IMHA RE BID SPECS.pdf

PDF 12 MB Posted

Attached to
REBID Roof Repair / Replacement
Solicitation number
2026-001
Issued by
Lake County, Ohio

About this file

This is a Project Manual and bid package for a roof replacement project issued by the Ironton Metropolitan Housing Authority (IMHA) in Ironton, Ohio, prepared by TSHD architects. The project consists of all labor, materials, and services necessary for the timely and proper completion of roof replacement work across five identified sites (Sites A through E). Sealed bids will be received until 11:00 a.m. local time on Tuesday, November 24, 2026, at the office of Katie Jones, Executive Director, 720 Washington Street, Ironton, Ohio 45638. A pre-bid meeting and site walk-through will be conducted at 11:00 a.m. on Tuesday, November 10, 2026, at the project site. The estimated total cost range is $600,000.00. The contract will be awarded to a single general contractor based on best value considerations including work history, past performance, financial capability, and compliance with applicable laws and regulations. The work is to be substantially completed within 360 consecutive calendar days from the Notice to Proceed, with liquidated damages assessed at $500.00 per day for each day of delay beyond the completion date.

The bid must be accompanied by a Contract Bond equal to 100 percent of the total bid amount or, in lieu thereof, a certified check, cashier's check, or letter of credit equal to 10 percent of the bid. The project is exempt from state sales and use taxes as IMHA is a political subdivision of Ohio, and the successful contractor will be provided with tax exemption certificates. Ohio's Prevailing Wage Law does not apply to this project. The contractor must maintain commercial general liability insurance with a minimum limit of $1,000,000.00 and current workers' compensation insurance as required by Ohio law. Contract award is contingent upon submission of required documentation within three business days of bid opening, including a list of subcontractors and suppliers, a detailed breakdown of labor and materials on AIA Document G702, and proof of tax compliance. The Owner reserves the right to reject any or all bids, request additional information from bidders, and negotiate pricing. No bidder may withdraw its bid for 60 days after the opening date.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Commission No. 2623

Re-BID PROJECT MANUAL for

IMHA Roof Replacement for the

Ironton Metropolitan Housing Authority

Ironton, Ohio

Prepared by:

TSHD architects Portsmouth, OH.

00 00 01 – TABLE OF CONTENTS

SECTION 00 00 01

TABLE OF CONTENTS

SECTION II - ENTIRE WORK

• DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 11 List of AIA Documents Used 00 11 14 Requests for Bids 00 21 16 Instructions for Submitting a Bid 00 42 13 Bid Form 00 45 10 Contractors Guarantee 00 49 00 Owner Contractor Agreement 00 60 10 Contract Bond 00 62 10 Contractor’s Personal Property Tax Affidavit 00 73 13 Supplementary General Conditions 00 53 69 HUD Instruction to Bidders for Contracts 00 53 69-A HUD Representations, Certifications, and Other Statements of Bidders 00 53 70 HUD General Conditions for Construction Contracts 00 50 70 HUD Certification for a Drug-Free Workplace 00 92 01 HUD Equal Employment Opportunity Certification HUD Section 3 Clause Davis Bacon Wage Rates Form of Quote Profile of Firm

Affidavit of Non-Collusion

• DIVISION 01 GENERAL REQUIREMENTS

01 00 00 General Requirements 01 22 51 Alternates 01 30 00(a) Submittals 01 74 23 Final Cleaning 01 77 00 Closeout Procedures 01 78 39 Project Record Documents

• DIVISION 06 WOOD, PLASTICS, AND COMPOSITES

06 10 00 Rough Carpentry

• DIVISION 07 FLASHING, SHEET METAL, GUTTERS, DOWNSPOUTS AND ROOFING

SPECIALTIES

07 31 00 Shingles 07 60 00 Flashing, sheet metal, gutters, downspouts and roofing specialties

00 11 14 – Requests for Bids

Requests for Bids

Sealed bids will be received by Katie Jones, Executive Director, Ironton Metropolitan Housing Authority, 720 Washington St., Ironton, OH. 45638 until

11:00 A.M. Local Time, Tuesday, November, 24th 2026 and will be publicly opened and read immediately thereafter, for furnishing the materials and performing the labor for the Ironton Metropolitan Housing Authority “IMHA Roof Replacement”. Mark on the outside of the bid envelope “IMHA Roof Replacement”. A pre-bid meeting will be held at 11:00 AM, Tuesday, November, 10th 2026. Contractors should meet at 720 Washington St., Ironton, Ohio 45638.

The total cost estimated range is $600,000.00 in accordance with the Drawings and Specifications prepared by:

TSHD architects 1010 Coles Boulevard, Portsmouth, OH 45662

740.354.6621 kdonges@tshdarchitects.com / lallen@tshdarchitects.com

Contract Documents may be obtained from DC Reprographics for actual purchase price, payable to DC Reprographics. (All shipping costs by Contractor.) In addition to the Contract Documents, DC Reprographics will maintain and disseminate all plan holder information. DC Reprographics can be contacted at www.dcplanroom.com. Or by mail / phone:

TSHD architects

1010 Coles Blvd., Portsmouth, OH 45662 740.354.6621

Each bid shall be accompanied by a BID GUARANTEE AND CONTRACT BOND as required by Section

153.571 of the Ohio Revised Code in an amount equal to the total sum of the bid, supported by a Power of Attorney, for the bonding agent, a Certificate from the Department of Insurance authorizing the Surety Company to do Surety business in the State of Ohio, and a current financial statement of the Surety Company. The bond shall be on the form bound in the Project Manual, (or in lieu of a bond, a certified check, cashier's check, or letter of credit pursuant to Chapter 1305 of the Revised Code. The amount of the certified check, cashier's check, or letter of credit shall be equal to 10% of the bid.).

Contractors and subcontractors for this project shall comply with all requirements of the Ohio Civil Rights Act, and shall, if requested by governing bodies, supply all reports or other information requested by them.

Ironton Metropolitan Housing Authority reserves the right to reject any and all bids. No bidder may withdraw his bid for a period of 60 days after the date set for the opening thereof.

Advertise: Saturday, October 31st.

mailto:kdonges@tshdarchitects.com mailto:lallen@tshdarchitects.com http://www.dcreprographics.com/

00 21 16 – Instructions for Submitting a Bid

SECTION 00 21 16

INSTRUCTIONS FOR SUBMITTING A BID

A. EXAMINATION OF DOCUMENTS AND POTENTIAL SITE CONDITIONS

1. Interested Contractors are strongly encouraged to inspect the existing conditions at the potential site and review the project requirements included in the drawings, specifications and other documents included in this bid package before submitting a bid.

B. OWNER & DESIGN PROFESSIONAL

1. The Owner is the Ironton Metropolitan Housing Authority, 720 Washington St. Ironton, Ohio 45638. The Owner’s Representative is Katie Jones, Executive Director.

2. The Design Professional is TSHD architects, Inc., 1010 Coles Blvd., Portsmouth, Ohio 45662.

The Design Professional’s contacts are Dave Stone for questions about the Project (740.354.6621; kdonges@tshdarchitects.com) and Lindsey Allen to request copies of the Bid Package (740.354.6621; lallen@tshdarchitects.com).

C. PROJECT

1. The Project consists of all labor, materials, and services necessary for the timely and proper completion of the work needed for the roof replacement, as generally described in the drawings and specifications prepared by the Design Professional and included in the bid packet (all of which is also referred to as Contract Documents in this Instructions for Submitting a bid).

2. The Project is outside the scope of the statutory competitive requirements for Ironton Metropolitan Housing Authority. The Owner is requesting bids for costs to construct the Project for its consideration as described in these Instructions.

D. WORK

1. A general contract will be awarded for the Work.

E. CONTRACT DOCUMENTS

1. Requests for Bids

2. Instructions for Submitting a Bid

3. Bid Form and Scope of Work

4. Contractor Qualifications Statement

5. Owner/Contractor Agreement

6. Personal Property Tax Affidavit

7. Contract Bond form

The Contract Documents are available upon request from TSHD architects.

This is a Tax-Exempt project and the contractor will have tax-exempt form from the owner when necessary for completing the project.

F. PRE-BID MEETING

A Pre-Bid meeting and site walk-thru will be conducted at the project site at 11:00 AM on Tuesday, November, 10th 2026 at 720 Washington St. Ironton, Oh 45663.

G. PREPARATION OF BIDS

1. Use the bid form included in the bid package and provide pricing information as requested on the sheet included with the bid form.

mailto:kdonges@tshdarchitects.com mailto:lallen@tshdarchitects.com

2. Complete all blank spaces on the bid form in ink or typewritten, in words and figures, and in figures only where no space is provided for words and sign the form. Use the wording on the bid form without change, alteration or addition. Any change in the wording or omission of specified accompanying documents may render the bid non-responsive, in which case it may not be considered. In the case of a discrepancy between the numbers and words written, the words will control.

3. Submit one (1) completed bid form to the Owner at the office of Katie Jones, Executive Director, Ironton Metropolitan Housing Authority, signed with the name typed or printed below the signature. A Contractor that is a corporation must sign its bids with the legal name of the corporation followed by the name of the state of incorporation and the legal signature of an officer authorized to bind the corporation to a contract.

4. If delivering the bid by U.S. Mail, private delivery service, or personal delivery, enclose the completed and signed bid form in a sealed opaque envelope with the Contractor's name and title of project printed in the upper left-hand corner and addressed as follows:

Ironton Metropolitan Housing Authority Katie Jones, Executive Director 720 Washington St.

Ironton, Ohio 45638

5. Bond. A Contract Bond covering payment and performance of the Work may be required, in the Owner’s discretion, from the successful contractor for the project. The form of contract bond is included in the bid package. In lieu of a contract bond, the successful contractor may provide an alternate form of security acceptable to Owner.

6. Contractor's Examination and Representation.

a. Before submitting a bid, each Contractor is responsible to carefully examine the documents and the potential construction site and inform itself of the limitations and conditions related to the Work covered by the bid and include in its bid a sum to cover the cost of such items. The Contractor awarded the contract will not be given extra payments for conditions that could have been determined by examining the site and documents.

b. It is the purpose and intent of the Contract Documents that a complete job be accomplished.

It is each contractor’s responsibility to include costs necessary to provide labor and materials for that portion of the Work included in the bid, including incidentals, whether or not specifically called for.

7. Clarification of Contractor Questions

a. Direct questions about the Project to Kirk Donges (kdonges@tshdarchitects.com) and Lindsey Allen (lallen@tshdarchitects.com) with TSHD architects.

b. Each Contractor is responsible for calling to the attention of the Owner, through the Design Professional, any ambiguities, inconsistencies, errors, or omissions that occur in the Contract Documents for the Work. If the Contractor fails to request clarification, the Contractor will be expected to overcome such conditions without additions to the bid price.

c. Prospective contractors with questions as to the true meaning of any part of the contract documents must submit to the Design Professional not later than the seven (7) days before the scheduled time for receiving bids, a written request for interpretation and clarification.

d. Contractors are instructed to request interpretations if the Contract Documents call for materials, equipment, or methods that adversely affect the cost or quality of the Project or are unavailable.

8. Opening of bids. bids will be accepted until 11:00 a.m. local time on Tuesday, November

24th 2026 at the Ironton Metropolitan Housing Authority, 720 Washington St. Ironton, Ohio 45638, and will be opened and read publicly. Bids may also be submitted electronically to Katie Jones at kjones@irontonmha.org . Each contractor is responsible for ensuring that its bid is mailto:kjones@irontonmha.org received at the designated location prior to the deadline for receiving bids. The Owner reserves the right to accept a bid, after the deadline stated, in its sole discretion after considering the circumstances.

H. METHOD OF AWARD

1. The Owner will award the Contract for the Work to the Contractor submitting the bid determined to be in the best interest of the Owner, with price being considered, but not being the determining factor. The Owner reserves the right to request additional information from any Contractor submitting a bid and to negotiate pricing for the work based upon information received.

The Owner, in its sole discretion, will determine whether the Contractor is qualified and capable of performing the work. In determining whether a contractor’s qualifications and experience to perform the work, the Owner may consider the following criteria and such other criteria as it determines proper:

a. Work history.

The Contractor’s record of consistent customer satisfaction and of consistent completion of projects, including projects which are comparable to or larger and more complex than the Owner's Project, on time and in accordance with the respective contract documents. If the Contractor’s management (i.e., president, chairman of the board, or any director) operates or has operated another construction company, the Owner may consider the work history of that company in determining Contractor’s qualifications and experience.

The Owner will consider the Contractor's prior experience on other projects for the Owner, including the Contractor's demonstrated ability to complete its work on these projects in accordance with the Contract Documents and on time and its ability to work with the Owner.

The Contractor authorizes the Owner and its representatives to contact the owners and design professionals on projects on which the Contractor has worked, and authorizes and requests such owners and design professionals to provide the Owner with a candid evaluation of the Contractor's performance. By submitting its bid, the Contractor agrees that if it or any person at its urging, directly or indirectly, brings an action against any of such owners or design professionals or their employees as a result of or related to such candidate evaluation and such action is not successful, the Contractor will reimburse such owners, design professionals and/or their employees for all legal fees and expenses incurred by them that are related to such legal action, including the cost of collection. This obligation is expressly intended for the benefit of such owners, design professionals and their employees.

b. The Contractor’s resources, including but not limited to the financial ability to complete the Contract successfully and on time and the experience, adequacy, and numbers of the Contractor’s work force.

c. The Contractor's compliance with federal, state, and local laws, rules, and regulations, including but not limited to the Occupational Safety and Health Act.

d. The foregoing information with respect to each of the Subcontractors that the Contractor intends to use on the Project.

e. The Contractor’s participation in a drug-free workplace program through the Ohio Bureau of Workers Compensation or a program approved by the Bureau of Workers Compensation.

f Depending upon the type of the work, other essential factors, as are included in the specifications.

2. Within three (3) business days after receipt of the bids, the apparent low Contractor, and any other contractor requested by the Design Professional, will complete and submit to the Design Professional the following documents:

a. The list of all bidding Subcontractors, suppliers, and manufacturers.

b. The breakdown of Labor and Material for the Project, including the sum for each, on AIA

Document G702, Schedule of Values or another form acceptable to Owner.

c. Contractor Qualifications Statement, if requested.

After approval by the Owner of the list of bidding Subcontractors, suppliers, and manufacturers submitted by the successful Contractor, the list may not be changed unless written approval of the change is authorized by the Owner.

3. The failure to submit requested information on a timely basis may result in the determination that the Contractor is not the best qualified company to perform the work.

4. By submitting its bid, the Contractor agrees that the Owner's determination of the contractor that submitted the bid in the best interest of the Owner will be final and conclusive, and that if the Contractor, or any person at the Contractor's urging, directly or indirectly challenges such determination in any legal proceeding and such challenge is not successful, the Contractor will reimburse the Owner for all legal fees and expenses incurred by the Owner that are related to such challenge, including the cost of collection.

5. No Contractor may withdraw its bid within 60 days after the date bids are opened.

6. The Owner reserves the right to disqualify bids, before or after opening, upon evidence of collusion with intent to defraud or other illegal practices on the part of the Contractor.

I. EXECUTION OF CONTRACT

1. Notice of Intent to Award Contract. The successful Contractor will be notified that it has submitted the bid determined to be in the best interest of the Owner to perform the work and provided with two (2) copies of the Owner-Contractor Agreement (Agreement) in the form included in the bid package.

2. The successful Contractor must sign and return the original forms to the Design Professional, or as otherwise directed, for execution by the Owner. The contract will be effective as soon as it has been signed by the Owner. The successful Contractor will be provided with a fully executed copy of the Agreement for its records. No property interest in the contract is created until the agreement is signed by the Owner.

3. If the successful Contractor does not return the executed contracts as directed within five (5) business days of its receipt of the contracts from the Design Professional, the Owner reserves the right to reject the bid and award the contract to the Contractor determined to have submitted the next bid that is in the best interest of the Owner and that is qualified to perform the Work.

J. ADDENDA

1. Any explanation, interpretation, correction or modification of the Contract Documents will be issued in writing in the form of an Addendum, which will be the only means considered binding;

explanations, interpretations, etc., made by any other means will NOT be legally binding. All Addenda will become a part of the Contract Documents.

2. Contractors should submit questions to the Owner in advance, to allow sufficient time for a response. All Addenda will be issued except as hereafter provided, and mailed or otherwise furnished to persons who have obtained Contract Documents for the Project, at least two (2) days prior to the published time for the opening of bids, excluding Saturdays, Sundays and legal holidays. If any Addendum is issued within such 2-day period, then the time for opening of bids may be extended for an amount of time determined by the Owner in consultation with the Design Professional as appropriate based upon the information included in the Addendum.

3. Copies of each Addendum will be sent only to the Contractors to whom Contract Documents have been issued by the Design Professional. Receipt of Addenda should be indicated by Contractors in the space provided on the bid form.

4. Each Contractor is instructed to carefully read and review the Contract Documents and immediately bring to the attention of the Owner any error, omission, inconsistency, or ambiguity therein.

5. If a Contractor fails to indicate receipt of all Addenda through the last Addenda issued by the Owner on its bid form, the Contractor will be provided with an opportunity to correct the bid to include any changes to the Work addressed in the Addenda.

K. STATE SALES AND USE TAXES

1. The Owner is a political subdivision of the State of Ohio. Building materials that the successful Contractor purchases for incorporation into the Project will be exempt from state sales and use taxes if the successful Contractor provides a properly completed sales tax exemption certificate, executed by the successful Contractor and the Owner, to the vendors or suppliers when the materials are acquired. The Owner will provide properly completed certificates to the successful Contractor.

L. PROJECT SCHEDULE

1. The Project Site will be available for the Contractor to begin work immediately after award of the contract. The Design Professional will coordinate the schedule for the work with the Contractors.

M. OWNER'S RIGHT TO WAIVE DEFECTS AND IRREGULARITIES

1. The Owner reserves the right to waive any and all irregularities provided that the defects and irregularities do not affect the amount of the bid in any material respect or otherwise give the Contractor a competitive advantage.

2. By submitting a bid, the Contractor agrees that (i) the Owner's determination of whether a defect or irregularity affects the amount of the bid in any material respect or otherwise gives the Contractor a competitive advantage will be final and conclusive; and (ii) the Contractor will pay the Owner's attorneys' and consultants' fees related to any challenge to the bid procedure or process, brought directly or indirectly by the Contractor and/or any of its affiliates, which is unsuccessful.

N. MODIFICATION AND WITHDRAWAL OF BIDS

1. Modification: A Contractor may modify its bid by written communication to the Owner addressed to the Treasurer at any time prior to the scheduled closing time for receipt of bids, provided such written communication is received by the Treasurer prior to the closing time. The written communication is not to reveal the bid price, but should provide the addition or subtraction or other modification so that the final prices or terms will not be known until the sealed bid is opened.

2. Withdrawal prior to bid opening: A representative of the Contractor may withdraw its bid at any time for any reason prior to the bid opening time established in the Notice issued for the Work.

The request to withdraw shall be made in writing and submitted to the Treasurer (with a copy to the Design Professional), at the Owner's address.

3. Withdrawal after bid opening: A Contractor may withdraw its bid after the bid opening.

O. EQUAL EMPLOYMENT OPPORTUNITY/NONDISCRIMINATION

1. Minority, female, and disadvantaged businesses will be afforded full opportunity to submit bids, and contractors will not be discriminated against on the grounds of race, color, religion, sex, age, handicap, ancestry, or national origin in the consideration of an award. The successful contractor will include a provision in any subcontract entered into for the Project that requires that each of its subcontractors not discriminate against any employee or applicant for employment on the basis of race, religion, color, sex, age, handicap, ancestry, or national origin in any actions that it takes.

Such actions include, without limitation, employment, upgrading, demotion, transfer recruitment or recruiting advertising, layoff or termination, rates of pay or other forms of compensation, and selection for training, including apprenticeships.

5. The contract document to be executed by the successful Contractor contains nondiscrimination provisions as required by Ohio Revised Code Sections 153.59 and 153.60.

END OF SECTION

00 42 13 - BID FORM

SECTION 00 42 13

BID FORM

NOTE: The wording of this bid form shall be used throughout, without change, alteration or addition. Any change in the wording of this bid form may cause it to be rejected as not complying with the law.

SUBMITTED BY:

, 2026 (Firm Name) (Date)

TO: Ironton Metropolitan Housing Authority, Ironton, Oh. 45638

Having carefully read and examined the drawings entitled “IMHA Roof Replacement” as prepared by TSHD architects, 1010 Coles Boulevard, Portsmouth, Ohio, for the Ironton Metropolitan Housing Authority, and having also received, read and taken into account Addenda (Bidder will list in the following space the number and date of each Addendum received), and likewise, having inspected the site and the conditions affecting and governing the construction of said Project, the undersigned hereby bids to furnish all equipment, materials and perform all labor as specified in and described in the specifications and as shown on the drawings for the work, for the following sums:

GENERAL CONTRACT BASE BID (Shingles)

Total / Dollars ($ )

Site A:_______________________________________/ Dollars ($___________________________) Site B:_______________________________________/ Dollars ($___________________________) Site C:_______________________________________/ Dollars ($___________________________) Site D:_______________________________________/ Dollars ($___________________________) Site E:_______________________________________/ Dollars ($___________________________)

TIME OF COMPLETION

1. It is understood and agreed that work embodied in this Contract shall be substantially completed on or by 360 consecutive calendar days from the Notice to Proceed.

2. Upon failure to have substantial completion of the work completed by the date above-mentioned, the

Contractor shall forfeit and pay, or cause to be paid, to the Ironton Metropolitan Housing Authority, for and as liquidated damages to be deducted from any payment due or to become due to the said Contract, the sum of $500.00 per day for each and every day thereafter that the said work remains in an unfinished condition.

3. The Bidder understands that the Owner reserves the right to reject any or all bids and to waive any informalities.

The Bidder agrees that this bid shall be valid and may not be withdrawn for a period of 60 calendar days after the scheduled closing time for receiving bids.

Upon receipt of written notice of the acceptance of this bid, the bidder will execute the formal contract attached within 10 days and deliver a Surety Bond or Bonds.

00 42 13 - BID FORM

Bidder shall supplement bid by supplying the following information for use in the preparation of the contract:

NAME OF INDIVIDUAL MEMBERS OF THE FIRM

Name of Corporation

Name of President

Corporation is Organized Under the Laws of

If Company, Name of Owner

If Partnership, Name of Partners

Bidder (Company)

(Street Address)

(City) (State) (Zip)

(Signature)

(Title)

(Date) (Phone) (Fax)

00 60 00 - CONTRACTOR'S GUARANTEE

SECTION 00 45 10

CONTRACTOR'S GUARANTEE

, 2026

Project: IMHA Roof Replacement

Location: ___________________________________________________________Ironton, Ohio 45638

Owner: Ironton Metropolitan Housing Authority

Date of Contract:

The undersigned, Contractor for the work on the above project, hereby guarantees all the workmanship and/or materials installed by him (them) or his (their) subcontractors to be of the quality that will comply with all the specific requirements of the "Specifications" and other Contract Documents governing the work under the Contract for the above project, and ensures the Owner against all defects of material and/or workmanship for a period of one year from and after the completion of the installation of equipment and its acceptance by the Owner.

It is agreed that if, after due inspection, the Architect, as provided in the General Conditions of said Contract Documents, shall decide that by reason of this Guarantee, the replacement or repair of any of the work is, in his opinion, necessary, such defective work shall be repaired or removed and new replaced, meeting all the requirements of the Contract Documents, same being done promptly and without expense to the Owner, including all costs for replacing or repairing other work damaged by the removal of the work covered by this Guarantee.

Such decision as the Architect shall render in connection with this Guarantee is subject to the provisions of the General Conditions.

Contractor

By

Title

The Architect hereby certifies that the date of acceptance of the building by the Owner on the above contract was .

TSHD architects by

00 49 00 – OWNER-CONTRACTOR AGREEMENT

SECTION 00 49 00

OWNER-CONTRACTOR AGREEMENT

Owner:

Ironton Metropolitan Housing Authority 720 Washington St.

Ironton, OH 45638

Project:

IMHA Roof Replacement Ironton, Ohio

Contract: General Contract Alternates:

Contractor:

Address:

Phone:

Fax:

Contact:

Email:

Owner, a political subdivision of the State of Ohio, and Contractor have entered into this Owner- Contractor Agreement (Agreement) as of the date signed by the Owner at the end of this Agreement.

Owner and Contractor agree as follows:

1. WORK.

1.1 Contractor will furnish all the labor, services, materials, plant, equipment, tools, scaffolds, appliances, and all other things (collectively called the Work) necessary for the timely and proper completion of the Work described in the Contract Documents for the Project.

1.2 The Date for Completion of the Project is to be 360 days from the Notice to Proceed, unless otherwise agreed to in writing by Owner. Contractor will at all times furnish sufficient skilled workers, materials, and equipment to perform the Work in strict conformance with the Contract Documents and to the entire satisfaction of Owner, so as to complete the Project by the Date for Completion. All materials and equipment provided must be new, free from all defects, and fit for the purpose for which intended.

1.3 Contractor will assign a competent Project Supervisor. At Owner’s request, Contractor will replace the Project Supervisor, provided that the request is reasonable. Design Professional and Owner’s Representative are not responsible for the acts or omissions of the Contractor’s Supervisor or his/her assistants.

2. CONTRACT DOCUMENTS.

2.1 The Contract Documents consist exclusively of the Owner-Contractor Agreement, Contractor's bid form, the Drawings and Specifications, and Change Orders, all of which are incorporated into this Agreement.

3. DESIGN PROFESSIONAL; OWNER'S REPRESENTATIVE.

3.1 The Design Professional for the Project is TSHD architects, Inc., 1010 Coles Blvd., Portsmouth, Ohio 45662; the Design Professional’s representative is Kirk Donges, (740.354.6621;

kdonges@tshdarchitects.com ).

3.2 The Owner Representative is Katie Jones, Executive Director.

3.3 Except as specifically stated to the contrary elsewhere in this Agreement, all communications to

Owner from Contractor must be directed through the Design Professional.

3.4 Design Professional will monitor the progress of Contractor’s Work and will conduct regular inspections of the progress of the Work as provided in the Contract Documents.

3.5 Contractor will at all times provide Owner and Design Professional access to the Work.

4. TIME FOR COMPLETION AND PROJECT COORDINATION.

4.1 PROJECT TIME SCHEDULE. Owner anticipates that off- site Work on the Project will begin as soon as the contract is awarded for the Project and be completed by the Date for Completion stated in Section 4.1, unless Owner and Contractor agree to different commencement and completion dates.

Contractor is responsible for coordinating its Work, through Design Professional, with any other Contractor performing Work related to the Project.

4.2 TIME IS OF THE ESSENCE. THE DATES IN THE PROJECT TIME SCHEDULE ARE OF THE

ESSENCE OF THIS AGREEMENT. CONTRACTOR AGREES TO PROSECUTE ITS WORK IN

ACCORDANCE WITH THE PROJECT TIME SCHEDULE, INCLUDING ANY AMENDMENTS THERETO.

4.3 DELAYS AND ACCELERATIONS.

4.3.1 NOTICE OF DELAYS. Contractor will give Owner written notice of any delay affecting its Work in the form and with the information specified in the Contract Documents within 2 business days of the commencement of the delay. Failure to give the required notice constitutes an irrevocable waiver of Contractor’s right to seek an extension of time and/or additional compensation/damages for the delay.

Owner, in its sole and reasonable discretion, will determine whether a delay entitles Contractor to an extension of time. Extensions of time will only be granted based on the procedures for Change Orders set forth in this Agreement.

5. CORRECTIVE ACTION. If Owner determines that Contractor is not cooperating or coordinating its work properly with its subcontractors, not supplying sufficient skilled workers, not cleaning up the Project, not furnishing the necessary materials, equipment, or any temporary services or facilities to perform the Work in strict conformance with the Contract Documents, or Contractor is not on schedule, or is not otherwise performing its obligations under the Contract Documents, CONTRACTOR MUST IMMEDIATELY, AND IN NOT LESS THAN 2 BUSINESS DAYS AFTER NOTICE OF SUCH DETERMINATION, OR SUCH LESSER TIME AS MAY BE PROVIDED IN THE CONTRACT DOCUMENTS, (1) COMMENCE SUCH ACTION AS IS NECESSARY TO CORRECT THE DEFICIENCIES NOTED BY OWNER, (2) PROCEED TO USE ITS BEST EFFORTS TO CORRECT SUCH DEFICIENCIES WITHIN 30 DAYS OF SUCH NOTICE AND/OR, (3) IF OWNER INSTRUCTS CONTRACTOR TO TAKE SPECIFIED CORRECTIVE ACTION, IMMEDIATELY TAKE SUCH CORRECTIVE ACTION, including but not limited to increasing the number of skilled workers, providing temporary services or facilities, and cleaning up the Project.

Such corrective action must be taken and continued uninterruptedly without waiting to initiate any dispute under Section 11 of this Agreement or the resolution of any dispute initiated under such section.

6. CONTRACT SUM. The Contract Sum to be paid by Owner to Contractor, as provided herein, for the satisfactory performance and completion of the Project and all of the duties, obligations and responsibilities of Contractor under this Agreement and the other Contract Documents will be ___________________________ Dollars ($__________). The Contract Sum includes all federal, state, county, municipal, and other taxes imposed by law, including but not limited to any sales, use, and personal property taxes payable by or levied against Contractor on account of the Work or the materials incorporated into the Work. Contractor is responsible to pay any such taxes.

6.1 LIQUIDATED DAMAGES.

1. Contractor will have its work complete by the date stated in Section 4.1; the timeline may be varied following award of the contract based upon Contractor’s ability to perform the work on a different timeline acceptable to Owner. By entering into this Agreement, Contractor agrees that the period for performing the Work is reasonable and that Contractor's Work can be complete by the date stated in this Agreement.

2. If Contractor does not have its Work on the Project complete by the date stated in Section 4.1 or as otherwise agreed by the parties, Contractor will pay Owner (and Owner may set off from sums coming due Contractor) liquidated damages in the per diem amount of $500.00 for each calendar day beyond the Date for Completion as such date may be extended in accordance with the Contract Documents.

3. Contractor acknowledges by signing this Agreement with Owner that the amount of liquidated damages represent a reasonable estimate of the actual damages Owner could incur if the work is not complete by the foregoing date and that the damages that may result from the failure to complete the work by the foregoing date are uncertain and difficult to ascertain.

These liquidated damages are damages for loss of use of the Project, and Contractor in addition to the liquidated damages will be obligated to indemnify and hold Owner harmless from any claims, and if the Work on the Project is accelerated because of delay, for all costs related to the acceleration of the Work, as provided in the Contract Documents.

7. LIMITATION ON LIABILITY. Owner’s total liability under this Agreement is limited to the amount set forth in the Treasurer’s certificate accompanying this Agreement. Under no circumstances will the elected officials, officers, employees, board members, or agents of Owner be personally liable for any obligations or claims arising out of or related to this Agreement.

8. PAYMENT.

8.1 PAYMENT.

8.1.1 APPLICATIONS FOR PAYMENT. Payment applications must be submitted on a monthly basis and must reflect the amount of work completed as of the date the application for payment is submitted. On or before the date of the month specified by Owner, Contractor will submit to Design Professional, an itemized payment application for such period.

8.1.2 Owner may withhold payment in whole or in part, and may demand that Contractor refund amounts previously paid, to protect Owner from loss because of:

1. Contractor’s default or failure to perform any of its obligations under the Contract Documents, including but not limited to: failure to provide sufficient skilled workers; Work, including equipment or materials, which is defective or otherwise does not conform to the Contract Documents; failure to conform to the Project Time Schedule; and failure to follow the directions of or instructions from Owner;

2. The Work has not proceeded to the extent set forth in the application for payment;

3. Any representations made by Contractor are untrue;

4. Failure of Contractor to make payments to its Subcontractors;

5. Damage to Owner’s property or the property of another person or laborer;

6. The determination that there is a substantial possibility that the Work cannot be completed for the unpaid balance of the Contract Sum; and/or

7. Liens filed or reasonable evidence indicating the probable filing of such liens.

8.1.3 Owner will pay Contractor within 30 days after receipt of Contractor's approved payment application from Design Professional, provided that the payment application has been properly submitted on a timely basis and is accompanied by all of the required documentation. Owner may establish a cut-off date for the submission of the payment application.

8.2 RETAINAGE. The statutory retainage requirements do not apply to the Project; Owner reserves the right to withhold 10% the amount requested in each payment application as retainage until the Work is complete.

9. CHANGE ORDERS.

9.1 A Change Order is a written instrument signed by Owner, Design Professional, and Contractor stating their agreement upon a change in the Work, the amount of the adjustment or the method for computing the amount of the adjustment of the Contract Sum, if any, and the extent of the adjustment in the Project Time Schedule, if any.

9.2 Any modification to the scope of Work, whether deductive or additive, or Contract Time, must be documented by a Change Order signed by both parties and Design Professional; failure to submit a change order request and obtain Owner’s approval prior to performing the Work is an express waiver of the right to seek a change in time or amount of this Agreement.

10 CLAIMS AND DISPUTES.

10.1 A Claim is a demand or assertion by one of the parties seeking, as a matter of right, adjustment, or interpretation of the terms of the Contract Documents, payment of money, extension of time, or other relief with respect to the terms of the Contract Documents, provided that the Owner’s decision to adjust or withhold payment under Section 8.1.2 will not be considered a Claim. The responsibility to substantiate claims rests with the party making the Claim. The Contractor will not knowingly (as “knowingly” is defined in the federal False Claims Act, 31 U.S.C. Section 3729, et seq.) present or cause to be presented a false or fraudulent Claim. As a condition precedent to making a claim, the Contractor must submit an affidavit sworn to before a notary public or other person authorized to administer oaths in the State of Ohio and executed by an authorized representative of the Contractor, which states:

The Claim submitted herewith complies with Section 10.1 of the Owner-Contractor Agreement, which provides that the “Contractor will not knowingly present or cause to be presented a false or fraudulent Claim.”

10.2 Claims must be made by written notice.

10.3 If Contractor wishes to make a Claim for an increase in the Contract Sum, written Notice as provided herein must be given before proceeding to execute the Work.

10.4 If Contractor wishes to make a Claim for additional time, Contractor must include an estimate of cost and probable effect of delay on progress of the Work. In the event of continuing delay, only one Claim is necessary. If adverse weather conditions are the basis for a Claim for additional time, such claim must be documented by data substantiating that weather conditions were abnormal for the period of time and could not have been reasonably anticipated, and that weather conditions had an adverse effect on the scheduled construction.

10.5 If conditions are encountered at the site that are (1) subsurface or otherwise concealed physical conditions that differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature that differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then the observing party must give written notice to the other party promptly before conditions are disturbed and in no event later than 2 business days after first observance of the conditions. If the conditions are materially different and cause an increase or decrease in Contractor’s cost of, or time required for, performance of any part of the Work, Owner will issue an appropriate Change Order.

10.6 Contractor must make all claims in writing within 7 days after the occurrence of the event giving rise to the Claim. Failure to do so is an irrevocable waiver of the Claim.

10.7 Within 10 days of its receipt of a written request, Contractor will make available to Owner or its representative any books, records, or other documents in its possession or to which it has access relating to any Claim and will require its Subcontractors, regardless of tier, and materialmen to do likewise.

10.8 If a Claim has not been resolved within 14 days after submission to the other party, unless agreed otherwise in writing by the parties, the claimant’s exclusive remedy is to file suit in the common pleas court or other local court having jurisdiction for the county in which the Project is located.

11. DEFAULT OF THE CONTRACTOR.

11.1 EVENTS OF DEFAULT. Each of the following constitutes an event of default by Contractor:

11.1.1 Contractor’s failure to perform any of its obligations under the Contract Documents and to proceed to commence to correct such failure within 2 business days after written notice thereof from Owner or such lesser time as is provided in the Contract Documents or notice, or

11.1.2 Contractor's failure thereafter to use its best efforts to correct such failure, or

11.1.3 Except when an extension of time is granted in writing by Owner, to correct such failure within

30 days after receipt of written notice thereof.

11.1.4 Contractor’s failure to pay its obligations as they become due or Contractor’s insolvency.

11.2 OWNER'S REMEDIES. Upon the occurrence of an event of default, Owner has the following remedies, which are cumulative:

11.2.1 Order Contractor to stop the Work, which Contractor will do immediately;

11.2.2 Perform through others all or any part of the Work remaining to be done and to deduct the cost thereof from the unpaid balance of the Contract Sum or, if the unpaid balance of the Contract Sum is inadequate, to demand reimbursement of amounts previously paid to Contractor;

11.2.3 Terminate this Agreement and take possession of, for the purpose of completing the Work or any part of it, all materials, equipment, scaffolds, tools, appliances, and other items belonging to or possessed by Contractor, all of which Contractor hereby transfers and assigns to Owner for such purpose, and to employ any person or persons to complete the Work, including Contractor’s employees, and Contractor will not be entitled to receive any further payment until the Work is completed; and/or,

11.2.4 All other remedies which Owner may have at law or in equity or otherwise under the Contract Documents.

11.3 TERMINATION OF AGREEMENT. The termination of this Agreement will be without prejudice to Owner’s rights and remedies, including without limitation Owner’s right to be indemnified by Contractor.

11.4 PAYMENTS DUE CONTRACTOR. If the unpaid balance of the Contract Sum exceeds the cost of finishing the Project, including any costs, expenses or damages incurred by Owner as a result of the event of default, including attorneys’ and consultants’ fees and the administrative expense of Owner’s staff, such excess will be paid to Contractor. If such costs exceed the unpaid balance, Contractor will pay the difference to Owner. The obligations under this section will survive the termination of this Agreement.

12. DEFAULT OF OWNER.

12.1 EVENTS OF DEFAULT. The following constitutes the exclusive events of default by Owner:

12.1.1 Failure of Owner to perform any of its obligations under the Contract Documents and to correct such failure within 30 days after receipt of written notice thereof from Contractor specifying the default and the necessary corrective action.

12.1.2 Failure of Owner to pay Contractor as payment becomes due under this Contract.

12.2 CONTRACTOR'S REMEDY.

12.2.1 Contractor’s sole and exclusive remedy for the default of Owner, other than the failure of Owner to pay Contractor, will be to bring a suit for damages in the common pleas court or other local court having jurisdiction in the county where the project is located. Contractor’s right to exercise that remedy is subject to its giving Owner the required notices and following any other procedures required by the contract documents.

12.2.2 If Owner fails to pay Contractor as payment becomes due, Contractor may, upon 15 days written Notice, stop the Work until payment of the amount owing has been received. An adjustment to the Contract Sum will be made as if the Work had been suspended for the convenience of Owner under Section 13.1.

13. SUSPENSION OR TERMINATION FOR THE CONVENIENCE OF OWNER.

13.1 SUSPENSION FOR THE CONVENIENCE OF OWNER.

13.1.1Owner may, without cause, order Contractor to suspend, delay, or interrupt the Work in whole or in part for such period of time as Owner may determine.

13.1.2 An adjustment will be made for increases in the cost of performance of the Work, including profit and overhead on the increased cost of performance, caused by the suspension, delay or interruption, provided that the total cost of profit and overhead will not exceed 10% of the amount of the increased cost not attributable to profit or overhead. No adjustment will be made to the extent that:

1. performance is, was or would have been so suspended, delayed or interrupted by another cause for which Contractor is responsible; or

2. an equitable adjustment is made or denied under another provision of this Agreement.

13.2 TERMINATION FOR THE CONVENIENCE OF OWNER.

13.2.1 Owner may, in its discretion and without cause, by written notice to Contractor terminate this

Agreement for Owner’s convenience.

13.2.2 Upon receipt of a written notice from Owner terminating this Agreement without cause and for

Owner’s convenience, Contractor will (i) immediately cease performing the Work, unless otherwise directed by Owner, in which case Contractor will take the action directed by Owner, (ii) take all reasonable and necessary action to protect and preserve the Work, and (iii) unless otherwise directed by Owner, terminate all agreements with Subcontractors and suppliers.

13.2.3 If this Agreement is terminated without cause and for Owner’s convenience and there exists no event of Contractor’s default, as defined in this Agreement, Owner will pay Contractor (i) for Work performed under this Agreement up to the date the notice of termination is received by Contractor at the rates for Work performed under this Agreement, including overhead and profit up to the date of termination, (ii) for Work performed at the direction of Owner on and after the date on which the notice of termination is received by Contractor, as determined by the procedures applicable to Change Orders, (iii) for Work necessary to protect and preserve the Work, as determined by the procedures applicable to Change Orders, (iv) the reasonable and necessary costs of terminating Contractor’s agreements with Subcontractors and suppliers, and (v) other costs incurred by Contractor directly as a result of the termination of this Agreement.

13.2.4 If this Agreement is terminated without cause for Owner’s convenience and there exists an event of Contractor’s default, as defined in this Agreement, Contractor will be entitled to receive only such sums as it would be entitled to receive following the occurrence of an event of default under this Agreement.

13.2.5 Termination of this Agreement will be without prejudice to any rights or remedies that exist at the time of termination.

14. INSURANCE AND INDEMNIFICATION.

14.1 Contractor must maintain commercial general liability and automobile insurance in the minimum amount of $1,000,000.00. In addition, Contractor must have current worker’s compensation insurance coverage as required by Ohio law and professional liability insurance if any work performed by Contractor includes design professional services. Contractor agrees to provide Owner with a certificate of insurance identifying its insurance coverages and limits.

14.2 Owner will provide property insurance in a form of builder’s risk insurance in the amount of the Contract Sum. Contractor will be responsible for paying the deductible associated with any covered event for which Contractor is responsible. The deductible for coverages under the insurance, except for flood and earthquake coverage deductibles, will not be more than $2,500. Flood and earthquake deductibles will be paid by Owner, unless the covered event under the flood coverage was triggered by the Contractor or one of its Subcontractors.

14.3 Insurance furnished by Owner, if any, is not intended to and will not cover equipment and materials before they are physically incorporated into the Work or tools. Contractor bears the entire risk of loss with respect to tools, equipment, and materials.

14.3 Owner and Contractor waive all rights against each other and against the Subcontractors, Sub-subcontractors, consultants, agents and employees of the other for damages, but only to the extent covered by property insurance during construction, except such rights as they may have to the proceeds of such insurance.

14.4 To the maximum extent permitted by law, Contractor will indemnify and hold harmless Owner and Owner’s consultants, agents, and employees from and against all claims, damages, losses, and expenses, including but not limited to attorneys’ and consultants’ fees, arising out of or related to the performance of the Work, including but not limited to the failure of Contractor to perform its obligations under the Contract Documents, any claims for bodily injury, sickness, disease, or death or to injury to or destruction of or loss of use of real or personal property, claims for additional storage and handling charges, liens against funds, claims related to the alleged failure of Contractor to perform in accordance with the Contract Documents, and/or claims related to the removal, handling, or use of any hazardous materials. Owner may set off amounts equal to any sums for which it is entitled to be indemnified from the amounts otherwise due Contractor under the Contract Documents.

14.5 In claims against any person or entity indemnified under this Contract by an employee of Contractor, a Subcontractor, anyone directly or indirectly employed by them or anyone for whose acts they may be liable, the indemnification obligations under this Contract will not be limited by a limitation on amount or type of damages, compensation, or benefits payable for Contractor or Subcontractor…

This is the start of the file's text. The full file is on GovTribe.