proposed railroad Quiet Zone improvements at the Maley Avenue railroad crossing, subject to the conditions established in the letter and its accompanying exhibits.

The Maintenance Consent Letter, including the Contractor Endorsement and Exhibits A, B, and

C, is incorporated into the contract documents as Exhibit D.

Union Pacific Project Information:

• REMS Project Number: 463708

• Agency Project Number: T131771

• Railroad Subdivision: Lordsburg Subdivision

• Railroad Crossing: Maley Street

• DOT Crossing Number: 741397H

• Milepost: 1074.75

• Maintenance Consent Effective Date: November 11, 2026

• Maintenance Consent Expiration Date: November 11, 2028

8.1 Contractor Endorsement

The successful contractor shall complete, sign, and submit the Contractor Endorsement included in Attachment C before performing any work on Union Pacific Railroad property.

The completed Contractor Endorsement shall include the contractor's company name, contact name, address, telephone number, email address, authorized signature, and date.

The executed Contractor Endorsement shall be submitted to:

Email: upmaintenance@olsson.com

A copy shall also be provided to the City of Willcox Public Works Department.

No contractor or subcontractor shall enter Union Pacific Railroad property or commence work requiring railroad authorization until the executed Contractor Endorsement has been received and all applicable railroad requirements have been satisfied.

8.2 Advance Notification and Railroad Coordination

The contractor shall provide a minimum of forty-five (45) days' advance notice to the designated Union Pacific Railroad representative before commencing work.

Railroad Representative:

Steven Thomas

Phone: (469) 724-6436

Email: sthomas@benesch.com

The contractor shall coordinate construction scheduling, railroad access, and required inspections with the designated railroad representative and the City.

8.3 Railroad Flagging Requirements

The contractor shall coordinate and arrange for railroad-approved third-party flagging services for the entire duration of work and/or traffic control activities occurring on Union Pacific

Railroad property, as required by Exhibit D.

Flagging services shall be provided by a Union Pacific-qualified third-party flagging contractor in accordance with Union Pacific's Third-Party Flagging Policy.

The contractor shall include the costs of required flagging and associated coordination in its bid unless otherwise specified by the City.

8.4 Railroad Property Access Training

The contractor shall ensure that all personnel required to enter Union Pacific Railroad property complete the applicable Union Pacific Property Access Training (UP-PAT) before entering railroad property.

Training requirements shall be determined in accordance with Exhibit D of applicable Union

Pacific requirements.

mailto:upmaintenance@olsson.com mailto:sthomas@benesch.com

8.5 Railroad Safety and Construction Restrictions

The contractor shall comply with all applicable Union Pacific Railroad safety requirements, including:

1. Conducting a preconstruction meeting with the designated railroad representative.

2. Maintaining required railroad flagging and protective measures.

3. Prohibiting counterflow traffic operations over the railroad crossing during construction.

4. Protecting existing railroad tracks, crossing panels, gates, flashers, signal equipment, and other railroad facilities.

5. Following Union Pacific's Call Before You Dig procedures when construction activities could affect railroad fiber-optic or telecommunications facilities.

6. Providing insurance documentation to Union Pacific upon request.

7. Complying with the Contractor Endorsement General Terms and Provisions.

8.6 Construction Plan Review and Inspection

Union Pacific Railroad shall be provided the opportunity to review project plans and construction submittals and perform construction observation in accordance with Exhibit D.

The contractor shall coordinate required reviews and inspections with the City and railroad representatives.

Following construction, the contractor shall assist the City in verifying that the completed median curb heights meet the applicable Quiet Zone requirements.

8.7 Project Completion Notification

Upon completion of work on Union Pacific Railroad right-of-way, the contractor shall provide photographs documenting the completed improvements.

8.8 Compliance and Contract Requirements

Compliance with Exhibit D is a mandatory requirement of the construction contract.

The contractor shall be responsible for completing the Contractor Endorsement, coordinating railroad access, providing required advance notification, satisfying applicable training and flagging requirements, and complying with all conditions of the Maintenance Consent Letter.

The Contractor Endorsement is valid for one year from execution or until completion of the work, subject to its termination provisions and the Maintenance Consent Letter expiration date.

Failure to satisfy applicable Union Pacific Railroad requirements shall prohibit commencement of work on railroad property until the deficiencies have been resolved.

All contractor obligations under Exhibit D shall be considered part of the project Scope of Work.

Attachment Schedule

• Exhibit A Standard Terms and Conditions

• Exhibit B Construction Plan

• Exhibit C Traffic Control Plan

• Exhibit D Union Pacific Maintenance Consent Letter

Important requirements identified in Exhibit D

The attached Union Pacific letter establishes several requirements that should be emphasized during bidding:

• 45-day advance notification: Contractors must account for this period when developing their construction schedule.

• Railroad flagging: Exhibit A specifically requires railroad-approved third-party flagging for the entire duration of work and/or traffic control through railroad property.

• No counterflow traffic: The construction traffic control plan must comply with this express restriction.

• Contractor Endorsement: The successful contractor must execute the endorsement before entering railroad property.

• Railroad review: Union Pacific retains the ability to review construction plans and submittals and observe the work.

Include a separate lump-sum bid item titled "Union Pacific Railroad Coordination, Flagging, and Compliance" so that each bidder identifies the costs associated with Exhibit D.

8.9 Construction Start Date, Advance Notification, and Compliance with Exhibit D

The successful contractor shall provide the City of Willcox Public Works Department with a proposed construction start date and anticipated project completion date, in writing within

10 calendar days following the City’s Notice of Award, prior to commencing any work.

The proposed construction start date shall account for all requirements identified in Exhibit D –

Union Pacific Railroad Maintenance Consent Letter and Contractor Endorsement, including the following:

1. Forty-Five (45) Day Advance Notification: The contractor shall provide the designated

Union Pacific Railroad representative with a minimum of forty-five (45) days' advance notice before performing work, as required by Exhibit D.

2. Contractor Endorsement: The contractor shall complete, execute, and submit the required

Union Pacific Contractor Endorsement before entering railroad property.

3. Railroad Flagging: The contractor shall coordinate and schedule railroad-approved third-party flagging services for the duration of work and/or traffic control activities on Union Pacific

Railroad property, as required by Exhibit D.

4. Railroad Property Access Training: The contractor shall ensure that all applicable personnel have completed the required Union Pacific Property Access Training (UP-PAT).

5. Preconstruction Meeting: The contractor shall coordinate and participate in the required preconstruction meeting with the designated Union Pacific Railroad representative.

6. Construction Submittals and Approvals: The contractor shall allow sufficient time for

Union Pacific Railroad to review applicable construction plans, submittals, traffic control arrangements, and other required documentation.

7. Traffic Control Restrictions: The contractor shall ensure that the proposed construction schedule and traffic control operations comply with Union Pacific's prohibition against counterflow traffic over the railroad crossing during construction.

Construction Start Date Approval

The contractor shall include in the proposal a construction start date to include the forty-five

(45) days before the anticipated commencement of work requiring railroad notification, together with a schedule identifying the anticipated completion dates of all applicable Exhibit D requirements.

The contractor shall not commence construction activities on Union Pacific Railroad property until all required railroad notifications, endorsements, coordination, training, flagging arrangements, and applicable approvals have been completed.

The proposed construction start date shall be subject to review and written authorization by the

City of Willcox. Any changes to the approved construction schedule shall be promptly communicated to the City and coordinated with Union Pacific Railroad as necessary.

The contractor shall be responsible for incorporating all Exhibit D requirements into its construction schedule and shall not assume that issuance of a City Notice to Proceed constitutes authorization to enter Union Pacific Railroad property.

By submitting a bid, the contractor acknowledges that it has received, reviewed, and understands the requirements outlined in Exhibit D – Union Pacific Railroad Maintenance Consent Letter and Contractor Endorsement. The contractor agrees to comply with all applicable Union

Pacific Railroad requirements, including the 45-day advance notification, execution of the

Contractor Endorsement, railroad coordination, required flagging services, safety training, insurance requirements, and construction restrictions.

The contractor further acknowledges that all associated requirements, costs, and scheduling considerations have been incorporated into its bid proposal and anticipated construction schedule.

Contractor Responsibility for Delays: The contractor shall be responsible for delays resulting from its failure to timely complete, submit, coordinate, or comply with the requirements of

Attachment D. Such delays shall not constitute grounds for additional compensation or an extension of the contract completion date unless otherwise authorized in writing by the City.

Delays attributable to Union Pacific Railroad that are beyond the contractor's reasonable control shall be promptly reported to the City in writing and evaluated in accordance with the contract's applicable delay provisions.

No work shall commence on Union Pacific Railroad property until all applicable requirements have been satisfied and the necessary authorizations obtained. The contractor shall be responsible for coordinating its construction schedule with Union Pacific Railroad and obtaining written authorization from the City prior to commencing construction.

VENDOR QUESTIONNAIRE (FORM)

Vendor:

Company Name:

Doing Business As (if different than above):

Address:

City: State: Zip:

Phone: Fax:

E-Mail Address:

Website:

Taxpayer Identification Number:

Mailing Address (if different than above):

Address:

City: State: Zip:

Vendor Contact for Questions about Offer:

Name: Title:

Phone: Fax:

E-Mail Address:

Transaction Privilege (Sales)Tax/Use Tax Information (check one):

Vendor is located outside Arizona and does not collect Arizona State Sales/Use Tax (The City will pay use tax directly to the Arizona Department of Revenue)

OR

Vendor is located outside Arizona, but is authorized to collect Arizona Sales/Use Taxes.

(Respondent will invoice the City the applicable sales tax and remit the tax to the appropriate taxing authorities.)

City of: __________________, AZ Applicable Tax Rate: _________%

Vendor is located in Arizona. (Vendor will invoice the City the applicable sales tax and remit the tax to the appropriate taxing authorities)

City of: __________________, AZ Applicable Tax Rate: _________%

Compliance with Applicable Terms and Conditions: Bidder complies with all terms and conditions within the solicitation. Any strikeouts, notes or modifications to the Solicitation documents shall be initialed in ink by the authorized person who signs the offer. If notations are made, they must be submitted with your offer and are considered Exceptions.

In addition to any notations on the Solicitation documents, please identify and list any exceptions to the Solicitation, by section/paragraph, on this Exceptions Form. The City reserves the right to reject, accept or further negotiate Exceptions. Exceptions may render the offer non-responsive.

You must indicate any, and all exceptions taken to the requirements, specifications, and/or terms and conditions of this Solicitation.

EXCEPTIONS: (INITIAL ONE):

_____ No exceptions

_____ Exceptions taken (describe and attach).

CONFIDENTIAL INFORMATION: (INITIAL ONE)

_____ No confidential/proprietary materials have been included with this Response.

_____ Confidential/Proprietary materials included with Response. Respondent must identify any portion of their Response deemed confidential or proprietary and attach additional pages if necessary. Requests to deem the entire bid as confidential will not be considered. The disclosure by the City of information deemed by Respondent as confidential or proprietary is governed by City of Willcox Procurement Rules.

DECLARATION OF NON-COLLUSION (FORM)

I hereby verify and declare that:

The pricing for this offer has been arrived at independently and without consultation, communication or agreement with any other vendor who may submit an offer.

The pricing for this offer has not been disclosed to any other vendor who may submit an offer, and will not be, prior to the Closing Date and Time.

No attempt has been made or will be made to induce any firm or person to refrain from submitting an offer, or to submit an offer with higher pricing than this offer, or to submit an intentionally high or noncompetitive offer or other form of complementary offer.

This offer is made in good faith and not pursuant to any agreement or discussion with, or inducement from, any firm or person to submit a complementary or other noncompetitive bid.

Vendor, its affiliates, subsidiaries, officers, directors, and employees are not currently under investigation by any governmental agency and have not in the last four years been convicted or found liable for any act prohibited by state or federal law in any jurisdiction, involving conspiracy or collusion with respect to bidding on any jurisdiction, involving conspiracy or collusion with respect to bidding on any public contract.

Signature of Person Authorized to Sign Offer

INVITATION FOR BID

OFFER AND ACCEPTANCE

OFFER

The undersigned hereby certifies on behalf of the named entity that:

• Reasonable diligence has been exercised in the preparation of this submission;

• All contents are true, accurate, and complete to the best of the signer’s knowledge; and

• The undersigned has the authority to make this Offer and to bind the entity named below.

The undersigned, on behalf of the entity named below, hereby offers to furnish equipment and materials as set forth in this Offer, in compliance with all terms, conditions, specifications in and amendments to the Invitation for Bid 2026-04, Railroad Quiet Zone Improvements. By making this offer, the entity will be contractually bound to provide these goods and services if the offer is accepted by the City.

Name of Company Bid Submitted By:

Contact Person: ____________________________________

Address: ___________________________________________

Phone: ____________________________________________

Email: _____________________________________________

Licensing Information: ________________________________

ROC #: ____________________________________________

Bid submitted to: City of Willcox

For: Bid 2026-04, Quiet Zone Improvements

In response and in compliance with the Instructions to Bidders for the abovenamed Project, the undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into a Contract with the City on the terms included in the Bidding Documents, and to provide all materials as specified or indicated in the Bidding Documents, for the prices and within the time frames indicated in this Bid and in accordance with the other terms and conditions of the Bidding

Documents. Bid shall be valid and irrevocable for ninety (90) days after the Closing Date and

Time.

Bidder acknowledges the receipt of the following Addenda to the Bidding Documents and has incorporated the effects of said Addenda into this Bid. Include initialed copy of addenda in bid packet.

(Bidder, check all that apply. Note, there may be more boxes than actual addenda. Do not check boxes that do not apply)

ADDENDA: #1 #2 #3 #4 #5

PROJECT SCHEDULE

Estimated mobilization time following authorization: __________________

Maximum number of calendar days to complete the scope of work herein after receipt of delivery of contract is __________Days. The start date of contract is _________________.

Contractor Bid Proposal – Schedule of Costs

The contractor shall provide a lump-sum bid for each of the following items. All costs shall include necessary labor, materials, equipment, supervision, coordination, applicable taxes, and incidental expenses required to complete the work.

Item Description Unit Bid Amount

Construction Scope of Work: Furnish all labor, materials, equipment, traffic control, and incidental services necessary to complete the Railroad Quiet Zone

Improvements in accordance with the approved civil construction plans, specifications, and Scope of Work.

LS $________________

Attachment D – Union Pacific Railroad Maintenance

Consent Letter and Contractor Endorsement: Complete all applicable requirements, including the Contractor

Endorsement, 45-day advance notification, railroad coordination, required flagging, safety training, insurance requirements, and compliance with Union Pacific Railroad conditions. Include all associated costs and scheduling requirements.

LS $________________

TOTAL BID AMOUNT $________________

Contractor Acknowledgment: By submitting this bid, the contractor acknowledges that it has reviewed and understands the Scope of Work and Exhibit D, and that all associated costs, coordination requirements, and contractor-responsible delays have been considered and incorporated into the total bid amount.

PAYMENT TERMS:

City of Willcox payment terms are Net 30 after receipt of invoice.

Please state other payment terms:

Authorized Signature for the Offer: _______________________________________

Date:_____________________

Printed Name and Title:

ACCEPTANCE OF OFFER

AND CONTRACT AWARD (For City of Willcox Use Only

Your offer for Bid 2026-04 is hereby accepted. You are now bound to provide the materials described in the Solicitation documents.

Attested by: _____________________________________________ City Clerk

Approved as to form: _______________________________________ City Attorney

Approved by: ______________________________________________ Mayor, City of Willcox

Notice to Proceed Issued On: ________________________, 2026

EXHIBIT A

CITY OF WILLCOX

STANDARD TERMS AND CONDITIONS

IN GENERAL

1. PARTIES: The City of Willcox (“City”) and the contractor identified in the Contract

(“Contractor”) may be referred to individually as “Party” or collectively as “Parties”.

2. NOTICE TO PROCEED: Contractor shall not commence performance until after the City has issued a Notice to Proceed.

3. LICENSES AND PERMITS: Contractor its expense shall maintain current federal, state, and local licenses, permits and approvals required for performance of the Contract and provide copies to City upon request.

4. COMPLIANCE WITH LAWS: Contractor shall comply with all applicable federal, state and local laws, regulations, standards, codes and ordinances in performance of the Contract.

5. NON-EXCLUSIVE: Unless expressly provided otherwise in the Contract, the Contract is non-exclusive and the City reserves the right to contract with others for materials or services.

6. SAMPLES: Any sample submitted to the City by the Contractor and relied upon by City as representative of quality and conformity, shall constitute an express warranty that all materials and/or service to be provided to City shall be of the same quality and conformity.

MATERIALS

7. PURCHASE ORDERS: The City will issue a purchase order for the materials covered by the Contract, and such order will reference the Contract number.

8. QUALITY: Contractor warrants that all materials supplied under the Contract will be new and free from defects in material or workmanship. The materials will conform to any statements made on the containers or labels or advertisements for the materials and will be safe and appropriate for use as normally used. The City’s inspection, testing, acceptance or use of materials shall not serve to waive these quality requirements. This warranty shall survive termination or expiration of the Contract.

9. ACCEPTANCE: All materials and services provided by Contract are subject to final inspection and acceptance by the City. Materials and services failing to conform to the

Contract specifications may be rejected in whole or part. If rejected, Contractor is responsible for all costs associated arising from rejection.

10. MANUFACTURER’S WARRANTIES: Contractor shall deliver all Manufacturer’s

Warranties to the City upon the City’s acceptance of the materials.

11. PACKING AND SHIPPING: Contractor shall be responsible for industry standard packing which conforms to requirements of carrier’s tariff and ICC regulations. Containers shall be clearly marked as to lot number, destination, address and purchase order number. All shipments shall be F.O.B. Destination, City of Willcox, 211 West Aspen Avenue, Willcox, Arizona 86001, unless otherwise specified by the City. C.O.D. shipments will not be accepted.

12. TITLE AND RISK OF LOSS: The title and risk of loss of material shall not pass to the City until the City actually receives the material at the point of delivery and the City has completed inspection and has accepted the material, unless the City has expressly provided otherwise in the Contract.

13. NO REPLACEMENT OF DEFECTIVE TENDER: Every tender of materials shall fully comply with all provisions of the Contract. If a tender is made which does not fully conform, this shall constitute a breach and Contractor shall not have the right to substitute a conforming tender without prior written approval from the City.

14. DEFAULT IN ONE INSTALLMENT TO CONSTITUTE TOTAL BREACH: Contractor and may not substitute nonconforming materials, or services. Delivery of nonconforming materials, and/or services, or a default of any nature, at the option of the City, shall constitute shall deliver conforming materials, or services, in each installment or lot of the Contract a breach of the Contract as a whole.

15. SHIPMENT UNDER RESERVATION PROHIBITED: Contractor is not authorized to ship materials under reservation and no tender of a bill of lading shall operate as a tender of the materials.

16. LIENS: All materials and other deliverables supplied to the City shall be free of all liens, other than the security interest held by Contractor, until payment in full is made by the City.

Upon request of the City, Contractor shall provide a formal release of all liens.

17. CHANGES IN ORDERS: The City reserves the right at any time to make changes in any one or more of the following: (a) methods of shipment or packing; (b) place of delivery; and

(c) quantities. If any change causes an increase or decrease in the cost of or the time required for performance, an equitable adjustment may be made in the price or delivery schedule, or both. Any claim for adjustment shall be evidenced in writing and approved by the City Purchasing Director prior to the institution of the change.

PAYMENT

18. INVOICES: A separate invoice shall be issued for each shipment and each job completed.

Invoices shall include the Contract and/or Purchase Order number and dates when goods had been shipped or work performed. Invoices shall be sent within thirty (30) days following performance. Payment will only be made for satisfactory materials and/or services received and accepted by City.

19. LATE INVOICES: The City may deduct up to 10% of the payment price for late invoices.

The City operates on a fiscal year budget, from July 1 through the following June 30. Except in unusual circumstances, which are not due to the fault of Contractor, the City will not honor any invoices or claims submitted after August 15 for materials or services supplied in the prior fiscal year.

20. TAXES: Contractor shall be responsible for payment of all taxes including federal, state, and local taxes related to or arising out of Contractor’s performance of the Contract. Such taxes include but are not limited to federal and state income tax, social security tax, unemployment insurance taxes, transaction privilege taxes, use taxes, and any other taxes or business license fees as required.

Exception: The City will pay any taxes which are specifically identified as a line-item dollar amount in the Contractor’s bid, proposal, or quote, and which were considered and approved by the City as part of the Contract award process. In this event, taxes shall be identified as a separate line item in Contractor’s invoices.

21. FEDERAL EXCISE TAXES: The City is exempt from paying certain Federal Excise Taxes and will furnish an exemption certificate upon request.

22. FUEL CHARGES: Contractor at its own expense is liable for all fuel costs related to performance. No fuel surcharges will be accepted or paid by the City.

23. DISCOUNTS: If the Contract provides for payment discounts, payment discounts will be computed from the later date of the following: (a) when correct invoice is received by the

City; or (b) when acceptable materials and/or materials were received by the City.

24. AMOUNTS DUE TO THE CITY: Contractor must be current and remain current in all obligations due to the City during performance. Payments to Contractor may be offset by any delinquent amounts due to the City or fees and charges owed to the City under the

Contract.

25. OFAC: No payments may be made to any person in violation of Office of Foreign Assets

Control regulations. 31 C.F.R. Part 501.

SERVICES

26. INDEPENDENT CONTRACTOR: Contractor shall be an independent contractor for purposes of all laws, including but not limited to the Fair Labor Standards Act, Federal

Insurance Contribution Act, Social Security Act, Federal Unemployment Tax Act, Internal

Revenue Code, Immigration and Naturalization Act; Arizona revenue and taxation, workers’ compensation, and unemployment insurance laws.

27. CONTROL: Contractor shall be responsible for the control of the work.

28. WORK SITE: Contractor shall inspect the work site and notify the City in writing of any deficiencies or needs prior to commencing work.

29. SAFEGUARDING PROPERTY: Contractor shall responsible for any damage to real property of the City or adjacent property in performance of the work and safeguard the worksite.

30. QUALITY: All work shall be of good quality and free of defects, performed in a diligent and professional manner.

31. ACCEPTANCE: If the City rejects…

This is the start of the file's text. The full file is on GovTribe.