About this file
This Invitation for Bid (IFB IGSA #26-05) is issued by the Town of Bowling Green, Virginia for the replacement of a failed HVAC system at Building 179 (Network Enterprise Command) located at Fort A.P. Hill under an intergovernmental support agreement (IGSA). The project involves the complete replacement of an existing 15-ton split-system HVAC unit with a new 10-ton heat pump and propane furnace system, including all associated ductwork, refrigerant lines, propane piping, electrical systems, controls, diffusers, and related components. One lump-sum bid is required for the entire scope of work. The solicitation was issued on November 13, 2026, with questions due by November 30, 2026 at 12:00 PM. An optional escorted site visit/prebid meeting is scheduled for November 20, 2026 at 11:00 AM, with RSVP required by November 19, 2026 at 4:30 PM. Sealed bids are due December 14, 2026 at 3:00 PM Eastern Time via eVA, with public bid opening at the same time via Microsoft Teams. The proposed contract completion period is 90 calendar days after the Town's written notice to proceed. Award will be made to the lowest responsive and responsible bidder based on the total lump-sum base bid.
Pricing must be firm and all-inclusive of labor, materials, equipment, delivery, supervision, overhead, profit, and applicable taxes. The solicitation does not specify a set-aside. No bid security is required as the anticipated contract value is not expected to exceed $500,000; however, if any bid exceeds $500,000, that bidder must provide 5% bid security. All successful bidders must provide performance and payment bonds at 100 percent of the contract value if the award exceeds $500,000. Required insurance includes workers' compensation at Virginia statutory limits, employers' liability at $500,000, commercial general liability at $1,000,000 combined single limit, and automobile liability at $1,000,000 combined single limit. Bidders must demonstrate five years of similar HVAC installation experience with three comparable references; all subcontractors must meet identical experience requirements. Bidders must hold a valid Virginia contractor license and appropriate trade licenses. The Town will pay invoiced work within 45 days of receipt, and subcontractors must be paid within seven days of the Town's payment to the prime contractor. All work is subject to Fort A.P. Hill inspection and approval, and must comply with applicable UFC, UFGS, IBC, IMC, NFPA, and other federal and state codes and standards.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TOWN OF BOWLING GREEN BUILDING 179 HVAC REPLACEMENT
Sealed Invitation for Bid
TOWN OF BOWLING GREEN, VIRGINIA
IFB IGSA #26-05
Building 179 NEC HVAC Replacement
| Solicitation information |
| Details |
| Issue date |
| November 13, 2026 |
| Questions due |
| November 30, 2026, 12:00 PM |
| Bids due |
| December 14, 2026, 3:00 PM |
| Public bid opening |
| December 14, 2026, 3:00 p.m. Eastern, via Teams. |
| Prebid meeting or site visit |
| Optional escorted visit • November 20, 2026, 11:00 AM. RSVP by November 19, 2026, 4:30 PM by email: IGSA@townofbowlinggreenva.gov |
| Contract period or completion |
| Proposed: 90 calendar days after notice to proceed |
Submission instructions Submit one complete, signed bid electronically through the eVA solicitation for this project. The eVA receipt timestamp controls.
Town of Bowling Green • Office of the Town Manager Fort A.P. Hill work order APHL_GE0003726 Use the assigned IFB number and project title on all bid documents. See Section 5 for submission and opening procedures. Identify the event as IFB IGSA #26-05.
Solicitation contact Town IGSA Procurement Office | IGSA@townofbowlinggreenva.gov | 804-633-6212 Postings and addenda: eva.virginia.gov and townofbowlinggreenva.gov (Bids and RFPs).
The Town welcomes bids from all qualified firms and will administer this procurement without discrimination on grounds prohibited by Virginia law, including religious character or affiliation (§§ 2.2-4310 and 2.2-4343.1).
IFB Submission Form Building 179 HVAC Company identification and ownership disclosure Legal company name ____________________________________________________________ Trade name if different _______________________________________________________ Business address ______________________________________________________________ Remittance address if different _______________________________________________ Contact name and title ________________________________________________________ Telephone and email ___________________________________________________________ State of organization _________________________________________________________ Parent company or affiliated entities _________________________________________ SCC identification number or exemption ________________________________________ Business type: [ ] Corporation [ ] LLC [ ] Partnership [ ] Sole proprietor [ ] Other Voluntary business classification: [ ] Small [ ] Minority owned [ ] Women owned [ ] Service-disabled veteran owned [ ] Other: __________________________ Persons with an ownership interest of 3% or more, with addresses (attach additional sheet if needed):
Conflict disclosure and certification The Bidder [ ] is [ ] is not aware of an actual or potential conflict of interest relating to this procurement. Explain any disclosed conflict on an attached sheet. This procurement is subject to applicable Virginia conflict-of-interest and procurement ethics requirements.
I certify that this bid is submitted independently and without collusion or fraud; that the information supplied is accurate and complete; and that I am authorized to bind the Bidder. The Bidder agrees to furnish the goods, services, or construction described in this IFB at the prices in Attachment B and in accordance with the solicitation and acknowledged addenda.
Authorized signature __________________________________________________________ Printed name and title ________________________________________________________ Date __________________________________________________________________________
BIDDER MUST COMPLETE AND RETURN THIS FORM WITH THE BID.
Contents 1 Introduction 2 Background Information 3 Procurement Rules and Definitions 4 Scope of Work and Specifications 5 Administrative Requirements and Instructions 6 Bid Submittal Requirements 7 Special Terms and Conditions 8 Insurance Requirements 9 Forms Form A Bidder References Form B Subcontractor Information and References Form C Subcontractor Conflict Disclosure Form D State Corporation Commission Information Form E Acknowledgment of Addenda 10 Attachments Attachment A Scope of Work and Specifications Attachment B Pricing Schedule Attachment C Required Insurance Attachment D General Terms and Conditions Sections 1 through 4 1 Introduction The Town invites sealed bids for one complete HVAC replacement at Fort A.P. Hill under its intergovernmental support agreement (IGSA). The Town awards and administers the construction contract, issues the notice to proceed and change orders, and pays the Contractor. Fort A.P. Hill reviews technical submittals, coordinates installation access and inspects the work.
2 Background Information The failed 15-ton split system serves the main office area of Network Enterprise Command Building 179. Two other systems serve different areas and must remain protected. The new dual-fuel system will replace the failed equipment, its associated ductwork and distribution components. See the October 30, 2026 work request in Attachment A.
3 Procurement Rules and Definitions This solicitation and resulting contract are governed by the Virginia Public Procurement Act and applicable Town requirements. Receipt of this IFB does not constitute a determination of bidder qualifications. “Shall,” “must,” and “will” identify requirements; “may” indicates permission, and “should” indicates a recommendation.
Bid. The offer submitted in response to this IFB, including the signed forms and pricing schedule.
Bidder. The person or entity submitting a bid.
Contractor. The successful Bidder with whom the Town enters into a contract.
Procurement Officer. The Town representative designated to administer the solicitation.
Town Project Manager. The Town representative designated to oversee performance and review deliverables. This designation alone does not authorize contract changes.
Contract Documents. The executed agreement or purchase order, this IFB and attachments, applicable addenda, the accepted bid, and authorized written amendments.
Addendum. A written clarification or revision issued by the Town before the bid deadline.
Change Order. An authorized written modification to the contract scope, price, or schedule.
Work. All goods, services, labor, materials, equipment, and documentation required by the contract.
Days. Calendar days unless business days are expressly specified. Times are Eastern Time.
4 Scope of Work and Specifications Provide one installed, tested and accepted system as described in Attachment A. Price the entire scope as one lump sum in Attachment B. Price the 10-ton design. Obtain Town approval for any cost or schedule change arising from field verification. Only a written Town change order authorizes changed work. The 30-day Town-to-Garrison proposal period shown in Attachment A is an intergovernmental milestone. The cover governs bidder deadlines.
5 Administrative Requirements and Instructions
5.1 Schedule and submission
The cover establishes the issue date, question deadline, bid deadline, and public opening details. Changes to these requirements will be made by written addendum. The Bidder is responsible for confirming receipt of its bid before the deadline.
Upload all signed forms and supporting documents to the eVA event by the closing time. Verify successful receipt. Paper copies are not required.
The Town will publicly open timely bids and announce bidder names and bid prices at the advertised opening. Email, fax and late bids will not be accepted.
Emergency closure. If the Town declares administrative or liberal leave on closing day, closing and opening move to the same times on the next Town business day. The Town will post updated instructions and any system-outage extension by addendum on eVA and the Town website.
5.2 Questions and addenda
Submit questions in writing to the solicitation contact by the question deadline on the cover. Use the subject line “Building 179 HVAC.” Only a written addendum issued by the Town changes the IFB. Oral statements do not amend the solicitation.
Bidders shall review the posting locations identified on the cover for addenda and acknowledge all addenda on Form E. Each Bidder is responsible for incorporating issued changes into its bid.
5.3 Bidder responsibility and communications
Bidders shall examine the solicitation, specifications, and relevant site conditions and promptly request clarification of discrepancies. Direct procurement communications to the designated contact. Other Town staff are not authorized to amend this solicitation or commit the Town. From issuance through selection, direct IFB discussions to the Procurement Officer, including questions arising during the site visit. The Town may reject a bid for unauthorized contacts intended to influence the procurement. The person identified on the submission form is the bidder’s representative.
5.4 Bid validity and preparation costs
Bids remain binding for 90 calendar days after opening. An extension requires mutual written consent. Bidders bear their own submission costs.
5.5 Correction and withdrawal
Before closing, use eVA to withdraw or replace a bid and confirm receipt. A replacement must be complete and timely.
Withdrawal due to error. Under Va. Code § 2.2-4330(B)(1), deliver written notice claiming withdrawal and the original work papers to the Town Procurement Officer within two business days after bid opening. Relief requires proof of a qualifying good-faith clerical mistake under § 2.2-4330. The Town will give written notice of its decision and return the work papers as the statute requires. Review is available under § 2.2-4358. Deliver original papers to the Office of the Town Manager, 117 Butler Street, Bowling Green, VA 22427. The Town will notify the bidder in writing within five business days of its decision.
5 Award and Contract Administration
5.6 Basis of award
The Town will make one award, if any, to the lowest responsive and responsible bidder based on the total lump-sum base bid. The Town will evaluate only the published criteria.
No alternates, unit-price extensions, renewal options or multiple awards will be evaluated. The Town has reserved no authority in this IFB to negotiate an over-budget bid. If funds are insufficient, the Town may reject bids and resolicit under § 2.2-4319.
The Town may investigate qualifications, references, financial capacity, licenses, resources, and past performance to determine responsibility. Bidders shall furnish reasonably requested supporting information. An adverse determination concerning the apparent low bidder’s responsibility is subject to the notice, records review, rebuttal and appeal procedures of § 2.2-4359.
5.7 Acceptance and rejection
The Town reserves the right to cancel the solicitation, reject any or all bids, and waive informalities as permitted by law. A waiver shall not permit a material change in a bid or give a bidder an unfair competitive advantage. Notice of award or intent to award will be posted at the Town website and eVA. The Town will document its reasons for cancellation or rejection in the procurement file. Award is subject to available funds and applicable approvals.
5.8 Preaward documents and contract term
Within ten calendar days of written notice of selection and before award, furnish license copies, the Town-furnished workers’ compensation form (§ 2.2-4332), insurance certificates and required endorsements. Furnish tax information through the Town’s secure process. Selection alone does not authorize purchases or fieldwork.
The proposed completion period is 90 calendar days after the Town’s written notice to proceed. Work shall begin only as authorized in that notice. Prices are firm except for authorized written changes.
5.9 Confidentiality and public records
Procurement records are subject to Virginia law. To seek protection for trade secrets or proprietary information under § 2.2-4342, the Bidder shall invoke protection before or upon submission, specifically identify the information, and explain why protection is necessary. An entire bid, nonproprietary information, line-item prices, and total prices may not be designated confidential. Disclosure will be determined in accordance with law. Upon request, bidders may inspect procurement records at the times and on the conditions provided in § 2.2-4342.
5.10 Protests
File a written protest with the Town Manager at IGSA@townofbowlinggreenva.gov within ten days of award or the decision to award, whichever occurs first, subject to the records-inspection extension in Va. Code § 2.2-4360. State the grounds and relief sought. The Town will issue a reasoned written decision within ten days. Appeal within ten days of receipt as provided by §§ 2.2-4360 and 2.2-4364. A nonresponsibility determination follows § 2.2-4359.
6 Bid Submittal Requirements Prepare a clear, economical bid. Submit the following documents using the method stated on the cover. Mark inapplicable forms “Not applicable” where permitted.
• Signed IFB Submission Form.
• Completed and signed Attachment B Pricing Schedule.
• Form E Acknowledgment of Addenda.
• Form D State Corporation Commission Information.
• Form A with three comparable references for the bidder and documentation of five years of similar HVAC installation experience.
• For each proposed subcontractor, Form B with three references and five years of similar installation experience, and a signed, notarized Form C. If none are proposed, mark Form B accordingly.
• Virginia contractor license number, class and specialty appropriate to the bid and evidence of applicable trade licenses. State whether the bidder is a Virginia resident or nonresident and provide its license expiration date under Title 54.1, Chapter 11.
• Proof of insurance capability, such as a certificate or insurer letter, for Attachment C requirements.
• Bid security for bids exceeding $500,000 as specified in Section 7.8.
• Identify proposed equipment and submit supporting product data for any proposed equivalent.
Bidder checklist [ ] IFB number and title are correct.
[ ] Forms are complete and authorized signatures are included.
[ ] Prices cover the entire required scope.
[ ] Addenda have been reviewed and acknowledged.
[ ] Required attachments and bid security are included.
[ ] Submission method, delivery location, and deadline have been verified.
Additional information The Town may request information needed to assess bidder responsibility or clarify the bid as permitted by law. Such requests do not authorize a Bidder to change a material requirement or price after opening.
7 Special Terms and Conditions
7.1 Brand name or equal. Unless expressly justified and designated otherwise in the issued specifications, brand references describe the required quality and characteristics. A proposed equivalent must be identified in the bid and supported with information showing compliance with the stated salient characteristics. The Town will determine acceptability under the specifications. For the new heat pump and furnace in Attachment A § 2.1, Daikin and Goodman are the basis of design. The Town will consider an equivalent that meets the stated performance and interface requirements. Existing equipment identified for reuse shall remain compatible.
7.2 Quantities. The base bid covers one complete changeout, including field verification and all incidental work necessary for the specified installation.
7.3 Subcontractors. Identify proposed subcontractors on Form B. Subcontracting and substitutions require prior written Town approval. The Contractor remains responsible for all subcontracted work. Approval does not create a contract between the Town and a subcontractor.
7.4 Licenses and permits. Obtain and pay for contractor and trade licenses, permits and certifications applicable to the work. Coordinate installation approvals with DPW. Provide license details with the bid and maintain licenses throughout performance.
7.5 Site coordination. Submit a project schedule before work. Coordinate access, outages and staging with DPW through the Town. Work hours are 7 a.m. to 5 p.m., Monday through Friday, excluding federal holidays. Obtain written DPW approval for other hours. The Town will give registered attendees the meeting and escort instructions for the optional prebid visit. After award, arrange a separate preconstruction visit with the IGSA Technical Representative and submit accident-prevention and property-protection plans before mobilizing.
7.6 Safety and property protection. The Contractor is responsible for safe work practices, compliance with applicable safety requirements, protection of people and property, and correction of damage caused by its operations.
7.7 Acceptance and warranty. Complete testing, air balancing, correction of deficiencies and DPW final inspection. The Town issues written acceptance. Provide a minimum five-year manufacturer warranty on applicable units and components and a one-year contractor warranty from final acceptance. Deliver warranties within 20 days of completion/final inspection.
7.8 Security. No discretionary bonds are required at the anticipated value. For bids exceeding $500,000, submit 5% bid security. For awards exceeding $500,000, furnish performance and payment bonds each for 100% of the contract, payable to the Town. Virginia-authorized sureties and statutory alternative security are accepted under §§ 2.2-4336 through 2.2-4338. Coordinate delivery of original security with the Procurement Officer before closing.
7.9 Invoicing. Submit monthly invoices to the Town IGSA Procurement Office using the cover email. Identify the contract, work order, billing period, accepted quantities of work, earned amounts by activity, prior invoices and balance. Attach progress records and DPW inspection support. The Town pays for verified work and releases final payment following acceptance and closeout. No retainage or advance payment applies. See D15–D16. Exclude the Town’s IGSA administrative fee from the base bid and invoices. Identify the portion of each billing attributable to each subcontractor.
8 Insurance Requirements Obtain required coverage before contract execution. Submit proof on the schedule in § 5.8 and maintain it during performance and for the completed-operations period in Attachment C. Require subcontractor coverage appropriate to their work. The Contractor remains responsible for losses within its contractual obligations.
9 Forms Form A Bidder References Building 179 HVAC Bidder: ____________________________________ Provide three comparable references. Attach a project history showing at least five years of similar installations. Duplicate this form as needed. Use references other than the Town of Bowling Green.
Reference 1 Owner or client and project ___________________________________________________ Contact name, telephone, and email ____________________________________________ Contract amount and performance dates _________________________________________ Description of comparable work and completion status __________________________ Reference 2 Owner or client and project ___________________________________________________ Contact name, telephone, and email ____________________________________________ Contract amount and performance dates _________________________________________ Description of comparable work and completion status __________________________ Reference 3 Owner or client and project ___________________________________________________ Contact name, telephone, and email ____________________________________________ Contract amount and performance dates _________________________________________ Description of comparable work and completion status __________________________ Form B Subcontractor Information and References Building 179 HVAC [ ] No subcontractors proposed. [ ] Subcontractors proposed; one form attached for each.
Bidder ________________________________________________________________________ Subcontractor legal name ______________________________________________________ Address _______________________________________________________________________ Contact name, telephone, and email ____________________________________________ License number, class, and specialty if applicable ____________________________ SCC identification number or exemption ________________________________________ Portion of work and estimated percentage ______________________________________ Provide three comparable project references and evidence of five years of similar installations for this subcontractor.
Subcontractor reference 1 Owner or client and project ___________________________________________________ Contact name, telephone, and email ____________________________________________ Scope, contract amount, and completion date ___________________________________ Subcontractor reference 2 Owner or client and project ___________________________________________________ Contact name, telephone, and email ____________________________________________ Scope, contract amount, and completion date ___________________________________ Subcontractor reference 3 Owner or client and project ___________________________________________________ Contact name, telephone, and email ____________________________________________ Scope, contract amount, and completion date ___________________________________ Form C Subcontractor Conflict Disclosure Building 179 HVAC Complete and notarize one disclosure for each proposed subcontractor. Upload the executed form with the bid.
Subcontractor legal name ______________________________________________________ Address _______________________________________________________________________ Authorized representative and title ___________________________________________ I am authorized to make this certification on behalf of the firm identified above. Except as disclosed below, I am not aware of any actual or potential conflict of interest arising from the firm’s ownership, personnel, clients, contracts, or other interests associated with this procurement. The firm’s participation in this bid is independent and without collusion or fraud.
[ ] No conflicts identified.
[ ] Potential conflicts disclosed below or on an attached sheet.
Disclosure and proposed measures to address the conflict:
Authorized signature __________________________________________________________ Printed name and title ________________________________________________________ Date __________________________________________________________________________ Commonwealth/State of ____________________ City/County of ____________________ Subscribed and sworn before me on __________________ by __________________________.
Notary signature __________________________ Commission expires ________________ Registration number ______________________ Notarial seal Form D State Corporation Commission Information Building 179 HVAC Complete the applicable statement concerning authority to transact business in Virginia under Code of Virginia § 2.2-4311.2. An SCC identification number is not a federal tax identification number.
Legal name of Bidder __________________________________________________________ [ ] The Bidder is authorized to transact business in Virginia.
SCC identification number: ____________________ [ ] The Bidder is not required to be authorized by the SCC. State the legal basis and supporting explanation below; attach additional documentation as necessary.
The Bidder certifies that this information is accurate and agrees to maintain any required authorization throughout the contract term.
Authorized signature __________________________________________________________ Printed name and title ________________________________________________________ Date __________________________________________________________________________ Form E Acknowledgment of Addenda Building 179 HVAC Bidder legal name _____________________________________________________________ The Bidder acknowledges receipt of the following addenda and has incorporated them into its bid.
| Addendum number |
| Date issued |
| Bidder initials |
[ ] No addenda were issued. The Bidder has checked the posting locations identified on the cover.
Authorized signature __________________________________________________________ Printed name and title ________________________________________________________ Date __________________________________________________________________________ 10 Attachments A Scope of Work and Specifications, including the included October 30, 2026 work request B Pricing Schedule C Required Insurance D General Terms and Conditions Attachment A Scope of Work and Specifications New Work Request Intergovernmental Service Agreement (IGSA) Town of Bowling Green
| Project Title: NEC 179 HVAC replacement |
| Date: 10/30/2026 |
| IGSA Number: 26-05 |
| Work Order Number: APHL_GE0003726 |
Fort A.P. Hill Project Manager
| Name: Cody Bobbitt |
| Title: Engineering Technician |
| Phone: 910-389-4820 |
| Email: cody.g.bobbitt.ctr@army.mil |
Project Information
Desired Project Completion Date or Period of Performance: Project goal is to be completed 90 days after Notice to Proceed
Proposal Due to Fort A.P. Hill Project Manager: 30 days after being accepted by Bowling Green
Table of Contents
· Section 1 – Description of Work/ Requirements
1.1 Work Description
1.2 Background
1.3 General Scope of Work
1.4 General Requirements
· Section 2 – Component Specific Requirements
2.1 Main HVAC Equipment (AHU / HPU / Furnace)
2.2 Piping
2.3 Ductwork & Air Distribution
2.4 Diffusers, Grilles, and Ceiling Components
2.5 Electrical Systems & Controls
2.6 Fire & Safety Systems (Firestopping / Dampers)
· Section 3 - Attachments, Pictures, and Drawings
· Section 4 - Antiterrorism/Operations Security
· Section 5 – Codes and Standards
Section 1 - Description of Work/ Requirements
1.0 Work Description
Project requirement is to replace the existing 15-ton heat pump system, hot water coil auxiliary heat, and all associated ductwork serving the Network Enterprise Command (NEC) administrative Building #179 with a new 10-ton heat pump/propane furnace system and all new ductwork.
1.1 Background
The building’s original HVAC system was a single 4-pipe hydronic system installed in 1975 during initial construction. The building has since had the single system replaced with 3 separate systems, serving dedicated areas. In 2011 the HVAC system serving the NEC main office area of Building 179 was replaced with a 15-ton split-system and reused the existing ductwork. Section 3 in this document shows the building area highlighted that this system serves. There are no drawings documenting the renovation and it is unknown what ductwork changes occurred. This existing equipment is a Trane 15-ton outdoor heat pump unit (HPU) with a Trane indoor air handler unit 180,000 BTU (AHU) with a hot water heat exchanger. The existing system has failed and requires replacement. The government’s load analysis identified the new system to be a 10-ton heat pump system with a propane fired furnace. The approach to replacing this system will include all system components: diffusers, insulated ductwork, HVAC equipment to include, but not limited to, refrigerant lines, propane lines, electrical disconnects, and breakers. The electrical panel is located in the HVAC mechanical room.
Location: Head Quarters Area, Fort A.P. Hill Garrison
· Affected Building: 179 NEC
1.2 General Scope of Work
The Contractor shall provide all demolition, disposal, preparation, labor, equipment, and materials as required to install a complete HVAC system to include but not limited to the heat pump unit (HPU-1), propane fired furnace/air handler unit (AHU-1), and additional components listed within this scope of work. All work must be performed in accordance with the manufacturer’s requirements and prevailing industry standards.
1.3 General Requirements
1. All materials shall be installed per manufacturer’s instructions, specifications, and recommendations.
2. The Contractor shall provide submittals for all equipment and materials to the Fort A.P. Hill Representative for approval. No equipment or materials shall be ordered prior to approval.
3. All materials and methods shall meet or exceed the requirements of the Nation Fire Protection Association (NFPA), International Building Code (IBC), and Unified Facilities Guide Specifications & Criteria (UFGS/UFC) construction details. Any deviation, without written approval from the Fort AP Hill DPW Representative, will be the Contractor's responsibility. The Contractor shall execute work in accordance with any and all applicable local, state, and federal codes, manufacturer’s recommendations, and trade and reference standards, including but not limited to: UFC, IBC, UBC, seismic codes, NEC, NFPA, ASME, and UMC. When more than one guiding document or section applies, the more stringent shall be implemented.
4. All applicable HVAC units and components shall have a minimum of a 5-year manufacturer’s warranty and a 1-year general Contractor’s warranty. All warranty documentation shall be provided to the Fort AP Hill DPW Representative within 20 days of completion/final inspection.
5. The Contractor shall comply with all local, state, federal, environmental, and occupational safety and health act (OSHA) rules and regulations. The Contractor shall assume full responsibility and liability for compliance with all applicable regulations pertaining to health and safety of personnel during the execution of the work and shall hold the government harmless for any Contractor action which results in illness, injury, or death. The Contractor shall immediately notify the POC and the Fort A.P. Hill safety office of all accidents or incidents involving Contractor use of or damage or injury to facilities, equipment, or personnel.
6. The Contractor shall field verify all measurements and quantities prior to ordering of any materials or starting work. Additionally, the Contractor shall conduct their own electrical load analysis to verify or correct the Governments recommendation of a 10-ton unit.
7. The Contractor shall identify the proposed location of all equipment for approval by the Fort A.P. Hill Representative prior to installation, to include but not limited to, the HPU, AHU, electrical disconnects, energy recovery ventilators, dampers, etc.
8. The Contractor shall ensure all materials are on site, prior to starting any work.
9. The Contractor shall protect all new materials from damage and weather.
10. The Contractor shall have 5 years of minimum experience with similar HVAC installations and provide supporting documentation to the Fort A.P. Hill Representative. All subcontractors used in this scope of work must meet the same requirements.
11. The Contractor shall advise DPW Representative of actionable items that may need addressing immediately. The Contractor shall send this information via email.
12. The Contractor shall report unexpected damages or potential problems and recommended solutions to the DPW Representative immediately. (IE. HVAC related damage: notify and advise of possible solution) If approved by DPW Representative and agreed by both parties, the Contractor shall repair or replace parts with products similar in appearance/specification to the original.
13. Damages caused by Contractor shall be repaired at no cost to the Government. The Contractor shall notify the DPW Representative immediately and return the damaged area to its previous condition, or better. The Contractor shall furnish all labor, materials, and equipment to perform the repair work including cultivating and applying seed, sprigging, or placing sod. The Contractor shall maintain all turf repair work to ensure successful growth.
14. The Contractor shall safeguard all government equipment, material, and supplies of every description from any type of damage. The Government shall not be liable for loss or damage to personal property belonging to the Contractor.
15. The Contractor shall complete daily inspections logs and submit copies to the Fort A.P. Hill DPW Representative via email on a daily basis during the execution phase of the project.
The Contractor is solely responsible for and has control over construction means, methods, techniques, sequences, and procedures, and for coordinating all portions of the work. Verify in the field that no conflicts exist which would prohibit the location of any and all mechanical and electrical elements, and that all required clearances for installation and maintenance of equipment are provided.
The Contractor shall coordinate all work with the government’s POC to minimize disturbance and cause no damage to the building. Provide protection to all existing finishes in all spaces within or adjacent to the scope of work. The Contractor shall patch, refinish, and repair any damage caused by the Contractor or its sub-Contractors. Provide strict control of job cleaning and prevent dust and debris from migrating from the construction area.
The Contractor shall provide a protective barricades and measures to ensure free and safe passage of personnel. Protect floors with suitable coverings. Construct temporary polyethylene sheeting dust barriers where required. Cover and protect furniture, equipment, and fixtures to remain.
16. The Contractor shall provide an on-site dumpster for debris. Dumpster(s) shall be utilized to clean up job site daily, and dumpster(s) shall be removed from the site before the final inspection and acceptance will be performed.
17. The Contractor shall provide an onsite portable restroom for their employees/ subcontractors to use during the duration of the project.
18. The Contractor shall ensure the site is clean of all project-related trash, debris, materials, tools, and equipment at the end of each day.
19. All trash, debris, and materials shall be disposed of offsite of the Fort A.P. Hill garrison.
20. The completed work will require a final inspection and approval by Fort A.P. Hill DPW Representative.
21. It is the responsibility of the Contractor to schedule all project related work with the DPW representative. All work shall be performed during normal base operating hours, defined as 0700 to 1700, Monday through Friday, excluding federal holidays. Any work required outside these hours must be requested in writing and approved by the DPW Representative.
22. The Contractor shall coordinate with the DPW Representative to designate a specific material laydown and dumpster area.
23. The Contractor shall submit a schedule to the DPW Representative of the entire length of the project before any work can begin.
Section 2 - Component Specific Requirements
2.1 Main HVAC Equipment (HPU and AHU / Furnace)
Demolition Requirements Remove existing HPU and AHU mechanical equipment to include all existing refrigerant lines and other associated equipment and/or materials that will not be re-used with the new system.
Refrigerant Recovery: The existing HVAC equipment has R-410a refrigerant. The Contractor shall coordinate with A.P. Hill personnel for removal prior to disconnecting equipment. The Contractor shall evacuate existing refrigerant into Fort A.P. Hill supplied tanks and notify the DPW Representative when they are ready to be picked up. This is to ensure refrigerant remains under Army ownership per the Department of the Army policy.
Disposal Forms: The Contractor must submit an equipment disposal form for each unit removed, including the quantity of refrigerant removed. The disposal form is provided by the Government.
Salvage & Recycling: All equipment deemed potentially suitable for reuse shall be identified to the Fort A.P. Hill Representative and turned over to the government if they choose. Recyclable materials (condensers, air handlers, metal duct) shall be sorted and placed in onsite government-provided recycling dumpsters. Recycling dumpsters shall be requested 5 days prior to the start of this project.
New Work Requirements Provide and install new mechanical equipment, including a new 10-ton heat pump (or agreed upon size) and propane fired furnace, both manufactured by Daikin or Goodman. All equipment shall meet or exceed Energy Star criteria.
Refrigerant type: The new HVAC system shall have either R-32 or R-454B refrigerant.
Furnace Specifications: The new furnace (part of AHU-1) shall have a variable speed blower motor and a modulating gas (propane) valve.
The system shall have an outside thermostat and configured to operate the propane furnace only when outside temperatures are below 40 degrees Fahrenheit.
Drainage Protection: Provide a new auxiliary drain pan with a connection and limit switch designed to shut the HVAC system down.
Condensate Drain: Provide a Schedule 40 PVC condensate trap with a drain extended to the building exterior or floor drain, sloped at 1/8” per foot. Shall incorporate a condensate pump only if necessary and approved by the Fort A.P. Hill Representative.
Outdoor Unit Elevation: Provide a minimum 6” high snow legs for the new outdoor unit (HPU-1).
Equipment Pad: The Contractor is to reuse the existing outdoor unit concrete pad.
Inventory Submission: The Contractor must submit an AC & R Equipment Inventory Input Form for the new equipment.
2.2 Piping
Demolition Requirements Water Line Removal: Remove supply and return water lines that connect to the existing AHU heat exchanger. Lines are to be removed back to a point where they can be isolated with valves and capped off without affecting domestic water distribution flow.
New Work Requirements Propane Piping Installation: Provide and install new propane piping from the closest allowable connecting location to the new furnace in the main mechanical room. The Contractor is responsible for installing pipe size, type, connection types, supports and type in accordance with all applicable codes.
Piping Standards: Comply with ASME B31.9, ANSI B31.1, and NFPA 54 for all gas piping, fittings, and joints.
Pressure Testing: All pressure tests shall follow the industry standards, guidelines, and specifications.
2.3 Ductwork & Air Distribution
Demolition Requirements Remove all existing Supply Air (SA) and Return Air (RA) ductwork associated with the system being replaced, to include in the building attic and areas above the suspended acoustic tile ceiling. If outside air ductwork exists, remove it to the outside louver, which is to remain.
Any existing abandoned or inactive ductwork that is not part of the existing system being removed and is interfering with the new work, shall be removed back far enough to allow for the new work installation. This includes removing abandoned-in-place ducts in the main mechanical room. The Contractor shall ensure these ducts are not connected to one of the other 2 active HVAC systems within this building or associated with other working systems.
New Work Requirements Provide and install insulated ductwork as required to properly connect to the new equipment and serve the targeted building area as identified in this scope of work (see Section 3 for floor plans), to include but not limited to, the Mechanical Room, attic, area above the suspended acoustic tile ceiling, and all. The Contractor shall design the duct size and layout and submit to the Fort A.P. Hill Representative for approval. The design shall identify all related items, to include dampers, and their proposed location and operation. A SA and RA diffuser location plan has been included in Section 3, that includes estimated flow rates. This should be used for estimating, but the final design may adjust that layout if recommended and approved by the Contractor.
All duct, fittings, and transitions shall be constructed per ANSI/SMACNA standards.
Duct Sealing: Provide a Class ‘A’ seal for all new ductworks.
Corrosion Protection: Provide corrosion-resistant coating or materials for any ductwork handling outside air.
Balancing Dampers: Provide manual volume dampers for all main and branch ducts (supply, return, and exhaust) as needed to properly balance system.
Outside Air Intake: Install a new motorized outside air control damper for the new AHU’s fresh air intake. The damper must comply with AMCA 500-D, be rated for 2000 FPM, and have linkages outside the airstream. Outdoor air intakes must be located at least 10 feet above grade.
Energy Recovery Ventilator: Provide and install a new passive Energy Recovery Ventilator (ERV) on the outside air intake and/or duct.
Flue & Exhaust Venting: The furnace intake air and exhaust shall be piped up through the roof of the mechanical room and connected to a concentric vent. The exhaust vent must extend at least two feet above any part of the roof within a ten-foot radius.
Filtration: Provide a filter cabinet with 2” thick MERV 8 filters to be located at the AHU-1.
2.4 Diffusers, Grilles, and Ceiling Components
Demolition Requirements Ceiling Component Removal: Remove and dispose of all existing diffusers and grills inside the office areas highlighted by a dashed line on the diagram in Section 3.
New Work Requirements Installation Locations: Provide and install new diffusers and grills in the ceiling in accordance with the locations indicated on the diagram in Section 3, SA and RA locations.
System Balancing: Balance all new supply diffusers and return grilles to the specified CFM in Section 3, SA and RA locations.
Ceiling Repairs: Where required in drywall ceilings to modify openings for new diffusers/grilles, repair the ceiling and paint it to match the existing finish.
Grid Work: Replace any damaged acoustic ceiling tiles with new matching acoustic tiles where required after relocating any diffusers.
2.5 Electrical Systems & Controls
Demolition Requirements Safety Devices: Disconnect all supply air smoke ductwork detectors and set them aside in a safe place to be reinstalled in the new work section.
Thermostat Wiring: Remove and dispose of the communication wire from HPU-1 and AHU-1 back to the existing thermostat(s); the thermostats are to remain.
Outdoor Disconnect: Disconnect and remove the existing outdoor heat pump unit disconnect and wires/conduit.
Indoor Disconnect: Disconnect and remove the existing AHU-1 unit disconnect and wires/conduit.
Breakers: Remove existing electrical breakers noted from panel “M” for the HPU-1 and AHU-1.
Circuit Cleanup: Remove all associated wiring back to the source of feed unless otherwise noted.
New Work Requirements Breakers & Panels: Install a new breaker for each piece of new HVAC system equipment in panel “M”. New breakers shall be bolt-on type, and panel labeling shall be completed once all new circuits are installed.
Disconnect Switches: Provide and install new heat pump and air handler equipment disconnects (one per equipment). Switches shall be non-fusible in a NEMA 3 enclosure rated per the manufacturer’s guidelines.
Thermostat & Controls: The three (3) existing Schneider Electric thermostats will remain and be re-used with the new system as they are part of a Building Automation System (BAS), but the thermostat wires will be replaced from each thermostat back to the Schneider Electric automated server (located in the Mechanical Room). The BAS is configured to use the average of the 3 thermostats for operation. Contractor shall notify the government POC for any required BAS reconfiguration if needed and it will be performed by the BAS Contractor. The thermostat wire shall be properly routed through the building’s attic and through conduit for any sections exposed to the outdoors.
Detectors & Interlocks: Reinstall the existing smoke detectors downstream of the air filters on the new AHU-1. If a carbon monoxide detector does not exist, provide and mount one on the ceiling in the mechanical room. These detectors shall be wired to stop the air handler fan upon detection and signal the building fire alarm control panel.
Patching: Where equipment is removed from walls, the Contractor shall patch and prepare walls for the scheduled finish or to match adjacent if not specified.
2.6 Fire & Safety Systems (Firestopping / Dampers)
Demolition Requirements Structural Integrity: (General) The fire-resistive integrity of the original building is not to be compromised by any action of the Contractor. No existing smoke detector, public address speaker, or fire alarm box shall be damaged.
New Work Requirements Fire Barrier Integrity: All penetrations are to be fire-stopped. Furnish and install tested and listed firestopping systems to form an effective barrier against flame, smoke, and gases.
Fire Dampers: Ductwork penetrating walls or ceilings that are 2-hour fire-rated barriers requires protection with a 90-minute fire damper and associated access doors.
2.7 Insulation
Demolition Requirements Remove insulation associated with any demolished ductwork, refrigerant lines, or piping.
New Work Requirements Duct Insulation: Insulate all new ductwork, including in the mechanical room, with 2” thick fiberglass duct insulation (minimum R-6) with a foil vapor barrier.
System Insulation: Provide field-applied insulation on all mechanical systems as specified; factory-applied insulation is specified under the piping, duct or equipment to be insulated in accordance with UFGS-23 07 00 (February 2013) change 7 - 05/20 division 23 - heating, ventilating, and air conditioning (HVAC).
Line Set Insulation: The new refrigerant line set shall be insulated with flexible closed-cell elastomeric pipe insulation: 3/4” thick for the liquid line and 1/2” thick for the hot gas line. All insulation exposed to sunlight or installed outdoors shall be protected with two coats of the manufacturer’s recommended coatings.
Section 3 – Attachments, Pictures, and Drawings:
Floor plans (red dash area is the area to be heated and cooled, green is mechanical room):
SA and RA diffuser locations and estimated sizes:
Concrete pad and HPU:
Outdoor refrigerant lines and disconnect box:
Outdoor HPU lines and wires(red arrow is thermostat wire):
AHU view with refrigerant lines and water exchange lines:
View of where propane and water lines come from/ will come from (red water, blue propane):
Commonly found SA difusser in building:
Commonly found RA difusser in building:
Section 4 - Antiterrorism/Operations Security:
Access to the Installation:
Contractor and all associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by the installation Provost Marshal Office, Director of Emergency Services, or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contract Personnel) as directed by DoD, HQDA and/or local policy. All Contractor and associated sub-Contractor employees who require physical access to Fort A.P. Hill for contract performance shall present an Acceptable Form of Identification, as identified in Section 5 of DoD Manual 5200.08 Volume 3, “Physical Security Program: Access to DoD Installations”, (available at the link below to access the installation:
https://www.esd.whs.mil/Portals/54/Documents/DD/issuances/dodm/520008_vol3.pdf?ver=2020-09-18-130526-407 The Contractor shall maintain awareness of Contractor or subcontractor employees who have been vetted and approved to access the installation and shall notify the Contracting Officer in writing within 48 hours of any Contractor or sub-Contractor employee who resigns, is terminated, or for any other reason is no longer authorized to access Fort A.P. Hill for the purpose of performance of this contract. For contracts with a performance period longer than three months, the Contractor shall reconcile his roster of currently-approved personnel quarterly with the Fort A.P. Hill Visitor Control Center (VCC) and provide an updated roster of contract personnel to the COR or Contracting Officer to ensure that both the Contractor and Fort A.P. Hill maintain accurate awareness of the Contractor and subcontractor employees who are authorized to access the installation. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in Contractor security matters or processes.
Access to the Installation but do NOT need Common Access Cards:
The Contractor and all associated subcontractor employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (Army Directive 2014-05/AR 190-13); applicable installation, facility and area commander installation and facility access and local security policies and procedures (provided by Government representative); or, at OCONUS locations, in accordance with status-of-forces agreements and other theater regulations.
The Contractor and all associated subcontractor employees shall account for all forms of Government-provided identification and access credentials issued to the Contractor employees in connection with performance under this contract. The Contractor shall surrender such identification to the issuing agency at the earliest of any of the following, unless otherwise determined by the Government, (1) When no longer needed for contract performance. (2) Upon completion of the Contractor employee’s employment, (3) Upon contract completion or termination, (c) The Contracting Officer may delay final payment under a contract if the Contractor fails to comply with these requirements, (d) The Contractor shall insert the substance of this clause, including this paragraph (d), in all subcontracts when the subcontractor’s employees are required to have routine physical access to a Federally-controlled facility and/or routine access to a Federally-controlled information system. It shall be the responsibility of the prime Contractor to return such identification to the issuing agency in accordance with the terms set forth in paragraph (b) of this section, unless otherwise approved in writing by the Contracting Officer.
Photography:
The Contractor shall ensure that all photography planned or conducted, whether in support of this contract or recreational in nature, conducted by any Contractor and sub-Contractor…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .