Attachment Three (3)

HSFE70-15-R-0031

Laundry Services

Performance Objective

Standard Performance Threshold

Method of Surveillance

Impact on Payments

Emergency Response/Sur ge Delivery

As listed in PWS Section 3.0 – Deliverables and Delivery Schedule

-75% of leased equipment delivered within 72 hours of task order issuance -25% of remaining leased equipment delivered within 96 hours of task order issuance -all leased equipment assembled, set up and operational within 12 hours of onsite delivery -repair/ replacement performed within 24 hours of notification

On-Site contractor rep/COR communication

Failure to perform without notification may lead to non-payment

Record Keeping and Acceptance

As listed in PWS Section 4.0 – Record Keeping and Acceptance maintain accurate records if all shipments and deliveries with proper signatures

On-Site contractor rep/COR communication

Failure to perform may lead to delayed and/or non-payment

Option 1 As listed in PWS Section 5.0 – LE Contents

Meeting or Exceeding all requirements of option 1 identified in the PWS

On-Site contractor rep/COR communication

Failure to perform may lead to non-payment

Option 2 As listed in PWS Section 5.0 – LE Contents

Meeting or exceeding all requirements of option 2 identified in the PWS

On-Site contractor rep/COR communication

Failure to perform may lead to non-payment

Option 3 As listed in PWS Section 5.0 – LE Contents

Meeting or exceeding all requirements of option 3 identified in the PWS

On-Site contractor rep/COR communication

Failure to perform may lead to non-payment

Reporting As listed in PWS Section 9.0 – Reporting

100% compliance with all reporting requirements identified in the PWS

Daily Report Delay on submitting reports as required by the PWS may lead to delayed payment.

Option 2 & 3 As listed in PWS Complies with DOJ On-Site contractor Failure to provide

Attachment Three (3)

HSFE70-15-R-0031

Laundry Services

Customer Clothing drop off & return area is ADA accessible

Section 5.0 – LE Contents & Department of Justice (DOJ) 2010 Americans with Disabilities Act (ADA) Standards for Accessible Design, dated September 15, 2010. Copy of full text document:

http://www.ada.g ov/regs2010/2010 ADAStandards/Gu idance2010ADAst andards.htm Additionally, for any contracted equipment or for services identified as “accessible:” A 12’ ramp shall be included, for every 1' in rise to provide for access to the service area for laundry drop off and return.

(DOJ) 2010

Americans with Disabilities Act (ADA) Standards for Accessible Design, dated September 15, 2010. (DOJ) 2010

Americans with Disabilities Act (ADA) Standards for Accessible Design, dated September 15, 2010. The clothing drop off/return area is accessible to include a ramp IAW with DOJ standard.

rep/COR Communication

ADA accessible area may lead to non-payment.

Basic Cleanliness of Laundry area to include Clothing drop off & return space.

As listed in PWS Section 5.0 – LE Contents

Maintain clean, presentable and sanitized laundry area

100% Compliance Met by On-Site/ contractor rep/COR thru random laundry room checks and customer feedback

Failure to comply may lead to violations of local municipal laws & regulations and could lead to delayed and/or non-payment http://www.ada.gov/regs2010/2010ADAStandards/Guidance2010ADAstandards.htm http://www.ada.gov/regs2010/2010ADAStandards/Guidance2010ADAstandards.htm