Solicitation HSFEHQ-10-R-0166 Questions and Answers

Q. When is the anticipated start date for the project?

A. September 30, 2010.

Q. What are the typical working hours for the construction crews?

A. Monday - Saturday, 8:00 am - 5:00 pm.

Q. Did the construction company prepare a schedule for the project?

A. The construction schedule will be prepared by the construction firm but the construction contract will not be awarded until September 29, 2010.