About this file
This is a Questions and Answers document from the Virginia Department of Transportation addressing clarifications on IFB 161206 for equipment with operator services for the Bridge Division covering Wythe and Grayson Counties. The document clarifies the treatment of supplemental equipment line items listed on Attachment H of the solicitation, specifying that while pricing must be submitted for all supplemental items for the bid to be deemed responsive, these items will not be evaluated or scored as part of the bid evaluation process. Supplemental equipment will only be added to the contract if the government deems the pricing fair and reasonable and if the items are needed during contract performance.
Pricing for supplemental equipment on Attachment H is limited to equipment costs only, with no operator costs included; if supplemental equipment is utilized during contract performance, associated labor costs will be compensated at the Skilled Laborer prevailing wage rate for actual time in use. The supplemental equipment items are considered essential for completing the work and are anticipated to be set up and operated by skilled laborers as needed throughout the contract term.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| IFB 161206 Addendum No. 1 & Attachment G.pdf | ||
| 161206 IFB Specifications_Revised.pdf | ||
| IFB 161206 Q&A.pdf | ||
| 161206_Attachments.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF TRANSPORTATION
Stephen C. Brich, P.E. 1221 East Broad Street (804) 482-5818 Commissioner Richmond, Virginia 23219
WE KEEP VIRGINIA MOVING
IFB 161206 Equipment with Operator-Bridge (Wythe-Grayson) Questions and Answers #2
1. On Attachment H, the first line states that pricing shall be provided on all line items and the last sentence says these are not going to be considered in the evaluation. So for clarification, you have to put pricing on it for the bid to be valid, but they’re not going to be considered in the pricing for the bid? And these lines on H, they don’t expressly say, but I guess the assumption would be that these are without operator since it talks about them being set up by the skilled laborer. But if you’re using both, you would get paid for both, right? Can you clarify these are additions? Not with operator?
Answer: Refer to paragraph IV.G.3.b. – Supplemental Equipment, which states that “Equipment listed on the Supplemental Pricing Page (Attachment H) are essential for completing work, bid prices shall be submitted for all items listed on the attachment, or the bid may be deemed as non-responsive.” And states, “These items will not be considered in the bid evaluation.” Also refer to Attachment H – Supplemental Line Items Attachment which states, “Pricing shall be provided on all line items being bid.” And states, “These items will be requested as needed, and are not going to be considered in the bid evaluation.”
Refer to paragraph IV.G.3.b. – Supplemental Equipment, which states “ Prices on the Supplemental Pricing Page shall be for the equipment only. If added to the contract, the labor For the items from the Supplemental Pricing Page will be paid at the Skilled Laborer rate for The actual time in use.”
The Supplemental Line Items Attachment, Attachment H states:
Note: Pricing shall be provided on all line items being bid. When requested these items will be set up/operated by the skilled laborer for the actual time in use. These lines will be added to the contract if the price is deemed to be fair and reasonable. These items will be requested as needed, and are not going to be considered in the bid evaluation.
Refer to paragraph IV.G.3.b – Supplemental Equipment states:
Equipment listed on the Supplemental Pricing Page (Attachment H) are essential for completing work, bid prices shall be submitted for all items listed on the attachment, or the bid may be deemed as non-responsive. These items will be added to the contract as needed if the price is deemed to be fair and reasonable. These items will not be considered in the bid evaluation. Prices on the Supplemental Pricing Page shall be for the equipment only. If added to the contract, the labor for the items from the Supplemental Pricing Page will be paid at the Skilled Laborer rate for the actual time in use.