RFI1LEWboiler.pdf

PDF 37 KB Posted

Attached to
Replace Boiler at the United States Penitentiary (USP) Lewisburg, Pennsylvania
Solicitation number
IFBP02071100001
Issued by

View the file

Other files

File Type Posted
BidResultsBOILERlewisburg.pdf PDF
WageRatesAUG5.PDF PDF
Amendment3.PDF PDF
Amendment2.PDF PDF
WageRatesJuly292011.PDF PDF
MeetingMinutes.pdf PDF
Amendment0001.PDF PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Information (RFI) 1

IFBP02071100001

Replace Boiler

USP Lewisburg

1. Under section 2 part 2-products number 7 the micro modulation controller it does not say what controller to use as long as it meets the specifications, however under subsection k ii, it calls out for a AutoFlame

MK7 controller. Just want to clarify if you are specifying the AutoFlame system or not.

ANSWER: Please omit the following paragraph:

PART 2 ~ Products, Section C, part 7, sub section k, number ii "The control panel will include a AutoFlame MK7 controller with servo motors mounted on the fuel valves and the FGR system."

All controls must be suitable and compatible with all current controls being used in the power plant.

2. Section c#7kii makes reference to an AutoFlame MK7 controller. Do we have any latitude in choice of other systems?

ANSWER: Please omit the following paragraph:

PART 2 ~ Products, Section C, part 7, sub section k, number ii "The control panel will include a AutoFlame MK7 controller with servo motors mounted on the fuel valves and the FGR system."

All controls must be suitable and compatible with all current controls being used in the power plant.

3. Section C1 specifies a four pass boiler. Would it be considered to do a like for like change of the existing three pass boiler?

ANSWER: Please follow the statement of work. Please prepare a bid for a four pass boiler.