This document is a Statement of Work (SOW) for the underwater cleaning, inspection, and renewal of zinc anodes on the USCGC ANGELA MCSHAN. The work must be performed pier-side from January 6-10, 2025. The contractor must clean the underwater body surfaces, ensure transducers are cleaned without power tools, and renew the government-furnished zinc anodes in accordance with the specified Maintenance Procedure Cards. Video recording of the underwater surfaces before and after cleaning is required. The contractor will be provided specific government-furnished anodes, nuts, screws, and plates to complete the renewal.

The related federal contract opportunity is a Request for Quotes (RFQ) to perform the work described in the SOW. The contract will be awarded as a firm-fixed price purchase order using simplified acquisition procedures. Interested offerors must submit quotes by November 26, 2024, including a cost breakdown, labor costs, extended and total price, payment terms, discount for prompt payment, and company DUNS and CAGE code. Award will be based on the quote most advantageous to the government considering price and other factors.

View the file

Other files

File Type Posted
NOVEMBER 2024 52000QR250000849 FAR CLAUSE 52.212-5.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U/W Body (Waterborne), Clean and Inspect, Renew Zinc Anodes

1. Scope

1.1 Intent. This work item describes the requirements for the Contractor to clean the vessel’s U/W body and to renew bolt-on zinc anodes, while the vessel is moored pier side.

1.2 Cutter, Address, Availability, and POC. USCGC ANGELA MCSHAN, 1 Munro Ave. Cape May, NJ.

08204. Cutter Availability: 06 Jan – 10 Jan, 2025. Cutter POC will coordinate service OOA 30 Dec 2024. MKC Raymond Beecher, (843) 529-0158, raymond.r.beecher@uscg.mil

1.3 Government-furnished property.

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

N Anode, stern tube P/N: Z0020202H3

NIIN: 016445483

28 ea. $11.15

N Nut, Self-Locking P/N: 90715A145

NIIN: 015085774

2 Bx *24 in a bx

$7.24

N Anode, Sea Chest Grate P/N: GA-4

NIIN: 016476179

4 ea. $21.93

N Screw, Prop zinc plate P/N: 950756

NIIN: 016340210

8 ea. $9.42

N Screw, Sea Chest Grate Anode, P/N: 93190A634

NIIN: 016197182

4 ea. $9.70

N Screw Cap, Stern Tube Covers

P/N: 90585A626

NIIN: 016161107

42 ea. $1.81

N Zinc plate, propeller P/N: 950733

NIIN: 016278941

2 ea. $618.85

N Anode, Bow Thruster, Gear Case, Bolt On

P/N: 1081226

NIIN: 123561870

1 ea. $64.97

N Anode, Bow Thruster, Tunnel, Bolt On

P/N: CM2000Z

NIIN: 200126334

12 ea. $29.46

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 154B WPC 111-301, Rev A, Shell Expansion Coast Guard Drawing 154B WPC 161-301, Rev -, Skegs and Stern Tubes Support Structures Coast Guard Drawing 154B WPC 562-201, Rev -, Rudder Details Coast Guard Drawing 154 WPC 565-201, Rev -, Fin Stabilizer System A & D Coast Guard Drawing 154B WPC 568-201, Rev B, Bow Thruster System A & D

Coast Guard Drawing 154 WPC 997-302, Rev -, Docking Plan

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Maintenance Procedure Card B10015.D (MPC B10015.D), 10/31/24, Insp/Cln U/W Equipment (Hull Plate) Surface Forces Logistics Center Maintenance Procedure Card B10018.D (MPC B10018.D), 5/31/23, Replace Underwater Zinc Anodes

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not Applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor must remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Requirements. The Contractor must:

3.2.1 Video recording. Submit video highlights of underwater body surfaces (e.g. bow thruster, propellers, rudders, transducers, heavily fouled hull areas, etc.) before and after cleaning.

3.2.2 Clean/inspect. Clean the U/W body surfaces free of all marine growth, debris, and all other surface contaminants in accordance with MPC B10015.D. Ensure all transducer surfaces are cleaned with only hand held brushes, without the use of power attachments. Ensure that existing u/w body coating system or non-coated surfaces do not incur any damage during cleaning process. Refer to Coast Guard drawings listed in Section 2.

3.2.3 Renew anodes. Renew Government-furnished components listed below paragraph 1.2. in accordance with MPC B10018.D.

U/W Body (Waterborne), Clean and Inspect, Renew Zinc Anodes