This file is an Industry Day Presentation for the Modified Central City and Dallas Floodway projects hosted by the U.S. Army Corps of Engineers Fort Worth District on July 9, 2025. The Modified Central City Project is a $2.4 billion flood protection initiative serving Fort Worth, involving an 8,400-foot bypass channel, three flood gates, one pump station, two dams, and multiple valley storage mitigation sites along the Clear Fork and West Fork of the Trinity River. The project aims to restore flood protection for 2,400 acres of established neighborhoods by realigning the river and adding closure gates.
The presentation outlines multiple upcoming contract opportunities across different project phases, with most solicitations being unrestricted and competitive. Key contract opportunities include the North Bypass Channel (Phase 1) valued between $100-250 million, South Bypass Channel Interior also in the $100-250 million range, and several smaller projects ranging from $1-100 million. The Dallas Floodway portion specifically highlights the Hampton 3 Pump Station as a major upcoming solicitation, anticipated to be advertised in FY26 Q3 with a contract magnitude between $100-150 million. The event serves to provide industry insight into project requirements, potential opportunities, and engagement strategies for potential contractors.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Industry Day Final Agenda 2025.pdf | ||
| Industry Day Notice 2025 .pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MODIFIED CENTRAL CITY
AND DALLAS FLOODWAY
INDUSTRY DAY
JULY 9, 2025
OPENING REMARKS
USACE
LTC Joshua Haynes Acting Commander
USACE, Fort Worth District
July 9, 2025
Industry Day Central City & Dallas Floodway
District Overview Welcome Fort Worth District U.S. Army Corps of Engineers
Central City 1950 Central City Present Day
U.S. Army Corps of Engineers
Fort Worth District rose from the waters
16 April 1950
INSTALLATIONS
ANNUAL VISITORS
*DAYUSEFEESWAIVEDIN SUMMER‘20
19M
603�5.54B DESIGN
CONSTRUCTIONPROJECTS�4.32B
2STATES
51PROJECTS
OF LEVEESAND BANK PROTECTION
M I L E S
33%
OFSTORED
TEXAS
SURFACE
WATER
OFLAND AND WATER
9.6M A C R E S
�170B
IN DAMAGESPREVENTED
2.6MACRES
OFREAL PROPERTY
MANAGED
CIVIL AND MILITARY
REALESTATEINSTRUMENTS4,462MANAGED
7400 �824MREAL PROPERTY ITEMS
MANAGED VALUEDAT
350RECRUITING LEASES
MANAGED
ANNUAL
ACROSS
ECONOMICIMPACT�46.2M COMMUNITIES
POWERPLANTS
USACE OPERATED NON-FEDERAL
3 2
MEGAWATT
GEN E RA TI N G
C A P A C I T Y
593HURRICANE/
WILDFIRE
VOLUNTEERS SINCE ‘16
EVENTS SINCE ‘1043EMERGENCY
OCONUSRESPONSE
AND DEPLOYMENTS SINCE ‘10 122
1892PER
AUTHO
FY
PERMIT
RIZATIONS
16OUTREACH
EFFO RTS
184COMPLIANCE
AND ENFORCEMENTACTIONS
CAMPSITES
�7.9M �3.5B
FEE REVENUE
STATE AND LOCAL
REVENUE
SUPPORTS
�400M
IN
ENVIRONMENTAL
PROJECTS
HQ - USACE
SWD
SWT SWF SWG SWL
EC OPS RE OC ECSO
ORG CHART
FOOTPRINT
CT PPMD RPEC
EC ENGINEERING &
CONSTRUCTION
OPS OPERATIONS
CT CONTRACTINGPPMD PROGRAMS AND PROJECT MANAGEMENT DIVISION
RPEC REGIONAL PLANNING AND ENVIRONMENTAL
CENTER
RE REAL ESTATE
OC OFFICE OF COUNSEL
ECSO ENGINEERING CONSTRUCTION SUPPORT OFFICE
CIVIL WORKS BOUNDARIES
MILITARY AND INTERAGENCY
BOUNDARIES
CONTACT
819 TAYLOR ST.
FORT WORTH, TX 76102
CORNERSTONE OF THE SOUTHWEST
Fort Worth Central City
Wharton Levee Westside CreekLewisville Dam Safety Modification
Dallas Floodway & Extension
CIVIL
WORKS
DATA CURRENTAS: 6 JUNE 25
Western Currency Center (BEP)
El Paso VA Health Care CenterFort Sam Houston VA Cemetery
Border Wall Construction
USDA Research Facilities
INTERNATIONAL
AND INTERAGENCY SUPPORT
Arlington Cemetery Project
Fort Cavazos Barracks #100 Fort Cavasas Motor Pool
JBSA Unaccompanied Barracks RRAD B551/561 Renovation Fort Johnson TEMF
Fort Johnson Railroad Project
JBSA Aquatics Center
MILITARY
CONSTRUCTION
Fort Johnson North Fire Station
O U R M I S S I O N The Fort Worth District provides vital public engineering services, in peace and war, to strengthen our
Nation’s security, energize the economy, and reduce risks from disasters.
817.886.1515 EXECUTIVEOFFICE
817.886.1306 PUBLICAFFAIRS
www.swf.usace.army.mil
FUDS FORMERLY USED DEFENSE SITES
CESU COOPERATIVE ECOSYSTEM STUDIES UNIT
MASTER PLANNING
REGIONALPLANNING
ANDENVIRONMENTALCENTER
HYDROPOWER
EMERGENCY
MANAGEMENT
RECREATION
REGULATORYREAL
ESTATE
INTERNATIONAL
ANDINTERAGENCYSUPPORT
PROVIDING TECHNICAL ASSISTANCE
TOFEDERALAGENCIES, STATE
AND LOCALGOVERNMENTS,TRIBAL
NATIONS AND PRIVATE U.S. FIRMS
BUREAU OFENGRAVING PRINTING
DEPARTMENTOF VETERAN AFFAIRS
NATIONAL CEMETARYADMINISTRATION
DEFENSELOGISTICSAGENCY
TRANSPORTATION SECURITYADMINISTRATION
U.S. CUSTOMSAND BORDER PROTECTION
IMMIGRATIONAND CUSTOMSENFORCEMENT
CIVIL
WORKS
MILITARY
CONSTRUCTION
Fort Bliss THAAD Renovation
EST. 1950
http://www.swf.usace.army.mil/
FORT BLISS
Ellis
Parker
SWGSWGGALVESTON DISTRICT
PINEY
WOODS
REGION
LITTLE ROCK DISTRICT
RIO GRANDE RIVER BASIN
COLORADO RIVER BASIN
GUADALUPE RIVER BASIN
NUECES RIVER BASIN
BRAZOS RIVER BASIN
SAN JACINTO RIVER BASIN
TRINITY RIVER BASIN
NECHES RIVER BASIN
SABINE RIVER BASIN
CYPRESS CREEK BASIN
SULPHUR RIVER
BASIN
RED RIVER BASIN
FORT HOOD
DYESS AFB
GOODFELLOW AFB
CAMP MABRY
CAMP SWIFT
LAUGHLIN AFB
CAMP BOWIE
FORT POLK
BARKSDALE AFB
RED RIVER ARMY DEPOT
TINKER AFB
VANCE AFB
NAS CORPUS CHRISTI
NAS KINGSVILLE
FORT SILL
25 10
SOUTHWEST AREA OFFICE
FORT Johnson PROJECT OFFICE
LITTLE ROCK AFB
TULSA DISTRICT
JBSA - CAMP BULLIS
NUECES RIVER BASIN
CAMP STANLEY
JBSA – LACKLAND AFB
JBSA – RANDOLPH AFB
JBSA – FORT SAM HOUSTON
SAN ANTONIO RIVER BASIN
GUADALUPE RIVER BASIN
CANYON LAKE
JBSA - MARTINDALE AAF
LACKLAND RESIDENT OFFICE
SAN ANTONIO AREA OFFICE
San Antonio
JBSA - KELLY FIELD
ATLUS AFB
CAMP MAXEY
MCALESTER ARMY AMMUNITION PLANT
BRAZOS RIVER BASIN
FORT WORTH DISTRICT
SULPHUR RIVER BASIN
SABINE RIVER BASIN
BENBROOK LAKE
TRINITY RIVER BASIN
JOE POOL
LAVON LAKE
LEWISVILLE LAKE
BARDWELL LAKE
TRINITY REGIONAL OFFICE
Fort Worth
FORT WORTH NAS JRB
GRAPEVINE LAKE
Dallas
ALBUQUERQUE
DISTRICT
HOLLOMAN AFB
AQUILLA #22 (1983)
HORDS CREEK #1 (1948)
OC FISHER #4 (1952)
NAVARRO MILLS #12 (1963)
WACO #15 (1965)
PROCTOR #13 (1963)
WHITNEY #3 (1951)
WHITE SANDS MISSILE RANGE
KIRTLAND AFB
Hoooodd
Hililll
Soomeerrvveellll
Boossqquuee
SHEPPARD AFB
CANNON AFB
JBSA
FORT WORTH DISTRICT
SOUTHWESTERN DIVISION
THREE RIVERS
REGION
CAPITAL REGION
BELTON #8 (1954)
GRANGER #20 (1980)
CANYON #14 (1964)
STILLHOUSE #19 (1968)
GEORGETOWN #21 (1980)
SOMERVILLE #18 (1967)
TRINITY
REGION
JOE POOL #23 (1985)
LEWISVILLE #9 (1954)
BARDWELL #17 (1965)
GRAPEVINE #5 (1952)
LAVON #7 (1953)
RAY ROBERTS #24 (1987)
BENBROOK #6 (1952)
COOPER DAM #25 (1991) LAKE O’ THE PINES #11 (1959)
WRIGHT PATMAN #10 (1956)TOWN BLUFF #2 (1951)SAM RAYBURN #16 (1965)
VICKSBURG DISTRICT
NEW ORLEANS
DISTRICT
SAN ANTONIO RIVER BASIN
LOWER RIO GRANDE RIVER VALLEY
AGENDA
Time Topic 9:00 AM - 9:15 AM Introduction/Opening Remarks 9:15 AM - 9:20 AM Safety Moment 9:20 AM - 9:50 AM Tarrant Regional Water District Central City Overview & Non-Federal Sponsor Perspective Doing Work with TRWD 9:50 AM - 10:20 AM City of Fort Worth Central City Opportunities Doing Work with the City of Fort Worth 10:20 AM - 11:30AM U.S. Army Corps of Engineers Central City: Program Overview, Industry Engagement, & Opportunities Dallas Floodway: Program Overview, Industry Engagement & Opportunities Doing work with USACE 11:30 AM – 12:00PM Wrap Up 12:00 PM - 1:00 PM Lunch 1:00 PM - 3:00 PM Networking Session and Project Feature Booths
TARRANT REGIONAL WATER DISTRICT
Kate Beck, P.E.
Program Director, Central City Flood Control Project
TRWD
CITY OF FORT WORTH
Dana Burghdoff Assistant City Manager
City of Fort Worth
SAFETY MOMENT
Julie Franco Safety and Occupational Health Specialist
HOW TO GET A CODE A ON YOUR FIRST SUBMITTAL
• Ensure you address everything in the APP or Site-Specific Plan per the EM 385-1-1
• Have all supporting documentation:
• Certifications
• Cut sheets
• Training records
• Resumes
• OM’s
• Load Charts
• Do not include information that will not be apart of that phase of work.
TARRANT REGIONAL WATER DISTRICT (TRWD)
Central City Overview & Non-Federal Sponsor Perspective Central City Small Business Program Overview, Tracking & Resources
Matt Oliver Public Information Officer
TRWD
Claudia Guerrero Contract Administrator
TRWD
Industry day
Central City Flood Control Project
What is the central city flood control project?
The Central City Flood Control Project is a proactive approach to flood control. The project addresses Fort Worth’s flood risks that are a result of explosive population growth with the city having tripled in size since the current levee system was constructed in the 1960s.
The Central City Flood Control Project has two main components:
• The rerouting of a section of the Trinity River due north of downtown (bypass channel).
• Modifying a large park on the east side of the city (Gateway Park) to better manage flood events in a manner that will also restore the area.
• Levee project of 1957 designed for 1960 population of 350,000
• Growth in Tarrant, Parker and Wise counties contributing to drainage problems
• Impervious developments contributing to drainage problems
• 2003: 86% of Fort Worth’s levees no longer adequate (USACE Central City Interim Feasibility Study)
• Fort Worth is now over 1,000,000 people! 11th Largest in U.S.
100,000 200,000 300,000 400,000 500,000 600,000 700,000 800,000 900,000
1,000,000
1960 1970 1980 1990 2000 2010 2019
Fort Worth Population
Gateway Park June 14, 1989
WATER
SUPPLY
CONSERVATIONFLOOD
PROTECTION RECREATIONWHAT WE DO:
Tarrant Regional Water District is a government entity committed to providing reliable, sustainable water supply, flood protection, recreational opportunities, and conservation in the North Texas region.
Doing Business with TRWD Types of Opportunities
TRWD offers a wide variety of vendor opportunities:
Infrastructure Engineering Services
Environmental
General Construction
Professional Services Consulting
Operations
Water Resources
Facilities
VENDOR
OPPORTUNITIES
Doing Business with TRWD Diverse Business Goals
DIVERSE
BUSINESS
TRWD is committed to promoting full and equal opportunity for all businesses to supply the goods and services needed to support the mission and operations of TRWD and seeks to encourage the participation and use of certified historically underutilized businesses.
Certifications we accept:
M/WBE
HUB
SBE
DBE
Visit us at www.trwd.com and select “vendors” under the “Work With Us” menu. VENDOR
REGISTRATION
Doing Business with TRWD Vendor Registration
Large chart or graph http://www.trwd.com/
Scroll down to select “register“ to be routed to OpenGov where you can register to be a vendor.
You can also select the hyperlink below for more information about registering with OpenGov.
VENDOR
REGISTRATION
Doing Business with TRWD Vendor Registration
Scroll down further on the vendor page to see current bid opportunities. CURRENT
OPPORTUNITIES
Doing Business with TRWD Current Opportunities
CITY OF FORT WORTH
Central City Opportunities Doing Work with the City of Fort Worth
Clair Davis, P.E., CFM Senior Capital Projects Officer City of Fort Worth
Central City Opportunities
Ongoing Utility Relocations The City, in partnership with TRWD and USACE, is working to clear the bypass channel in preparation for construction North Bypass Channel
Storm Drainage System: 3 ongoing relocations under construction
Sanitary Sewer and Water System: 1 ongoing relocation under construction
South Bypass Channel Storm Drainage System: 2 ongoing relocations under construction Sanitary Sewer and Water System: 3 ongoing relocation under construction Franchise Utilities: coordinating Oncor, AT&T, and Atmos relocations
Central City and TRV TIF 9
Water and Sanitary Sewer Projects
Part 13 – Channel Segment D (NTP 2) Water and Sanitary Sewer Relocations – 12/25
University Drive
Local Street Modifications
Part 3 - Bypass Channel Segment D
Part 4 - Bypass Channel Segment A
Part 2 - Bypass Channel Segment B
G R
EEN
LEA
F
DAKOTA
KANSAS
A R
TH
U
R
C O
M M
ER
C
IA
L
LEGEND
Proposed Street Vacate
Proposed Local Street
LEGEND
Proposed Street Vacate
Proposed Local Street
R U
PER
T
Central City Opportunities
University Drive Utility Relocations (multiple) University Drive Access Road Construction Gateway/Oxbow Ecosystem Restoration Utility Relocation(s) Local Street Modifications Clear Fork Isolation Gate Water and Sanitary Sewer Relocations Beach Street 54” water line
Doing Work with the City of Fort Worth
Doing Work for the City of Fort Worth https://www.fortworthtexas.gov/departments/finance/purchasing/online-bidding-platform
USACE
Central City and Dallas Program Overview, Industry Engagement, & Opportunities
Donovan Blakeley, P.E.
Program Manager
FORT WORTH CENTRAL CITY
Donovan Blakeley, PE Program Manager
U.S. Army Corps of Engineers
Date: 09 July 2025
CENTRAL CITY FLOOD RISK MANAGEMENT PROJECT SUMMARY
Background:
Fort Worth floods in 1922, 1949, and 1989 basis for study Levee project of 1957 designed for 1960 population of 350,000; population is now near 1,000,000 and growing Growth in Tarrant, Parker and Wise Counties and impervious developments are contributing to drainage problems Project levee and floodwall designed to Standard Project Flood (SPF)+4 feet
Purpose:
To provide continued flood protection for the citizens and properties within the City and the 2,400 acres of established
Fort Worth neighborhoods Restores the design level of flood protection to the existing system by realigning the river and adding closure gates
Authorization:
2005 Energy and Water Appropriations Act authorized program as described in the 2003 Trinity River Master Plan 2016 Water Infrastructure Improvements for the Nation increased project scope and cost
Non-Federal Sponsor:
Tarrant Regional Water District
Original Authorization:
2005 Energy and Water Appropriations Act
Original PPA:
Executed 5 Sep 2008 FRM (Cost Share 50/50)
Features Include:
Bypass Channel Valley Storage 2 Isolation Gates Marine Creek Dam & Channel Expansion
Reauthorization:
2016 Water Infrastructure Improvements for the Nation Amended PPA:
Executed 19 Jan 2021 FRM (Cost Share 65/35) ER (Cost Share 65/35) REC (Cost Share 50/50) Features Include:
Bypass Channel Valley Storage 3 Isolation Gates Marine Creek Dam & Channel Expansion Samuels Avenue Dam Pump Station Pedestrian/Maintenance Bridges Ecosystem Restoration Interior Water Feature (Recreation Only)
PPA = Project Partnership Agreement FRM = Flood Risk Management ER = Ecosystem Restoration REC = Recreation
PROJECT AUTHORIZATION
HISTORY
MODIFIED CENTRAL CITY PROJECT PHASING
Bypass Channel North Channel South Channel Trinity Point, Clear Fork, and Tarrant
Regional Water District (TRWD) Isolation Gates
TRWD Pump Station Valley Storage (5,250 acre-ft) 6 primary sites completed (Samuels, Riverside Park, Ham Branch, Site A, Site C, and Site H)
4 primary sites remaining 3 contingency sites identified (not shown) Dams Samuels Ave Lock and Dam Marine Creek Dam and Channel
Expansion Aquatic Habitat Mitigation Sycamore Creek (Site A) Ham Branch Ecosystem Restoration Rockwood Park Ecosystem
Restoration Gateway Oxbow Ecosystem
Restoration (not shown) Pedestrian and Maintenance Bridges North and South Bypass Pedestrian
Bridges (not shown) West Fork Maintenance Bridge
Samuels Avenue/Marine Creek Dams & Marine Creek Expansion
Samuels Avenue Valley Storage
Riverside Park Valley Storage
Ham Branch Valley Storage
Site A Valley Storage
Site C Valley Storage Site E Valley
Storage
Site H Valley Storage
Site K Valley Storage
Rockwood Park Valley Storage
Rockwood Park Ecosystem Restoration
University Drive Valley Storage
South Bypass Channel
Clear Fork Gate
Trinity Point Gate
North Bypass Channel
TRWD Gate & Pump Station
West Fork Maintenance Bridge
Remaining Upstream Valley Storage Remaining Downstream Valley Storage
Channel is constructed over 6-7 phases to avoid inducing H&H impacts to valley storage
FLOOD RISK MANAGEMENT
COMPLETED VALLEY STORAGE SITES
Samuels Avenue Valley Storage
Riverside Park Valley Storage
Ham Branch Valley Storage
Site A Valley Storage
Site C Valley Storage
Site H Valley Storage
MITIGATION: HAM BRANCH & SYCAMORE CREEK
AQUATIC HABITAT
Design Funded? Yes (BIL)
Construction Funded? Yes (BIL)
Status Issued Phase 2 RFP
Next Major Milestone Final Design
Ham Branch Aquatic Habitat Mitigation
Implementation Funded? Yes
Status
Plantings completed by Lewisville Aquatic Ecosystem Restoration Facility (LAERF)
Sycamore Creek Aquatic Habitat Mitigation
Ham Branch Aquatic Habitat Mitigation
Sycamore Creek (Site A) Aquatic Habitat Mitigation
PROJECT SEQUENCING ROADMAP
NORTH BYPASS CHANNEL – PHASE 1
Design Funded? Yes (BIL)
Construction Funded? Yes
Status Solicitation
Next Major Milestone Award
Magnitude of Construction
(DFAR 236.204)
Between $100,000,000 and $250,000,000
Temporary Levee
Temporary Levee
Partial Tie-In A
Hard Edge
Soft Edge
SOUTH BYPASS CHANNEL INTERIOR
Design Funded? Yes (BIL)
Construction Funded? Partially
Status 60% Design Reviewed
Next Major Milestone 95% Design Submittal
Magnitude of Construction
(DFAR 236.204)
Between $100,000,000 and $250,000,000
Soft Edge
Hard Edge
UPSTREAM VALLEY STORAGE – PHASE 1
Design Funded? Yes (BIL)
Construction Funded? Yes
Status 30% Design Reviewed
Next Major Milestone 60% Design Submittal
Magnitude of Construction
(DFAR 236.204)
Between $25,000,000 and $100,000,000
Rockwood Park Valley Storage
University Drive Valley Storage
Tie-In B
TRINITY POINT GATE & TIE-IN
Trinity Point Gate
Tie-In C
Design Funded? Yes (FY23 Workplan)
Construction Funded? No
Status 15% Design Completed
Next Major Milestone 30% Design Submittal
Magnitude of Construction
(DFAR 236.204)
Between $25,000,000 and $100,000,000
CLEAR FORK GATE & TIE-IN
Design Funded? Yes (BIL & FY23 Workplan)
Construction Funded? No
Status 15% Design Completed
Next Major Milestone 30% Design Submittal
Magnitude of Construction
(DFAR 236.204)
Between $25,000,000 and $100,000,000
Clear Fork Gate
Tie-In D
TRWD GATE & PUMP STATION
Design Funded? Yes (FY23 Workplan)
Construction Funded? No
Status 15% Design Completed
Next Major Milestone 30% Design Submittal
Magnitude of Construction
(DFAR 236.204)
Between $25,000,000 and $100,000,000
TRWD Gate & Pump Station
DAMS
Design Funded? Yes (FY24 Workplan)
Construction Funded? No
Status Updating Schedule & Budget
Next Major Milestone Design Start
Magnitude of Construction
(DFAR 236.204)
Between $25,000,000 and $100,000,000
Samuels Avenue/Marine Creek Dams & Marine Creek Expansion
FINAL TIE-IN
Design Funded? Yes (BIL)
Construction Funded? No
Status 100% Design Reviewed
Next Major Milestone Ready to Advertise
Magnitude of Construction
(DFAR 236.204)
Between $10,000,000 and $25,000,000
Final Tie- In A
DOWNSTREAM VALLEY STORAGE
Design Funded? No
Construction Funded? No
Status Awaiting TRWD Site Preparation
Next Major Milestone 90% Design Submittal
Magnitude of Construction
(DFAR 236.204)
Between $10,000,000 and $25,000,000
Site E Valley
DOWNSTREAM VALLEY STORAGE
Design Funded? Yes
Construction Funded? No
Status Updating Schedule & Budget
Next Major Milestone Design Start
Magnitude of Construction
(DFAR 236.204)
Between $1,000,000 and $5,000,000
Site K Valley
MAINTENANCE BRIDGE
Design Funded? Yes (FY24 Workplan)
Construction Funded? No
Status 30% Design Reviewed
Next Major Milestone 60% Design Submittal
Magnitude of Construction
(FAR 36.204)
Between $5,000,000 and $10,000,000
West Fork Maintenance Bridge
ECOSYSTEM RESTORATION
ROCKWOOD PARK
Rockwood Park Ecosystem Restoration
Design Funded? Yes (FY24 Workplan)
Construction Funded? No
Status Updating Schedule & Budget
Next Major Milestone Design Start
Magnitude of Construction
(FAR 36.204)
Between $1,000,000 and $5,000,000
ECOSYSTEM RESTORATION
GATEWAY/OXBOW
Design Funded? Yes (FY24 Workplan)
Construction Funded? No
Status Updating Schedule & Budget
Next Major Milestone Design Start
Magnitude of Construction
(DFAR 236.204)
Between $25,000,000 and $100,000,000
*Includes City of Fort Worth Master Plan elements not included in Central City project
FEATURE STATUS
Feature Name Design Status Construction Status
North Bypass Channel Completed Acquisition Process North Bypass Channel Tie-In B Completed FY28 University Drive Valley Storage and Rockwood Park Valley Storage 35 % Design FY28 South Bypass Channel 60% Design FY27* South Bypass Channel Tie-In C & Trinity Point Isolation Gate 15% Design TBD* South Bypass Channel Tie-In D & Clear Fork Isolation Gate 15% Design TBD* TRWD Isolation Gate & Pump Station 15% Design TBD* Samuel Avenue & Marine Creek Dams AE Acquisition Ongoing TBD* North Bypass Change Tie-In A 90% Design TBD*
Site E Valley Storage TBD TBD* Site K Valley Storage AE Acquisition Ongoing TBD* West Fork Maintenance Bridge 60% Design TBD* Gateway Oxbow Ecosystem Restoration AE Acquisition Ongoing TBD* Rockwood Park Ecosystem Restoration AE Acquisition Ongoing TBD*
* - Pending receipt of funding and further construction sequence analysis
Dallas Floodway System Program Overview & Forecasted Opportunities
Mark Herrmann, P.G., PMP Program Manager
FORT WORTH DISTRICT
DALLAS FLOODWAY LEVEE SYSTEM
FORECASTED OPPORTUNITIES
Mark E. Herrmann, P.G., PMP Program Manager United States Army Corps of Engineers
Presentation for:
Fort Worth Industry Day Date: July 8, 2025
City of Dallas
LET’S PRIME THE PUMP
AI JOKE
Why did the dam and the levee break up?
Because the dam said, “You’re too controlling!” and the levee replied……
“At least I don’t’ crack under pressure!”
250 YEARS OF SERVICE
AGENDA & PURPOSE
Purpose: Generate awareness, enthusiasm, and strategic planning insight among this room of premier general contractors and industry partners for the forthcoming Dallas Floodway System, Hampton 3 Pump Station; the pinnacle pump station remaining for construction.
XDecision Guidance Recommendation Information
Agenda:
1. Dallas Floodway Program Summary
2. Hampton 3 Contract Details
3. Hampton 3 Scope Considerations
4. Successful Offeror Tips
5. Successful Execution Tips
6. Closing
** All Information is subject to change as the Program is further developed. **
DALLAS FLOODWAY PROJECT OVERVIEW
Flood Risk Management Portion
• AT&SF Bridge Modification
• 277K cfs Levee Raise & Slope Flattening
• Charlie Pump Station
• Delta Pump Station
• Nobles Branch Sump Improvements
• Hampton 3 Pump Station
• Trinity Portland Pump Station
• New Hampton Renovation
• Old Hampton Demolition
Authorization for Dallas Floodway by WRDA 2007, PL 110-114, Section 5141
Ecosystem Restoration
• River Relocation (add meanders to approx.
8 miles of the Trinity River in the Floodway)
• Approx. 80 acre wetland in Floodway
277K Levee Raise Complete
Hampton PS Pre-Solicit
Trinity Portland PS Pre-Solicit
Delta PS In Construction
Charlie PS In Construction
Nobles Branch Sump In Construction
AT&SF Bridge Complete
Color Code Complete In Construction Solicitation
DALLAS FLOODWAY VIDEO
HAMPTON 3 PUMP STATION
OVERVIEW
Contractor Name: TBD Designer of Record: Arcadis Non-Federal Sponsor: City of Dallas Program Manager: Mark Herrmann Lead Engineer: Sarwenaj Ashraf Contracting Officer: Carl Oelschig Contracting Specialist: Alexander Rust
CONTRACT INFORMATION
Acquisition: Unrestricted / Full & Open Solicitation Type: Design-Bid-Build RFP NAICS: 237990 – Heavy Civil Period of Performance: ~48 Months Advertise: Jan 2026 Bid Opening: Mar 2026 Award: Sep 2026 NTP Construction: Oct 2026 Project Complete: Jan 2031 Options: None
PROJECT SUMMARY
A Design Bid Build contract, the project includes construction of a new Hampton 3 Pump Station which will comprise five concrete volute pumps capable of 140K GPM each discharging via 84” steel discharge pipes over the levee. One 10K GPM low flow pump with new outfall canal will be constructed to convey discharge to the Trinity River.
Utility relocations and coordination, drilling thru levees, instrumentation planning and monitoring, temporary flood protection measure implementation, among other ancillary items will be needed to successfully deliver the project.
Contract Magnitude: $100M – $150M
HAMPTON 3 PUMP STATION CONCEPTUAL
Site Considerations
• Two adjacent pump stations in operation
• Pedestrian recreators in floodway
• Winter & Spring flood chances
• Variable stratigraphy and groundwater conditions
HAMPTON 3 PUMP STATION SEQUENCING
Sequencing Considerations
• Utility Relocations
• Intake channel box culverts and diversion
• Factory testing and inspection of pumps prior to shipping with matchmarks to project site
SUCCESSFUL OFFERORS TIPS
DO your homework. Review fact sheets and know your capabilities. Plan for long lead items/market conditions.
DO respond to Sources Sought opportunities during market research phase. Update SAM regularly.
DO sharpen your pencils – Incumbents are not automatically the winners. Searching for best value!
DO register with the SWF Small Business. Attend SWF Small Business Industry Day in the Spring.
DO read the RFP and ask questions. When in doubt, ask a RFI or bidder inquiry in DrChecks. In some cases, a call to the Contracting Officer is appropriate.
DO ask for a debrief – This could impact your CPARS going forward.
DON’T use blast email hoping to reach the right person.
DON’T overextend yourself. Do not take on work that you cannot do well or inexperienced. It could hurt you going forward in your CPARS.
DON’T play with the math – Do not plan to bid low and make it up using modifications.
DON’T be afraid to leverage your Contracting Officer or Alternate Contracting Officer.
SUCCESSFUL EXECUTION TIPS
Partnering for success: Familiarity and application of EP 34-1-1; Alignment of subs with project specifications, shared risk register, streamlined decision making in field office
Labor Compliance & Certified Payroll: Usage of approved electronic payroll software (EMARS, LCP Tracker);
Prime to Subs payment w/in 7 days of receipt from government; Redundant personnel to access/process payroll system
Buy American Act--Construction Materials: Only the Contracting Officer (not ACO) can approve a waiver/deviation. Notify the Government ASAP if something is non-compliant. (FAR 52.225-9)
Texas Pollutant Discharge Elimination System (TPDES) is required for this job. Needs to be submitted to the state. Application reviewed thru USACE Environmental.
Resident Management System (RMS) proficiency including but not limited to correspondence, Requests for Information, Submittals, Daily Reports, Deficiency Tracking, Insurance, and Payment Requests.
QUESTIONS?
Dallas Floodway Dallas Floodway ExtensionSWF SBA
Small Business Programs Overview, Industry Engagement, & Opportunities
Doing Work with USACE
Ali Marshall Deputy, Office of Small Business Programs
Industry Day Central City & Dallas Floodway
Office of Small Business Programs Fort Worth District (SWF) U.S. Army Corps of Engineers http://go.usa.gov/xPQUK http://go.usa.gov/xPQUK
How may we serve you
Advocate Assure Small Business (SB) are given fair opportunity and consideration in procurements
Inform Forecast Opportunities, Acquisition Strategy, Outreach Events
Counsel Capability Statement Improvements Experience, Contract Number, $ Amount, Prime/Sub-Contractor, Performance Rating, Certification SBA’s DSBS Profile Improvements Capability Statement LINK, Keywords, Performance Area, Bonding Increases, Update Experience
Assist Encourage Industry Response: Sources Sought, PLA Survey, RFI, Participation, Subcontracting District Staff with Market Research / Acquisition Strategy (Recommend SB for procurements)
Review Acquisition Plans, SB Coordination Records, SB Participation & SB Subcontracting Plans
Marketing to SWF USACE
Capability Statement Improvement Suggestions
1. Type of Work Experience: General Construction, Civil, Horizontal, etc.
2. Contract Number: Include
3. $ Amount: Include $ amount / $ amount performed as subcontractor
4. Prime or Sub-Contractor: Did you perform as Prime or Subcontractor?
5. Performance Rating: How well did you perform (CPARS / PPQ)
6. Primary NAICS code(s): 237990, 237310, etc.
7. SBA Certified: 8(a), HUBZone, SDVOSB, WOSB (must appear SAM.gov Profile)
Capability Briefing (Power Point) Improvement Suggestions
1. UEI and CAGE (as appears on SAM.gov profile)
2. Primary NAICS code(s)
3. SBA Certifications (must be federal recognized by SBA & appear on SAM.gov)
4. POC Email address & phone number
5. General SOW, Contract # / YR, $ Amount, Customer Ex: 2024 Road Repairs, W9126G24C0123, USACE Tulsa, $3.4M
Marketing Continued
SBA’s DSBS Profile Improvement Suggestions
1. Capabilities Statement LINK: Upload and ensure operational
2. SBA Federal Certifications: 8(a), HUBZone, SDVOSB, WOSB (SBA Certified)
3. Narrative: General construction DB, DBB, primarily civil horizontal … Narrative continued: Include geographical area or states … TX, LA, or North TX
4. Bonding: Update Bonding when Increased
5. NAICS: 237990, Other Heavy & Civil Engr Construction, 236220, 237110, 237310, etc.
6. Keywords: Site prep, Haul dirt, drainage, paving, concrete, demo, excavation, grading, erosion control, debris removal, water/sewer line, electrical utilities installation, Hwy, road, bridge construction, civil, federal, etc. (HVAC, SCIF)
7. Performance History (Experience): Update recent
Project Labor Agreements (PLA)
Head of the Contracting Activity (HCA) has delegated authority to grant an exception from the requirements at FAR 22.503(b) which requires the use of PLAs on large-scale construction projects ($35M), signed 12 June 2025.
FAR allows agency discretion to grant an exception where market research indicates that competition would be hindered by lack of offerors or lack of competitive pricing.
https://www.whitehouse.gov/wp-content/uploads/2025/02/M-25-29-Use-of-Project-Labor-Agreements-on-Federal-Construction- Projects-Amendments-to-OMB-Memorandum-M-24-06.pdf
What does this mean?
Contracting Officer issues Special Notice, PLA Survey, and or RFI, requesting industry feedback on the use of PLA for each specific project.
PLEASE RESPOND
Your response is our Market Research Justification
No guarantee, however, industry feedback MAY grant an exception to PLA in solicitation https://www.whitehouse.gov/wp-content/uploads/2025/02/M-25-29-Use-of-Project-Labor-Agreements-on-Federal-Construction-Projects-Amendments-to-OMB-Memorandum-M-24-06.pdf https://www.whitehouse.gov/wp-content/uploads/2025/02/M-25-29-Use-of-Project-Labor-Agreements-on-Federal-Construction-Projects-Amendments-to-OMB-Memorandum-M-24-06.pdf
AFAR Update ~ AS3
Army Federal Acquisition Regulation (AFAR) updated Dec 2024 Appendix – AA, ARMY SOURCE SELECTION SUPPLEMENT (AS3) https://www.acquisition.gov/afars/appendix-aa-table-contents
Three significant updates:
1. Past Performance
Allows Contracting Officer discretion to determine how far back past performance may go & should be used …
* Large & Complex Construction, may be appropriate to extend the time period considered for past performance to more than 6 years to obtain realistic examples.
2. SBA Certified
* Under SB Participation Factor: Proposals including HUBZone, VOSB, SDVOSB, and WOSB percentages must ensure those socio-economic category submissions are SBA Certified.
Impact may be that they are not counted towards SB Participation / SB Subcontracting Plan Goals.
3. Commitment Letter
If commitment letter is not signed by BOTH the prime and subcontractor the evaluation team is NOT to evaluate or consider the subcontractor's reference.
https://www.acquisition.gov/afars/appendix-aa-table-contents
SBA Bona Fide Office Rule
SBA Reinstates Rule to Return Federal Contractors to Work COVID-Era Moratorium on Physical Office Requirement for 8(a) Program Will End September 30
Published on June 17, 2025
What does this mean?
Effective October. 1, 2025, construction contractors that are 8(a) Certified, in SBA’s 8(a) Business Development Program, will be required to have an actual, physical office within the geographic area where the construction work is being performed (Place of Performance) in which they are bidding on federal construction contracts.
DON’T PANIC … We have a solution
* Derek Gadberry, SBA PCR, will discuss in further detail below
OSBP Website Updates
Launch of Opportunity Forecast Report
OSBP Website Updates - FAQ
1. Calculation Excel Spreadsheet: How to calculate percentages % Calculations Formula - SB Participation & SB Subcontracting Plan
2. FAR 19.704 Subcontracting Plan Requirements: Include 15 required Elements
3. DoD Checklist for reviewing SB Subcontracting Plans
4. In accordance with AFARS Subpart 5119.705-4 Reviewing the Subcontracting Plan (d)(ii)
(ii) Plans are not acceptable if they do not adequately address the subcontracting plan requirements at FAR 19.704, DFARS 219.704, and AFARS Appendix DD. If the plan is still rated unacceptable after clarifications or discussions, the offeror shall be ineligible for contract award.
* Ensure detailed efforts, explanations, justifications are addressed for proposed goals
Office of Small Business Programs
View Forecast, Events, and FAQ’s How to Request Capability Briefing (LB must include SB)
Office of Small Business Programs, Fort Worth District WEBSITE
Please review Website for requesting Capability Briefing
Small Business Set-Aside Self-Certified SB Joint Venture-Identified in SAM.gov
8(a) Program Set-Aside SBA-Certified Sole Source not exceed $4.5M for services Sole Source to ANC/NHO/Tribal up to $100M
HUBZone Set-Aside SBA-Certified Sole Source not exceed $4.5M for services
Service-Disabled Veteran-Owned Set-Aside SBA-Certified Sole Source not exceed $4.5M for services
Women-Owned Set-Aside or Economically-Disadvantaged, WO Set-Aside SBA-Certified Based on NAICS Code: WO: 236, 237, 541 & 562 / EDWO: 238 Sole Source not exceed $4.5M for services https://www.acquisition.gov/far/part-19 https://www.acquisition.gov/far/part-19 https://www.acquisition.gov/far/subpart-19.13 https://www.acquisition.gov/far/subpart-19.14 https://www.acquisition.gov/far/subpart-19.15 https://www.sba.gov/document/support-eligible-naics-women-owned-small-business-federal-contracting-program https://certify.sba.gov/
Market Research Determines Acquisition Strategy
Competitive OR Sole Source ~ Socio-Economic SB Set-asides:
• 8(a) Program (Preferred sole source method)
• HubZone
• SDVOSB
• WOSB
NO Order of Precedence (Determined by Market Research)
1. 8a, HZ, SDVOSB or WOSB socio-economic set-asides
2. SB Set Aside
3. SB MATOC (Multiple Award Task Order Contract)
4. UR MATOC (Unrestricted with SB Reserves)
5. Full & Open Competition / Unrestricted (UR)
Be Prepared for Solicitation
SAM.gov = Keep profile Active and Updated (Bonding $) www.sam.gov
APEX Accelerator = Become a client. Join Email List. Subcontractor Resource.
https://www.apexaccelerators.us/#/service-area-locator
Certify.SBA.gov = New application for SBA federal contracting certifications.
Must be federally recognized by the Small Business Administration
If you’re 8(a), HUBZone, VOSB, SDVOSB, and or WOSB SBA Certified must appear on SAM.gov profile
Learn more at https://certify.sba.gov/ http://www.sam.gov/ https://www.apexaccelerators.us/#/service-area-locator https://certify.sba.gov/
Central City (CC) Opportunities
Contracting Method Set Aside Location Project Name Range NAICS Advertisement
Period
Competitive Request for Proposal - One Step
(Full Design) Unrestricted Forth Worth, TX CC, Upper Trinity River Basin, North
Bypass Channel – Phase 1 $100-250M 237990 FY25 Q3
Competitive Request for Proposal - One Step
(Full Design) Unrestricted Fort Worth, TX CC, South Bypass Channel Interior $100-250M 237990 TBD
Competitive Request for Proposal - One Step
(Full Design) Unrestricted Fort Worth, TX CC, Upstream Valley Storage –
Phase 1 $25-100M 237990 TBD
Competitive Request for Proposal - One Step
(Full Design) Unrestricted Fort Worth, TX CC, Trinity Point Gate & Tie-In C $25-100M 237990 TBD
Competitive Request for Proposal - One Step
(Full Design) Unrestricted Fort Worth, TX CC, Clear Fork Gate & Tie-In D $25-100M 237990 TBD
* Subject to change
Name Range NAICS Advertisement
Period
Competitive Request for Proposal - One Step
(Full Design) Unrestricted Fort Worth, TX CC, TRWD Gate & Pump Station $25-100M 237990 TBD
Competitive Request for Proposal - One Step
(Full Design) Unrestricted Forth Worth, TX
CC, DAMS (Samuels Avenue / Marine Creek Dams & Marine
Creek Expansion
$25-100M 237990 TBD
Competitive Request for Proposal - One Step
(Full Design)
Small Business Set-aside Forth Worth, TX CC, Final Tie-In A $10-25M 237990 TBD
Competitive Request for Proposal - One Step
(Full Design)
Small Business Set-aside Forth Worth, TX CC, Downstream Valley Storage –
Phase 1 $10-25M 237990 FY28
TBD
(Full Design)
Small Business Set-aside Forth Worth, TX CC, Downstream Valley Storage –
Phase 2 $1-5M 237990 FY28
Name Range NAICS Advertisement
Period
TBD
(Full Design)
Small Business Set-aside Forth Worth, TX CC, Upstream Valley Storage –
Phase 2 $5-10M 237990 TBD
TBD
(Full Design)
Small Business Set-aside Forth Worth, TX CC, Ecosystem Restoration
Rockwood Park $1-5M 237990 TBD
Competitive Request for Proposal - One Step
(Full Design) Unrestricted Forth Worth, TX CC, Ecosystem Restoration
Gateway / Oxbow $25-100M 237990 TBD
Dallas Floodway Opportunities
Name Range NAICS Advertisement
Period
Competitive Request for Proposal - One Step
(Full Design) Unrestricted Dallas, TX
Dallas Floodway – Flood Risk Management Elements – Bi-
Partisan Budget Act 2018 (Hampton Pump Station)
$100-250M 237990 FY26 Q3
Subcontracting Resources
SUBNet: To find small business subcontractors, any large business can post a notice of a subcontracting opportunity, including the solicitation, to SBA’s subcontracting database, called SUBNet. Small Businesses can search and view all posts.
https://subnet.sba.gov/client/dsp_Landing.cfm
DSBS: Prime contractors may also use SBA’s Dynamic Small Business Search website to find small businesses. DSBS has a mass Email Feature to notify SB of inquiries.
https://dsbs.sba.gov/
APEX: Contact an APEX Accelerator (formerly known as a Procurement Technical Assistance Center) for more help finding small businesses subcontracting opportunities.
https://www.apexaccelerators.us/#/service-area-locator
Small Business may use APEX Accelerators to LEARN how to do business with the Government.
Large Business may use APEX Accelerators to find subcontractors / support subcontracting goals.
https://subnet.sba.gov/client/dsp_Landing.cfm https://subnet.sba.gov/client/dsp_Landing.cfm https://dsbs.sba.gov/ https://dsbs.sba.gov/ https://www.sba.gov/local-assistance/find?location%5Bsource_configuration%5D%5Borigin_address%5D=&location%5Bvalue%5D=25&type=151 https://www.apexaccelerators.us/#/service-area-locator for Central City or Dallas Floodway
Official Name: Cross Timbers APEX Accelerator (DFW and North TX Area)
Services: We help companies prepare for contracting with local, state and federal governments. Our mission is to increase the number of contracts awarded to companies in the 72-county service area resulting in increased revenue and jobs in the area.
Our mission is to support the Department of Defense National Security and small business strategies. This paradigm shift has impacted the way we do business and provide technical assistance to our clients.
The shift includes:
- Limited assistance to newly formed companies that do not have innovative solutions for the war fighter.
- Technical assistance is only provided to those companies that are in the Defense and Government Industrial Base (DIB/GIB) as well as, those companies wishing to enter the DIB/GIB who have demonstrated past contracting performance and sound financial capabilities.
- Assistance with SAM registration, socioeconomic applications and other client needs
Phone: 817-272-5978 Email: CrossTimbers@uta.edu Website: https://www.uta.edu/research/centers/cross-timbers
CLOSEST APEX TO PROJECT(S)
mailto:CrossTimbers@uta.edu https://www.uta.edu/research/centers/cross-timbers
Small Business Administration
Derek Gadberry Procurement Center Representative (PCR), North Texas Area V, Small Business Administration (SBA)
Office of Government Contracting
Derek.Gadberry@sba.gov 817-886-1024 mailto:derek.gadberry@sba.gov
PCR Customers
PCR Customer Involvement
RESOURCE PARTNERS
Participate in outreach/industry events
Referral System Provide technical training on federal procurement topics Support Sm Bus Innovation
Research (SBIR) and Sm Bus Technology Transfer (STTR)
DO Engagement
FEDERAL BUYERS
Acquisition Reviews Business Operation Plans Annual Agency Procurement
Center SB Goals Analysis Advise Sr Level Executives (HCA) Collaborate w/agency SBP/SBS Informal/Formal Form 70 Assist w/Market Research
SMALL BUSINESSES
Public Speaking Events Invite & endorse Subject Matter
Experts (SME) Provide Counsel to Small
Businesses Owners Connect SBs to Agency
Procurement Centers Recommend Policy changes
How to find your PCR h t t p s : / / w w w . s b a . g o v /
SBA Reinstates Rule to Return Federal Contractors to Work COVID-Era Moratorium on Physical Office Requirement for 8(a)
Program Will End September 30 Published on June 17, 2025
SBA Reinstates Rule to Return Federal Contractors to Work | U.S. Small Business Administration https://www.sba.gov/article/2025/06/17/sba-reinstates-rule-return-federal-contractors-work https://www.sba.gov/article/2025/06/17/sba-reinstates-rule-return-federal-contractors-work https://www.sba.gov/article/2025/06/17/sba-reinstates-rule-return-federal-contractors-work https://www.sba.gov/article/2025/06/17/sba-reinstates-rule-return-federal-contractors-work
What does this mean?
Effective October. 1, 2025, construction contractors that are 8(a) Certified, in SBA’s 8(a) Business Development Program, will be required to have an actual, physical office within the geographic area where the construction work is being performed (Place of Performance) in which they are bidding on federal construction contracts.
What is a “Bona Fide Office”
- Generally, the geographic area serviced by the SBA District Office, Metropolitan Statistical
Area, where the work will be performed
- A bona fide place of business within a state will be deemed eligible for contracts awarded in that state
- SBA may determine that a Participant may be eligible if nearby
- May have more than one bona fide place of business
- Must submit a request to the District Office at least 20 working days before initial offers
13 C.F.R. § 124.501(k)(2) https://www.ecfr.gov/current/title-13/chapter-I/part-124/subpart-A/subject-group-ECFRd1e9fd1d2f2a3ac/section-124.501
QUESTIONS
Thank You
Go forth and be successful
WRAP UP
Questions Lunch Options
Afternoon Session
QUESTIONS
WHAT’S FOR LUNCH?
There are numerous options within walking distance of the Lanham Building
Branch & Bird 640 Taylor St.
Potbelly 540 Throckmorton St.
Salsa Limon 550 Throckmorton St.
Picchi Pacchi 411 W 7th St.
Panther City BBQ 826 Taylor Street Salata 520 Commerce St.
Corner Bakery 615 Main Street Mi Cocina 509 Main Street
CLOSING
BE ON THE LOOKOUT FOR A SURVEY IN THE COMING WEEKS…
THANK YOU… AND BE SAFE!!!
| Modified Central City�AND Dallas FLOODWAY �Industry Day��July 9, 2025� |
| Opening Remarks�USACE |
| Slide Number 3 |
| Slide Number 4 |
| Slide Number 5 |
| Slide Number 6 |
| Slide Number 7 |
| Agenda |
| Opening Remarks�Tarrant Regional Water District |
| Opening Remarks�City of Fort Worth |
| Safety Moment |
| How to get a Code A on your first submittal |
| Tarrant Regional Water District (TRWD) |
| Slide Number 14 |
| Slide Number 15 |
| Slide Number 16 |
| Slide Number 17 |
| Slide Number 18 |
| Slide Number 19 |
| Slide Number 20 |
| Slide Number 21 |
| Slide Number 22 |
| Slide Number 23 |
| Slide Number 24 |
| Slide Number 25 |
| Slide Number 26 |
| Slide Number 27 |
| Slide Number 28 |
| Slide Number 29 |
| Slide Number 30 |
| Slide Number 31 |
| Slide Number 32 |
| Slide Number 33 |
| Slide Number 34 |
| Slide Number 35 |
| City of Fort Worth |
| Slide Number 37 |
| Ongoing Utility Relocations |
| Central City and TRV TIF 9 |
| Slide Number 40 |
| Slide Number 41 |
| Central City Opportunities |
| Slide Number 43 |
| Doing Work for the City of Fort Worth |
| USACE |
| Fort Worth Central City |
| Central City Flood Risk Management Project Summary |
| Project Authorization�History |
| Modified Central City Project Phasing |
| Flood Risk Management�Completed Valley Storage Sites |
| MITIGATION: Ham Branch & Sycamore Creek �Aquatic Habitat |
| Project Sequencing Roadmap |
| Flood Risk Management�North Bypass Channel – Phase 1 |
| Project Sequencing Roadmap |
| Flood Risk Management �South Bypass Channel Interior |
| Project Sequencing Roadmap |
| Flood Risk Management�Upstream valley storage – Phase 1 |
| Project Sequencing Roadmap |
| Flood Risk Management�Trinity Point Gate & Tie-In |
| Project Sequencing Roadmap |
| Flood Risk Management�Clear ForK Gate & Tie-In |
| Project Sequencing Roadmap |
| Flood Risk Management�TRWD Gate & Pump Station |
| Project Sequencing Roadmap |
| Flood Risk Management�Dams |
| Project Sequencing Roadmap |
| Flood Risk Management�Final Tie-In |
| Flood Risk Management�Downstream valley storage |
| Flood Risk Management�Downstream valley storage |
| Flood Risk Management�maintenance Bridge |
| Ecosystem Restoration�RockwooD Park |
| Ecosystem Restoration�Gateway/Oxbow |
| Feature Status |
| USACE |
| Fort worth district�Dallas floodway Levee System�forecasted opportunities |
| Let’s prime the pump |
| AI JOke |
| 250 years of service |
| Slide Number 79 |
| Dallas Floodway project overview |
| Dallas floodway video |
| Slide Number 82 |
| Hampton 3 pump station conceptual |
| Hampton 3 pump station sequencing |
| Successful offerors tips |
| successful execution tips |
| Slide Number 87 |
| USACE |
| Slide Number 89 |
| Slide Number 90 |
| Slide Number 91 |
| Slide Number 92 |
| Slide Number 93 |
| Slide Number 94 |
| Slide Number 95 |
| Slide Number 96 |
| Slide Number 97 |
| Slide Number 98 |
| Slide Number 99 |
| Slide Number 100 |
| Slide Number 101 |
| Slide Number 102 |
| Slide Number 103 |
| Slide Number 104 |
| Slide Number 105 |
| Slide Number 106 |
| Closest APEX to project(s) |
| Slide Number 108 |
| Slide Number 109 |
| Slide Number 110 |
| Slide Number 111 |
| Slide Number 112 |
| Slide Number 113 |
| Questions |