Infection Prevention Criteria.pdf

PDF 260 KB Posted

Attached to
Rooftop Animal Waste Removal Amendment 0001 Federal contract opportunity
Solicitation number
36C24426Q0457
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 4

About this file

This is a construction infection control procedures document that specifies dust and debris containment requirements for a rooftop cleaning and bird netting project classified as Class II work. The document establishes four classification levels (Class I through Class IV) with progressively stringent containment and safety protocols based on construction risk and contamination potential.

For the Rooftop Cleaning and Bird Netting project designated as Class II, contractors must implement active dust and debris prevention measures during construction, including water misting of work surfaces, sealing unused doors with duct tape, blocking off airways into the main hospital, placing sticky mats at work area entrances and exits, and removing or modifying HVAC systems in affected areas. Upon project completion, contractors must wipe work surfaces and interior hospital areas with disinfectant, contain waste in tightly covered containers, wet mop and/or vacuum the work area, and restore isolated HVAC systems. The document requires signatures from the Contracting Officer Representative (COR), Chief of Facilities Engineering Services (FES), Safety Officer, and Infection Prevention Practitioner. Infection Control approval is mandated for Class III or Class IV control procedures, planned water line disruptions beyond normal non-use periods, or situations where contracting staff may be exposed to patients with possible tuberculosis.

View the file

Other files for this federal contract opportunity

Other files attached to Rooftop Animal Waste Removal Amendment 0001, newest first.
File Type Posted
pic1.png PNG image
36C24426Q0457 0001.pdf PDF
pic2.png PNG image
bird netting area pic3.png PNG image
RFI - Questions Rooftop Animal Waste.docx DOCX document
Water Spigot Locations.pdf PDF
Attachment 2 - Main Hospital Roof Drawing.pdf PDF
SCA WD 2015-4215 Rev 30.pdf PDF
Rooftop AHU Drawings.pdf PDF
Rooftop Square Footage.pdf PDF
36C24426Q0457 P0001 Solicitation Rooftop Animal Waste.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

During Construction Project Upon Completion of Projects

C la ss I

1. Execute work by method to minimize raising dust from construction operations

2. Immediately replace a ceiling tile displaced for visual inspection

1. Clean work upon completion of task

C la ss

II

1. Provide active means to prevent airborne dust/debris from dispersing into ventilation or inside main hospital atmosphere.

2. Water mist work surfaces to control dust/debris while cutting

3. Seal unused doors with duct tape

4. Block off and seal airways into main hospital if necessary

5. Place sticky mat at entrance and exit of work area.

6. Remove, isolate, or modify HVAC system in areas where work is being performed.

1. Wipe work surfaces and interior hospital areas with disinfectant.

2. Contain waste before transport in tightly covered containers.

3. Wet mop &/or vacuum before leaving work area.

4. Remove isolation of HVAC system in area where work is being performed.

C la ss I

II

1. Remove or isolate HVAC system in area where work is being done to prevent contamination of duct system.

2. Complete all critical barriers, i.e. sheetrock, plywood, plastic, to seal area from non-work area or implement control cube method (cart with plastic covering & sealed connection to work site with HEPA vacuum for vacuuming prior to exit) before construction begins.

3. Maintain negative air pressure within worksite utilizing HEPA-equipped air filtration units.

4. Contain construction waste before transportation in tightly covered containers.

5. Cover transport receptacles or carts. Tape covering unless solid lid is used.

1. Do not remove barriers from work area until completed project is inspected by Safety Management & Infection Control & thoroughly cleaned by Environmental Management.

2. Remove barrier materials carefully to minimize spreading of dirt & debris associated with construction.

3. Vacuum work area with HEPA-filtered vacuums.

4. Wet mop with disinfectant.

5. Remove isolation of HVAC system in areas where work is being performed.

C la ss I

V

1. Isolate HVAC system in area where work is being done to prevent contamination of duct system.

2. Complete all critical barriers, i.e., sheetrock, plywood, plastic, to seal area from non-work area or implement control cube method (cart with plastic covering & sealed connection to work site with HEPA vacuum for vacuuming prior to exit) before construction begins.

3. Maintain negative air pressure within worksite utilizing HEPA-equipped air filtration units.

4. Seal holes, pipes, conduits and punctures appropriately.

5. Construct anteroom and require all personnel to pass through this room so they can be vacuumed using a HEPA vacuum cleaner before leaving work site; or the can wear cloth or paper coveralls that are removed each time they leave the work site.

6. All personnel entering the work site are required to wear shoe covers.

Shoe covers must be changed each time the worker exits the work area.

7. Do not remove barriers from work area until completed project is inspected by Safety Management & Infection Control & thoroughly cleaned by Environmental Management.

1. Remove barrier materials carefully to minimize spreading of dirt & debris associated with construction.

2. Contain construction waste before transport in tightly covered containers.

3. Cover transport receptacles or carts. Tape covering unless solid lid.

4. Vacuum work area with HEPA-filtered vacuums.

5. Wet mop with disinfectant.

6. Remove isolation of HVAC system in areas where work is being performed.

Project Name: Rooftop Cleaning and Bird Netting Class Type: Class II

Signature:

COR

Date:

Signature:

Chief, FES

Date:

Signature:

Safety Officer

Date:

Signature:

Infection Prevention Practitioner

Date:

Note: Infection Control approval will be required when Construction Activity and Risk Level indicate that Class III or Class IV control procedures are necessary, when disruption in the water lines is a planned part of the activity (beyond water not being used for a period of time) or when it is likely contracting staff will be exposed to a patient with possible tuberculosis.