STATEMENT OF WORK FOR COPPER SONAR CABLE ASSEMBLIES
1.0 BACKGROUND
The Fleet Sensors & Cables Engineering Branch (Code 1535) of the Sensors and Arrays Division (Code 153) of the Naval Undersea Warfare Center Division Newport serves as the Navy's Technical Design Agent (TDA) and In-Service Engineering Agent (ISEA), and assists with Acquisition Engineering Agent (AEA) activities for surface ship and submarine transducers, hydrophones and cables. Code 1535 maintains the Navy's outboard SONAR cable inventory in large part through contract vehicles established to procure the cables which are delivered to the stock system and are available to support new construction and fleet needs.
1.1 SPONSORS
· PMS 397 Columbia Class Program Office
· PMS 401 Submarine Acoustic Systems Program Office
· PMS 450 Virginia Class Program Office
· Type Commanders
· Naval Shipyards
1.2 NUWCDIVNPT DEPARTMENTS
This contract is applicable to the Sensors and SONAR Department, Code 15, of the Naval Undersea Warfare Center Division Newport, RI.
1.3 FUNDING TYPES
· Other Procurement, Navy (OPN)
· Shipbuilding and Conversion, Navy (SCN)
· Operation & Maintenance, Navy (O&MN)
· Service Cost Center (SCC)
· National Sea-Based Deterrence Fund (NSBDF)
2.0 SCOPE
This Statement of Work (SOW) reflects a build-to-print approach. The contractor shall manufacture, inspect, test, package, and deliver production Copper SONAR Cable Assemblies in accordance with the individual cable drawings. The Copper SONAR Cable Assemblies are integral to systems on all submarine platforms.
3.0 APPLICABLE DOCUMENTS (AD)
The following documents are applicable to tasking under Section 4.0 and form a part of the SOW for this procurement to the extent stated herein.
3.1 Copper SONAR Cable Assemblies NAVSEA Drawings
Table 1. Copper SONAR Cable Assembly Drawings
Cable Type
| Drawing No. |
| Rev |
| Part Number |
| NSN |
| CABLE ASSEMBLY, POWER, DT-100/DT-699 |
| 7335392 |
| L |
| -1 |
| 5845-01-480-9223 |
| -2 |
| 5845-01-480-9221 |
| -3 |
| 5845-01-480-9222 |
| -4 |
| 5845-01-480-9217 |
| CABLE ASSEMBLY, POWER, DT-100/DT-699 |
| 7335183 |
| E |
| -1 |
| 5995-01-513-4369 |
| -2 |
| 5995-01-513-4364 |
| CABLE ASSEMBLY, POWER, DT-100 |
| 8691988 |
| C |
| -1 |
| 5995-01-697-8032 |
3.2 NAVSEA S9320-AM-PRO-020/MLDG REV 2, Underwater Cable Assembly and Encapsulated Components, Fabrication, Repair, and Installation Manual
3.3 NAVSEA S9320-AM-PRO-030/MLDG REV 3, Underwater Cable Assembly and Encapsulated Components, Fabrication, Repair, and Installation Manual, Volume III Plasma Spray Procedure
4.0 REQUIREMENTS
The contractor shall manufacture, inspect, test, package, and deliver Copper SONAR Cable Assemblies in accordance with the individual cable assembly drawings listed in Table 1 of section 3.1. Table 2 defines the procurement requirements.
Table 2. Requirements
| Requirement |
| Description |
| Contract Timeframe |
| Applicable CDRLs |
4.1 GENERAL
| 4.1.1 Contract Kick-Off Meeting |
| The contractor shall host a Contract Kick-Off meeting at its facility. The meeting agenda shall include the following: |
· Introductions including meeting personnel assigned to the work
· Contract review
· Drawings review
· Facility tour
| Within 45 days after contract award |
| N/A |
4.2 PRODUCTION PHASE
| 4.2.1 Production Hardware |
| The contractor shall manufacture, inspect, test, package and deliver Production cable assemblies in accordance with AD 3.1 through 3.3. |
| N/A |