CC-1280-6699023.pdf

PDF 4 MB Posted

Attached to
Replace Steam Condensate Recovery Unit Chase B, USCG Academy, New London, CT
Solicitation number
HSCGG1-17-Q-PFA016
Issued by

About this file

Drawings CC-1280=6699023

View the file

Other files

File Type Posted
Specs_6699023.pdf PDF
RFQ_HSCGG1-17-Q-PFA016.pdf PDF
Wage_Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MAIN

GATE

DESHON ST

GATE

GENERAL NOTES

(GENERAL NOTES APPLY TO DRAWINGS ME-100 TO ME-103)

1. THE PLANS WERE DERIVED FROM EXISTING DRAWINGS. IT WILL BE THE CONTRACTOR'S

RESPONSIBILITIES TO FIELD VERIFY EXISTING SITE CONDITIONS TO IMPLEMENT INTENT

OF SCOPE OF WORK PER PLANS AND SPECIFICATIONS.

2. EQUIPMENT SHALL BE INSTALLED PER MANUFACTURER'S INSTALLATION INSTRUCTIONS.

REFER TO MANUFACTURER CERTIFIED DRAWINGS FOR EQUIPMENT DIMENSIONS AND

MAINTAIN RECOMMENDED CLEARANCES.

3. CONTRACTOR SHALL COORDINATE WITH THE CONTRACTING OFFICER'S

REPRESENTATIVE (COR) FOR TEMPORARY STEAM SHUTDOWN AS NECESSARY TO

REMOVE AND RECONNECT CONDENSATE RETURN UNIT. SHUTDOWN AS NECESSARY

SHALL BE SCHEDULED IN WRITING AND APPROVED BY THE COR. CONTRACTOR IS

REQUIRED TO FIELD VERIFY PIPE ROUTING AND IDENTIFY STEAM SHUTOFF VALVES

REQUIRED TO ISOLATE PROPOSED SYSTEM. TEMPORARY CONDENSATE DISCHARGE TO

FLOOR DRAIN WILL BE PERMITTED, FLOOR DRAIN IS LOCATED WITHIN THE

MECHANICAL ROOM.

4. CONTRACTOR SHALL PROVIDE CONSTRUCTION COORDINATION AND AS-BUILT MARK-UP

PLANS REQUIRED FOR MECHANICAL AND ELECTRICAL SYSTEMS.

5. CONTRACTOR SHALL LEAVE THE ENTIRE MECHANICAL AND ELECTRICAL SYSTEMS

UNDER THIS CONTRACT IN PROPER WORKING ORDER AND SHALL REPLACE, WITHOUT

ADDITIONAL CHARGE, ALL WORK OR MATERIAL WHICH MAY DEVELOPED EFFECTS,

ORDINARY WEAR AND TEAR OR DAMAGE RESULTING FROM IMPROPER HANDLING,

WITHIN A PERIOD OF ONE YEAR FROM THE DATE OF INITIAL TESTING AND ACCEPTANCE

BY USCGA.

6. COMMISSION ALL NEW EQUIPMENT AND SYSTEMS. ALL COMMISSIONING REPORTS

SHALL BE SUBMITTED TO USCGA FOR APPROVAL. REPORT SHALL INCLUDE ALL

COMPLETED TEST FORMS, EQUIPMENT CHECKLISTS, AND MANUFACTURER STARTUP

FORMS.

7. CONTRACTOR SHALL PROVIDE A FACTORY CERTIFIED TECHNICIAN FOR THE STARTUP OF

ALL INSTALLED EQUIPMENT. ALL EQUIPMENT MANUFACTURER'S RECOMMENDED

STARTUP AND CHECK-OUT PROCEDURES SHALL BE COMPLETED BY AN AUTHORIZED

TECHNICIAN AND DOCUMENTED ON THE MANUFACTURER'S FORMS.

ELECTRICAL GENERAL NOTES:

8. ALL ELECTRICAL WORK SHALL BE PERFORMED BY LICENSED ELECTRICIANS AND IN

ACCORDANCE WITH THE 2011 EDITION OF THE NATIONAL ELECTRICAL CODE (NEC).

9. DRAWINGS ARE DIAGRAMMATIC AND DO NOT SHOW ALL BENDS, FITTINGS, BOXES ETC.

PROVIDE ALL MATERIALS AND LABOR REQUIRED FOR A COMPLETE AND FULLY

OPERATIONAL SYSTEM.

10. WHEN SECURING POWER TO CIRCUITS AND EQUIPMENT AS PART OF THIS PROJECT,

CONTRACTOR SHALL FOLLOW OSHA GUIDELINES AS RELATED TO LOCKOUT/TAGOUT

PROCEDURES. ALL POWER OUTAGES REQUIRE A MINIMUM 72 HOUR NOTICE PRIOR TO

DE-ENERGIZING. COORDINATE ALL POWER OUTAGES WITH THE USCGA CONTRACTING

OFFICER'S REPRESENTATIVE (COR).

LEGEND & ABBREVIATIONS

NEW PIPING / EQUIPMENT (HEAVY LINE)

EXISTING PIPING / EQUIPMENT TO REMAIN (THIN LINE)

DIRECTION OF FLOW IN PIPE

POINT OF CONNECTION

PROPOSED DEMO AND NEW WORK

REVISION TAG

FEET

GLYCOL MAKE-UP UNIT

ROOM

CODES AND STANDARDS

CONTRACTOR SHALL COMPLY WITH USCGA REQUIREMENTS, THE MOST CURRENT LOCALLY ADOPTED EDITIONS OF

FOLLOWING CODES AND STANDARDS:

1. INTERNATIONAL BUILDING CODE

2. INTERNATIONAL MECHANICAL CODE

3. INTERNATIONAL PLUMBING CODE

4. LIFE SAFETY CODE (NFPA 101)

5. NATIONAL ELECTRICAL CODE (NFPA 70 & 70E)

6. FIRE CODE (NFPA 1)

7. INTERNATIONAL ENERGY CONSERVATION CODE (IECC)

8. NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA).

9. AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI).

10. AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME).

11. AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM).

12. INTERNATIONAL ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE).

13. AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING ENGINEERS (ASHRAE).

14. U.S. DEPARTMENT OF LABOR - OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA) STANDARDS.

15. UNDERWRITERS LABORATORY (UL).

16. AIR CONDITIONING AND REFRIGERATION INSTITUTE (ARI).

NOTE: THE MORE STRINGENT CODE/STANDARD SHALL GOVERN IN CASES WHERE THE LAW AND REGULATIONS

REFERENCED HEREIN CONFLICT.

PROJECT DESCRIPTION

THE PROJECT CONSISTS OF ALL WORK, INCLUDING LABOR AND MATERIALS NECESSARY TO REPLACE

AND INSTALL FOLLOWING SCOPE OF WORK:

1. REMOVE EXISTING CONDENSATE RETURN UNIT, FURNISH AND INSTALL NEW CONDENSATE

RETURN UNIT, PIPING, FITTINGS AND INSULATION AS PER PLANS.

2. REMOVE EXISTING ROOF EXHAUST FAN CURRENTLY SERVING BATHROOM. FURNISH AND

INSTALL NEW ROOF EXHAUST FAN TO SERVE BOTH BATHROOM AND GREASE TRAP

ROOM. PROVIDE NEW DUCTWORK, FITTINGS, AND ACCESSORIES. MODIFY

MECHANICAL ROOM DOOR WITH NEW TRANSFER LOUVER AS PER PLANS.

3. FURNISH AND INSTALL GLYCOL MAKE-UP UNIT. UNIT SHALL BE CONNECTED TO CENTRAL

CHILLED WATER SYSTEM AS PER PLANS.

KEY CONSTRUCTION SCHEDULE

CONTRACTOR IS REQUIRED TO COMPLY WITH FOLLOWING ONSITE CONSTRUCTION SCHEDULE

NECESSARY TO SUPPORT USCGA ACADEMIC CALENDAR:

1. PROJECT PERIOD OF PERFORMANCE: 3-1/2 MONTHS (AWARD TO CLOSING)

2. ONSITE CONSTRUCTION: THREE WEEKS, REQUIRE COORDINATION AND APPROVAL BY COR

3. KITCHEN APPLIANCES SHUTDOWN (KETTLES, DISHWASHER ETC.) AS NECESSARY TO REMOVE

AND INSTALL CONDENSATE RETURN UNIT: TWO DAYS, 4 HOURS PER SHUTDOWN, REQUIRE

COORDINATION AND APPROVAL BY COR

WALL BETWEEN CONDENSATE

RETURN UNIT MECHANICAL

ROOM AND GREASE TRAP

ROOM. SEE ADDITIONAL PLANS

2 3 4 5 6 7

PRESSURE POWERED CONDENSATE PUMP PACKAGE SCHEDULE

DEMOLITION & NEW WORK

REMOVE EXISTING CONDENSATE REMOVAL UNIT, PIPING,

FITTINGS AND ACCESSORIES NECESSARY TO FACILITATE

PROPOSED UNIT AS PER PLAN AND DETAIL.

FURNISH AND INSTALL NEW PRESSURE POWERED PUMP PACKAGE

WITH RECEIVER, PIPING, FITTINGS AND SKID MOUNTING. UNIT

SHALL BE SECURELY ANCHORED TO THE FLOOR.

ALL PIPING SHALL BE SIZED TO MATCH PUMP AND RECEIVER

CONNECTIONS. PROVIDE UNIONS, REDUCER, INCREASER AND

OTHER FITTINGS NECESSARY TO FACILITATE NEW

INSTALLATIONS PER UNIT MANUFACTURER RECOMMENDATIONS.

FURNISH AND INSTALL INSULATION TO ALL NEW PIPING (EXCEPT

VENT). PROVIDE MINIMUM 1" FIBERGLASS INSULATION WITH FSK

JACKETING.

KITCHEN OR PARTIAL BUILDING STEAM SHUTDOWN AS

NECESSARY TO FACILITATE NEW UNIT INSTALLATIONS SHALL BE

COORDINATED WITH COR.

INSTALLATIONS AND START-UP SHALL BE COMPLETED AS PER

MANUFACTURER RECOMMENDATIONS FOR A FUNCTIONAL

SYSTEM OPERATION. CONTRACTOR IS REQUIRED TO PROVIDE

ADDITIONAL PIPING,VALVES, FITTINGS AND ACCESSORIES

NECESSARY PER MANUFACTURER RECOMMENDATIONS.

PIPING SPECIFICATIONS:

STEAM:

MATERIAL: STEEL

TYPE: BLACK

WEIGHT: SCHEDULE 40

CONDENSATE:

MATERIAL: STEEL

TYPE: BLACK

WEIGHT: SCHEDULE 80

VENT:

MATERIAL: STEEL

TYPE: BLACK

WEIGHT: SCHEDULE 40 (OR MATCH EXISTING)

4 5

ROOF EXHAUST FAN

DEMOLITION & NEW WORK

REMOVE EXISTING ROOF EXHAUST FAN TO FACILITATE NEW FAN.

FURNISH AND INSTALL NEW FAN WITH ROOF CURB ADAPTER &

FITTINGS.

FURNISH AND INSTALL EXHAUST GRILLE, PLENUM, DUCTWORK,

DAMPER, FITTINGS AS PER PLAN. EXHAUST GRILLE LOCATION, DUCT

ROUTING SHALL BE FIELD VERIFIED. ALL DUCTWORK SHALL BE

SUPPORTED FROM CEILING STRUCTURE, DUCT SUPPORT REQUIRED

WITHIN EVERY 10 FEET.

WALL OPENING SHOULD BE CLOSED WITH MASONRY TO MATCH

WALL THICKNESS AND TYPE.

REMOVE AND RESTORE EXISTING GREASE TRAP ROOM DOOR WITH

NEW TRANSFER LOUVER.

FURNISH AND INSTALL ONE (1) DUCT AIRFLOW VOLUME DAMPER

(VD) ON EXISTING BATHROOM EXHAUST PER PLAN. SYSTEM

AIRFLOW BALANCING IS NOT REQUIRED. CONDUCT VISUAL

AIRFLOW TEST WITH COR ASSIGNED PERSONNEL.

ELECTRICAL NEW WORK:

DISCONNECT AND SECURE ELECTRICAL FROM EXISTING ROOF

EXHAUST FAN. EXISTING WIRING AND CONDUIT SHALL BE REUSED

TO NEW FAN, PROVIDE EXTENSION AS NECESSARY.

FAN PANEL BREAKER IS LOCATED IN THE KITCHEN, PANEL# LP1B1,

BREAKER# 24 (20A)

EXISTING EXHAUST FAN (EF-6)

NEW EXHAUST FAN

EXISTING GREASE TRAP ROOM DOOR

CUT EXISTING DOOR

TO INSTALL NEW DOOR

LOUVER.

LOUVER SPECIFICATIONS:

TYPE: DOOR LOUVER

HEIGHT: 10-1/2" (MINIMUM)

WIDTH: 20-1/2" (MINIMUM)

LOUVER DOOR THICKNESS:

1-3/8" TO 2-1/4" (FIELD VERIFY)

PROVIDE NEW ROOF CURB

ADAPTER REQUIRED TO

INSTALL NEW EXHAUST FAN

EXISTING ELECTRICAL

WIRING AND CONDUIT SHALL

BE RE-USED, PROVIDE

EXTENSION AS NECESSARY

EXISTING GREASE TRAP ROOM

STEAM VENT CONNECTION

POINT, SEE DETAIL ON PLAN

ME-101

PROPOSED/ ALTERNATE EXHAUST

GRILLE LOCATION.

1 35

GLYCOL MAKE-UP UNIT

5#10 THHN

3/4" EMT

MCC-19

1 2 3

FIELD INSTALL 3/4"

MATERIAL: STEEL SCHEDULE-40

FILED INSTALL RELIEF

VALVE RATED 30 PSI

CONNECT TO EXISTING CHILLED

WATER RETURN LINE

FIELD INSTALL DRAIN

VALVE WITH HOSE &

CAP

EXISTING CHILLED

WATER RETURN MAIN

EXISTING CHILLED

WATER RETURN MAIN

FIELD INSTALL 3/4"

MATERIAL: STEEL SCHEDULE-40

DEMOLITION & NEW WORK

FURNISH AND INSTALL NEW GLYCOL MAKE-UP UNIT AS PER PLAN

AND EQUIPMENT SCHEDULE. UNIT SHALL BE SECURELY

MOUNTED ON EXISTING CONCRETE PAD.

FURNISH AND INSTALL 25 FT. OF 3/4" PIPING AND FITTINGS TO

CONNECT TO EXISTING CHILLED WATER LINE AS PER DETAIL ON

THIS PLAN.

PROVIDE ADDITIONAL 50 GALLON GLYCOL SOLUTION STORAGE

TANK. CONTRACTOR IS REQUIRED TO FILL BOTH TANKS (TOTAL

100 GALLON) WITH 30% PROPYLENE GLYCOL SOLUTION.

PROPYLENE SOLUTION SHALL BE SAFE-T-THERM HD

MANUFACTURED BY HOUGHTON CHEMICAL CORPORATION.

ELECTRICAL NEW WORK:

PROVIDE 20A SINGLE POLE BREAKER IN PANEL PPSB. PROVIDE

NEW 3/4" RIGID STEEL CONDUIT AND 3 #12 THHN WIRING.

(APPROXIMATE 100 FT. OF RIGID CONDUIT, WIRING AND 5 FT. OF

FLEX CONDUIT WITH NEW JUNCTION BOX IS REQUIRED TO NEW

PUMP). PROVIDE WALL MOUNTED PUMP CONTROL SWITCH.

File details come from the government source that posted it. Updated .