About this file
This document is a Quality Assurance Surveillance Plan (QASP) related to Request for Quote (RFQ) No. 2032H8-24-Q-00054 for IRS, Technology Strategy Management (TSM) Technical Integrations Support Services. The QASP defines the roles and responsibilities, performance standards, methodologies to monitor contractor performance, quality assurance documentation, and analysis of quality assurance assessments. It establishes a performance management approach focused on achieving desired outcomes rather than just compliance. The key performance standards and acceptable quality levels are outlined in the Performance Requirements Summary, with surveillance methods including random monitoring, periodic inspection, and customer feedback. The QASP enables the government to take advantage of the contractor's own quality control program. It also specifies reporting, review, and resolution processes to address performance issues.
The related federal contract opportunity is a Special Notice for RFQ No. 2032H8-24-Q-00054 for IRS Technical Integrations Support services. This is a Total Small Business Set-Aside for SBA-Certified Economically Disadvantaged Woman-Owned Small Businesses (EDWOSB) under SIN 541611. The solicitation will be distributed solely by email with a closing date of September 23, 2024. No telephone, written, or question requests will be accepted.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
RFQ No. 2032H8-24-Q-00054 IRS, Technology Strategy Management (TSM)
Technical Integrations Support Services
TABLE OF CONTENTS
1 INTRODUCTION
1.1 Purpose
1.2 Performance Management Approach
1.3 Performance Management Strategy
2 ROLES AND RESPONSIBILITIES
2.1 The Contracting Officer
2.2 The Contracting Officer’s Representative
3 IDENTIFICATION OF REQUIRED PERFORMANCE STANDARDS/QUALITY LEVELS
4 METHODOLOGIES TO MONITOR PERFORMANCE
4.1 Surveillance Techniques
4.2 Customer Feedback
4.3 Acceptable Quality Levels
5 QUALITY ASSURANCE DOCUMENTATION
5.1 Ongoing Review By Technical Office Staff / Management ....... Error! Bookmark not defined.
5.2 Monitoring Forms
6 ANALYSIS OF QUALITY ASSURANCE ASSESSMENT
6.1 Determining Performance
6.2 Reporting
6.3 Reviews and Resolution
ATTACHMENT 1: PERFORMANCE REQUIREMENTS SUMMARY
ATTACHMENT 2: SAMPLE QUALITY ASSURANCE MONITORING FORM
QUALITY ASSURANCE SURVEILLANCE PLAN
(QASP)
1 INTRODUCTION
This quality assurance surveillance plan (QASP) is pursuant to the requirements listed in the performance work statement (PWS) entitled Technical Integrations Support Services. This plan sets forth the procedures and guidelines the IRS, Technology Strategy Management (TSM) will use in ensuring the required performance standards or services levels are achieved by the contractor.
1.1 Purpose
1.1.1 The purpose of the QASP is to describe the systematic methods used to monitor performance and to identify the required documentation and the resources to be employed. The QASP provides a means for evaluating whether the contractor is meeting the performance standards/quality levels identified in the PWS and the contractor’s quality control plan (QCP), and to ensure that the government pays only for the level of services received.
1.1.2 This QASP defines the roles and responsibilities of all members of the integrated project team (IPT), identifies the performance objectives, defines the methodologies used to monitor and evaluate the contractor’s performance, describes quality assurance documentation requirements, and describes the analysis of quality assurance monitoring results.
1.2 Performance Management Approach
1.2.1 The PWS structures the acquisition around “what” service or quality level is required, as opposed to “how” the contractor should perform the work (i.e., results, not compliance). This QASP will define the performance management approach taken by IRS, TSM to monitor and manage the contractor’s performance to ensure the expected outcomes or performance objectives communicated in the PWS are achieved. Performance management rests on developing a capability to review and analyze information generated through performance assessment. The ability to make decisions based on the analysis of performance data is the cornerstone of performance management; this analysis yields information that indicates whether expected outcomes for the project are being achieved by the contractor.
1.2.2 Performance management represents a significant shift from the more traditional quality assurance (QA) concepts in several ways. Performance management focuses on assessing whether outcomes are being achieved and to what extent. This approach migrates away from scrutiny of compliance with the processes and practices used to achieve the outcome. A performance-based approach enables the contractor to play a large role in how the work is performed, as long as the proposed processes are within the stated constraints.
The only exceptions to process reviews are those required by law (federal, state, and local) and compelling business situations, such as safety and health. A “results” focus provides the contractor flexibility to continuously improve and innovate over the course of the contract as long as the critical outcomes expected are being achieved and/or the desired performance levels are being met.
1.3 Performance Management Strategy
1.3.1 The contractor is responsible for the quality of all work performed. The contractor measures that quality through the contractor’s own quality control (QC) program. QC is work output, not workers, and therefore includes all work performed under this contract regardless of whether the work is performed by contractor employees or by subcontractors. The contractor’s QCP will set forth the staffing and procedures for self-inspecting the quality, timeliness, responsiveness, customer satisfaction, and other performance requirements in the PWS. The contractor will develop and implement a performance management system with processes to assess and report its performance to the designated government representative. The contractor’s QCP will set forth the staffing and procedures for self-inspecting the quality, timeliness, responsiveness, customer satisfaction, and other performance requirements in the PWS. This QASP enables the government to take advantage of the contractor’s QC program.
1.3.2 The government representative(s) will monitor performance and review performance reports furnished by the contractor to determine how the contractor is performing against communicated performance objectives. The government will make determination regarding incentives based on performance measurement metric data and notify the contractor of those decisions. The contractor will be responsible for making required changes in processes and practices to ensure performance is managed effectively.
2 ROLES AND RESPONSIBILITIES
2.1 The Contracting Officer
The contracting officer (CO) is responsible for monitoring contract compliance, contract administration, and cost control and for resolving any differences between the observations documented by the contracting officer's representative (COR), or program manager (PM) and the contractor. The CO will designate one full-time COR as the government authority for performance management. The number of additional representatives serving as technical inspectors depends on the complexity of the services measured, as well as the contractor’s performance, and must be identified and designated by the CO.
2.2 The Contracting Officer’s Representative
The contracting officer’s representative (COR) is designated in writing by the CO to act as his or her authorized representative to assist in administering a contract. COR limitations are contained in the written appointment letter. The COR is responsible for administration of the project and ensures proper government surveillance of the contractor’s performance. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the government’s behalf. Any changes that the contractor deems may affect contract price, terms, or conditions shall be referred to the CO for action. The COR will have the responsibility for completing QA monitoring forms used to document the inspection and evaluation of the contractor’s work performance. Government surveillance may occur under the inspection of services clause for any service relating to the contract.
3 IDENTIFICATION OF REQUIRED PERFORMANCE STANDARDS/QUALITY LEVELS
The required performance standards and/or quality levels are included in the Performance Requirements Summary. If the contractor meets the required service or performance level, it will be paid the monthly amount agreed on in the contract. If the contractor exceeds the service or performance level, it is eligible to receive an incentive or award fee as stated in the contract. Failure to meet the required service or performance level will result in a deduction from the monthly amount.
4 METHODOLOGIES TO MONITOR PERFORMANCE
4.1 Surveillance Techniques
In an effort to minimize the performance management burden, simplified surveillance methods shall be used by the government to evaluate contractor performance when appropriate. The primary methods of surveillance are
Random monitoring, which shall be performed by the COR designated inspector.
Periodic Inspection – COR typically performs the periodic inspection on a monthly basis.
4.2 Customer Feedback
The contractor is expected to establish and maintain professional communication between its employees and customers. The primary objective of this communication is customer satisfaction. Customer satisfaction is the most significant external indicator of the success and effectiveness of all services provided and can be measured through customer complaints.
Performance management drives the contractor to be customer focused through initially and internally addressing customer complaints and investigating the issues and/or problems but the customer always has the option to communicate complaints to the CO, as opposed to the contractor.
Customer complaints, to be considered valid, must set forth clearly and in writing the detailed nature of the complaint, must be signed, and must be forwarded to the COR.
Customer feedback may also be obtained either from the results of formal customer satisfaction surveys or from random customer complaints.
4.3 Acceptable Quality Levels
The acceptable quality levels (AQLs) included in Attachment 1, Performance Requirements Summary Table, for contractor performance are structured to allow the contractor to manage how the work is performed while providing negative incentives for performance shortfalls.
5 QUALITY ASSURANCE DOCUMENTATION
5.1 Ongoing Review by Technical Office Staff / Management
Performance standards are expressed in the PRS and are assessed using the performance monitoring techniques shown in Attachment 1 – Ongoing Review by Technical Office Staff/ Management
5.2 Monitoring Forms
The government’s QA surveillance, accomplished by the COR and PM, will be reported using the monitoring form (Attachment 2). The forms, when completed, will document the government’s assessment of the contractor’s performance under the contract to ensure that the required results are being achieved.
5.2.1 The COR and PM will retain a copy of all completed QA surveillance forms.
6 ANALYSIS OF QUALITY ASSURANCE ASSESSMENT
6.1 Determining Performance
6.1.1 Government shall use the monitoring methods cited to determine whether the performance standards have been met. If the contractor has not met the minimum requirements, it may be asked to develop a corrective action plan to show how and by what date it intends to bring performance up to the required levels.
6.2 Reporting
6.2.1 At the end of each month, the COR will prepare a written report for the PM summarizing the overall results of the quality assurance surveillance of the contractor’s performance. This written report, which includes the contractor’s submitted monthly report and the completed quality assurance monitoring forms (Attachment 2), will become part of the QA documentation. It will enable the government to demonstrate whether the contractor is meeting the stated objectives and/or performance standards, including cost/technical/scheduling objectives.
6.3 Reviews and Resolution
6.3.1 The COR may require the contractor’s project manager, or a designated alternate, to meet with the PM and other government IPT personnel as deemed necessary to discuss performance evaluation. The PM will define a frequency of in-depth reviews with the contractor, including appropriate self-assessments by the contractor; however, if the need arises, the contractor will meet with the COR and PM as often as required or per the contractor’s request. The agenda of the reviews may include:
Monthly performance assessment data and trend analysis
Issues and concerns of both parties
Projected outlook for upcoming months and progress against expected trends, including a corrective action plan analysis
Recommendations for improved efficiency and/or effectiveness
6.3.2 The PM must coordinate and communicate with the contractor to resolve issues and concerns regarding marginal or unacceptable performance.
6.3.3 The COR and contractor should jointly formulate tactical and long-term courses of action.
Decisions regarding changes to metrics, thresholds, or service levels should be clearly documented.
Changes to service levels, procedures, and metrics will be incorporated as a contract modification at the convenience of the CO.
ATTACHMENT 1: PERFORMANCE REQUIREMENTS SUMMARY
Required Services (Tasks)
Performance Standards
Acceptable Quality Levels
Methods of
Surveillance
Incentive (Positive and/or
Negative)
Task 1
Program Management
Support
Provide necessary program management and administrative support to carry out the objectives of the contract successfully, provide periodic executive briefings, meeting minutes, quad charts, work requests, report the progress on key metrics, and manage time and resources for timely and cost-effective deliverables.
99%
Ongoing Review by Technical Office Staff/ Management
Positive /
Negative Past Performance Evaluations
May be factored into Government’s decision on whether to exercise options.
Task 2
Project Management necessary project management and administrative support to carry out the objectives of the contract successfully, provide periodic executive briefings, meeting minutes, quad charts, work requests, report the progress on key metrics, and
99% Ongoing Review by
Technical Office Staff/ Management
Positive / Negative Past
Government’s decision on manage time and resources for timely and cost-effective deliverables.
Task 3
Operational Support support to develop and maintain all factors and components impacting successful deliverables.
99% Ongoing Review by
Technical Office Staff/ Management
Positive / Negative Past
Government’s decision on
Task 4
Strategy Support support to analyze, develop, update, and document the Technical
Integrations Support Program strategy. Provide technical strategy support for TSM programs and initiatives.
99% Ongoing Review by
Technical Office Staff/ Management
Positive / Negative Past in to Government’s decision on
Task 5
Technical Integration
Provide technical support for integrations for various programs and support within TSM required documentation to proceed with a successful implementation of Technical Integrations
Support.
99% Review by
Technical Office Staff/ Management
Positive / Negative Past
Task 6
Transition Support
Provide support for transition that includes documentation of requirements, scope, risks and issues, Standard
Operating Procedures
(SOPs), guidelines and step-by-step instructions on implementations and integrations screenshots, and training.
99% Review by
Technical Office Staff/ Management
Positive / Negative Past
ATTACHMENT 2:
SAMPLE QUALITY ASSURANCE MONITORING FORM
Monthly Review by CFO:FM Staff/ Management
SERVICE or STANDARD:
SURVEY PERIOD:
SURVEILLANCE METHOD (Check):
Random Sampling 100% Inspection Periodic Inspection Customer Complaint
LEVEL OF SURVEILLANCE (Check):
Monthly
PERCENTAGE OF ITEMS SAMPLED DURING SURVEY PERIOD: ______ %
ANALYSIS OF RESULTS:
Observed Service Provider Performance Measurement Rate: ______%
Service Provider’s Performance (Check): Meets Standards
Does Not Meet Standards
Narrative of Performance During Survey Period:
PREPARED BY: ___________________________________ DATE: _________________
| 1 INTRODUCTION |
| 1.1 Purpose |
| 1.1.1 The purpose of the QASP is to describe the systematic methods used to monitor performance and to identify the required documentation and the resources to be employed. The QASP provides a means for evaluating whether the contractor is meeting th... |
| 1.1.2 This QASP defines the roles and responsibilities of all members of the integrated project team (IPT), identifies the performance objectives, defines the methodologies used to monitor and evaluate the contractor’s performance, describes quality a... |
| 1.2 Performance Management Approach |
| 1.2.1 The PWS structures the acquisition around “what” service or quality level is required, as opposed to “how” the contractor should perform the work (i.e., results, not compliance). This QASP will define the performance management approach taken by... |
| 1.2.2 Performance management represents a significant shift from the more traditional quality assurance (QA) concepts in several ways. Performance management focuses on assessing whether outcomes are being achieved and to what extent. This approach mi... |
| 1.3 Performance Management Strategy |
| 1.3.1 The contractor is responsible for the quality of all work performed. The contractor measures that quality through the contractor’s own quality control (QC) program. QC is work output, not workers, and therefore includes all work performed under ... |
| 2 ROLES AND RESPONSIBILITIES |
| 2.1 The Contracting Officer |
| 2.2 The Contracting Officer’s Representative |
| 3 IDENTIFICATION OF REQUIRED PERFORMANCE STANDARDS/QUALITY LEVELS |
| 4 METHODOLOGIES TO MONITOR PERFORMANCE |
| 4.1 Surveillance Techniques |
| 4.2 Customer Feedback |
| 4.3 Acceptable Quality Levels |
| 5 QUALITY ASSURANCE DOCUMENTATION |
| 5.1 Ongoing Review by Technical Office Staff / Management |
| 5.2 Monitoring Forms |
| 5.2.1 The COR and PM will retain a copy of all completed QA surveillance forms. |
| 6 ANALYSIS OF QUALITY ASSURANCE ASSESSMENT |
| 6.1 Determining Performance |
| 6.1.1 Government shall use the monitoring methods cited to determine whether the performance standards have been met. If the contractor has not met the minimum requirements, it may be asked to develop a corrective action plan to show how and by what d... |
| 6.2 Reporting |
| 6.2.1 At the end of each month, the COR will prepare a written report for the PM summarizing the overall results of the quality assurance surveillance of the contractor’s performance. This written report, which includes the contractor’s submitted mon... |
| 6.3 Reviews and Resolution |
| 6.3.1 The COR may require the contractor’s project manager, or a designated alternate, to meet with the PM and other government IPT personnel as deemed necessary to discuss performance evaluation. The PM will define a frequency of in-depth reviews wi... |
| 6.3.2 The PM must coordinate and communicate with the contractor to resolve issues and concerns regarding marginal or unacceptable performance. |
| 6.3.3 The COR and contractor should jointly formulate tactical and long-term courses of action. Decisions regarding changes to metrics, thresholds, or service levels should be clearly documented. Changes to service levels, procedures, and metrics wil... |
| ATTACHMENT 1: PERFORMANCE REQUIREMENTS SUMMARY |
| ATTACHMENT 2: |
| SAMPLE QUALITY ASSURANCE MONITORING FORM |
File details come from the government source that posted it. Updated .