This is a set of presentation slides for an Industry Day event scheduled for December 4, 2024, regarding the Caño Martin Peña Ecosystem Restoration Project Contract 3 Phase 1 in Puerto Rico. The presentation outlines key details for a major construction project to restore the ecosystem and tidal connection between San Jose Lagoon and San Juan Bay.
The scope includes developing a Material Management Area at Ciudad Deportiva Roberto Clemente, preparing aquatic disposal pits, dredging approximately 4,350 meters of channels (including a 3,000m access channel, 450m transition channel, and 900m main channel), installing steel sheet pile walls with concrete caps, and constructing riprap protection at bridges. The anticipated solicitation number is W51DQV-25-R-0006, with an estimated value between $25M-$100M, NAICS code 237990 (size standard $45M). Key dates include solicitation release on March 31, 2025, and award by September 30, 2025. The US Army Corps of Engineers Caribbean District will execute this firm-fixed-price contract, with the project funded through the Bipartisan Infrastructure Law at $163.3M federal share and $90.7M non-federal matching. Questions must be submitted through ProjNet by December 13, 2023, using Bidder Inquiry Key W962NH-ARD6QD.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CMP CNT 3 Industry Day Sign in.pdf | ||
| CMP_Capability Briefing Schedule.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INDUSTRY DAY
CAÑO MARTIN PEÑA
ECOSYSTEM RESTORATION PROJECT
EVENT AGENDA
US Army Corps of Engineers Caribbean District 04 December 2024
Registration: 12:45 pm 1:00 pm – 2:30 pm
• Welcome Remarks
• How to submit questions
• Caño Martin Peña: Project Overview
• Contract 3: Phase 1
• Scope of Work/Design Information
• Construction Considerations/Testing Requirements
• Contracting Requirements
• Small Business Opportunities
• Procurement Integrated Enterprise Environment (PIEE) – APEX Accelerator 2:30 pm – 3:00 pm
• Question and Answer Session 3:00 pm– 4:30 pm
• Capability Briefings
04 December 2024 Afternoon Session: 1300 - 1630
Focus: Caño Martin Peña, Contract 3: Phase 1
AGENDA
QUESTION AND ANSWER SESSION
• Notecards are available at the registration table
• Write down your questions on the notecards and place them in the basket on the registration table
• Questions that can be answered during this event will be addressed during the Q&A session
• All questions and answers will be provided on SAM.gov
04 December 2024 1430 - 1500
• All questions to be submitted through ProjNet
• Deadline: 5:00 pm, AST on 13 December 2023
• The Solicitation Number is: W51DQV-25-R-0006
• The Bidder Inquiry Key is: W962NH-ARD6QD https://www.projnet.org/projnet/binKornHome/index.cfm
HOW TO SUBMIT QUESTIONS
SAM.GOV
• Please visit SAM.gov after Industry Day
• All presentations, questions and answers, and the attendance sheet will be posted
Notice ID: W51DQV-25-R-0006
CAÑO MARTIN PEÑA ECOSYSTEM RESTORATION PROJECT
CNT 3 PHASE 1 – INDUSTRY DAY
CARIBBEAN DISTRICT
4 DEC 2024
PROJECT LOCATION
San Juan Metropolitan Area
SAN JOSE
LAGOON
SAN JUAN BAY
BOCA DE
CANGREJOS
LA TORRECILLA
LAGOON
LOS COROZOS
LAGOON
CAÑO MARTIN PEÑA CHANNEL
The CAÑO MARTIN PEÑA (CMP) is a 3.5-mile-long tidal channel extending from San Juan Bay to the San José Lagoon.
It is an integral part of the San Juan Bay Estuary system.
ECOSYSTEM RESTORATION PROJECT
MINIMAL DEVELOPMENT ADJACENT TO CANAL (1930)
SPONSORS
Puerto Rico Department of Natural and Environmental Resources (DNER) and Corporación del Proyecto ENLACE del Caño Martín Peña.
AUTHORIZATION
• WRDA of 2007 authorized project for construction amount $150M
• Later amended by Section 402(e) of WRDA of 2020 cost $255M
• ENLACE prepared the Feasibility Report and EIS for the CMP-ERP dated
February 2016. ASA (CW) approved the report on 16 MAY 16, in effect authorizing the project for construction.
COST SHARE
AER (65% Fed/35% Non-Fed); Recreation features (50% Fed/50% Non-Fed).
PROJECT TYPE
Ecosystem Restoration
PROJECT COST DATA
Received Appropriations for Full Construction: $ 163.3M Under Bipartisan Infrastructure Law (BIL) The Non-Federal Sponsors’ matching share is $90.7M (includes LERRDs and cash contributions)
CAÑO MARTÍN PEÑA OVERVIEW
PURPOSE
The Caño Martín Peña Ecosystem Restoration Project (CMP) aims to re-establish the tidal connection between the San José Lagoon and the San Juan Bay (SJB), which would improve dissolved oxygen levels and salinity stratification, increase biodiversity by restoring fish habitat and benthic conditions, and improve the functional value of mangrove habitat within the San Juan Bay Estuary.
CAÑO MARTÍN PEÑA OVERALL IMPLEMENTATION
LUIS
MUÑOZ
RIVERA
BRIDGE
TREN
URBANO
BRIDGE
Martin Pena
BRIDGE
CONTRACT 1|VEGETATION REMOVAL
CONTRACTS
STATUS: Awarded Sep 2024, $14.7M.
Construction start Dec 2024. Expect completion in Oct 2026
SCOPE
Excavation of ~ 25K CY of material from the western end of the channel Construction of a 115-foot-wide by
6.5-foot-deep channel located at western bridges.
Installation of riprap at the channel bottom and the side slopes to prevent scour Steel sheet pile walls will be installed at the eastern end
CONTRACT 3 | CHANNEL EXCAVATION / STABILIZATION
PROJECT IMPLEMENTATION, FEATURES, AND MAP
SOLID WASTE REMOVAL CONTRACT
STATUS: Completed Oct 2023, $2.3M, 15K Tons removed + Modification for additional 3.8K Tons ($600K).
STATUS: Completed June 2023, $3,4M, 36 acres vegetation removed.
CONTRACT 2 | WESTERN BRIDGES SCOUR
PROTECTION. Martín Peña, Tren Urbano, and Luis Muñoz Rivera
STATUS: Phase 1 & Phase 2 Contracts award anticipated in Sep 2025 and Jan 2028, respectively
SCOPE
1.8 miles channel dredging 2 miles access channel dredging from staging area to eastern end of CMP Bank stabilization to include sheet pile Barbosa Bridge scour protection ~ 35 acres Mangrove/wetland restoration for entire channel Recreation features
Contract 2
Contract 3: Phase 1
Contract 3: Phase 2
BARBOSA
BRIDGE
Barbosa
BRIDGE
CAÑO MARTIN PEÑA ECOSYSTEM RESTORATION PROJECT
CNT 3 PHASE 1
Jorge A. Rivera-Cruz, PhD, PE Engineering Technical Lead
*Designed by: AECOM-Black & Veatch Civil Works JV
CONTRACT 3 PHASE 1 OVERVIEW
• Material Management Area (MMA) / Staging Site Development (CDRC)
• San Jose Lagoon Disposal Pits Preparation
• Access Channel Preparation
Moscoso Bridge Protection
• Transition Channel Improvements from main channel to access channel
• Main Channel Improvements from Barbosa Bridge to transition channel
Sheet Pile Installation
Barbosa Bridge Scour Protection
Barbosa
BRIDGE
SJ1
SJ2
SJ4/5
SJ3
Access Channel
Transition Channel
MMA
Disposal Pits Main Channel
12CONTRACT 3 PHASE 1 FEATURES
MATERIAL MANAGEMENT AREA / STAGING AREA
Features:
• Access Road
• Concrete Dock (29.2 x 25.9 m)
• Concrete Ramp
Dock
Boat ramp
MMA
(6-8 acres)
Access road extension ~400 m
Ciudad Deportiva Roberto Clemente (CDRC)
12 m
Precast Concrete Pile
Concrete Slab
Fender System
13CONTRACT 3 PHASE 1
SAN JOSE LAGOON DISPOSAL PITS
• Disposal of dredged material (sediment)
• SJ1 Pit will be dredged to a bottom elevation of -9.1 m (total capacity ~ 350K cubic meters)
• Dredged material from SJ1 will be disposed directly (no screening needed) into
SJ2/3/4/5
• SJ1 will be capped by 61 cm of clean sand during Phase 2
SJ1
SJ2
SJ4/5
SJ3
SJ1
SJ2
SJ3
SJ4/5
Disposal Pits
14CONTRACT 3 PHASE 1
ACCESS CHANNEL
• Dimensions (trapezoidal) 3000 meters long
15.2 meters bottom width
1.8 meters depth 3:1 side slopes Moscoso Bridge will be protected
• Anticipated minimum dredging ~ 10K cubic meters
• Dredged material will be disposed directly into pits
(no screening needed)
SJ1
Access Channel
Typical Cross Section
7.6 m 7.6 m
EL -1.8 m
Bathymetry
15CONTRACT 3 PHASE 1
MOSCOSO BRIDGE PROTECTION
• 8.7 meters clearance at the access channel cross point
• 30.1 meters span length
• Piers will be protected by means of fenders
15 m precast concrete pile composite lumber
16CONTRACT 3 PHASE 1
TRANSITION CHANNEL
• Dimensions (trapezoidal) 450 meters long channel
3.1 meters depth
30.5 meters bottom width 3:1 slope
• Estimated dredged volume ~ 34K cubic meters
• Dredged material will be disposed directly into SJ1 pit (no screening needed)
Typical Cross Section
15.25 m 15.25 m
EL -3.1 m
17CONTRACT 3 PHASE 1
MAIN CHANNEL
• Dredging of 1,000 meters long channel
• Rectangular cross section (30.5 x 3.1 m)
• Steel sheet pile channel walls with concrete cap (12 m)
• Estimated dredged volume ~ 103K cubic meters
• Expected higher trash and debris. Separation of solid waste from sediments will be performed by a metal sieve.
• After screening and removal of solid waste, the remaining dredged material will be transported by shallow-draft barges and bottom dumped in a controlled manner at SJ1 disposal pit.
• The solid waste will be transported to the MMA, and then, trucks will haul material to an approve landfill.
Main Channel
CONTRACT 3 PHASE 1
CHANNEL WALLS
• Approximately 1,000 meters long channel
• Rectangular cross section (30.5 x 3.1 m)
19CONTRACT 3 PHASE 1
BARBOSA BRIDGE SCOUR PROTECTION
• Dimensions (trapezoidal) 61 meters length
3.1 meters depth
30.5 meters bottom width 3:1 slope riprap size: 0.51 meters
CONSTRUCTION CONSIDERATIONS
Limited access: Most of the access routes are local roads (narrow streets) with adjacent residential structures vulnerable to damages
Construction on the wet: Diversion of the channel won't be allowed
Activities below Barbosa and Moscoso Bridges: Low vertical clearance
Higher solid waste: Percentage of solid waste (garbage, debris) could be higher than the percentage assumed during design
Dredged material management: Material management must comply with the Water Quality Certificate, state and federal laws.
Water quality in the SJL: turbidity control, controlled placement of the sediments into the pits to limit the release of grey waters.
Water releases from the MMA : Water returning into water of the US must be tested and comply with the Water Quality Certificate before release
Community Outreach: Working in CMP area requires extensive coordination with ENLACE (NFS) and the G-8 due to the proximity of residential structures and dense population
CAÑO MARTIN PEÑA - CNT 3 PHASE 1
Jorge Ayala-Burgos, PE Construction Division
ESTIMATED QUANTITIES FOR MAIN SUPPLY NEEDS
Barbosa
BRIDGE
SJ1
SJ2
SJ4/5
SJ3
Note: Implementation contracts are at different stages in the design process.
Estimated quantities developed with the latest available design data.
Subject to change.
FEATURES CNT 3 PH1
Dredging (CY) 569,000 Stone Placement (Tons) 12,300 Steel Sheet Pile (Tons) 3,274 Concrete (CY) 1,100 Reinforcing Steel (Tons) 200 Prestressed Concrete Piles 309
Main Materials
[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]
Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts
RDLP CNT 1 2,323,578 2,080,528 272,000 2412 On the works On the works 4 concrete culverts (need to estimate this and add to concrete quantities)
RDLP CNT 2 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold
RDLP CNT 3 1,722,000 224,000 101,000
RGDA 325,000 520,000 29,000 6,500 On the works 14000LF (60in DS), +2000CY, 50000 tons of stone protection
RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY
RPN CNT 2 119,000 4,801 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)
RPN CNT 3 600,000 25,000 12,204 8,000 200,000 46,000 1600 DS 72 in ERROR:#NAME?
RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in
RPN CNT 5A 9,000 5,000 636 8,000 537 34,000 100 DS 72 in
RPN CNT 5B 47,000 1,400 1,100 62,000 2,500 140,000 1000 DS 60 in
RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in
RPN CNT 7 300,000 100,000 3,200 75,000 2,000
RPN La Chuleta 32,460 32,460 360 360 CY of concrete, 4,834 cy of bituminous pavement
Total 7,729,038 3,463,388 419,005 121,100 32,848 563,860 71,037 799,000
Main Materials (2)
[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]
Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts
RDLP CNT 1 2,234,000 1,962,000 272,000 2412 14000 1000 4 concrete culverts (need to estimate this and add to concrete quantities)
RDLP CNT 2 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold
RDLP CNT 3 1,722,000 224,000 101,000
RGDA 325,000 520,000 29,181 6,500 On the works 14000LF (60in DS), +2000CY, 50000 tons of stone protection
RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY
RPN CNT 2 119,000 4,801 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)
RPN CNT 3 600,000 25,000 12,204 8,000 200,000 46,000 1600 DS 72 in ERROR:#NAME?
RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in
RPN CNT 5A 9,000 5,000 584 636 14,000 3,505 34,000 100 DS 72 in, 1000 tons of riprap
RPN CNT 5B 76,000 1,400 14,000 52,000 2,250 102,000 1000 DS 60 in
RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in
RPN CNT 7 300,000 100,000 3,200 75,000 2,000 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed
RPN La Chuleta 31,700 31,700 360 360 CY of concrete, 2,555 tons of bituminous pavement
Total 7,667,700 3,344,100 419,770 121,100 45,748 573,860 74,755 761,000
Main Materials (3)
[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]
Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts
RDLP CNT 1 2,234,000 1,962,000 272,000 2412 14000 1000 4 concrete culverts (need to estimate this and add to concrete quantities)
RDLP CNT 2 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold
RDLP CNT 3 1,722,000 224,000 101,000
Total RDLP 3,956,000 2,186,000 373,000 0 2,412 14,000 1,000
RGDA 325,000 520,000 29,181 6,500 1300 14000LF (60in DS), +2000CY, 50000 tons of stone protection
RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY
RPN CNT 2 119,000 4,801 1,608 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)
RPN CNT 3 600,000 25,000 12,204 8,000 200,000 46,000 1600 DS 72 in ERROR:#NAME?
RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in
RPN CNT 5A 9,000 5,000 584 636 14,000 3,505 34,000 100 DS 72 in, 1000 tons of riprap
RPN CNT 5B 76,000 1,400 14,000 52,000 2,250 102,000 1000 DS 60 in
RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in
RPN CNT 7 300,000 100,000 3,200 75,000 2,000 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed
RPN La Chuleta 31,700 31,700 360 360 CY of concrete, 2,555 tons of bituminous pavement
Total RPN 3,386,700 638,100 17,589 121,100 44,944 553,360 73,755 761,000
Total 7,667,700 3,344,100 419,770 121,100 47,356 573,860 76,055 761,000
Sheet2
RPN CNT 2 lb/ft2 tons
Temporary Bypass Sheet Pile 48329 sqft 36.98 893.60321
Temporary Trnasverse Sheet Pile 19275 sqft 36.98 356.39475
Transition Sheet Pile 19372 sqft 36.98 358.18828
1608.18624
Main Materials No LC
[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]
Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts
RDLP CNT 1 2,234,000 1,962,000 272,000 2412 8000 1000 4 concrete culverts (need to estimate this and add to concrete quantities)
RDLP CNT 2 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold
RDLP CNT 3 1,722,000 224,000 101,000
Total RDLP 3,956,000 2,186,000 373,000 0 2,412 8,000 1,000
RGDA 325,000 520,000 29,181 6,500 1300 14000LF (60in DS), +2000CY, 50000 tons of stone protection
RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY
RPN CNT 2 119,000 4,801 700 1,608 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)
RPN CNT 3 600,000 25,000 12,204 8,000 200,000 46,000 31,974 1600 DS 72 in ERROR:#NAME?
RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in
RPN CNT 5A 9,000 5,000 584 636 14,000 3,505 34,000 100 DS 72 in, 1000 tons of riprap
RPN CNT 5B 76,000 1,400 14,000 52,000 2,250 102,000 1000 DS 60 in
RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in
RPN CNT 7 300,000 100,000 3,200 75,000 2,000 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed
Total RPN 3,355,000 606,400 17,589 121,800 44,944 553,000 73,755 792,974
Total 7,636,000 3,312,400 419,770 121,800 47,356 567,500 76,055 792,974
Contract Awards
FY23 FY24 FY25 FY26 FY27 FY28
RPN CNT 2 RPN CNT 3 RPN CNT 1 RPN CNT 6 RDLP CNT 3
RGDA RPN CNT 5A RPN CNT 4 RPN CNT 7
RDLP CNT 1 RPN CNT 5B
Excavation (CY) 119,000 925,000 2,243,000 327,000 2,300,000 1,722,000
Fill (CY) 0 545,000 1,967,000 146,400 430,000 224,000
Stone Placement (CY) 4,801 41,385 272,584 0 0 101,000
Soil Improvement (CY) 700 0 0 121,100 0 0
Sheet Piles (Tons) 1,608 8,000 3,048 23,500 11,200 0
Concrete (CY) 19,000 206,500 22,000 165,000 155,000 0
Reinforcing Steel (Tons) 7,000 47,300 4,505 8,250 9,000 0
ACBM (SQFT) 0 31,974 34,000 406,000 321,000 0
Main Materials No LC (2)
[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]
Estimated award date Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts
Mar-25 RDLP CNT 1 2,234,000 1,962,000 272,000 2412 8000 1000 4 concrete culverts (need to estimate this and add to concrete quantities)
RDLP CNT 2 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold
May-28 RDLP CNT 3 1,722,000 224,000 101,000
Total RDLP 3,956,000 2,186,000 373,000 0 2,412 8,000 1,000
17-Jun-27 RGDA 325,000 520,000 29,181 6,500 1300 14000LF (60in DS), +2000CY, 50000 tons of stone protection
28-Nov-25 RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY
19-Jul-24 RPN CNT 2 119,000 4,801 700 1,608 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)
8-Jul-24 RPN CNT 3 600,000 25,000 12,204 8,000 200,000 46,000 31,974 1600 DS 72 in ERROR:#NAME?
17-Aug-26 RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in
3-Jan-25 RPN CNT 5A 9,000 5,000 584 636 14,000 3,505 34,000 100 DS 72 in, 1000 tons of riprap
30-Jun-26 RPN CNT 5B 76,000 1,400 14,000 52,000 2,250 102,000 1000 DS 60 in
28-May-27 RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in
30-Jun-27 RPN CNT 7 300,000 100,000 3,200 75,000 2,000 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed
Total RPN 3,355,000 606,400 17,589 121,800 44,944 553,000 73,755 792,974
Total 7,636,000 3,312,400 419,770 121,800 47,356 567,500 76,055 792,974
Contract Awards
2023 2024 2025 2026 2027 2028
RPN CNT 3 RPN CNT 1 RPN CNT 6 RDLP CNT 3
RPN CNT 2 RPN CNT 5A RPN CNT 4 RPN CNT 7 FEATURES 2024 2025 2026 2027 2028 TOTAL
RDLP CNT 1 RPN CNT 5B RGDA Excavation (CY) 719,000 2,243,000 327,000 2,625,000 1,722,000 7,636,000
Fill (CY) 25,000 1,967,000 146,400 950,000 224,000 3,312,400
Excavation (CY) 719,000 2,243,000 327,000 2,625,000 1,722,000 Stone Placement (CY) 17,005 272,584 29,181 101,000 419,770
Fill (CY) 25,000 1,967,000 146,400 950,000 224,000 Soil Improvement (CY) 700 121,100 121,800
Stone Placement (CY) 17,005 272,584 0 29,181 101,000 Sheet Piles (Tons) 9,608 3,048 23,500 11,200 47,356
Soil Improvement (CY) 700 0 121,100 0 0 Concrete (CY) 219,000 22,000 165,000 161,500 567,500
Sheet Piles (Tons) 9,608 3,048 23,500 11,200 0 Reinforcing Steel (Tons) 53,000 4,505 8,250 10,300 76,055
Concrete (CY) 219,000 22,000 165,000 161,500 0 ACBM (SQFT) 31,974 34,000 406,000 321,000 792,974
Reinforcing Steel (Tons) 53,000 4,505 8,250 10,300 0
ACBM (SQFT) 31,974 34,000 406,000 321,000 0
FEATURES RPN RDLP RGDA TOTAL
Excavation (CY) 3,355,000 3,956,000 325,000 7,636,000
Fill (CY) 606,400 2,186,000 520,000 3,312,400
Stone Placement (CY) 17,589 373,000 29,181 419,770
Soil Improvement (CY) 121,800 121,800
Sheet Piles (Tons) 44,944 2,412 47,356
Concrete (CY) 553,000 8,000 6,500 567,500
Reinforcing Steel (Tons) 73,755 1,000 1,300 76,055
ACBM (SQFT) 792,974 792,974
Main Materials No LC (3)
[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]
Estimated award date Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts
Mar-25 RDLP CNT 1 2,234,000 1,962,000 272,000 2412 8000 1000 4 concrete culverts (need to estimate this and add to concrete quantities)
RDLP CNT 2 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold
May-28 RDLP CNT 3 1,222,000 224,000 101,000
Total RDLP 3,456,000 2,186,000 373,000 0 2,412 8,000 1,000
17-Jun-27 RGDA 325,000 520,000 29,181 6,500 1300 14000LF (60in DS), +2000CY, 50000 tons of stone protection
28-Nov-25 RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY
19-Jul-24 RPN CNT 2 119,000 4,801 700 1,608 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)
8-Jul-24 RPN CNT 3 600,000 25,000 12,204 8,000 200,000 46,000 31,974 1600 DS 72 in ERROR:#NAME?
17-Aug-26 RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in
3-Jan-25 RPN CNT 5A 9,000 5,000 584 636 14,000 3,505 34,000 100 DS 72 in, 1000 tons of riprap
30-Jun-26 RPN CNT 5B 76,000 1,400 14,000 52,000 2,250 102,000 1000 DS 60 in
28-May-27 RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in
30-Jun-27 RPN CNT 7 300,000 100,000 3,200 75,000 2,000 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed
Total RPN 3,355,000 606,400 17,589 121,800 44,944 553,000 73,755 792,974
Total 7,136,000 3,312,400 419,770 121,800 47,356 567,500 76,055 792,974
Contract Awards
2023 2024 2025 2026 2027 2028
RPN CNT 3 RPN CNT 1 RPN CNT 6 RDLP CNT 3
RPN CNT 2 RPN CNT 5A RPN CNT 4 RPN CNT 7 FEATURES 2024 2025 2026 2027 2028 TOTAL
RDLP CNT 1 RPN CNT 5B RGDA Excavation (CY) 719,000 2,243,000 327,000 2,625,000 1,222,000 7,136,000
Fill (CY) 25,000 1,967,000 146,400 950,000 224,000 3,312,400
Excavation (CY) 719,000 2,243,000 327,000 2,625,000 1,222,000 Stone Placement (CY) 17,005 272,584 29,181 101,000 419,770
Fill (CY) 25,000 1,967,000 146,400 950,000 224,000 Soil Improvement (CY) 700 121,100 121,800
Stone Placement (CY) 17,005 272,584 0 29,181 101,000 Sheet Piles (Tons) 9,608 3,048 23,500 11,200 47,356
Soil Improvement (CY) 700 0 121,100 0 0 Concrete (CY) 219,000 22,000 165,000 161,500 567,500
Sheet Piles (Tons) 9,608 3,048 23,500 11,200 0 Reinforcing Steel (Tons) 53,000 4,505 8,250 10,300 76,055
Concrete (CY) 219,000 22,000 165,000 161,500 0 ACBM (SQFT) 31,974 34,000 406,000 321,000 792,974
Reinforcing Steel (Tons) 53,000 4,505 8,250 10,300 0
ACBM (SQFT) 31,974 34,000 406,000 321,000 0
FEATURES RPN RDLP RGDA TOTAL
Excavation (CY) 3,355,000 3,456,000 325,000 7,136,000
Fill (CY) 606,400 2,186,000 520,000 3,312,400
Stone Placement (CY) 17,589 373,000 29,181 419,770
Soil Improvement (CY) 121,800 121,800
Sheet Piles (Tons) 44,944 2,412 47,356
Concrete (CY) 553,000 8,000 6,500 567,500
Reinforcing Steel (Tons) 73,755 1,000 1,300 76,055
ACBM (SQFT) 792,974 792,974
CMP QTYs
[yd3] [Tons] [Tons] [yd3] [Tons]
Estimated award date Materials: Dedging Stone Placement Steel Sheet Pile Concrete Reinforcing Steel Prestressed Concrete Piles Concrete Culverts
Oct-24 CMP CNT 2 22,000 13,200 323 105 14 4 concrete culverts (need to estimate this and add to concrete quantities)
Oct-25 CMP CNT 3 PH1 569,000 12,300 3,274 1,100 200 309 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold
Feb-28 CMP CNT 3 PH2 300,000 7,857 2,816 373
Total CMP 891,000 25,500 11,454 4,021 587
17-Jun-27 RGDA 14000LF (60in DS), +2000CY, 50000 tons of stone protection
28-Nov-25 RPN CNT 1 30,000 CY of concrete, asphalt 28990 SY
19-Jul-24 RPN CNT 2 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)
8-Jul-24 RPN CNT 3 1600 DS 72 in ERROR:#NAME?
17-Aug-26 RPN CNT 4 1200 DS 60 in
3-Jan-25 RPN CNT 5A 100 DS 72 in, 1000 tons of riprap
30-Jun-26 RPN CNT 5B 1000 DS 60 in
28-May-27 RPN CNT 6 1300 DS 60 in
30-Jun-27 RPN CNT 7 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed
Total RPN 0 0 0 0 0 0 0 0
Total 891,000 25,500 11,454 4,021 587 309 0 0
Contract Awards
2023 2024 2025 2026 2027 2028
CMP CNT 2 CMP CNT 3 PH1 RDLP CNT 3
FEATURES 2024 2025 2026 2027 2028 TOTAL
Dredging (CY) 22,000 569,000 300,000 891,000
Stone Placement (Tons) 13,200 12,300 25,500
Dredging (CY) 22,000 569,000 0 0 300,000 Steel Sheet Pile (Tons) 323 3,274 7,857 11,454
Stone Placement (Tons) 13,200 12,300 0 0 0 Concrete (CY) 105 1,100 2,816 4,021
Steel Sheet Pile (Tons) 323 3,274 0 0 7,857 Reinforcing Steel (Tons) 14 200 373 587
Concrete (CY) 105 1,100 0 0 2,816
Reinforcing Steel (Tons) 14 200 0 0 373
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
FEATURES CNT 2 CNT 3 PH1 CNT 3 PH2 TOTAL FEATURES CNT 3 PH1
Dredging (CY) 22,000 569,000 300,000 891,000 Dredging (CY) 569,000
Stone Placement (Tons) 13,200 12,300 25,500 Stone Placement (Tons) 12,300
Steel Sheet Pile (Tons) 323 3,274 7,857 11,454 Steel Sheet Pile (Tons) 3,274
Concrete (CY) 105 1,100 2,816 4,021 Concrete (CY) 1,100
Reinforcing Steel (Tons) 14 200 373 587 Reinforcing Steel (Tons) 200
Prestressed Concrete Piles 309 Prestressed Concrete Piles 309
Main Materials (RPN3-RDLP1)
[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]
Estimated award date Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts 1780000
Mar-25 RDLP CNT 1 2,328,000 1,000,000 210,000 271,000 2500 8000 1000 28000 4 concrete culverts (need to estimate this and add to concrete quantities) 772000
RDLP NCSA 112,875 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold 160000
May-28 RDLP CNT 3 1,222,000 224,000 101,000
Total RDLP 3,550,000 1,224,000 311,000 271,000 2,500 8,000 1,000
17-Jun-27 RGDA 325,000 520,000 29,181 6,500 1300 14000LF (60in DS), +2000CY, 50000 tons of stone protection
28-Nov-25 RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY
19-Jul-24 RPN CNT 2 119,000 4,801 700 1,608 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction)
1-Jun-26 RPN CNT 3 600,000 25,000 12,000 370 8,000 200,000 46,000 32,000 1600 DS 72 in ERROR:#NAME?
17-Aug-26 RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in
3-Jan-25 RPN CNT 5A 9,000 5,000 584 636 14,000 3,505 34,000 100 DS 72 in, 1000 tons of riprap
30-Jun-26 RPN CNT 5B 76,000 1,400 14,000 52,000 2,250 102,000 1000 DS 60 in
28-May-27 RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in
30-Jun-27 RPN CNT 7 300,000 100,000 3,200 75,000 2,000 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed
Total RPN 3,355,000 606,400 17,385 122,170 44,944 553,000 73,755 793,000
Total 7,342,875 2,350,400 357,566 393,170 47,444 567,500 76,055 821,000
Contract Awards
2023 2024 2025 2026 2027 2028
RDLP CNT 1 RPN CNT 3
FEATURES 2024 2025 2026 2027 2028 TOTAL FEATURES 2025 2026 TOTAL
Excavation (CY) 0 2,328,000 600,000 0 0 2,928,000 Excavation (CY) 2,328,000 600,000 2,928,000
Fill (CY) 0 1,000,000 25,000 0 0 1,025,000 Fill (CY) 1,000,000 25,000 1,025,000
Excavation (CY) 2,328,000 600,000 Stone Placement (CY) 0 210,000 0 0 210,000 Stone Placement (CY) 210,000 12,000 222,000
Fill (CY) 1,000,000 25,000 Soil Improvement (CY) 0 370 370 Soil Improvement (CY) 271,000 370 271,370
Stone Placement (CY) 210,000 12,000 Sheet Piles (Tons) 0 2,500 8,000 0 10,500 Sheet Piles (Tons) 2,500 8,000 10,500
Soil Improvement (CY) 271,000 370 Concrete (CY) 0 8,000 200,000 0 208,000 Concrete (CY) 8,000 200,000 208,000
Sheet Piles (Tons) 2,500 8,000 Reinforcing Steel (Tons) 0 1,000 46,000 0 47,000 Reinforcing Steel (Tons) 1,000 46,000 47,000
Concrete (CY) 8,000 200,000 ACBM (SQFT) 0 28,000 32,000 0 60,000 ACBM (SQFT) 28,000 32,000 60,000
Reinforcing Steel (Tons) 1,000 46,000
ACBM (SQFT) 28,000 32,000
FEATURES RPN RDLP RGDA TOTAL FEATURES RDLP CNT 1 RPN CNT 3 TOTAL
Excavation (CY) 3,355,000 3,550,000 325,000 7,230,000 Excavation (CY) 2,328,000 600,000 2,928,000
Fill (CY) 606,400 1,224,000 520,000 2,350,400 Fill (CY) 1,000,000 25,000 1,025,000
Stone Placement (CY) 17,385 311,000 29,181 357,566 Stone Placement (CY) 210,000 12,000 222,000
Soil Improvement (CY) 122,170 122,170 Soil Improvement (CY) 271,000 370 271,370
Sheet Piles (Tons) 44,944 2,500 47,444 Sheet Piles (Tons) 2,500 8,000 10,500
Concrete (CY) 553,000 8,000 6,500 567,500 Concrete (CY) 8,000 200,000 208,000
Reinforcing Steel (Tons) 73,755 1,000 1,300 76,055 Reinforcing Steel (Tons) 1,000 46,000 47,000
ACBM (SQFT) 793,000 793,000 ACBM (SQFT) 28,000 32,000 60,000
Main Materials (RDLP NCSA)
[yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft2]
Estimated award date Materials: Excavation Fill Stone Placement Soil Imp Sheet Piles Concrete Reinforcing Steel ACBM Concrete Culverts 1780000 [yd3] [yd3] [yd3] [yd3] [Tons] [yd3] [Tons] [ft] [ft]
Mar-25 RDLP CNT 1 2,328,000 1,000,000 210,000 271,000 2500 8000 1000 28000 4 concrete culverts (need to estimate this and add to concrete quantities) 772000 Materials: Excavation (CY) CLSM Sand Backfill (CY) Select Backfill (CY) Sheet Piles (Tons) Concrete (CY) Reinforcing Steel (Tons) 72-Inch Welded Steel Pipe (FT) 48-Inch Steel Bypass Pipe (FT)
RDLP NCSA 112,875 48 DS, 55 (137ft) AASHTO Bridge Girders, 70000ft2 concrete bridge deck This contract is currently on hold 160000
May-28 RDLP CNT 3 1,222,000 224,000 101,000 RDLP NCSA 112,875 2,894 8,279 45,857 3,900 4,500 50 1,000 1,670
Total RDLP 3,550,000 1,224,000 311,000 271,000 2,500 8,000 1,000
17-Jun-27 RGDA 325,000 520,000 29,181 6,500 1300 14000LF (60in DS), +2000CY, 50000 tons of stone protection Total RDLP 0 0 0 0 0 0 0
RGDA
28-Nov-25 RPN CNT 1 181,000 145,000 121,100 6,000 30,000 2,000 30,000 CY of concrete, asphalt 28990 SY
19-Jul-24 RPN CNT 2 119,000 4,801 700 1,608 19,000 7,000 19,000 CY of concrete (110 DS 72 in, 90 DS 60in, bridge construction) RPN CNT 1
1-Jun-26 RPN CNT 3 600,000 25,000 12,000 370 8,000 200,000 46,000 32,000 1600 DS 72 in ERROR:#NAME? RPN CNT 2
17-Aug-26 RPN CNT 4 70,000 3,500 83,000 4,000 304,000 1200 DS 60 in RPN CNT 3
3-Jan-25 RPN CNT 5A 9,000 5,000 584 636 14,000 3,505 34,000 100 DS 72 in, 1000 tons of riprap RPN CNT 4
30-Jun-26 RPN CNT 5B 76,000 1,400 14,000 52,000 2,250 102,000 1000 DS 60 in RPN CNT 5A
28-May-27 RPN CNT 6 2,000,000 330,000 8,000 80,000 7,000 321,000 1300 DS 60 in RPN CNT 5B
30-Jun-27 RPN CNT 7 300,000 100,000 3,200 75,000 2,000 Evaluating braced steel sheet pile and ACBM bottom, Qtys need to be verified after the design is changed RPN CNT 6
Total RPN 3,355,000 606,400 17,385 122,170 44,944 553,000 73,755 793,000 RPN CNT 7
Total 7,342,875 2,350,400 357,566 393,170 47,444 567,500 76,055 821,000
Contract Awards NCSA
2023 2024 2025 2026 2027 2028 FEATURES RDLP NCSA TOTAL
RDLP CNT 1 RPN CNT 3 Excavation (CY) 112,900 112,900
FEATURES 2024 2025 2026 2027 2028 TOTAL FEATURES 2025 2026 TOTAL Control Low Strength Material (CY) 2,900 2,900
Excavation (CY) 0 2,328,000 600,000 0 0 2,928,000 Excavation (CY) 2,328,000 600,000 2,928,000 Sand Backfill (CY) 8,300 8,300
Fill (CY) 0 1,000,000 25,000 0 0 1,025,000 Fill (CY) 1,000,000 25,000 1,025,000 Select Backfill (CY) 45,900 45,900
Excavation (CY) 2,328,000 600,000 Stone Placement (CY) 0 210,000 0 0 210,000 Stone Placement (CY) 210,000 12,000 222,000 Sheet Piles (Tons) 3,900 3,900
Fill (CY) 1,000,000 25,000 Soil Improvement (CY) 0 370 370 Soil Improvement (CY) 271,000 370 271,370 Concrete (CY) 4,500 4,500
Stone Placement (CY) 210,000 12,000 Sheet Piles (Tons) 0 2,500 8,000 0 10,500 Sheet Piles (Tons) 2,500 8,000 10,500 Reinforcing Steel (Tons) 50 50
72-Inch Welded Steel Pipe (FT) 1,000 1,000
Soil Improvement (CY) 271,000 370 Concrete (CY) 0 8,000 200,000 0 208,000 Concrete (CY) 8,000 200,000 208,000 48-Inch Steel Bypass Pipe (FT) 1,670 1,670
Sheet Piles (Tons) 2,500 8,000 Reinforcing Steel (Tons) 0 1,000 46,000 0 47,000 Reinforcing Steel (Tons) 1,000 46,000 47,000
Concrete (CY) 8,000 200,000 ACBM (SQFT) 0 28,000 32,000 0 60,000 ACBM (SQFT) 28,000 32,000 60,000
Reinforcing Steel (Tons) 1,000 46,000 FEATURES RDLP NCSA TOTAL
ACBM (SQFT) 28,000 32,000 Excavation (CY) 112,900 112,900
FEATURES RPN RDLP RGDA TOTAL FEATURES RDLP CNT 1 RPN CNT 3 TOTAL Control Low Strength Material (CY) 2,900 2,900
Excavation (CY) 3,355,000 3,550,000 325,000 7,230,000 Excavation (CY) 2,328,000 600,000 2,928,000 Sand Backfill (CY) 8,300 8,300
Fill (CY) 606,400 1,224,000 520,000 2,350,400 Fill (CY) 1,000,000 25,000 1,025,000 Select Backfill (CY) 45,900 45,900
Stone Placement (CY) 17,385 311,000 29,181 357,566 Stone Placement (CY) 210,000 12,000 222,000 Sheet Piles (Tons) TBD TBD
Soil Improvement (CY) 122,170 122,170 Soil Improvement (CY) 271,000 370 271,370 Concrete (CY) TBD TBD
Sheet Piles (Tons) 44,944 2,500 47,444 Sheet Piles (Tons) 2,500 8,000 10,500 Reinforcing Steel (Tons) TBD TBD
Concrete (CY) 553,000 8,000 6,500 567,500 Concrete (CY) 8,000 200,000 208,000 72-Inch Welded Steel Pipe (FT) 980 980
Reinforcing Steel (Tons) 73,755 1,000 1,300 76,055 Reinforcing Steel (Tons) 1,000 46,000 47,000 48-Inch Steel Bypass Pipe (FT) 1,670 1,670
ACBM (SQFT) 793,000 793,000 ACBM (SQFT) 28,000 32,000 60,000
HEAVY EQUIPMENT
Barbosa
BRIDGE
SJ1
SJ2
SJ4/5
SJ3
Note: This list is not all inclusive
• Excavator
• Dredging Equipment
• Dozer
• Loader
• Backhoe loader
• Roller compactor
• Crane
• Water truck
• Dump truck (on-road and off-road)
• Generators
• Pumps
• Vibratory hammer
• Impact hammer
• Power unit
SERVICES
Barbosa
BRIDGE
SJ1
SJ2
SJ4/5
SJ3
Note: This list is not all inclusive
• QC Staff Personnel:
• Surveyors,
• Geotechnical and Structural Consultants,
• Scheduler,
• Environmental Monitoring (Puerto Rican Boa Monitor, Manatee Observer, Environmental Compliance Inspections), etc.
• Safety Personnel
• Vibration Monitoring
• Material Testing
MATERIAL TESTING
Barbosa
BRIDGE
SJ1
SJ2
SJ4/5
SJ3
Note: This list is not all inclusive of all required tests
Aggregates C 33 - Standard Specification for Concrete Aggregates C 88 - Soundness of Aggregates C 117 - Material Finer than 75 μm (No. 200) Sieve C 127 - Density, Relative Density, and Absorption of Coarse
Aggregates C 128 - Density, Relative Density, and Absorption of Fine
Aggregates C 131 - Resistance to Degradation by Abrasion and Impact C 136 - Sieve Analysis of Aggregates C 535 - Resistance to Degradation of Large-Size Coarse
Aggregate C 566 - Total Moisture Content
Concrete C 39 - Compressive Strength of Cylindrical Specimens C 143 - Slump C 231 - Air Content by Pressure C 1064 - Temperature of Concrete
Soils D 698 - Compaction Characteristics by Standard Effort D 1556 - Density & Unit Weight by Sand Cone D 1557 - Compaction Characteristics by Modified Effort D 2166 - Unconfined Compressive Strength D 2216 - Water Content D 2487 - Classification of Soils D 4253 - Maximum Index Density by Vibratory Table D 4254 - Minimum Index Density D 4318 - Liquid Limit, Plastic Limit, and Plasticity Index D 6938 - Density and Water Content by Nuclear Methods
Environmental Testing for Landfill Disposal
CAÑO MARTIN PEÑA
ECOSYSTEM RESTORATION
PROJECT
Samuela Adams Contract Specialist
Katrina Chapman Contracting Officer
File Name
CONTRACTING INFORMATION
•System for Award Management (SAM) - the Official U.S. Government System for contract opportunities. Every contract announcement is posted in the SAM.gov website. To receive an award with us you must be registered in
SAM.
•Federal Acquisition Regulations System (FAR 1.101) - is established for the codification and publication of uniform policies and procedures for acquisition by all executive agencies.
oThe Federal Acquisition Regulations System consists of the Federal Acquisition Regulation (FAR), which is the primary document, and agency acquisition regulations that implement or supplement the FAR.
ohttps://www.acquisition.gov/browse/index/far
DOING BUSINESS WITH
CARIBBEAN DISTRICT PUERTO RICO
https://www.acquisition.gov/browse/index/far
•Procurement Integrated Enterprise Environment (PIEE), (Cont.)
oThe only authorized transmission method of proposals in response to the subject solicitation is electronically via the Procurement Integrated Enterprise Environment (PIEE) website. No other transmission methods, such as email, facsimile, hand-carried, proprietary or DOD SAFE submissions, proposals submitted by mail, etc. will be accepted. Offers submitted via any other transmission method other than the Procurement Integrated Enterprise Environment (PIEE) website will not be evaluated.
oThe Offeror’s proposal/bid must be received by the Government no later than the date/time specified in the solicitation and cited above. Offerors shall submit their proposal/bid using the following link:
ohttps://piee.eb.mil/
DOING BUSINESS WITH
CARIBBEAN DISTRICT PUERTO RICO
https://piee.eb.mil/
• Solicitation Number will be W51DQV25R0006
• Applicable North American Industry Classification System (NAICS) code is 237990, Heavy and Civil Engineering Construction
• The Small Business Size Standard for NAICS 237990, Heavy and Civil Engineering Construction, is $45.0 million.
• Current Range of Magnitude $25M - $100M
• Anticipated Solicitation Date is 31 March 2025.
• Anticipated Award Date is NLT 30 September 2025
• Executive Order on Use of Project Labor Agreements for Federal Construction Projects, issued on February 4, 2022, DOES NOT apply to US territories (American Samoa, Guam, Puerto Rico, the Northern Mariana Islands, and the U.S. Virgin Islands)
• Subcontracting Plan is required from Other than Small Business Firms (FAR Part 19)
PROJECT GENERAL INFORMATION
ACQUISITION APPROACH
• Type of contract: Firm-fixed-price
• Acquisition Method: To Be Determined
• Acquisitions will be in accordance with (IAW) Procedures established in one of the following and their supplements:
• FAR Part 14 – Invitation for Bid (IFB) or
• FAR Part 15 – Request for Proposals (RFP) and/or
15.002 Types of negotiated acquisition.
(a) Sole source acquisitions. When contracting in a sole source environment, the request for proposals (RFP) should be tailored to remove unnecessary information and requirements; e.g., evaluation criteria and voluminous proposal preparation instructions.
(b) Competitive acquisitions. When contracting in a competitive environment, the procedures of this part are intended to minimize the complexity of the solicitation, the evaluation, and the source selection decision, while maintaining a process designed to foster an impartial and comprehensive evaluation of offerors’ proposals, leading to selection of the proposal representing the best value to the Government (see 2.101).
– Other Important References
Defense Federal Acquisition Regulation Supplement (DFARS)
Army Federal Acquisition Regulation Supplement (AFARS) Part 5115.000
DoD Source Selection Procedures
Army Source Selection Supplement (AS3), Appendix AA
ACQUISITION APPROACH
RESOURCES 33
Looking for Opportunities in All the Right Places
• Puerto Rico Federal Contracting Center -is a division of the Puerto Rico Department of Commerce focused to assist local business sell their goods and services to the federal government.
o https://www.federalcontractingpr.com
• Dynamic Small Business Search (DSBS)
- is a database where Small Business firms keep a profile current with bonding, past performance, and capabilities.
o http://dsbs.sba.gov/dsbs/search/dsp_d sbs.cfm https://www.federalcontractingpr.com/ http://dsbs.sba.gov/dsbs/search/dsp_dsbs.cfm http://dsbs.sba.gov/dsbs/search/dsp_dsbs.cfm
SMALL BUSINESS PROGRAM
Mariano Torres Feliciano Office Of Small Business Programs
OFFICE OF SMALL
BUSINESS
PROGRAMS
MARIANO TORRES FELICIANO
CHIEF, OFFICE OF SMALL BUSINESS
PROGRAMS
USACE, CARIBBEAN DISTRICT
DATE: NOVEMBER 2024
Working Today to Build a Better Tomorrow
OFFICE OF SMALL BUSINESS PROGRAMS
MISSION: USACE Office of Small Business leads the organization to fully utilize small businesses, to deliver the USACE mission.
VISION: Expand the USACE Office of Small Business and community, Commit to add value to all projects and communicate outcomes & Maximize innovation to lead the small business program into the future.
37SMALL BUSINESS’ ROLES DURING THE
CONTRACTING PROCESS
Pre-Solicitation: Attend planning meeting as the requirement is developed. Once the projects is clearly defined, assist in market research to identify potential work for small businesses. After market research is completed, assist in developing the acquisition strategy.
Solicitation-Award: Asist in the development of the solicitation and source selection plan (if required).
Ensure the solicitation contains proper small business clauses required by the regulations and policies. During award, assist in evaluating bids or proposals and subcontracting plans. Also, take lead to resolve protests concerning small business related issues.
Post Award: Monitor the performance of small business contractors and evaluate how well large businesses comply with subcontracting requirements.
SUBCONTRACTING OPPORTUNITIES
o Trucking and hauling o Sheet pile, anchor installation, pile driving o Drilled shaft construction o Reinforcing steel o Structural and nonstructural concrete o Utilities Relocation - electrical, telecommunications, sewer, and potable water related work o ACBM installation o Soil improvement o Embankment and levee construction o Sod and hydroseeding o Suppliers - concrete, asphalt, aggregates, stone, steel, precast concrete, ACBM, etc o Services: surveyor, geotechnical and structural consultants, material testing, environmental monitoring, etc.
Note: This list is not all inclusive of potential sub-contracting opportunities
PROCUREMENT ASSISTANCE
SBA Resources
• Business Opportunity Specialist
• Procurement Center Representative
Marketing Resources
• Contract Opportunities on SAM.gov
• Contract Data on SAM.gov
• System for Award Management
• Dynamic Small Business Search System
• Subcontracting Networking System
(SubNet)
Other Resources
• USASpending
• GSA Subcontracting Directory
• DoD Prime Contracting Directory https://beta.sam.gov/ https://beta.sam.gov/ https://beta.sam.gov/ http://web.sba.gov/pro-net/search/dsp_dsbs.cfm https://eweb1.sba.gov/subnet/client/dsp_Landing.cfm https://www.usaspending.gov/ https://www.gsa.gov/small-business/find-and-pursue-government-contracts/seek-opportunities/subcontracting-directory-for-small-businesses https://business.defense.gov/
PROCUREMENT ASSISTANCE
Jezebel Rodriguez Procurement Center Representative Puerto Rico and US Virgin Islands
Pedro Acevedo Puerto Rico Accelerator Director
Mariano Torres Feliciano Chief Small Business Programs
USACE, Caribbean District Fundación Angel Ramos, Annex Building
2nd Floor, Suite 202 383 Franklin D. Roosevelt Ave.
San Juan, PR 00918 Mobile: 787-220-0225
SB Email: saa-sb@usace.army.mil
CONTACT INFORMATION
mailto:SAJ-SB@usace.army.mil
| INDUSTRY DAY�Caño Martin Peña�ECOSYSTEM RESTORATION PROJECT |
| AGENDA |
| QUESTION AND ANSWER SESSION |
| HOW TO SUBMIT QUESTIONS |
| SAM.gov |
| Caño Martin Peña ECOSYSTEM RESTORATION PROJECT�CNT 3 Phase 1 – industry day |
| Project location |
| CAÑO MARTÍN PEÑA OVERVIEW |
| CAÑO MARTÍN PEÑA OVERALL IMPLEMENTATION |
| Caño Martin Peña ECOSYSTEM RESTORATION PROJECT �CNT 3 Phase 1 |
| Slide Number 11 |
| CONTRACT 3 PHASE 1 FEATURES �MATERIAL MANAGEMENT AREA / STAGING AREA |
| CONTRACT 3 PHASE 1�SAN JOSE LAGOON Disposal pits |
| Slide Number 14 |
| Slide Number 15 |
| CONTRACT 3 PHASE 1�TRANSITION Channel |
| CONTRACT 3 PHASE 1�main Channel |
| Slide Number 18 |
| Slide Number 19 |
| CONSTRUCTION CONSIDERATIONS |
| Caño Martin Peña - CNT 3 Phase 1 |
| Slide Number 22 |
| Slide Number 23 |
| Slide Number 24 |
| Slide Number 25 |
| Caño martin peña |
| Contracting information |
| Doing Business with �Caribbean district PUERTO RICO |
| Doing Business with �Caribbean district PUERTO RICO |
| Project General Information |
| Acquisition approach |
| ACQUISITION APPROACH |
| resources |
| Small business program |
| Office of Small Business Programs |
| Office of Small Business Programs |
| Small Business’ Roles During The Contracting process |
| �Subcontracting OPPORTUNITIES |
| PROCUREMENT ASSISTANCE |
| PROCUREMENT ASSISTANCE |
| Slide Number 41 |