This is a Project Detail Sheet for an Invitation for Bid (IFB-SL0000000043SL) issued by the City of St. Louis for a mowing project along Interstate 70. The project encompasses mowing and litter removal services across approximately 96.48 acres of contract limits. The contractor shall complete six mowing and litter removal cycles during the initial contract term, with an additional four optional litter removal cycles anticipated between December and March. The total mowing quantity is 578.88 acres over the contract term, with matching litter removal quantities of 578.88 acres for required cycles and 385.92 acres for optional cycles. The initial contract term commences March 1, 2026, and terminates February 28, 2027, with two extension options: the first extended term running March 1, 2027, through February 29, 2028, and the second extended term running March 1, 2028, through February 28, 2029. The contractor must complete all work within nine working days following the notice to proceed for each mowing and litter removal cycle.
Mowing equipment shall have a minimum adjustable height of 2 to 6 inches, with all grass and vegetation cut and trimmed to a height of four inches unless otherwise directed by the engineer. No special equipment or equipment restrictions are required for this contract. The project includes a special sign detail specification with a black background and orange florescent sheeting, consistent with MoDOT standards. The document does not provide pricing information, set-aside details, incumbent contractor information, or funding source specifications within the scope of this Project Detail Sheet.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Mowing Project SL-2026-F Interstate 70 City of St. Louis Project Detail Sheet 1 of 4
Contract Limits and Location Sketch
IFB-SL0000000043SL
Project Detail Sheet 2 of 4
Contract Term and Extension
Initial Contract Term: Commencing March 1, 2026 and shall terminate February 28, 2027 First Extended Term: Commencing March 1, 2027 and shall terminate February 29, 2028
Second Extended Term: Commencing March 1, 2028 and shall terminate February 28, 2029
Contract Limits and Exclusions
See attached display for mowing areas.
Mowing and Litter Removal Cycles
6 mowing and litter removal cycles are anticipated
Optional Litter Removal Cycle
4 optional litter removal cycles anticipated between December and March
Mowing Quantities
The quantities shown are the total estimated acres to be mowed during one contract term if all areas are mowed and the anticipated number of mowing cycles are authorized.
The quantities are calculated as follows:
TOTAL AREA PER MOWING CYCLE (APPROXIMATE): 97.09 ACRES
Total Area in Number of Mowing Total Mowing Quantity Contract Limits X Cycles During Contract = During Contract Term (Acres) Term (Acres)
96.48 (FULL) X 6 = 578.88
TOTAL CONTRACT QUANTITY – MOWING: 578.88 ACRES
Project Detail Sheet 3 of 4
Litter Removal Quantities
In accordance with the contract specifications the litter removal area is presumed to be equal to the mowing area.
Total Area in Number of Litter Removal Total Litter Removal Quantity Contract Limits X Cycles During Contract = During Contract Term
96.48 (FULL) X 6 = 578.88
TOTAL CONTRACT QUANTITY – LITTER REMOVAL: 578.88 ACRES
Optional Litter Removal Quantities
Total Area in Number of Litter Removal Total Litter Removal Quantity Contract Limits X Cycles During Contract = During Contract Term
96.48 X 4 = 385.92
TOTAL CONTRACT QUANTITY – OPTIONAL LITTER REMOVAL: 385.92 ACRES
Contract Time for Completion of Work
The contractor shall complete all work required through the entire contract limits within the working days specified below after the notice to proceed date.
Mowing Cycle with Litter Removal Cycle:
96.48 Acre Cycle: 9 Working Days
Optional Litter Removal Cycle:
96.48 Acre Cycle: 9 Working Days
Mowing Height & Special Equipment
1) Mowing equipment shall have a minimum adjustable height of 2 to 6 inches.
2) No special equipment or equipment restrictions are required for this contract.
3) All grass and vegetation shall be cut and trimmed to a height of four (4) inches unless otherwise directed by the engineer.
Project Detail Sheet 4 of 4
Special Sign Detail
COLOR
Legend & Border – Black
Background – Orange
SHEETING
MoDOT Florescent Orange
| Contract Limits and Location Sketch |
| Mowing and Litter Removal Cycles |
| Mowing Quantities |
| Litter Removal Quantities |
| Mowing Height & Special Equipment |
| Special Sign Detail |
File details come from the government source that posted it. Updated .