QUESTIONS AND ANSWERS

IFBP010617000001

REPLACE LIFT STATION

USP MCCREARY - PROJECT 1B7J

Question from Locke-Lane Construction Company, Incorporated:

1. The contract Period of Performance is currently 119 Days. The equipment supplier, who is the basis of design, has advised that delivery of new equipment, including time for shop drawings and approval, will take 210 days. Can the Period of Performance be extended to 255 days to allow for material delivery and proper coordination of installation?

CHANGE: Yes. An amendment to the solicitation has been issued to change the performance period from 119 calendar days to 252 calendar days.