Statement of Work.docx
DOCX document 22 KB Posted
- Solicitation number
- HT941025Q2026
- Issued by
-
Defense Health Agency
About this file
This Statement of Work details the installation requirements for dental chair lights at the Lemoore Hornet Health Dental Clinic, located at Building 11, Reeves Blvd, Lemoore CA, 93246. The project involves installing previously ordered lights and seven 551 Assistant's Instrumentations to bring dental chairs to full functionality.
The vendor's responsibilities include placement of all equipment (which will be delivered prior to installation), assembly and anchoring according to factory specifications, and making final air and vacuum connections. The vendor must perform calibration and function testing of all equipment. The installation team will dispose of trash in customer-provided dumpsters, conduct a walk-through with the owner/contractor to note punch-list items, and obtain a customer acceptance sign-off letter upon completion. The customer is responsible for delivering equipment near the dental treatment rooms before installation begins.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Combined Synopsis Services - Dental Light Installation.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Name of Project
ADEC Light Installation
Background
Lemoore Hornet Health Dental Clinic has dental chairs without lights attached. Lights have been ordered; however, they need to be installed. This statement of work details the work that will be completed by the vendor to install lights and seven 551 Assistant’s Instrumentations used for the installation, bringing the chairs to full functionality.
Location
Hornet Health Dental Clinic Lemoore Building 11, Reeves Blvd Lemoore CA, 93246
Tasks
· Placement of all items into specified location.
· Boxed deliveries will be delivered prior to installation and will need to be offloaded and stored at the customer expense. Customer is responsible for delivering the equipment within close proximity to the dental treatment room prior to installation team’s arrival.
· Assembly of all items per factory specifications and agency requirements.
· Anchoring of all items per factory specifications and agency requirements.
· Final air and vacuum connections
Standards and Testing
· Calibration and function testing of equipment.
Closure
· Trash Removal
· For boxed deliveries, the installation team will dispose of all trash at an on-site dumpster provided by the customer.
· Walk-through with the owner and/or contractor will be completed, noting any punch-list items.
· A “customer Acceptance” sign-off letter will be requested upon completion.
File details come from the government source that posted it. Updated .