OPOAM 3016.505-90(a)(2)(ii) Justification for Exception to Fair Opportunity

Exceeding the SAT pursuant to FAR 16.505(b)(2)(i)(B)

JEFO No.: FY18-0033 Rev. 11/9/2017 - 1 -

JEFO No.: FY18-0033

Date: 11/24/2017 PR Number: ICS180005

1. Agency and Contracting Activity.

The Department of Homeland Security, United States Citizenship and Immigration Services (USCIS), Office of Contracting (OCON) prepared this justification for an exception to fair opportunity. USCIS proposes to extend task order HSSCCG-12-J- 00113 for Tier 1, National Customer Service Center (NCSC) service for the USCIS Customer Service and Public Engagement Directorate (CSPED).

2. Nature and/or description of the action being approved.

USCIS intends to noncompetitively extend the existing task order issued under contract GS00V08PDD0066 without considering other GSA USA Contact Indefinite Delivery/Indefinite Quantity (IDIQ) awardees pursuant to FAR 16.505(b)(2)(ii)(B). GSA USA Contact vehicle is not a GSA Schedule, rather a multi-award IDIQ contract. This extension will allow USCIS the time necessary to transition to new technology required for the performance of follow on task order. The current task order will be extended five months, with a total possible value of $12,424,500.

3. A description of the supplies or services required to meet the agency’s needs.

CSPED has a continuing requirement for contract support to provide Tier 1 call center customer assistance under the NCSC task order. Applicants and U.S. citizens contact the NCSC seeking general information, to inquire about the status of their case(s), to report suspected fraud, to change their address, and discuss other areas of general inquiry by telephone and/or electronic means, such as web-chat. The Tier 1 call center serves as the first line of customer support in USCIS; annually answering over 7.2 million customer inquiries, creating over 500,000 service requests, and transferring calls to Tier 2, which deals with matters outside the scope of the task order.

The intent is to extend the current task order with CSRA five months. See table below for breakdown of performance period and pricing.

Exceeding the SAT pursuant to FAR 16.505(b)(2)(i)(B)

JEFO No.: FY18-0033 Rev. 11/9/2017 - 2 -

Proposed Extension Table

Proposed Extension

Period of Performance 12/1/2017- 4/30/2018

CLIN X001 – 1-150,000 calls $6,307,500 CLIN X002 – 150,001-400,000 Calls $4,747,500 CLIN X003 – Incentive Award $1,105,500 CLIN X004 - EMMA Live Chat $264,000 Total $12,424,500

4. Identify the exception to fair opportunity and supporting rationale, including a demonstration that the proposed contractor’s unique qualifications or the nature of the acquisition requires use of the exception cited.

FAR 16.505(b)(2)(i)(B). Only one awardee is capable of providing the supplies or services required at the level of quality required because the supplies or services ordered are unique or highly specialized.

Rationale:

The purpose of this action is to ensure the continued operation of the Tier 1 call center without mission degradation during the transition from the NSCS task orders. USCIS solicited the recompeteof the NSCS task order, giving fair opportunity to all USA Contact IDIQ holders. The result was the award to CSRA, LLC of the Customer Engagement Center (CEC) task order, 70SBUR18F00000028, on 10/19/2017. At the time of award, USCIS had not received the necessary funding needed to order the government furnished property (GFP) or government circuits which are required before performance can begin on the CEC task order. That funding came through on or about 11/17/2017. The GFP and circuits will be placed on order through the GSA Verizon Networx contract by the end of November, 2017.

For historical reference, on 5/17/2012 USCIS competitively awarded two task orders under the GSA USA Contact IDIQ contract; HSSCCG-12-J-00113 to CSRA, LLC and HSSCCG-12-J-00114 to Enterprise Services.

- The tasks orders are for the operation of the Customer Service and Public Engagement Directorate (CSPED) Tier 1 telephone call center support.

- Under these two task orders the government owns and maintains the voice and data circuits in to the contractor’s facilities; while the contractor owns all the equipment and software past the demarcation point of the circuits to operate the centers.

- The feasible alternative of a single award was rejected in order to take advantage of the competition that two task orders would provide. It was anticipated that the

Exceeding the SAT pursuant to FAR 16.505(b)(2)(i)(B)

JEFO No.: FY18-0033 Rev. 11/9/2017 - 3 -competition would improve (decrease) the wait time for callers. Instead, having two task orders has created an extensive administrative burden.

Of the original two task order awards, CSRA, LLC’s task order’s initial 5 year performance period started 6/1/2012 and ended on 5/30/2017. USCIS exercised the FAR Clause 52.217-8 Option to Extend Services six months performance period, which ends on 11/30/2017. This clause was evaluated at the time of the task order award. This expiring task order is the subject of this justification.

It is not feasible to use the new CEC task order to provide services prior to the installation of GFP and upgraded government circuits.

- From the recompete, CSRA, LLC was the successful offeror of the new Tier 1 CEC task order, awarded on 10/19/2017. The original period of performance (POP) start date of the task order was 2/1/2018. Funding and equipment lead-times have contributed to the start of the POP being shifted to 5/1/2018.

- Consideration was given to using the CEC task order to provide services prior to the installation of government furnished property GFP; however, this would require a major rewrite of the task order requirements and repricing; which would be a scope change to the tasks and pricing.

- The new task order is different from the current task order, as it incorporates GFP inside the contractor’s facilities in order to allow greater continuity between Tier 1 and 2 contact centers. The move from the contractor furnished property to GFP represents a major shift between NCSC and CEC.

- The government is required to procure all new data and voice circuits in order for the contractor to perform under the new award. This is a major upgrade from the existing NCSC circuits.

- Before the newly awarded task order performance can start, the Office of Information Technology (OIT) needs to purchase GFP and a complete government owned computer network, with voice over internet protocol (VOIP) capacities, and install the equipment inside the contractor owned facilities.

- OIT is projecting to have equipment ordered by the end of November, 2017. That should allow for equipment to be installed by 3/31/2018.

- CSRA will need 30 days for training on the government network and government software before starting performance on 5/1/2018.

While USCIS OIT works on purchasing and installing GFP for the new task order, only one awardee is capable of providing the services required at the level of quality needed for a contractor to successfully perform the NCSC services, as it requires the government to supply the voice and data circuits.

- The current cost of the circuits is $8.7 Million. For a non-incumbent contractor to perform the services, the government would have to procure the circuits. Typically there is a 90 to 120 day lead-time to install new government circuits.

Exceeding the SAT pursuant to FAR 16.505(b)(2)(i)(B)

JEFO No.: FY18-0033 Rev. 11/9/2017 - 4 -

- Each of the two current contractors has circuits installed through the GSA Verizon Networx contract. It is not feasible that any contractors other than the current two incumbents could perform services for USCIS without substantial cost and delay to the government.

- Neither of the two incumbent contractors has the government circuit capacity to handle the entire USCIS Tier 1 call volume; therefore, the extension requirement could not be competed between the two incumbent contractors.

Failure to award a sole source extension to CSRA, LLC will result in major degradation to the USCIS primary mission. Since CSRA handles nearly 50% of the call volume for Tier 1, that call center capacity would be lost until the new CEC task order is at full performance; which will be five months from now.

5. Determination by the contracting officer that the anticipated cost to the government will be fair and reasonable.

Award is being made against the GSA USA Contact IDIQ contract; which has an ordering period currently set to expire on 3/10/2018. GSA informed the USCIS Contracting Office on 11/15/2017 of its intent to extend the ordering period through 9/10/2018. The current IDIQ includes pricing tables already determined by the GSA contracting officer to be fair and reasonable, which covers task orders issued against the IDIQ prior to the end of the ordering period for performance periods through 3/10/2023.

The contracting officer will perform a price analysis comparing approved GSA pricing tables against the CSRA price proposal. Therefore, the contracting officer will have an adequate basis upon which to determine the anticipated cost to the government to be fair and reasonable.

6. Any other facts supporting the justification.

None.

7. A statement of the actions, if any, the agency may take to remove or overcome any barriers that led to the exception to fair opportunity before any subsequent acquisition for the supplies or services is made.

Closer coordination will take place with the financial office and OIT for the newly awarded task order for CEC. Once successful transition to the newly competed task order is accomplished, there will be no longer be a barrier that led to the exception to fair opportunity.

8. USCIS Office of Contracting intends to post this requirement on FedBizOpps, pursuant to FAR 16.505(b)(2)(ii)(D).

Exceeding the SAT pursuant to FAR 16.505(b)(2)(i)(B)

JEFO No.: FY18-0033 Rev. 11/9/2017 - 5 -

9. Technical/Requirements Personnel Certification.

Pursuant to FAR 16.505(b)(2)(ii)(B)(9), I certify that this requirement meets the government’s minimum need and that the supporting data, which form a basis for the justification, are accurate and complete.

Freddie G. Jordan Date Supervisory Management and Program Analyst

USCIS CSPED

10. Contracting Officer Certification and Approval

Pursuant to FAR 16.505(b)(2)(ii)(B)(8), I certify that this justification is accurate and complete to the best of my knowledge and belief and hereby determine that the circumstances for an exception to fair opportunity exist.

Sarah Rizner Date Contracting Officer USCIS Office of Contracting

11. Approval.

Pursuant to FAR 16.505(b)(2)(ii)(B)(10), I hereby determine that the circumstances in FAR 16.505(b)(2)(i)(B) for an exception to fair opportunity exist and applies to this task order extension.

Gary Hickey Date OPO Procuring Activity Advocate for Competition freddie.jordan@ uscis.dhs.gov

Digitally signed by freddie.jordan@uscis.dhs.gov

DN:

cn=freddie.jordan@uscis.dhs.gov Date: 2017.11.28 11:13:43 -05'00'

Sarah E Rizner

Digitally signed by Sarah E Rizner DN: c=US, o=U.S. Government, ou=Department of Homeland Security, ou=USCIS, ou=People, cn=Sarah E Rizner, 0.9.2342.19200300.100.1.1=100739025 Date: 2017.11.28 11:22:38 -05'00'

GARY E

HICKEY

Digitally signed by

GARY E HICKEY

Date: 2017.11.28 13:01:23 -05'00' 11/28/2017