IFPQ_Public_Works_10A2969.pdf
PDF 714 KB Posted
- Attached to
- IFPQ Replace Chiller Coils - San Joaquin County
- Solicitation number
- 10A2969
- Issued by
- San Joaquin County, Santa Monica City, California
About this file
This Invitation for Price Quote (IFPQ) 10A2969 is issued by the California Department of Transportation (Caltrans), Division of Procurement and Contracts, for a small business set-aside public works project in San Joaquin County. The project involves the removal and legal disposal of three failed chiller coils and installation of three new equivalent chiller coils at Caltrans' District 10 Office located at 1976 East Dr. Martin Luther King Jr. Boulevard, Stockton, California. The work includes full lockout/tagout procedures, crane removal and placement of coils, nitrogen purging, brazing operations, pressure testing, deep vacuum pulling, and system charging with R-410A refrigerant. A mandatory site inspection is scheduled for December 1, 2026, at 10:00 a.m., with written questions due by December 2, 2026, at 5:00 p.m., and final quote submissions required by December 7, 2026, at 5:00 p.m. The estimated award date is December 21, 2026. The agreement term is estimated from February 1, 2027, through January 31, 2028, with services to be performed outside normal business hours or on weekends.
Bidders must be certified Small Businesses (SB), Micro Businesses (MB), SB for Public Works purposes (SB-PW), or Disabled Veteran Business Enterprises (DVBE) and must possess a current C-20 Warm-Air Heating, Ventilating and Air-Conditioning Contractor license from the California Contractors State Licensing Board. The total bid amount cannot exceed $484,000, with prevailing wage requirements applying if the bid exceeds $15,000. The price quote must include all labor, materials, equipment, and disposal costs, with line items for base work, hourly rates for unforeseen labor at eight dollars per hour, and a five-percent allowance for pre-approved parts and materials. At least two certified SB/MB or DVBE price quotes must be received before award can be made. If the bid exceeds $25,000, a Payment Bond equal to 100 percent of the contract amount is required prior to work commencement. Insurance requirements include Commercial General Liability ($1,000,000 per occurrence/$2,000,000 aggregate), Automobile Liability ($1,000,000 combined single limit), Workers' Compensation with statutory limits, and Pollution Liability ($1,000,000 per incident/$2,000,000 annual aggregate). Department of Industrial Relations registration is mandatory, and certified payroll records must be submitted with each invoice.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CALIFORNIA STATE TRANSPORTATION AGENCY GAVIN NEWSOM, GOVERNOR
California Department of Transportation
ADMINISTRATION
DIVISION OF PROCUREMENT AND CONTRACTS
1727 30TH STREET, MS 65
SACRAMENTO, CA 95816-7006
PHONE (916) 227-6000
TTY 711
https://dot.ca.gov/programs/procurement-and-contracts/
November 18, 2026
Invitation for Price Quote (IFPQ)
IFPQ 10A2969
Notice to Prospective Contractors
You are invited to review and respond to this Small Business (SB) Invitation for Price Quote (IFPQ), IFPQ 10A2969 entitled Replace Chiller Coils - San Joaquin County. In submitting your quote, you must comply with the instructions found herein.
“This solicitation is authorized pursuant to Government Code Section 14838.7, which provides for the award of contracts for the acquisition of construction, including the erection, construction, alteration, repair, or improvement of any State structure, building, road, or other State improvement of any kind, that has an estimated value of greater than $5,000.00, but not more than $484,000.00,to a certified SB, including a micro business (MB), SB for the purpose of public works (SB-PW), or a Disabled Veteran Business Enterprise (DVBE). A bid over $484,000.00 will result in rejection of your bid due to non-responsiveness.”
This contract requires Prevailing Wages if the total bid amount exceeds $15,000. If the total bid amount is under $15,000, then Prevailing Wage language will be removed prior to award. Refer to Attachment 3, Proposed Form of Agreement, for requirement details.
In the opinion of Caltrans, this IFPQ is complete and without need of explanation; however, if you have questions, or should you need any clarifying information, the contact person for this IFPQ is:
Laura Heberle California Department of Transportation (Caltrans) Email address: laura.heberle@dot.ca.gov Phone: (279) 234-2526
Please note that no verbal information given will be binding upon Caltrans unless such information is issued in writing as an official addendum.
*Technical questions regarding this solicitation will be addressed, in writing and at a site inspection to be held on December 1, 2026. See Section C1, Time Schedule, for more details.
ALL REQUIRED DOCUMENTS ARE EITHER ATTACHED (ATTACHMENT 1) OR THE DOCUMENT
LINK IS PROVIDED ON ATTACHMENT 2, REQUIRED DOCUMENTS.
Sincerely, Laura Heberle Contract Analyst https://dot.ca.gov/programs/procurement-and-contracts/ mailto:laura.heberle@dot.ca.gov
Invitation for Price Quote IFPQ Number 10A2969
A) Purpose and Description of Services
1. Contractor shall furnish all labor, tools, materials, parts, supplies, equipment, vehicles, travel, and incidentals necessary to remove and legally dispose of three (3) chiller coils and install three (3) new chiller coils for Caltrans.
2. The services shall be performed at Caltrans’ District 10 Office, located at 1976 East Dr. Martin Luther King Jr. Boulevard, Stockton, CA 95205, in San Joaquin County.
3. Refer to the Proposed Form of Agreement, Exhibit A, for a more complete description of services.
B) Bidder’s Minimum Qualifications
1. Bidder shall have at time of bid submittal, continually thereafter, and for the duration of this
Agreement a current and valid C-20 (Warm-Air Heating, Ventilating and Air-Conditioning Contractor) license issued by the California Contractors State Licensing Board (CSLB).
2. By submitting its bid, bidder certifies, under penalty of perjury, that its Contractors State License Board (CSLB) license is in a classification appropriate to the work to be undertaken as identified in the Proposed Form of Agreement, Exhibit A. This requirement has also been added in the Proposed Form of Agreement, Exhibit E. Refer to Section C, Price Quotation Requirements and Information, Contractor’s License, for submittal requirements. Caltrans will verify bidder’s Contractor License, and any Subcontractor Licenses, thus it is not necessary for bidders to provide a copy.
3. Bidder and subcontractor(s) shall possess at the time of bid submittal, continuously thereafter, and for the duration of the Agreement, a valid and current registration with the Department of Industrial Relations (DIR). Caltrans will verify bidder’s DIR registration; it is not necessary to provide a copy.
4. Failure of Bidder to sufficiently provide any or all the minimum qualifications, in the opinion of Caltrans, will result in the bidder’s bid deemed non-responsive.
C) Price Quotation Requirements and Information
1. Time Schedule
It is recognized that time is of the essence. All bidders are hereby advised of the following schedule and will be expected to adhere to the required dates and times.
Event Date Time (Pacific Time)
IFPQ available to prospective bidders 11/18/2026 Mandatory Site Inspection 12/01/2026 10:00 a.m.
Written Question Submittal 12/02/2026 5:00 p.m.
Final Date for Quote Submission 12/07/2026 5:00 p.m.
Proposed Award Date (estimate) 12/21/2026
2. Site Inspection A. A mandatory site inspection is scheduled at 10:00 a.m., December 1, 2026, at Caltrans’ District
10 Office, 1976 East Dr. Martin Luther King Jr. Boulevard, Stockton, CA 95205 for the purpose of discussing concerns regarding this IFPQ.
B. In the event a potential prime contractor is unable to attend the site inspection, an authorized representative may attend on its behalf. The representative may only sign in for one (1) company. Subcontractors may not represent a potential prime contractor at a site inspection.
C. If the site inspection is mandatory, bidders must sign in (on the sheet provided) upon arrival and sign out upon completion of the walk-through activities. Failure to comply with these provisions may result in the rejection of your quote. Caltrans will conduct the site inspection of the facilities and disseminate any additional information to participants, if necessary. Bidders should bring any questions they have to the site inspection.
3. Reasonable Accommodation For bidders who have and need assistance due to a physical impairment, a reasonable accommodation will be provided upon request for the site inspection. The bidder must call the designated Contract Analyst contact no later than the fifth (5th) working day prior to the scheduled date and time of the site inspection to arrange for a reasonable accommodation.
4. Questions and Answers A. Questions regarding this IFPQ must be submitted in writing. Bidders are encouraged to submit their written questions by 5:00 p.m., December 2, 2026.
B. Written questions must include the individual's name, firm name, complete address, and must reference IFPQ No. 10A2969. Questions must be sent to the following email:
Email: laura.heberle@dot.ca.gov
C. Written responses to all questions will be collectively compiled and posted, as an Addendum, to the Cal eProcure website https://caleprocure.com. It is the responsibility of the bidder to access the website for any changes or addenda that may be posted. Refer to Section C1, Time Schedule, for the IFPQ’s schedule of events and dates/times. Bidder can contact the Contract Analyst named above.
5. ADM-1412 – Price Quote Proposal The total price quote proposal for this Agreement must not exceed $484,000.00. A bid amount more than $484,000.00 will be deemed non-responsive and will be rejected.
6. Costs Included in Bid Rates Quotation prices/rates shall include the cost of employer payments to or on behalf of employees, subsistence, travel, compensation insurance premiums, unemployment contributions, social security taxes, contract bond premiums, and any other taxes or assessments, including, but not limited to, sales and use taxes required by law or otherwise and no additional allowance will be made thereof unless separate payment provisions in the Agreement should specifically so provide.
7. Employment of Undocumented Workers No State agency or department, as defined in Public Contract Code Section 10335.7, that is subject to this code, shall award a public works contract to a bidder or contractor, nor shall a bidder or contractor be eligible to bid for or receive a public works contract, who has, in the preceding five (5) years, been convicted of violating a State or Federal law regarding the employment of undocumented workers (Pub. Cont. Code Section 6101).
8. State Prevailing Wages State General Prevailing Wage Rates will apply for the County of San Joaquin as described in the Proposed Form of Agreement, Exhibit B. The predetermined general prevailing wage rates published by the Director of Industrial Relations (DIR) may be obtained via the Internet at https://www.dir.ca.gov/OPRL/DPreWageDetermination.htm. It is the bidder's responsibility to use the correct classification determination published by the DIR. By signing the attached Bid/Bidder Certification Sheet, the bidder acknowledges this is a public works contract subject to Labor Code Sections 1720-1861, and that if awarded this Agreement, it will be the bidder’s responsibility to ensure that all prevailing requirements are met, including but not limited to the payment of appropriate prevailing wages rates to all employees who participate and perform services under this mailto:laura.heberle@dot.ca.gov https://caleprocure.com/ https://www.dir.ca.gov/OPRL/DPreWageDetermination.htm
Agreement, Department of Industrial Relations registration, submittal of weekly certified payroll records, and employment of apprentices throughout the duration of the Agreement.
9. Mandatory Organic Waste Recycling Contractor generating organic waste or commercial solid waste shall comply with SB 1383; also Contractor will arrange for recycling services required by this section in a manner that is consistent with State and local laws and requirements, including a local ordinance or local jurisdiction’s franchise agreement, applicable to the collection, handling, or recycling of organic waste and commercial solid waste. This requirement does not modify, limit, or abrogate the Contractor’s right to sell or donate its recyclable organic waste materials consistent with the requirements of Public Resources Code Section 42649.8 et seq. When applicable, Contractor must comply with these provisions.
10. Motor Carrier Permit Requirements A. Contractor is responsible for determining whether California Vehicle Code Sections 34601 and
34620 require Contractor to have a valid Motor Carrier Permit (MCP) issued by the Department of Motor Vehicles (DMV) in order for Contractor to lawfully perform any part or aspect of the work described in Proposed Form of Agreement, Exhibit A, Scope of Work, and, if California Vehicle Code Sections 34601 and 34620 do require same for any part or aspect of such work, Contractor must have a valid MCP(s) issued from the DMV for its services as a Motor Carrier of Property under this Agreement. Contractor shall pay any required fees necessary to obtain and maintain in good standing during the entire term of this Agreement any such required MCP(s).
B. The MCP(s), if any, required for Contractor’s Motor Carriers of Property under California Vehicle Code Sections 34601 and 34620 shall be on file with Contractor for the duration of this Agreement. Upon request of Caltrans Contract Manager or their designee, Contractor must immediately provide to Caltrans a copy of the required MCP(s), if any.
11. Contractor Registration Program A. No Contractor or Subcontractor may be listed on a price quote proposal for a contract with prevailing wages unless registered with the DIR, pursuant to Labor Code Section 1725.5 (with limited exceptions from this requirement for bid purposes only under Labor Code Section 1771.1(a)).
B. No Contractor or Subcontractor may be awarded a contract with prevailing wages unless registered with DIR pursuant to Labor Code Section 1725.5.
C. Caltrans will verify each of the registration numbers provided by the bidder prior to Agreement award. Bidders that do not possess the required DIR registration will be deemed non-responsive and rejected from further consideration in the solicitation process.
D. If Contractor lists Subcontractor who is believed to be performing work that is not subject to the registration requirements, written confirmation from DIR must be obtained and submitted with the proposal to validate the bid.
12. Contractor’s License Bidder must have, at time of quote submittal and for the duration of the contract, a valid, current C-20 (Warm-Air Heating, Ventilating and Air-Conditioning Contractor) license issued by the CSLB, for the type of work to be performed. Bidder shall obtain, pay for, and maintain, in good standing, all necessary licenses and permits to accomplish the work. Bidders will be considered non-responsive unless proper licensing requirements are met. An invalid license will result in rejection of the bid. Positive verification of a valid license issued by the CSLB will be performed by Caltrans (Bus. and Prof. Code Section 7028.15).
13. Subcontractors
Bidder may subcontract portions of the work as defined in the attached Proposed Form of Agreement. If subcontractors are used, complete the Bidder Declaration (GSPD–05-105). Failure of a subcontractor to have the proper licenses, permits, and/or certifications, shall be cause for rejection of price quote. Bidder may only subcontract portions of the work to a qualified Department of General Services (DGS) Certified Small Business (SB), Micro Business (MB), or SB for the purpose of Public Works (SB-PW), or Disabled Veteran Business Enterprise (DVBE), with the same status of bidder. No work may be subcontracted to any business not certified as a SB/MB/SB-PW or DVBE by DGS. Bidder must ensure the Subcontractor(s) is DGS Certified SB/MB/SB-PW or DVBE and has all necessary licenses, permits, and/or certifications to accomplish its portion of the work.
14. Standard Title VI/Nondiscrimination Assurances (DOT Order No. 1050.2A) Caltrans, in accordance with the provisions of Title VI of the Civil Rights Act of 1964 (78 Statute 252, 42 USC Sections 2000d to 2000d-4) and the Regulations, hereby notifies all bidders that it will affirmatively ensure that any Agreement entered into pursuant to this advertisement, disadvantaged business enterprises will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, or national origin in consideration for an award.
15. Non-Collusion Declaration for Public Works Bidder must submit a non-collusion declaration for Public Works. The Non-Collusion Declaration for Public Works is provided as a link in Attachment 2, Required Documents.
16. Bonds Payment Bond Requirement: If the successful bidder’s bid exceeds $25,000, the successful bidder shall furnish a Payment Bond for not less than 100 percent (100%) of the total amount payable by the terms of this Agreement. The Payment Bond is due prior to the start date of work. No work may commence without receipt of a valid Payment Bond. The Payment Bond must be in effect at all times for the duration of the Agreement. If the Payment Bond expires during the term of the Agreement, a new Payment Bond must be provided to the Caltrans Contact Manager not less than 10 business days prior to its expiration. Failure to maintain a Payment Bond for the full term of this Agreement will be grounds for termination for default in addition to other legal remedies Caltrans may have. Inadequate or lack of a Payment Bond does not negate the Contractor’s obligations under this Agreement.
17. Insurance A. The bidder who receives the Agreement award must provide a Certificate of Insurance providing proof of insurance to the Division of Procurement and Contracts within 10 working days from the date of notification of award. The State’s Office of Risk and Insurance Management will review insurance certificates and/or proof of self-insurance documentation before execution of the Agreement. Refer to the Proposed Form of Agreement, Exhibit E, for the applicable and specific Insurance requirements and coverage limits.
B. The insurance carrier shall provide an endorsement for the additional insured statement as follows:
Caltrans, State of California, its officers, agents, and employees shall be included as additional insured, but only with respect to work performed for the State of California under this Agreement.
C. The additional insured endorsement must accompany the certificate of insurance.
D. Satisfying a Self-Insured Retention (SIR)
All insurance required by this Agreement must allow, but not require, the State to pay any SIR and/or act as Contractor’s agent in satisfying any SIR. The choice to pay any SIR and/or act as Contractor’s agent in satisfying any SIR is at the State’s discretion. If the State chooses to pay any SIR and/or act as Contractor’s agent in satisfying any SIR, Contractor shall reimburse the State for the same.
E. Available Coverages/Limits In the event the insurance coverages obtained by Contractor is broader in scope than, and/or the limits are higher than, those required under the Agreement, all such broader coverage and/or higher limits available to Contractor shall also be available and applicable to the State.
18. Darfur Contracting Act A. The Darfur Contracting Act, Public Contract Code Section 10475-10481, applies to any company that currently or within the previous three (3) years has had business activities or other operations outside of the United States. The Act was passed by the California Legislature and signed into law by the Governor to preclude State agencies generally from contracting with “scrutinized” companies that do business in the African nation of Sudan (of which the Darfur region is a part), for the reasons described in Public Contract Code Section 10475. All bidders shall complete the Darfur Contracting Act Certification (DOT ADM-0077), provided as a link in Attachment 2, Required Documents, and submit with the proposal.
B. If your company has not, within the previous three (3) years, had any business activities or other operations outside of the United States, complete Option 1 on the Darfur Contracting Act Certification form.
C. A scrutinized company is a company doing business in Sudan as defined in Public Contract Code Section 10476. Scrutinized companies are ineligible to, and cannot, bid on or submit a proposal for an Agreement with a State agency for goods or services (Pub. Cont. Code Section 10477(a)).
D. Therefore, Public Contract Code Section 10478(a) requires a company that currently has (or within the previous three (3) years has had) business activities or other operations outside of the United States to certify that it is not a “scrutinized” company, during the Agreement award process with a State agency.
E. A scrutinized company may still, however, submit a bid or proposal for a Contract with a State agency for goods or services if the company first obtains permission from the Department of General Services (DGS) according to the criteria set forth in Public Contract Code Section 10477(b).
19. Price Quote Submittal A. The Price Quote should be emailed as described below. All price quotes must be received by the Caltrans, Division of Procurement and Contracts (DPAC), by dates and times shown in Section C, Price Quotation Requirements and Information.
B. The price quote email should be clearly marked with the IFPQ number, title, and ‘PRICE QUOTATION SUBMITTAL’, as shown in the following example:
IFPQ Number: 10A2969
PRICE QUOTATION SUBMITTAL
C. All quotes shall include the documents identified in the IFPQ; see Attachment 2, Required Documents. Quotes not including the required documents may be deemed non-responsive. A non-responsive price quote is one that does not meet the basic quote requirements.
D. Only an individual who is legally authorized to bind the proposing firm contractually shall sign all documents requiring a signature, and each document must bear a signature.
E. Email to: laura.heberle@dot.ca.gov mailto:laura.heberle@dot.ca.gov
F. Pursuant to Government Code Section 14838.7, Caltrans must receive at least two (2) price quotes from certified SB/MBs or at least two (2) price quotes from DVBEs before it can make an Agreement award. Therefore, at Caltrans’ discretion, if only one price quote is received, the timeframe for receipt of price quotes may be extended in order to receive the minimum number of quotes required by the Government Code. All prospective bidders will be notified via email of any extensions.
G. Price quotes must include the performance of all the services described herein. Any attempt to modify the Price Quote Proposal document to deviate from the work specifications will not be considered and will cause a price quote to be rejected.
H. A price quote may be rejected if it is conditional, incomplete, or if it contains any alterations of form or other irregularities of any kind. Caltrans may reject any price quote on the basis that it is not responsive or from responsible bidder and may waive any immaterial deviation in a quote.
Caltrans’ waiver of an immaterial defect shall in no way modify the IFPQ document or excuse the bidder from full compliance with all requirements if awarded the Agreement.
I. Costs for developing price quotes and in anticipation of award of the Agreement are entirely the responsibility of the bidder and shall not be charged to Caltrans.
J. A bidder may modify a price quote after its submission by first withdrawing the original price quote and then by resubmitting a new price quote prior to the price quote submittal deadline.
Bidder modifications offered in any other manner, oral or written, will not be considered.
K. A bidder may withdraw a price quote by, prior to price quote submission deadline, submitting a written withdrawal request to Caltrans, at laura.heberle@dot.ca.gov, signed by the bidder or an agent authorized in accordance with Section L, below. A bidder may thereafter submit a new price quote prior to the price quote submittal deadline. Price quotes may not be withdrawn without cause subsequent to the price quote submittal deadline.
L. Only an individual who is authorized to bind the bidding firm contractually shall sign the Bid/Bidder Certification Sheet. The signature must also indicate the title or position that the individual holds in the firm. An unsigned price quote may be cause for bid rejection.
M. Caltrans may modify the IFPQ prior to the date fixed for submission of price quotations by the issuance of an addendum sent to all parties who received an IFPQ package.
N. Caltrans reserves the right to reject all price quotes for reasonable cause.
O. Bidders are cautioned not to rely on Caltrans during its evaluation process to discover and report to the bidder any defects and errors in the submitted documents. Before submitting their documents, bidders should carefully proof them for errors and full adherence to the IFPQ requirements.
P. Where applicable, bidder should carefully examine work sites and specifications. Bidder shall investigate conditions, character, and quality of surface or subsurface materials or obstacles that might be encountered. No additions or increases to the Agreement amount will be made due to a lack of careful examination of work sites and specifications.
Q. Caltrans does not accept alternate Agreement language from a bidder. A price quote with such language will be considered a counter proposal and will be rejected. The State’s General Terms and Conditions (GTC 02/2025) and Contractor Certification Clauses (CCC 04/2017) are not negotiable. The GTC 02/2025 may be viewed at Internet site https://www.dgs.ca.gov/OLS/Resources/Page-Content/Office-of-Legal-Services-Resources-List- Folder/Standard-Contract-Language.
20. Evaluation and Selection A. At the time of quote opening, price quotes will be checked for the presence or absence of required information in conformance with the submission requirements of this IFPQ.
mailto:laura.heberle@dot.ca.gov https://www.dgs.ca.gov/OLS/Resources/Page-Content/Office-of-Legal-Services-Resources-List-Folder/Standard-Contract-Language https://www.dgs.ca.gov/OLS/Resources/Page-Content/Office-of-Legal-Services-Resources-List-Folder/Standard-Contract-Language
B. Caltrans will check the price quote submittal package to verify it received all required documents. Positive verification of required documents will be performed to determine its responsiveness to the State’s needs.
C. Price quotes that contain false or misleading statements, or which provide references, which do not support an attribute or condition claimed by the bidder, shall be rejected.
D. The Agreement, if awarded, shall be awarded to the responsible bidder who submits the lowest price quote and meets all the specifications. A price quote meets the specifications if it complies with all the requirements in this solicitation. In the event of a tie quote, Caltrans will draw lots to determine the successful bidder. Only one (1) price quote may be submitted by an entity:
individual, firm, partnership, corporation, joint venture, or combination thereof. Receipt of more than one (1) price quote from an entity will result in all quotes from that entity being rejected and returned to the bidder.
21. Standard Conditions of Service A. Service shall not begin before the start date set forth in the Agreement. After all approvals have been obtained, and the Agreement is executed should Contractor fail to commence work at the agreed upon time, Caltrans, upon five (5) days written notice to contractor, reserves the right to terminate the Agreement. In addition, contractor shall be liable to Caltrans for the difference between contractor’s quote price and the actual cost of performing the work by the second low bidder or by another contractor.
B. All performance under the Agreement shall be completed on or before the expiration date of the Agreement.
C. Antitrust Provisions
1) Bidder offers and agrees, and will require all of his other Subcontractors and suppliers to agree, that if the bid is accepted to assign to the awarding body all rights, title, and interest in and to all causes of action they may have under Section 4 of the Clayton Act (15 USC Section 15) or under the Cartwright Act (Chapter 2 (commencing with Section 16700) of Part 2 of Division 7 of the Business and Professions Code) arising from purchases of goods, services, or materials pursuant to the public works Agreement or subcontract. The assignment made by Contractor and all additional assignments made by Subcontractors and suppliers shall be deemed to have been made and will become effective at the time the awarding body tenders final payment to Contractor without further acknowledgment or the necessity of tendering to the awarding body any written assignments.
2) If an awarding body or public purchasing body receives, either through judgment or settlement, a monetary recovery for a cause of action assigned under Government Code Sections 4550-4554, the assignor shall be entitled to receive reimbursement for actual legal costs incurred and may, upon demand, recover from the public body any portion of the recovery, including treble damages, and attributable overcharges that were paid by the assignor but were not paid by the public body as a part of the price quote, less the expenses incurred in obtaining that portion of the recovery.
3) Upon demand in writing by the assignor, the assignee shall, within one year from such demand, reassign the cause of action assigned under Government Code Sections 4550- 4554 if the assignor has been or may have been injured by the violation of law for which the cause of action arose and (a) the assignee has not been injured thereby, or (b) the assignee declines to file a court action for the cause of action (See Government Code Section 4554).
D. If bidder is awarded Agreement and refuses to sign Agreement presented for signature within time and manner required, bidder will be liable to Caltrans for actual damages resulting to Caltrans therefrom or 10 percent (10%) of the amount quoted, whichever is less.
E. Loss Leader usage is prohibited in this Solicitation: It is unlawful for any person engaged in business within this State to sell or use any article or product as a "loss leader" as defined in Business and Professions Code Section 17030. "Loss Leader" means any article or product sold at less than cost: a) where the purpose is to induce, promote, or encourage the purchase of other merchandise; or b) where the effect is a tendency or capacity to mislead or deceive purchasers or prospective purchasers; or c) where the effect is to divert trade from or otherwise injure competitors.
F. No oral understanding or agreement shall be binding on either party.
22. Executive Order N-6-22 – Russia Sanctions
On March 4, 2022, Governor Gavin Newsom issued Executive Order N-6-22 (the EO) regarding Economic Sanctions against Russia and Russian entities and individuals. “Economic Sanctions” refers to sanctions imposed by the U.S. government in response to Russia’s actions in Ukraine, as well as any sanctions imposed under state law. By submitting a bid or proposal, Contractor represents that it is not a target of Economic Sanctions. Should the State determine Contractor is a target of Economic Sanctions or is conducting prohibited transactions with sanctioned individuals or entities, that shall be grounds for rejection of the Contractor’s bid/proposal any time prior to contract execution, or, if determined after contract execution, shall be grounds for termination by the State.
23. Executive Order N-12-23 – Generative Artificial Intelligence (GenAI) Technology Use and Reporting A. The State of California seeks to realize the potential benefits of GenAI, through the development and deployment of GenAI tools, while balancing the risks of these new technologies.
B. Bidder / Offeror must notify the State in writing if it:
1) Intends to provide GenAI as a deliverable to the State; or
2) Intends to utilize GenAI as a deliverable to the State; including GenAI from third parties, to complete all or a portion of any deliverable that materially impacts:
a) Functionality of a State system,
b) Risk to the State, or
c) Contract performance.
Note: For avoidance of doubt, the term “materially impacts” shall have the meaning set forth in State Administrative Manual (SAM) § 4986.2 Definitions for GenAI.
C. Failure to report GenAI to the State may result in disqualification. The State reserves the right to seek any and all relief to which it may be entitled to as a result of such non-disclosure.
D. Upon notification by a Bidder / Offeror of GenAI as required, the State reserves the right to incorporate GenAI Special Provisions into the final contract or reject bids/offers that present an unacceptable level of risk to the State.
E. Government Code 11549.64 defines “Generative Artificial Intelligence (GenAI)” as an artificial intelligence system that can generate derived synthetic content, including text, images, video, and audio that emulates the structure and characteristics of the system’s training data https://www.gov.ca.gov/wp-content/uploads/2022/03/3.4.22-Russia-Ukraine-Executive-Order.pdf
STATE OF CALIFORNIA ∙ DEPARTMENT OF TRANSPORTATION Agreement Number 10A2969 PRICE QUOTE PROPOSAL Attachment 1 Page 1 of 1
ADM-1412 (REV. 9/2025)
Contractor’s Name (Please Print):
Item Number
Estimated Quantity
Unit Of Measure Item
Unit Price (Price Per
Unit of Measure)
Total (Estimated Quantity X Unit Price)
1 1 Each all labor, tools, materials, parts, supplies, equipment, vehicles, travel, and incidentals necessary to remove and legally dispose of three (3) chiller coils and furnish and install three (3) new chiller coils, per STD 213, Exhibit A, Scope of Work.
2 8 Per Hour
Hourly rate for all labor, equipment, tools, travel, and incidentals necessary to effectuate unforeseen unanticipated work needed to complete services (not included in item 1 above) as directed and approved by Caltrans Contract Manager per STD 213, Exhibit A, Scope of Work.
Subtotal: $
Maximum allowable expenditure for all parts, materials, supplies, fees, and permits per Exhibit A, Item 8. Actual cost will be reimbursed based on submitted original receipts. This Amount Shall be 5 percent (5%) of the Actual Subtotal Amount (0.05 x Subtotal). Enter calculated 5% in Total column.
1) The above quantities are estimates only and are given as a basis for comparison of quotes. No guarantee is made or implied as to the exact quantity that will be needed.
2) In case of discrepancy between the unit price and the total set forth for a unit basis time, the unit price shall prevail.
3) Do not alter, modify, or change this quote proposal sheet. Any alterations, modifications, or changes to this quote proposal sheet will be grounds to reject the quote.
4) Each line item must be quoted. Do not leave any unit price column blank or this quote proposal sheet will be deemed non-responsive.
Total This Proposal (Subtotal + Line 3)
Attachment 2
Required Documents
The following documents should be submitted, or your bid may be considered non-responsive.
Do not submit this checklist, the Proposed Form of Agreement, company advertisements, brochures, informational pamphlets, or any other document unless specifically noted in the IFPQ Requirements and/or as listed below.
☐ Attachment 1 – Price Quote Proposal (ADM-1412)
☐ Bid/Bidder Certification Sheet (DOT ADM-1416) Bid/Bidder Certification Sheet
☐ Bidder Declaration (GSPD-05-105) Bidder Declaration
☐ Non-Collusion Declaration Non-Collusion Declaration
☐ Darfur Contracting Act Certification (DOT ADM-0077) Darfur Contracting Act Certification
The following documents will be requested of the WINNING BIDDER at time of contract award;
they are NOT required at time of bid submittal:
Contractor Certification Clauses (CCC 04/2017) Contractor Certification Clauses
Payment Bond Payment Bond
Insurance (Requirements outlined in Proposed Form of Agreement, Exhibit E, Items 1 & 2)
Payee Data Record (STD 204) Payee Data Record https://forms.dot.ca.gov/v2Forms/servlet/FormRenderer?frmid=DOTADM1416 https://www.documents.dgs.ca.gov/dgs/fmc/gs/pd/gspd05-105.pdf https://forms.dot.ca.gov/v2Forms/servlet/FormRenderer?frmid=DOTADM1418 https://forms.dot.ca.gov/v2Forms/servlet/FormRenderer?frmid=DOTADM0077 https://www.dgs.ca.gov/-/media/Divisions/OLS/Resources/CCC-042017.pdf?la=en&hash=4DE3E4DC414511AE378794200BA43EBF91C758EE https://forms.dot.ca.gov/v2Forms/servlet/FormRenderer?frmid=DOTADM2009 https://www.documents.dgs.ca.gov/dgs/fmc/pdf/std204.pdf
Attachment 3
Proposed Form of Agreement
Note to Bidders: The following pages represent a sample of the Agreement that will be awarded, if any, from this IFPQ. Please review it carefully and present any questions in writing to the contact identified for this IFPQ.
2. The term of this Agreement is:
Contractor’s Name TBD Agreement Number 10A2969
Exhibit A
Public Works (State)
Scope of Work
1. Contractor agrees to provide to the California Department of Transportation (Caltrans) all labor, tools, materials, parts, supplies, equipment, vehicles, travel, and incidentals necessary to remove and legally dispose of three (3) chiller coils and install three (3) new chiller coils, as described herein.
2. The services shall be performed at Caltrans’ District 10 Office, located at 1976 East Dr.
Martin Luther King Jr. Boulevard., Stockton, CA 95205, in San Joaquin County.
3. Any reference to Caltrans Contract Manager shall also include his/her designee.
4. This Agreement will commence on February 1, 2027 (estimate), or upon approval by
Caltrans, whichever is later, and no work shall begin before that time. This Agreement is of no effect unless approved by Caltrans. Contractor shall not receive payment for work performed prior to approval of the Agreement and before receipt of notice to proceed by Caltrans Contract Manager. This Agreement will expire on January 31, 2028 (estimate).
The services shall be provided outside of the normal business hours of 7:00 a.m. to 5:00 p.m., Monday through Friday, except State holidays, or on the weekend. The parties may amend this Agreement as permitted by law.
5. All inquiries during the term of this Agreement will be directed to the project representatives listed below. Contractor shall provide advance written notice and receive advance written approval by Caltrans Contract Manager, without the necessity of an amendment, before changing the Project Manager noted below.
California Department of Transportation (Caltrans)
Contractor: TBD
Section/Unit: District 10/Facilities Project Manager:
Caltrans Contract Manager: TBD Address: 1976 East Dr. Martin Luther King Jr. Boulevard, Stockton, CA 95205
Address:
Business Phone Number: Business Phone Number:
Email: Email:
6. Detailed Description of Work A. The coils are located on two (2) different Daikin Plate and Frame Air Cooled Chillers, model number is AGZ130EDSEMNN00. Both chillers are located on the rooftop of the Caltrans District 10 Office building (see Attachment A, Map Showing Location of Chiller Coils to be Replaced).
B. Contractor shall remove and legally dispose of three (3) failed or failing chiller coils.
1) Chiller number 1, circuit 2 needs one (1) coil.
2) Chiller number 2, circuit 1 needs two (2) coils.
C. Contractor shall furnish and install three (3) new chiller coils utilizing the following steps:
1) New chillers shall be equivalent to the brand/model listed in Item 6A above.
Exhibit A
Public Works (State)
2) Contractor shall shut down both chillers and perform full lockout/tagout.
3) Contractor shall remove bolts and surrounding plates securing the existing coils.
4) Contractor shall cut and remove the three (3) failed coils.
5) Contractor shall use a crane to lift and remove the three (3) failed coils from the roof.
6) Contractor shall clean and prep all copper piping and fittings.
7) Contractor shall use a crane to lift and place the new coils onto the roof.
8) Contractor shall dry fit the three (3) new coils to confirm alignment.
9) Contractor shall purge with nitrogen and braze in new coils once fit is confirmed.
10) Contractor shall perform a standing pressure test to inspect for leaks.
11) Contractor shall pull into a deep vacuum after passing the pressure test.
12) Contractor shall charge the system with 65lbs per circuit, 195lbs total of R-410A refrigerant.
13) Contractor shall start the unit and complete an operational test.
D. Site preparation
1) Contractor shall block working area as needed.
2) Contractor shall be responsible for limiting dust and dirt migration in the project area.
E. Contractor shall be responsible for verifying all details and requirements in accordance with this Exhibit A, Scope of Work at the mandatory site inspection.
7. Bid Proposal (Attachment 1), Line Item 1 includes the cost of parts, materials, supplies, and equipment referenced within this Exhibit A, Section 6. If applicable, other parts, materials, and supplies shall be in accordance with Exhibit A, Item 8.
8. Parts/Materials/Supplies/Fees/Permits A. Contractor shall notify Caltrans Contract Manager in writing of any parts/materials/ supplies/fees/permits not specifically identified in Attachment 1, Price Quote Proposal, that are necessary to complete the work. Written approval from the Caltrans Contract Manager must be obtained prior to the purchase or installation of such items for the costs to be eligible for reimbursement.
B. Contractor will be reimbursed for the actual cost of pre-approved parts/materials/ supplies/fees/permits purchased to be consumed or installed at the work site in performance of the Agreement (including applicable sales tax), without additional allowance for markup. No additional compensation will be made for the cost to acquire, store, deliver, or use/install any purchased items. Cost of parts/materials/supplies/fees/ permits are to be verified and substantiated by submitting a copy of appropriately signed receipts. Total expenditure for parts/materials/supplies/fees/permits shall not exceed the amount set forth in Attachment 1.
C. Contractor shall not be reimbursed for any parts/materials/supplies/fees/permits that were not pre-approved in writing by Caltrans Contract Manager.
Exhibit A
Public Works (State)
9. Unforeseen Labor A. Contractor must notify Caltrans Contract Manager in writing of any labor not reasonably anticipated in Exhibit A, Scope of Work but necessary for completion of the work.
Contractor must receive written approval from Caltrans Contract Manager prior to performing unforeseen labor.
B. The cost of unforeseen labor shall be in accordance with bid rate in Attachment 1, Price Quote Proposal.
C. Contractor shall not be reimbursed for any unforeseen labor that was not pre-approved in writing by Caltrans Contract Manager.
10. Damages to State Property A. In the event that any Caltrans property is damaged as a result of the actions of
Contractor, or its employees, Contractor shall repair, at its sole expense, the damage which has occurred as a direct result of Contractor, or its employees.
B. Repair efforts must be performed in a manner that ensures all warranties are maintained for any products that are damaged.
C. Repair efforts shall include the full costs for all required labor and materials. If the repair must be completed by an outside entity, Caltrans Contract Manager will approve of who shall be hired to complete the work.
11. Code of Conduct A. It is the duty of Contractor and its staff to read and adhere to Caltrans policies and directives, available to Caltrans staff including, but not limited to the most current version of Director’s Policy (DP) 3-Health and Safety, DP 18-Workplace Violence Prevention, Deputy Directive (DD) 8-Drug Free Workplace, DD 22-Weapons Prohibited on or in Caltrans Buildings and Caltrans Property, and DD 49-Sexual Harassment Prevention.
B. Contractor and its employees shall be aware they are working on Caltrans property and be courteous and respectful at all times. Contractor and its employees shall refrain from using loud voices, inappropriate language, and shall conduct themselves in a professional manner at all times.
12. Work Site Clean-up A. Contractor shall own and assume all responsibility for all litter, waste, debris, and similar materials arising from or produced by the work performed under this Agreement.
Contractor shall haul away and legally discard any materials or debris caused by its work actions from the job site.
B. Contractor shall clean and keep the area in orderly, safe, and clean condition as applicable to the services in accordance with this Statement of Work. If the work site is not left in a clean and orderly condition in the sole opinion of Caltrans Contract Manager, then Contractor shall be called back to correct the condition at no additional charge to Caltrans.
C. No litter, waste, debris, or other materials shall be deposited in any Caltrans dumpsters without advance written permission of Caltrans Contract Manager.
Exhibit A
Public Works (State)
D. Contractor’s bid shall include the cost to dispose of and/or recycle refrigerant, to include any discarded materials resulting from installs, repairs. Contractor shall be responsible for such disposal, recycling costs and shall be included in Attachment 1.
13. Inspection and Acceptance for Payment A. It is Contractor's responsibility to notify Caltrans Contract Manager that work is complete and ready for inspection. Contractor shall notify Caltrans Contract Manager within 24 hours of work completion for final inspection.
B. Caltrans Contract Manager will have the ultimate responsibility and authority to determine whether Contractor has satisfied the Contractor’s duties and obligations under the Agreement, including specifically whether Contractor delivered all work product and deliverables and whether Contractor’s work product and deliverables satisfied all of the applicable Agreement requirements (including acceptance criteria or tests).
C. Approval of work constitutes approval for payment and not transference or termination of Contractor’s responsibility to perform work in accordance with the terms of the Agreement. Any work that needs corrections shall be provided by Contractor at Contractor's sole cost and expense in a timely manner, which may be expressly agreed upon in writing by the parties.
14. Warranty A. Upon completion of work and acceptance of work by Caltrans Contract Manager, Contractor shall provide a warranty for a term of one (1) year, against defects and deficient workmanship for all work performed under this Agreement.
B. Contractor shall provide a warranty on any new installations for a period of one (1) year, from the completion date.
C. Contractor shall guarantee all parts, components, and services that were provided under this Agreement for one (1) year.
15. Waste Disposal Prior to the commencement of waste disposal, Contractor must adhere to the provisions highlighted in Senate Bill 1383 (Lara) of 2016 Title 14, CCR, General Provisions section 18981.2, Public Resources Code sections 42652 et. Seq.
Exhibit B
Public Works–State
Budget Detail and Payment Provisions
1. Invoicing and Payment
A. For services satisfactorily rendered and approved by Caltrans Contract Manager, and upon receipt and approval of the invoices, Caltrans agrees to compensate Contractor in accordance with the Attachment 1, Price Quote Proposal, and this Exhibit B.
Incomplete or disputed invoice(s) shall be returned to Contractor, unpaid, for correction.
B. Invoice(s) shall be itemized in accordance with Attachment 1, Price Quote Proposal, and shall be signed and submitted in triplicate not more frequently than monthly in arrears of the service.
C. Each invoice shall include:
1) Agreement Number 10A2969
2) Dates of Service
3) Location of Service
4) Description of Work Performed
5) Receipts for Parts/Materials/Supplies/Fees/Permits
D. Each invoice shall be submitted in triplicate to:
California Department of Transportation (Caltrans) District 10/Business Operations / Facility Operations Branch Attention: Contract Manager’s Name TBD 1976 E. Dr. Martin Luther King Jr. Boulevard Stockton, CA 95205
E. Contractor shall submit a certified copy of all payroll records for verification by Caltrans Contract Manager and/or designee with each invoice. Delinquent or inadequate certified payrolls or other required documents will result in the withholding of payment until such documents are submitted by Contractor.
2. Budget Contingency Clause A. It is mutually understood between the parties that this Agreement may have been written before ascertaining the availability of congressional or legislative appropriation of funds, for the mutual benefit of both parties in order to avoid program and fiscal delays that would occur if the Agreement were executed after that determination was made.
B. This Agreement is valid and enforceable only if sufficient funds are made available to Caltrans by United States Government or California State Legislature for the purpose of this program. In addition, this Agreement is subject to any additional restrictions, limitations, conditions, or any statute enacted by the Congress or the State Legislature that may affect the provisions, terms, or funding of this Agreement in any manner.
C. It is mutually agreed that if Congress or State Legislature does not appropriate sufficient funds for the program, Agreement shall be amended to reflect any reduction in funds.
D. Pursuant to Government Code Section 927.13, no late payment penalty shall accrue during any time period for which there is no Budget Act in effect, nor on any payment or
Exhibit B
Public Works–State refund that is the result of a federally mandated program or that is directly dependent upon the receipt of federal funds by a state agency.
E. Caltrans has the option to terminate the Agreement under the 30-day termination clause or to amend the Agreement to reflect any reduction of funds.
3. Prompt Payment Clause A. Payment will be made in accordance with, and within the time specified in, Government
Code, Chapter 4.5, commencing with Section 927 and all agreements must comply with Public Contract Code Sections 10262 and 10262.5.
B. Pursuant to Public Contract Code Section 10262, Contractor shall pay its Subcontractor(s) within seven (7) calendar days from receipt of each payment made to Contractor by Caltrans.
C. Failure of Contractor adhering to Public Contract Code Section 10262 may result in termination of this Agreement per Public Contract Code Section 10253 and disciplinary action by the Contractors State License Board may be implemented.
D. Any subcontract entered into as a result of this Agreement shall contain all the provisions of this clause.
4. Cost Limitation A. Total amount of this Agreement shall not exceed $TBD.
B. It is understood and agreed that this total is an estimate and that Caltrans will pay only for those services actually rendered as authorized by Caltrans Contract Manager up to the total amount set forth in Section 4A, above.
5. Excise Tax State of California is exempt from Federal excise taxes, and no payment will be made for any taxes levied on employees’ wages. Caltrans will pay for any applicable State or local sales or use taxes on the services rendered or equipment or parts supplied pursuant to this Agreement. Caltrans may pay any applicable sales and use tax imposed by another state.
6. Costs Included in Bid Rates A. The cost of employer payments to or on behalf of employees, subsistence, travel, compensation insurance premiums, unemployment contributions, social security taxes, Agreement bond premiums, and any other taxes or assessments including sales and use taxes required by law or otherwise shall be included in the Agreement rates and no additional allowance will be made thereof, unless separate payment provision should specifically so provide.
B. Contractor shall make travel and subsistence payments to each worker in compliance with Labor Code Sections 1773.1 and 1773.9. Travel and subsistence requirements are available on the of Department of Industrial Relations (DIR) website at https://www.dir.ca.gov/OPRL/DPreWageDetermination.htm.
7. Cost Principles A. Contractor agrees that…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .