Hunter West Building Lower Roof Replacement RFB.pdf

PDF 249 KB Posted

Attached to
Hunter College - West Building Lower Roofs Replacement
Solicitation number
HC-CUCF-20-26
Issued by
New York County, New York

About this file

This Request for Bid issued by the City University Construction Fund (CUCF) on behalf of the City University of New York (CUNY) Office of Facilities Planning, Construction, and Management seeks qualified contractors to replace all lower roofs and the gymnasium floor at Hunter College's West Building in New York. The project encompasses comprehensive scope of work including mobilization and site protection, asbestos-containing material abatement, demolition, concrete repairs, roof resurfacing, masonry repointing, liquid applied roofing systems, gymnasium floor replacement with bleacher reinstallation, interior repairs, plumbing and electrical work, and exterior coating applications. The bid was released on November 10, 2026, with a mandatory pre-bid conference on November 16, 2026, and a mandatory site visit on December 3, 2026. Questions must be submitted by December 10, 2026, with bids due by 11:59 PM on January 11, 2027. Construction is to commence upon issuance of Notice-to-Proceed and be completed within one year thereafter. Award is contingent upon successful contract negotiations and approvals by CUCF's Board of Trustees, the New York State Attorney General, and the New York State Comptroller.

The contract will be awarded to the lowest responsive and responsible bidder. Respondents must be legally capable of entering contracts with CUCF and authorized to conduct business in New York State. Prevailing wage requirements apply under Article 8 of New York State Labor Law, with prevailing wage number 2025013824, and all work must comply with the CUCF Project Labor Agreement. A 30% Minority-owned and Women-owned Business Enterprise (MWBE) participation goal and a 6% Service-Disabled Veteran-Owned Business (SDVOB) participation goal are required. Comprehensive insurance requirements include Commercial General Liability of $2,000,000 per occurrence/$3,000,000 aggregate, Automobile Liability of $2,000,000, Owner's Protective Liability of $1,000,000 per occurrence/$2,000,000 aggregate, Builder's Risk equal to contract value, and Contractor's Pollution Liability of $2,000,000 per occurrence. Payment and performance bonds each equal to the full contract value are required. New York State Vendor Responsibility Questionnaire certification, New York State Tax Law Section 5-a compliance for contracts exceeding $100,000, and Public Work Contractor and Subcontractor Registry registration are mandatory. Proposals must remain binding for 180 days from bid opening.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Bid

Hunter College - West Building Lower Roofs Replacement

Project No.: HC-CUCF-20-26

Bid Release Date: November 10, 2026 Due Date for Responses: January 11, 2027

All inquiries and questions must be directed in writing to:

CUNY.Builds@cuny.edu mailto:CUNY.Builds@cuny.edu

Table of Contents

I. Introduction II. Scope of Work III. Regulatory and Compliance Requirements IV. Procurement Protocol and Process V. Selection Process VI. Terms & Conditions of Solicitation

ATTACHMENTS:

EXHIBIT 1 RESPONDER’S INFORMATION & CERTIFICATIONS

EXHIBIT 2 SPECIFICATIONS AND DRAWINGS

EXHIBIT 3 BID FORMS

EXHIBIT 4 CUCF PROJECT LABOR AGREEMENT (PLA)

APPENDIX A STANDARD CLAUSES FOR NYS CONTRACTS

I. Introduction

A. Purpose & Description

The City University Construction Fund (CUCF), on behalf of the City University of New York (CUNY) Office of Facilities Planning, Construction, and Management (FPCM), is seeking bids from qualified contractors to replace all the lower roofs and the gymnasium floor at Hunter College’s West Building.

B. Period of Performance

Construction Start: Upon issuance of Notice-to-Proceed (NTP)

Construction Completion: One year after issuance of NTP

C. Background

CUCF is a New York State public benefit corporation established by New York State with the mission of managing the resources necessary for the design, rehabilitation, and construction of CUCF educational facilities. CUCF is the nation’s largest urban public university with 26 Campuses ranging from community colleges to senior colleges to professional schools, across all five boroughs of New York City. The University has approximately 300 buildings, comprising 29,000,000 square feet of classrooms, computer centers, science and other instructional and research labs, theaters, athletic facilities, greenhouses, observatories, and spaces for many other purposes.

D. Minimum Qualification Requirements

Respondents to this solicitation must meet the following minimum qualification requirements. Respondents who do not meet the required minimum qualification requirements shall be deemed non-responsive.

1. The respondent must, at the time of Proposal submission and throughout the term of the contract, possess the legal capacity to enter into a contract with CUCF.

2. The respondent must, at the time of Proposal submission and throughout the term of the contract, be authorized to conduct business in New York State.

E. Schedule of Key Events

CUCF will adhere to the following schedule regarding this procurement. Any changes to the schedule will be made via an addendum:

Key Event Date and Time

Bid Release Date November 10, 2026

Pre-Bid Conference November 16, 2026

Site Visit Date December 3, 2026

Due Date for Questions December 10, 2026

Bids Due Date January 11, 2027

II. Scope of Work

The Scope of Work contains the work needed to replace all the lower roofs and the gymnasium floor at Hunter College’s West Building per Exhibit 2 (Specifications & Drawings). This project includes:

A. All necessary and required Mobilization and Site Protection, including sidewalk sheds, fencing, pipe scaffolding, netting, hoists, related Site Safety Measures, equipment, and on-site trailer (where indicated on architectural plans).

B. Asbestos Containing Material (ACM) Abatement as per specs, plans, and test reports.

C. Demolition, including masonry pavers, built-in masonry planters, soil removal, removing vines at the neighbor’s west wall, removing ramp and decking at the 3rd floor terrace, removing damaged ceiling tiles, indicated roofing removal (coordinated with ACM abatement), removal of topping slab at the 3rd floor, and removal of existing gymnasium wood flooring.

D. Concrete spall and crack repairs.

E. Concrete beam end repair, including reinforcement, limited reinforcement repairs.

F. Re-pitching, resurfacing, and screed repair at roof slabs.

G. Brick masonry repointing, limited face brick replacement, and brick parapet replacement.

H. Cold-formed metal framing for air shaft louver grille enclosure.

I. Steel roof guardrails at 4th floor, Triangular Roofs using no infill panel (Please see Design Option 1, detail 4 & 5 on Exhibit 2 Specifications & Drawings; 90

LF.

J. Treated wood blocking at copings.

K. Liquid Applied Roofing System with VIP insulation in the 2nd floor Mechanical

Roof and 2nd & 3rd floor bulkhead roofs.

L. Liquid Applied Roofing System with tapered Polystyrene Insulation for new

Vent Shaft Roof at 2nd floor Mech Roof Area.

M. Liquid Applied Roofing System with spray-in insulation at the cavity located at the raised slab on the 3rd floor terrace.

N. Bituthene Flashings in wall between 2nd & 3rd floor at area of Parapet Replacement.

O. Standing Seam & Flat Metal Wall Panels and Cleated Copings at bulkheads and parapets.

P. Sheetmetal: scuppers and leaders, expansion joint covers, Gooseneck

Exhaust Vents.

Q. Sealant work at copings, expansion joints.

R. New Exterior Door and Door Hardware onto 4th floor roof.

S. Rain Louvers.

T. Exterior Painting.

U. Replacing Acoustical Ceiling Panels.

V. Gymnasium floor replacement with reinstallation and raising of existing bleachers, including transition thresholds at doors and top of bleachers;

adjusting the basketball hoops upwards and modification to the volleyball poles mounting sleeves, and restoring/replicating all existing striping and logos on to the new floor.

W. Carpet floor replaced with slip-resistant vinyl tile.

X. Interior wall repairs and repainting.

Y. Reinforced exterior waterproof coating to West Concrete Wall of West Building that abuts the adjacent property to help eliminate and further water penetration.

Z. Restore bird deterrent wires and posts.

AA. Plumbing: retrofit drains and allowance for testing of the drain piping & replacing piping from drains to drain risers, where found defective.

BB. Electrical: exterior lighting, outlets, and conduits on the 3rd floor terrace.

[Please note, any quantities or dimensions given in Exhibit 2 (Specifications & Drawings) are for the contractor’s convenience in bidding. However, all final measurements and quantities, and layout of the work are subject to the contractor’s verification in the field to accomplish the intended repairs and replacements at locations shown on the plans].

III. Regulatory and Compliance Requirements

The awarded respondent must comply with the provisions in Appendix A (Clauses for New York State Contracts) and complete all the items noted in this Section III of the solicitation.

A. New York State Vendor Responsibility Questionnaire

The Prime Consultant selected for award and each of its Sub-consultant(s) with a subcontract equal to or greater than $100,000 must certify a New York State Vendor Responsibility Questionnaire (VendRep). Such Certification of the VendRep Questionnaire must be within six months of the selection date and it must include the dates of birth and legal names of the principals identified in their VendRep. CUCF may reach out to the selected Prime and its Subcontractors as part of its responsibility determination process.

CUCF recommends that respondents file the required VendRep Questionnaire online via the New York State VendRep System. To enroll in and use the New York State VendRep System, see the VendRep System Instructions available at http://www.osc.state.ny.us/vendrep/enroll.htm or go directly to the VendRep System online at https://onlineservices.osc.state.ny.us.

Professionals must provide their New York State Vendor Identification Number when enrolling. To request assignment of an ID or for VendRep System assistance, contact OSC’s IT Service Desk at 866-370-4672 or 518-408-4672 or by email at ITServiceDesk@osc.state.ny.us.

B. New York State Law Section 5-a

Tax Law § 5-a requires certain respondents awarded state Contracts for commodities, services and technology valued at more than $100,000 to certify to New York State Department of Taxation and Finance (DTF) that they are registered to collect New York State and local sales and compensating use taxes. The law applies to contracts where the total amount of such respondent’s sales delivered into New York State is in excess of $300,000 for the four quarterly periods immediately preceding the quarterly period in which the certification is made, and with respect to any Affiliates and subcontractors whose sales delivered into New York State exceeded $300,000 for the four quarterly periods immediately preceding the quarterly period in which the certification is made.

A respondent is required to file the completed and notarized Form ST-220-CA with the Department certifying that the respondent filed the ST-220-TD with DTF. Failure to make either of these filings may render a respondent non-responsive and non-responsible. The respondent must take the necessary steps to provide properly certified forms within a timely manner to ensure compliance with the law.

https://nam02.safelinks.protection.outlook.com/?url=http%3A%2F%2Fwww.osc.state.ny.us%2Fvendrep%2Fenroll.htm&data=05%7C02%7CChristine.Lee%40cuny.edu%7C7467a9130c9b4491a35e08dc2e6755f4%7C6f60f0b35f064e099715989dba8cc7d8%7C0%7C0%7C638436269274914871%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=ZL%2F%2FkmnCzw00yiqXW7N3fF7p0Psapa5I876IrJ80R10%3D&reserved=0 https://nam02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fonlineservices.osc.state.ny.us%2F&data=05%7C02%7CChristine.Lee%40cuny.edu%7C7467a9130c9b4491a35e08dc2e6755f4%7C6f60f0b35f064e099715989dba8cc7d8%7C0%7C0%7C638436269274924543%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=zQvVvzhPCGVx9g%2FMQXYdAHy8ObQsJubLFO8Rsqk4prM%3D&reserved=0 mailto:ITServiceDesk@osc.state.ny.us

Website links to the respondent certification forms and instructions are provided below.

1. Form ST-220-TD must be filed with and returned directly to DTF and can be found at:

http://www.tax.ny.gov/pdf/current_forms/st/st220td_fill_in.pdf

Unless the information upon which the ST-220-TD is based changes, this form only needs to be filed once with DTF. If the information changes for the respondent, its Affiliate(s), or its subcontractor(s), a new Form ST-220-TD must be filed with DTF.

2. Form ST-220-CA must be submitted to CUCF. This form provides the required certification that the respondent filed the ST-220-TD with DTF.

This form can be found at:

http://www.tax.ny.gov/pdf/current_forms/st/st220ca_fill_in.pdf

C. MWBE and SDVOB Participation Goals

Pursuant to Article 15-A and 17-B of New York State Executive Law, the selected respondent must meet a Minority-owned and Women-owned Business Enterprise (MWBE) participation goal of 30% and a Service-Disabled Veteran-Owned Business (SDVOB) participation goal of 6%. Only New York State MWBE and SDVOB Certified vendors will be utilized to meet the participation goals. Contractors and sub-contractors are encouraged to utilize the directories for the New York State Certified MWBEs and SDVOBs to identify eligible vendors to fulfill these goals, located at:

http://www.esd.ny.gov/mwbe.html and https://online.ogs.ny.gov/SDVOB/search, respectively.

Awarded respondents must submit the following documents and information as evidence of compliance:

1. MWBE and SDVOB Utilization Plans.

2. A Workforce Utilization Report to CUCF on a quarterly basis during the term of the contract for assigned Task Orders.

D. Public Work Contractor and Subcontractor Registry

Starting December 30, 2024, all contractors and subcontractors submitting bids or performing construction work on public work projects or private projects covered by Article 8 of the Labor Law are required to register with the New York State Department of Labor (NYSDOL) under Labor Law Section 220-i.

Contractors need to register before submitting any new bids or commencing new work on a covered project on or after December 30, 2024. Subcontractors http://www.tax.ny.gov/pdf/current_forms/st/st220td_fill_in.pdf http://www.tax.ny.gov/pdf/current_forms/st/st220ca_fill_in.pdf http://www.esd.ny.gov/mwbe.html https://online.ogs.ny.gov/SDVOB/search https://www.dropbox.com/scl/fo/r9k1atdr5p68u7zn6jned/AFeJ-OIhe7h_pF1A8ZuHFvM?dl=0&e=1&preview=MWBE+Utilization+Plan_06.2017.pdf&rlkey=lqstph91jhl5dj0kl1blzkw43 https://www.dropbox.com/scl/fo/7xtcdbql5bzrpr5kl7pcn/AJBWfq0JB6hGFGbjMNHhJVc?dl=0&e=1&preview=SDVOB_100_Utilization_Plan_CUCF_08-22-2023.pdf&rlkey=trztz1zdxuai79q8rl0wovvd1 https://dol.ny.gov/twef-mwbe-workforce-utilization-form-eeo need to register before commencing new work on a covered project on or after December 30, 2024. Information on the registration can be found at Public Work Contractor and Subcontractor Registry Landing | Department of Labor

E. Insurance Requirements

The successful respondent shall be required to procure, at its sole cost and expense, all insurance required below. Upon request, Contractors shall deliver to CUCF evidence of the insurance required by this solicitation and any Contract resulting from this solicitation in a form satisfactory to CUCF. All insurance shall be written by companies that have an A.M. Best Company rating of “A-,” Class “VII” or better. In addition, companies writing insurance intended to comply with the requirements of this Contract should be licensed or authorized by the New York State Department of Financial Services to issue insurance in the State of New York. CUCF may, in its sole discretion, accept policies of insurance written by a non-authorized carrier or carriers when certificates and/or other policy documents are accompanied by a completed Excess Lines Association of New York (ELANY) affidavit or other documents demonstrating the company’s strong financial rating. If, during the term of a policy, the carrier’s A.M. Best rating falls below “A-,” Class VII, the insurance must be replaced, on or before the renewal date of the policy, with insurance that meets the cited requirements. The Contractor shall cause to be included in each of the Commercial General Liability, Business Automobile Liability, and Umbrella/Excess Liability policies required below coverage for on-going and completed operations naming as additional insureds (via ISO coverage forms CG 20 10 12 19 and CG 20 37 12 19 and form CA 20 48 10 13, or a form or forms that provide equivalent coverage): The People of the State of New York, CUCF, any entity authorized by law or regulation to use any Contract resulting from this solicitation and their officers, agents, and employees. An Additional Insured Endorsement, or the equivalent, evidencing such coverage shall be provided to CUCF upon request. A blanket Additional Insured Endorsement evidencing such coverage is also acceptable. For Contractors who are self-insured, the Contractor shall be obligated to defend and indemnify the above-named additional insureds with respect to the Commercial General Liability and Business Automobile Liability policies in the same manner that the Contractor would have been required had the Contractor obtained such insurance policies.

1. Commercial General Liability Insurance. Such liability shall be written on the current edition of ISO occurrence form CG 00 01 & ACORD 855, or a substitute form providing equivalent coverage and with no modification to the contractual liability coverage provided therein, shall be provided on an occurrence basis, and limits shall not be less than $2,000,000 per occurrence; and $3,000,000 general aggregate. CUCF, CUNY, and the State of New York must be included as additional insureds on ISO Forms CG 20 10 12 19 and CG 20 37 12 19 or a form or forms that provide equivalent coverage on policies held by the selected respondent and any of its subcontractors. Should the respondent’s work include construction https://dol.ny.gov/public-work-contractor-and-subcontractor-registry-landing https://dol.ny.gov/public-work-contractor-and-subcontractor-registry-landing activities of any kind, then the respondent must maintain Products / Completed Operations coverage for no less than three years after the construction work is completed, and continue to include Additional Insured protection for CUCF, CUNY, and the State of New York for the prescribed timeframe. When providing evidence of insurance, the respondent must include a completed Acord 855 NY form. Limits may be provided on a primary basis or a combination of primary and excess/umbrella. The Policy shall:

i. Cover liability arising from premises operations, independent contractors, products-completed operations, broad form property damage, personal & advertising injury, cross liability coverage, liability assumed in a contract (including the tort liability of another assumed in a contract) [and explosion, collapse & underground coverage].

ii. Include bodily injury, property damage, and broad form contractual liability within General Aggregate, Products – Completed Operations Aggregate, Personal and Advertising Injury, Each Occurrence.

iii. Include, but not be limited to premises liability; independent contractors; blanket contractual liability, including tort liability of another assumed in a contract; defense and/or indemnification obligations, including obligations assumed under any Contract resulting from this solicitation; cross liability for additional insureds; and products/completed operations for a term of no less than three years, commencing upon acceptance of the work, as required by the Contract.

2. Automobile Liability Insurance. With a combined single limit of not less than

$2,000,000. Coverage must apply to the successful respondent’s owned, hired, and non-owned vehicles and include CUCF, CUNY, and the State of New York as additional insured. Such insurance shall cover liability arising out of automobiles used in connection with performance under any Contract resulting from this Solicitation, including owned, leased, hired and non-owned automobiles bearing or, under the circumstances under which they are being used, required by the Motor Vehicles Laws of the State of New York to bear, license plates. If the Contractor does not own, lease or hire any automobiles used in connection with performance under any Contract resulting from this solicitation, the Contractor does not need to obtain Business Automobile Liability Insurance, but must attest to the fact that the Contractor does not own, lease or hire any automobiles used in connection with performance under any Contract resulting from this Solicitation/Contract on a form provided by CUCF. If, however, during the term of the Contract, the Contractor acquires, leases or hires any automobiles that will be used in connection with performance under any

Contract resulting from this solicitation, the Contractor must obtain Business Automobile Liability Insurance that meets all of the requirements of this section and provide proof of such coverage to CUCF in accordance with the insurance requirements of any Contract resulting from this solicitation.

3. Owner's Protective Liability Insurance. Covering the liability for damages in respect to all operations of the respondent on a project and in an amount not less than $1,000,000 per occurrence combined single limit and $2,000,000 aggregate. Coverage must be provided for the Contractor, all subcontractors, CUCF, CUNY, and the State of New York; and must include the insurable interests of all subcontractors retained by the Contractor.

4. Builder’s Risk Insurance. In an amount appropriate for the project generally equal to the value of the contract. Coverage must apply to property while on site, off site, and in transit, include an agreed amount provision which eliminates any coinsurance provision, and include CUCF as a loss payee.

5. Contractor’s Pollution Liability Insurance. Covering bodily injury, property damage, clean-up costs/remediation expenses, and legal defense costs.

Such insurance shall provide coverage for sudden and non-sudden pollution conditions arising out of the respondent’s operations at CUNY facilities. The limit of coverage shall not be less than $2,000,000 per occurrence. CUCF, CUNY, and the State of New York must be included as additional insureds on policies held by the selected respondent and any of its subcontractors. If the work involves abatement, removal, repair, replacement, enclosure, encapsulation and/or disposal of any pollutants, which includes but are not limited to, petroleum, petroleum product, hazardous materials or substances including asbestos, lead, fungus and those as defined by applicable state and federal laws and regulations, the Contractor shall procure, or otherwise obtain through an approved Subcontractor, and maintain in full force and effect throughout the term of any Contract resulting from this Solicitation/Contract, and for two years after completion hereof, providing coverage for bodily injury and property damage, including loss of use of damaged property or of property that has not been physically injured. Such policy shall provide coverage for actual, alleged or threatened emission, discharge, dispersal, seepage, release or escape of pollutants, including any loss, cost or expense incurred as a result of any cleanup of pollutants or in the investigation, settlement or defense of any claim, suit, or proceedings against The People of the State of New York, CUCF, and any Authorized User of any Contract resulting from this Solicitation and their officers, agents, and employees, arising from the Contractor’s work. This requirement applies to mold as well, if excluded in the Commercial General Liability policy. If automobiles are to be used for transporting hazardous materials, the Contractor shall provide pollution liability broadened coverage for covered autos (endorsement CA 99 48 03 06 or CA 01 12 01 21).

6. Workers’ Compensation, Employer’s Liability, and Disability Benefits Sections 57 and 220 of the New York State Workers’ Compensation Law require the heads of all municipal and State entities to ensure that businesses applying for contracts have appropriate workers’ compensation and disability benefits insurance coverage. These requirements apply to both original contracts and renewals. The following forms are available on the Workers’ Compensation Board website.

i. Proof of Compliance with Workers’ Compensation Coverage

Requirements:

(a) Form CE-200 (Certificate of Attestation of Exemption);

or

(b) Form C-105.2 (Certificate of Workers’ Compensation

Insurance); or

(c) Form SI-12 (Certificate of Workers’ Compensation

Self-Insurance); or

(d) Form GSI-105.2 (Certificate of Participation in

Workers’ Compensation Group Self-Insurance).

ii. Proof of Compliance with Disability Benefits Coverage Requirements:

(a) Form CE-200 (Certificate of Attestation of Exemption);

or

(b) Form DB-120.1 (Certificate of Disability Benefits

Insurance); or

(c) Form DB-155 (Certificate of Disability Benefits Self-

Insurance).

7. Miscellaneous Insurance Provisions

i. Professional shall make the following endorsements on all certificates and policies provided by Professional:

(a) Named Insureds. CUCF, CUNY, DASNY, the State of

New York and the City of New York (“Named Insureds”) shall be included in all policies required hereunder to be procured and maintained by the successful respondent and its subcontractor (except for worker’s compensation and professional liability) as additional insureds for claims against Named Insureds under this

Contract, with the understanding that any affirmative obligation upon the insured successful respondent or subcontractor (including without limitation the liability to pay premiums) shall be the sole obligation of the successful respondent or subcontractor.

(b) Notice of Cancellation of Policy: The policy shall not be canceled or terminated by the Company unless 30 days’ prior written notice is sent to the insured and to CUCF by Registered Mail, and the policy shall not be canceled, terminated, modified, or changed by the insured without the prior written consent of CUCF.

(c) Additional insurance coverage may be required based on project specifics and such requirements shall be included in a contract request.

F. Prevailing Wages

This solicitation, and its resulting contract, will be covered by Article 8 of the New York State Labor Law. Accordingly, all work will be subject to Prevailing Wages and to the CUCF Project Labor Agreement (Exhibit 4) between CUCF and the New York City Building and Construction Trades Council and Signatory Local Unions. The Prevailing Wage Number of this solicitation is 2025013824.

G. Bonding Requirements

The awarded respondent must provide a payment bond and performance bond, each with a penal sum equal to the full value of the contract.

IV. Procurement Protocol and Process

A. Designated Contact

In accordance with the Procurement Lobbying Law [State Finance Law § 139-j(2)(a)], respondents to this solicitation must address all questions relating to this solicitation to Designated Contact: CUNY.Builds@CUNY.edu

B. Summary of Policy Prohibition on Procurement Lobbying

Pursuant to State Finance Law § 139-j and § 139-k, this solicitation includes and imposes certain restrictions on communications between CUCF and a respondent during the procurement process. A respondent is restricted from making contact to other than the Designated Contact (as cited in Section IV.A.

of this solicitation) from the earliest posting of the solicitation on the CUCF website, the City Record, or the New York State Contract Reporter through final execution of the contract, defined as the date the contract has received all required approvals.

C. Pre-Bid Conference

A mandatory online pre-bid conference will be held to allow all prospective bidders the opportunity to hear a summary of the scope of work and ask questions. Respondents who wish to attend the conference must submit Exhibit 1 (Responders' Information and Certifications) to the designated contact referenced in Section II.A. An email with the conference details will be sent to those who fill out and return a signed Exhibit 1. Bidders who fail to attend will be deemed non-responsive and will not be eligible to submit a bid for this project.

D. Site Visit

A mandatory Pre-Bid site visit will be held to allow all prospective bidders the opportunity to inspect the site and review existing conditions. Respondents who wish to attend the Site Visit must submit Exhibit 1 (Respondent Information and Certification) to the designated contact referenced in Section IV. An email with the site visit details will be sent to those who submitted a completed Exhibit 1. Bidders who fail to attend and sign the official attendance sheet will be deemed non-responsive and will not be eligible to submit a bid for this project. Prospective bidders must arrive on time and be advised to bring a copy of the bid documents and any questions they may have.

E. Questions

All questions pertaining to this procurement must be submitted in writing via email to CUNY.Builds@CUNY.edu no later than the date specified in the mailto:CUNY.Builds@CUNY.edu mailto:CUNY.Builds@CUNY.edu

Schedule of Key Events in Section I.E. of this solicitation. Questions will not be accepted after this time and date.

F. Notification of Award

An award letter will be sent to the selected respondent indicating a tentative award subject to successful contract negotiations. The remaining respondents will also be notified.

Any tentative award will be subject to all required internal and external oversight approvals, including, as applicable and required, approvals by CUCF’s Board of Trustees, the Office of the New York State Attorney General (OAG), and the Office of the New York State Comptroller (OSC); and shall be contingent on the availability of funds.

G. Debriefing

Unsuccessful respondents may request a debriefing of their proposal by submitting a request via email to the Designated Contact for this solicitation (as cited in Section IV.A of this solicitation) within fifteen calendar days of being notified of being unsuccessful. The debriefing will be given as soon as practicable thereafter but no later than 30 calendar days from receipt of the debriefing request.

H. Submission of Protest

Protests concerning this procurement must be initially filed with the OSC Director of Financial Administration according to OSC’s procedure for protest of procurements at the following link: https://www.osc.ny.gov/state-agencies/gfo/chapter-xi/xi17-protest-procedures.

I. Disclaimer

FPCM is not liable for any cost incurred by a respondent prior to final execution of the contract. Additionally, no cost will be incurred by FPCM for any prospective respondent’s participation in any procurement-related activities.

All information, descriptions, data, tables, calculations, examples, opinions or assumptions made in connection with this solicitation are made in good faith for information purposes only. The respondent shall not rely on any such information without conducting its own independent research and verification.

CUCF, CUNY, and its officers, agents and employees make no representations or warranties, including without limitation representations or warranties as to the accuracy of any information, opinions or assumptions contained in this solicitation or otherwise furnished to respondent by CUCF, CUNY, and will assume no responsibility or liability for any errors and https://www.osc.ny.gov/state-agencies/gfo/chapter-xi/xi17-protest-procedures https://www.osc.ny.gov/state-agencies/gfo/chapter-xi/xi17-protest-procedures omissions contained herein.

J. Freedom of Information Law (FOIL)

CUCF and CUNY’s records, including its solicitation documents, responses received, and contracts, are subject to inspection pursuant to the Freedom of Information Law (“FOIL”) of the Public Officers Law. CUCF will protect confidential and proprietary information from disclosure to the extent permitted by FOIL. Accordingly, respondents should identify those page(s) of their proposal that they believe contain such information and mark it as “Confidential and Proprietary.” In addition, respondents must explain the reason(s) why this information should be considered exempt from public disclosure under FOIL. Include the identification of pages that contain “Confidential and Proprietary information” and the reasons for exemption of such “Confidential and Proprietary information” as an exhibit to the Administrative Proposal and put the following title on top of the page: FOIL - Confidential and Proprietary Information.

K. Format for Submission of Responses

Proposals that do not meet the following requirements may be deemed non-responsive.

1. All Proposals must be submitted to Proposals@cuny.edu and must include the title of the solicitation and the Project Number in the Subject Line.

2. Respondents must submit the following:

i. Exhibit 1 (Respondent Information & Certification): filled and signed.

ii. One PDF, labeled Contractor Qualifications, which must include a list of at least five projects demonstrating the respondent’s work completed within the last five years of this solicitation due date of similar scope and value to the scope of services described in Section II of this solicitation, including the following for each project:

a. A description of the project, including client names and contact information, consultant name and contact information, and the subcontractors used, if any. If client and consultant references cannot be verified within 14 calendar days, after a minimum of three outreach attempts by email and phone by CUCF, the proposer will be deemed non-responsive mailto:Proposals@cuny.edu

b. A detailed description of the scope of services provided, with increased detail on the scope items relevant to this project.

c. The size and scope of the project, including relevant size descriptors such as square feet, and cubic yards, etc. and specific systems deployed.

d. Relevant budget and financial data, including initial construction budget, final construction budget, and a detailed explanation of any changes, identifying what caused the change in construction budget.

e. Relevant schedule data, including initial construction schedule and completion date, final construction completion date, and an explanation of any changes, including how the contractor attempted to mitigate the construction delay and whether they were successful.

f. A description of whether the project was completed as part of a component of a broader construction project or a standalone project for an owner.

iii. Financial Proposal: One PDF, labeled Financial Proposal, containing completed, signed, and notarized Exhibit 3 (Bid Forms).

3. All Proposals must be submitted by 11:59 PM on the Proposal Due Date specified in the Schedule of Key Events in Section I.E of this solicitation.

All Proposals received after the Due Date, will not be accepted and may be returned to the submitting entity at the discretion of CUCF.

4. All Proposals submitted become the property of CUCF.

5. Respondents must ensure information is consistent across submitted documents.

6. CUCF will accept amendments to a respondent’s proposal if the amendment is received by the Due Date, as specified in the Schedule of Key Events in Section I.E of this solicitation.

7. Submitted proposals are binding for 180 days. CUCF may consider a withdrawal of a Proposal only in the following cases:

i. Timing. A respondent may withdraw its proposal at any time before the Proposal Due Date and time. A request to withdraw a proposal must be made in writing on letterhead from the person who signed the proposal. The withdrawal letter may be submitted as an exhibit in an email to the Designated Contact as specified in Section II.A. of this solicitation.

ii. Errors. Upon notification of a material error by CUCF, a respondent may request to withdraw its proposal. Such request must be received in writing on letterhead from the person who signed the proposal within three business days of the notification by CUCF. The respondent may submit this letter as an exhibit in an email to the Designated Contact as specified in Section II.A.

of this solicitation. CUCF will determine whether to grant such request for withdrawal of the Proposal and will respond in writing to the respondent with its decision.

V. Selection Process

The contract will be awarded to the lowest bidding respondent who meets the mandatory requirements and the Contractor Qualifications noted in Section IV.J.2.ii of this solicitation.

VI. Terms & Conditions of Solicitation

A. Important Notices to Respondents

1. Receipt of this solicitation does not indicate that CUCF has pre-determined a respondent is qualified to receive an award. CUCF will make such determination only after it evaluates the proposals in the context of the requirements and specifications contained in this solicitation.

2. CUCF will undertake an initial administrative review of all responses received to determine if they are complete. To be complete, a proposal must include all required information, forms, signatures, and notarizations. CUCF will refer all complete proposals for further evaluation.

3. Issuance of this solicitation does not commit CUCF to award a contract and does not constitute an offer to contract; nor does acceptance or evaluation of any proposals commit CUCF to award a contract or constitute an offer to contract.

4. CUCF shall have no obligation or liability to the respondent(s) selected (if any) as a result of this solicitation unless and until a contract satisfactory to CUCF is signed by the respondent and CUCF, all required internal and external oversight approvals are obtained; and CUCF has notified the respondent of Award of Contract or a Notice to Proceed.

5. Respondents shall be presumed conclusively to have full knowledge of any and all conditions affecting in any way the performance of the contract that were or should have been discovered by a reasonably prudent respondent.

It is each respondent’s responsibility to familiarize itself with all obligations and relevant facilities at CUCF.

6. Under no circumstances shall CUCF be liable for any costs incurred by respondents for any services performed prior to the respondent’s receipt of a fully executed contract approved by all required government authorities and a Notice of Award or Notice to Proceed from CUCF.

7. By submitting a proposal, the respondent promises not to make any claim against CUCF for and acknowledges that it does not have any right to, damages because of any misinterpretation or misunderstanding of the solicitation requirements or specifications or because of any misinformation or lack of information.

B. Reserved Rights

CUCF reserves the right to:

1. Reject any and all Responses received in response to this Solicitation.

2. Withdraw the solicitation at any time, at the agency’s sole discretion.

3. Make an award under the solicitation in whole or in part.

4. Disqualify any respondent whose conduct and/or proposal fails to conform to the requirements of the solicitation.

5. Seek clarifications and revisions of proposals.

6. Use proposal information obtained through site visits, management interviews and the investigation of a respondent’s qualifications, experience, ability or financial standing, and any material or information submitted by the respondent in response to the agency’s request for clarifying information in the course of evaluation and/or selection under the solicitation.

7. Prior to the bid opening, amend the solicitation’s specifications to correct errors or oversights, or to supply additional information, as it becomes available.

8. Prior to the bid opening, direct respondents to submit proposal modifications addressing subsequent solicitation amendments.

9. Change any of the scheduled dates.

10. Eliminate any mandatory, non-material specifications that cannot be complied with by all of the prospective respondents.

11. Waive instances in a response for immaterial non-compliance with this solicitation and reject a response as non-responsive for material non-compliance with these requirements.

12. Negotiate with the successful respondent within the scope of the solicitation in the best interests of CUNY.

13. Conduct contract negotiations with the next responsible respondent, should the agency be unsuccessful in negotiating with the selected respondent.

14. Use any and all ideas submitted in the responses received without liability.

15. Unless otherwise specified in the solicitation, every offer is irrevocable for a period of 180 days from the bid opening.

16. Require clarification at any time during the procurement process and/or require correction of arithmetic or other apparent errors for the purpose of assuring a full and complete understanding of a respondent’s proposal and/or to determine a respondent’s compliance with the requirements of the solicitation.

I. Introduction
II. Scope of Work
III. Regulatory and Compliance Requirements
The successful respondent shall be required to procure, at its sole cost and expense, all insurance required below. Upon request, Contractors shall deliver to CUCF evidence of the insurance required by this solicitation and any Contract resulting from...
1. Commercial General Liability Insurance. Such liability shall be written on the current edition of ISO occurrence form CG 00 01 & ACORD 855, or a substitute form providing equivalent coverage and with no modification to the contractual liability cov...
i. Cover liability arising from premises operations, independent contractors, products-completed operations, broad form property damage, personal & advertising injury, cross liability coverage, liability assumed in a contract (including the tort liabi...
ii. Include bodily injury, property damage, and broad form contractual liability within General Aggregate, Products – Completed Operations Aggregate, Personal and Advertising Injury, Each Occurrence.
iii. Include, but not be limited to premises liability; independent contractors; blanket contractual liability, including tort liability of another assumed in a contract; defense and/or indemnification obligations, including obligations assumed under ...
2. Automobile Liability Insurance. With a combined single limit of not less than $2,000,000. Coverage must apply to the successful respondent’s owned, hired, and non-owned vehicles and include CUCF, CUNY, and the State of New York as additional insure...
3. Owner's Protective Liability Insurance. Covering the liability for damages in respect to all operations of the respondent on a project and in an amount not less than $1,000,000 per occurrence combined single limit and $2,000,000 aggregate. Coverage...
4. Builder’s Risk Insurance. In an amount appropriate for the project generally equal to the value of the contract. Coverage must apply to property while on site, off site, and in transit, include an agreed amount provision which eliminates any coinsu...
5. Contractor’s Pollution Liability Insurance. Covering bodily injury, property damage, clean-up costs/remediation expenses, and legal defense costs. Such insurance shall provide coverage for sudden and non-sudden pollution conditions arising out of t...
6. Workers’ Compensation, Employer’s Liability, and Disability Benefits Sections 57 and 220 of the New York State Workers’ Compensation Law require the heads of all municipal and State entities to ensure that businesses applying for contracts have app...
i. Proof of Compliance with Workers’ Compensation Coverage Requirements:
(a) Form CE-200 (Certificate of Attestation of Exemption); or
(b) Form C-105.2 (Certificate of Workers’ Compensation Insurance); or
(c) Form SI-12 (Certificate of Workers’ Compensation Self-Insurance); or
(d) Form GSI-105.2 (Certificate of Participation in Workers’ Compensation Group Self-Insurance).
ii. Proof of Compliance with Disability Benefits Coverage Requirements:
(a) Form CE-200 (Certificate of Attestation of Exemption); or
(b) Form DB-120.1 (Certificate of Disability Benefits Insurance); or
(c) Form DB-155 (Certificate of Disability Benefits Self-Insurance).
IV. Procurement Protocol and Process
V. Selection Process
VI. Terms & Conditions of Solicitation