INSTALL 65' WYTL SHORE-TIE, USCG STATION PT. ALLERTON, HULL, MA (PLYMOUTH COUNTY)
Solicitation number
HSCGG1-16-Q-PRV161
Issued by

About this file

Scope of Work

View the file

Other files

File Type Posted
P7140562DWGS.pdf PDF
DAVIS_BACON_WAGES_MA13_dtd_051316.docx DOCX document
RFQ_HSCGG1-16-Q-PRV161.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INSTALL 65’ WYTL SHORE-TIE WORK ORDER No. 7140562

DEPARTMENT OF HOMELAND SECURITY

UNITED STATES COAST GUARD

SHORE INFRASTRUCTURE LOGISTICS COMMAND

SCOPE OF WORK

FOR

INSTALL 65’ WYTL SHORE-TIE

AT

CG STA POINT ALLERTON, MA

(PLYMOUTH COUNTY)

WORK ORDER No. 7140562

PROJECT ENGINEER BRANCH CHIEF

TECHNICAL DIRECTOR, by direction

COMMANDING OFFICER

UNITED STATES COAST GUARD

CIVIL ENGINEERING UNIT PROVIDENCE

300 METRO CENTER BLVD

WARWICK, RHODE ISLAND 02886

TABLE OF CONTENTS

SPEC SECTION PART PAGE TITLE

01 11 00 5 SUMMARY OF WORK

01 11 00 1 5 GENERAL

01 11 00 1.1 5 GENERAL REQUIREMENTS

01 11 00 1.2 8 LOCATION

01 11 00 1.3 8 EXISTING CONDITIONS

01 11 00 1.4 11 DRAWINGS

01 11 00 1.5 11 ADDITIONAL REQUIREMENTS

01 11 00 1.6 17 DIFFERING SITE CONDITIONS

01 11 00 1.7 18 SUBMITTALS

01 11 00 2 18 PRODUCTS

01 11 00 3 18 EXECUTION

01 11 00 3.1 18 SAFETY

01 11 00 3.2 19 ELECTRICAL RACEWAYS

01 11 00 3.3 19 UNDERGROUND OBSTRUCTIONS

01 11 00 3.4 20 GENERAL EXCAVATION

01 11 00 3.5 22 FINISHING

01 32 00 1 23 CONSTRUCTION SCHEDULE/

SCHEDULE OF VALUES

01 32 00 1 23 GENERAL

01 32 00 1.1 23 SUBMITTALS

01 32 00 1.2 23 CONSTRUCTION SCHEDULE

01 32 00 1.3 24 UPDATED SCHEDULES

01 32 00 2 25 PRODUCTS (Not Used)

01 32 00 3 25 EXECUTION

01 32 00 3.1 25 PROGRESS UPDATES

01 33 00 26 SUBMITTAL PROCEDURES

01 33 00 1.1 26 DEFINTIONS

01 33 00 1.2 28 SUBMITTALS

01 33 00 1.3 28 USE OF SUBMITTAL REGISTER

01 33 00 1.4 29 PROCEDURES FOR SUBMITTALS

01 33 00 1.5 32 FORMAT OF SUBMITTALS

01 33 00 1.6 34 QUANTITY OF SUBMITTALS

01 33 00 2 34 PRODUCTS (Not Used) 01 33 00 3 34 EXECUTION (Not Used)

01 35 29 35 SAFETY & OCCUPATIONAL HEALTH

REQUIREMENTS

01 35 29 1.1 35 REFERENCES

01 35 29 1.2 36 SUBMITTALS

01 35 29 1.3 36 ACCIDENT PREVENTION PLAN (APP)

01 35 29 2 37 PRODUCTS (Not Used)

01 35 29 3 37 EXECUTION

01 35 29 3.1 37 CONSTRUCTION

01 35 29 3.2 38 PERSONNEL PROTECTION

01 35 29 3.3 38 ELECTRICAL

01 35 29 3.4 39 HOUSEKEEPING

01 50 00 40 TEMPORARY FACILITIES AND

CONTROLS

01 50 00 1.1 40 REFERENCES

01 50 00 1.2 40 WEATHER PROTECTION

01 50 00 1.3 40 STATION OPERATION EFFECTS ON

CONTRACTOR OPERATIONS

01 50 00 1.4 41 SANITARY FACILITIES

01 50 00 2 41 PRODUCTS (Not Used)

01 50 00 3 41 EXECUTION

01 50 00 3.1 41 TEMPORARY PHYSICAL CONTROLS

01 50 00 3.2 41 TEMPORARY WIRING

01 57 19 42 TEMPORARY ENVIRONMENTAL

CONTROLS

01 57 19 1.1 42 REFERENCES

01 57 19 1.2 43 DEFINITIONS

01 57 19 1.3 44 SUBMITTALS

01 57 19 1.4 44 ENVIRONMENTAL PROTECTION

REQUIREMENTS

01 57 19 1.5 45 UNFORESEEN HAZARDOUS MATERIAL

01 57 19 2 45 PRODUCTS (Not Used)

01 57 19 3 46 EXECUTION

01 57 19 3.1 46 PROTECTION OF NATURAL RESOURCES

01 57 19 3.2 46 HISTORICAL AND ARCHAEOLOGICAL

RESOURCES

01 57 19 3.3 47 CONTROL AND DISPOSAL OF SOLID

WASTE

01 57 19 3.4 47 PETROLEUM PRODUCTS

01 57 19 3.5 47 RELEASES/SPILLS OF OIL AND

HAZARDOUS SUBSTANCES

01 70 00 49 CLOSEOUT PROCEDURES

01 70 00 1 49 GENERAL

01 70 00 1.1 49 SUBMITTALS

01 70 00 1.2 49 AS-BUILT DRAWINGS

01 70 00 1.3 49 EQUIPMENT/PRODUCT WARRANTIES

01 70 00 1.4 50 CLEANUP

01 70 00 2 50 PRODUCTS (Not Used) 01 70 00 3 50 EXECUTION (Not Used)

26 00 00 1 51 BASIC ELECTRICAL MATERIALS AND

METHODS

26 00 00 1.1 51 REFERENCES

26 00 00 1.2 51 DEFINITIONS

26 00 00 1.3 52 ADDITIONAL SUBMITTAL INFORMATION

26 00 00 1.4 52 QUALITY ASSURANCE

26 00 00 1.5 53 WARRANTY

26 00 00 1.6 53 MANUFACTURER’S NAMEPLATE

26 00 00 1.7 53 WARNING SIGNS

26 00 00 1.8 54 ELECTRICAL REQUIREMENTS

26 00 00 1.9 54 INSTRUCTIONS TO GOVERNMENT

PERSONNEL

26 00 00 2 54 PRODUCTS

26 00 00 2.1 54 WARNING SIGN MOUNTING

26 00 00 3 54 EXECUTION (Not Used)

26 10 00 1 55 ELECTRICAL SHORE-TIE FACILITIES

26 10 00 1 55 GENERAL

26 10 00 1.1 55 REFERENCES

26 10 00 1.2 55 SUBMITTALS

26 10 00 1.3 55 GENERAL REQUIREMENTS

26 10 00 2 57 PRODUCTS

26 10 00 2.1 57 EQUIPMENT STANDARDS

26 10 00 2.2 57 SHORE-TIE RECETPACLE

26 10 00 2.3 57 ISOLATION TRANSFORMER

26 10 00 2.4 58 GROUND FAULT DETECTION SYSTEM

26 10 00 2.5 61 ENCLOSURES

26 10 00 2.6 61 FIBERGLASS U-CHANNEL

26 10 00 2.7 62 FASTENERS

26 10 00 2.8 63 RACEWAYS AND CONDUCTORS

26 10 00 2.9 63 CONTROL TRANSFORMERS

26 10 00 2.10 63 INSTRUMENTATION TRANSFORMERS

26 10 00 2.11 64 INSTRUMENTATION

26 10 00 2.12 64 ENCLOSED CIRCUIT BREAKER

26 10 00 3 64 EXECUTION

26 10 00 3.1 64 INSTALLATION

26 10 00 3.2 66 ACCEPTANCE TESTING

APPENDIX A1 70 PANEL DIRECTORIES

APPENDIX DIAGRAM A3 73 LOW POWER CUTTERS, 450V, 3PH

ONE-LINE DIAGRAM

APPENDIX DIAGRAM B2 75 SHORE-TIE GROUNDING DIAGRAM

450V, DELTA UNGROUNDED SERVICE

--End Table of Contents--

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 General Requirements

1.1.1 The following work is associated with the

installation of a new 450VAC, 60-ampere, 3Ø, 3-wire (UNGROUNDED) electrical shore-tie receptacle at US Coast Guard Station Point Allerton located in Hull, Massachusetts.

VIEW OF 400 FOOT WALKWAY LEADING TO THE OFFSHORE BOATHOUSE

1.1.2 Contractor shall provide and install the

following:

A. Approximately 500 linear feet of raceway and conductors along a walkway (located over the water of Hingham Bay), which leads to an offshore Boathouse where the new shore-tie receptacle and associated equipment shall be installed.

B. Although the majority of the conduits can be installed from the 400 foot long walkway decking between the shore and Boathouse, there is a significant amount of conduit and conductors that will require the contractor to installed beneath the Wharf/Boathouse (over the water of Hingham Bay). Contractor shall determine the means of safely executing this work. Refer to Subpart 1.5.7 (Safety Plan) below.

C. 45 KVA, 208∆-450∆ (ungrounded), 3Ø, dry type, isolation transformer (to include primary overcurrent protection). This work shall include a concrete foundation per Section 1.5.2 (Concrete Foundation) below.

D. Approximately 100 linear feet of conduit for two branch circuits from Boathouse electrical Panel BHP-2 to the new shore-tie location for powering a 120VAC ground fault monitor and general use duplex receptacle. Refer to Drawing sheet E-100 One Line Diagram.

E. 450VAC, 60-ampere, 3-phase, electrical shore-tie receptacle

F. 60AT/100AF enclosed circuit breaker.

G. Ground Fault Detection Monitor to include ungrounded delta surge protection and shunt trip devices. Refer to Drawing sheet E-100 One-Line Diagram and Appendix Diagram A3.

H. Contractor fabricated marine grade aluminum stanchion to support new electrical equipment. Refer to Drawing P7140562D03.DWG and Subpart 1.5.3 (Marine Grade Aluminum Stanchion) below.

I. A 6” wide aluminum cable tray to the existing aluminum gangway to support a future mating cable between boat and receptacle. Refer to Subpart 1.5.4 (New Cable Tray).

J. CG Approved Advanced Energy Metering. Refer to Subpart 1.5.6.

1.1.3 Identifying and Labeling of Electrical Shore-Tie

Circuits

A. Currently there are a total of five (5) 120V, 100- Ampere, 1-Ø; Russellstoll manufactured electrical shore-tie receptacles out on the wharf/Boathouse. However, Boathouse electrical Panel BHP1’s panel directory indicates there are six (6) of these circuits & Panel BHP2’s directory shows there are four (4) for a total of ten (10) 120V, 100- Ampere, shore-tie receptacle circuits. Based on that, there are five circuits shore-tie receptacles that have been removed over the years; yet the panel directories indicate otherwise.

B. Contractor shall trace these ten (10) Boathouse panelboard circuits labeled “100A 120V Recp. Main Pier” and determine which are active and which are not. Re-type new panelboard directories and label per 1.1.3.C below. Assure non-used circuit breakers are in the off position and labeled in the directory as “Spare”. For bidding purposes, assume removal of conductors from five of these circuits breakers and panelboard.

C. Contractor shall label each 120V, 100-Ampere, 1-Ø shore-tie receptacle housing with outdoor rated, minimum 8 mil anodized self adhering labels as follows (label should cover Shore-Tie #1 thru #5):

120V, 100A, 1-Ø, 3W

SMALL BOAT SHORE-TIE #1

D. Contractor shall label new 450V, 60-Ampere, 3-Ø shore-tie receptacle housing with outdoor rated, minimum 8 mil anodized self adhering labels as follows:

CAUTION

UNGROUNDED DELTA

450V, 60A, 3-Ø, 3W

65’ WYTL

E. Contractor shall label new isolation transformer ANSI Z535 standard outdoor label as follows:

CAUTION

SHIP SERVICE ONLY

450 VOLTS, THREE-PHASE

UNGROUNDED DELTA

1.1.4 Licensed Professionals

All electrical work shall be performed by a Massachusetts licensed electrician. Submit a copy of the electrician’s license.

1.1.5 Codes and Standards

A. All electrical work shall be in strict accordance with the NFPA 70 (National Electrical Code (NEC)), NFPA 70E (Standard for Electrical Safety in the Workplace), and

OSHA.

B. Contractor shall pay special attention to NEC Articles 555 (Marinas and Boatyards); 250 (Grounding and Bonding) to include Article 250.21 (A) & (B).

1.1.6 Arc Flash Hazard Analysis

A. Perform Arc-Flash Hazard Analysis in accordance with NFPA 70E. Determine the arc flash hazard associated with the Pier Panel and new isolation transformer. Install Arc- Flash Hazard labels posted on the front of the enclosure to include PPE class.

B. Provide a copy of the final report/analysis.

1.2 Location

Work is to take place at the U.S. Coast Guard Station Point Allerton located at 93 Main Street, Hull, Massachusetts.

1.3 Existing Conditions

1.3.1 Shore-Side

A. Adjacent to the wood walkway on shore is the “Pier Panel”; see photos below. This distribution panel feeds two Boathouse panelboards; BHP-1 and BHP-2 respectively. The Pier Panel shall be the source of power for the new shore-tie circuit; while the Boathouse Panel BHP-2 will feed 120VAC controls and a 120V/20A duplex receptacle. Refer to panelboard directories in Appendix A.

B. Also depicted below is the proposed shore-side location for a new 208∆-450∆, 3-Ø, 45-KVA isolation transformer. The concrete between the Pier Panel and new transformer location shall be saw-cut and trenched for new underground raceway.

VIEW OF PIER PANEL, FUTURE XFMR LOCATION, WALKWAY & BOATHOUSE

1.3.2 Walkway

The existing wood constructed walkway is approximately 400-feet long between the shore and the Boathouse. The walkway is oriented North (looking towards Boathouse from shore) and South. The west side of the wood walkway will be used to secure new 1-1/4” raceway. This is a relatively congested area in which the Contractor shall carefully plan work both above and below the walkway and Boathouse.

VIEW OF SHORE FROM BOATHOUSE VIEW OF WALKWAY WEST SIDE

1.3.3 Boathouse

The Pier Panel on shore feeds two Boathouse Panelboards;

BHP-1 & BHP-2 respectively. BHP-2 shall be used for the 120VAC, 20-ampere circuit to the new Ground Fault Detection Monitor and general use receptacle.

120V/208Y, 3-Ø, “PIER PANEL”

NEW ISO

XFMR AND

PAD

LOCATION

VIEW OF BOATHOUSE PANELS BHP-1 & BHP-2

1.3.4 New Shore-Tie Location

A. The new shore-tie, stanchion, and associated electrical equipment shall be installed on the north side of the Boathouse walkway. The aluminum gangway to receive the new cable tray can be seen in the photo.

B. Refer to Drawing set.

VIEW OF BOATHOUSE WALKWAY (NORTH)

LOCATION OF

NEW

STANCHION

WITH SHORE-TIE

VIEW OF GANGWAY FOR NEW CABLE TRAY

1.4 Drawings

P7140562D01.DWG TITLE SHEET

P7140562D02.DWG ONE-LINE DIAGRAM

P7140562D03.DWG ELECTRICAL DETAILS I

P7140562D04.DWG ELECTRICAL DETAILS II

1.5 Additional Requirements

1.5.1 Mandatory Site Visit

A. Prior to commencing construction and ordering of materials, the Contractor shall visit the site and field-verify all existing conditions. Any ambiguities between the design documents and the field conditions shall be brought to the attention of the Contracting Officer in writing within two working days upon completion of the visit.

B. If the Contractor has no comments or questions upon completion of this site visit; submit a letter (or email) to the Contracting Officer indicating the site visit has been completed and that there are no comments or questions at this time.

1.5.2 Concrete Foundation

A. Contractor shall design and build a concrete foundation to support the weight of the new isolation transformer. Refer to Drawing set. The mounting height for the transformer shall be between 28”-34” above grade with chamfered edges.

NEW CABLE TRAY

TO BE SECURED TO

EXISTING

GANGWAY

B. The new foundation may be Contractor formed and/or pre-fabricated by manufacturer. As can be seen from the photos, there is an abandoned concrete foundation where the new pad is to be located. It is the Contractors discretion as to whether build on top of the abandoned pad or demolish.

C. Submit for approval a sketch indicating the dimensions of the new foundation to include base preparation. The pad shall be dimensioned from the Contractor selected transformer. Include a cut sheet of the new transformer to include dimensions and weights.

1.5.3 Marine Grade Aluminum Stanchion

A. Contractor shall refer to Drawing P7140562. Contractor shall carefully measure all existing conditions prior to fabricating the stanchion. This will also require the Contractor to scale the equipment they are installing onto the stanchion.

B. Once the Contractor has field verified the existing conditions and new equipment scales, submit to the Contracting Officer for approval on an 8” X 8-1/2” sketch of the proposed stanchion and equipment to scale. Indicate the scale on the sketch.

C. Provide minimum 0.25” thick, Type 5086 Marine Grade Alloy to fabricate the new stanchion with welded seems.

D. Use Type 316 stainless steel bolts, fender washers and self locking nuts.

E. Bolt the stanchion through the existing wood curbing using ½” diameter Type 316 stainless steel bolts to include fender washers and self locking nuts. Bolt at the center and equidistant to the left and right of center for three base connections.

1.5.4 New Cable Tray

A. Contractor shall install a new 6” wide X 35’ long marine grade aluminum cable tray along the outside of the existing aluminum gangway (secure on side closet to Boathouse).

B. Contractor shall submit an installation detail on 8- 1/2” X 11” sheet detailing the means of securing the cable tray to the existing gangway; using type 316 stainless steel hardware. There is a vertical post every 51 inches, hence new installation shall secure cable tray at a minimum of every vertical post. Include a cut sheet of the selected cable tray with manufacturer’s instructions.

1.5.5 Existing Cable Support

A. Refer to the photo below. There is an existing lighting circuit cable that is currently secured to the west side of the wood walkway where the new 1-1/4”C and associated U-Channel will be installed. Basically this cable will impede the installation of U-Channel and associated new raceway. Contractor shall remove this cable from their one-hole supports and re-install the cable onto the new U-Channel system with new U-Channel clips.

B. Dispose of old clips.

NEW CABLE TRAY

TO BE SECURED TO

EXISTING

GANGWAY

1.5.6 Advanced Metering

A. General

(1) Contractor shall install advanced energy usage metering for the new shore-tie circuit and existing Pier Panel.

(2) Currently there is an existing Obvius manufactured metering system on site which consists of a Data Acquisition Server (DAS) which is linked via CT’s to monitor various electrical load usages.

(3) Under this scope of work, the Contractor shall install energy metering equipment for the new shore-tie circuit and existing Pier Panel, then link to the existing DAS with Obvius compatible transceivers and CT’s (i.e. Modhopper or equivalent).

(4) Refer to Drawing sheet E-100.

B. Requirements

(1) All equipment installed shall be compatible with the existing Data Acquisition Server (DAS) Model A8812 and wireless transceivers, called ModHoppers Model 9120-5 (256 bit AES encryption technology), manufactured by Obvius, LLC.

Existing 3/8 diameter cable

(2) All equipment installed to include associated cabling and hardware shall be weather resistant or installed in a weather resistant enclosure per manufacturer’s instructions.

(3) All equipment shall be installed per manufacturer’s instructions and shall comply with NEC standards, industry specifications and standards and local codes for performance, reliability, and compatibility. The latest installation manuals for the DAS can be found on www.obvius.com

(4) Install equipment rigidly and adequately for the operating environment. RS485 cable, power cable, and any other wires shall be neatly routed and secured resulting in a neat, orderly appearance. RS485 wiring shall be protected from abrasion upon passing through electrical panel cutout or hole.

(5) Install transceivers as per manufacturer's recommendations and best practices, in order to maximize strength of wireless communication. If the wireless connection between transceivers is weak or intermittent, additional relay transceiver(s) or external antennas shall be installed to facilitate reliable communication.

(6) Upon final installation, equipment shall not interfere with the panelboard or switchgear covers or doors.

(7) The contractor shall ensure that the transceivers are connected to an existing 120VAC power supply.

(8) The Coast Guard will provide diagrams and drawings of the current metering system installed throughout the facility. If removal of existing advanced metering components is necessary as part of the current scope of work, the contractor shall reuse existing equipment where possible and return unused equipment to the Coast Guard.

(9) Programming of the equipment shall be in accordance with the manufacturer’s Installation and Operation Manual.

The Coast Guard will provide the contractor with access to the existing DAS to obtain the existing Modbus addresses, radio channel, and other pertinent information.

(10) Prior to the installation of the equipment, the contractor shall provide the Coast Guard with the number of DAS’s, metering devices and transceivers to be installed.

Upon receipt of the information, DAS, meter and transceiver device names will be provided by the Coast Guard to the contractor.

(11) DASs and Transceivers shall be numbered. The numbering scheme shall be approved by the Coast Guard prior to installation. Each DAS and transceiver installed shall be physically labeled with the corresponding number.

(12) The contractor shall provide a screenshot of the Acquisuite route mapping display/ModHopper route map to depict the signal strength between transceivers at the meter and DAS. Procedures are outlined in the manufacturer’s installation and operation manual. The graphic shall depict green lines for communications between transceivers at the meter and DAS indicating good signal strength. Transceiver numbers shall be included in the screenshots. The intent of the screenshot is to verify that the equipment is properly communicating information at an acceptable quality signal strength from each meter to the DAS.

(13) The contractor shall provide the following information to the Coast Guard for each metering device installed: CG installation name, the common name of the equipment being metered, location of installation (to include the electrical panel number and building name or number), size of meter, device number, device address, serial number, location of associated transceiver, device number of associated transceiver. The contractor shall provide a digital photograph of each set of metering devices after it has been installed in its final location. Multiple devices may be captured in a single photograph if installed within the same location.

(14) The contractor shall provide the following information to the Coast Guard for each transceiver device installed:

CG installation name, location of installation (to include the building name or number), device number, device address, serial number, location of power supply, transceiver signal strength (bars), location of external antennas (if applicable) and the DAS device number the meter is transmitting.

(15) The contractor shall include the location of metering equipment on electrical and building utility drawings (as applicable for electrical, water and gas meters) submitted as part of the original scope of work.

1.5.7 Safety Plan

Refer to Specification Section 01 35 29 (Safety and Occupational Health Requirements) Sub-Part 1.3.1 (Accident Prevention Plan).

1.5.8 Training

A. Contractor shall provide training on the complete operation and testing for CG personnel responsible for using and maintaining the new shore-tie system. This shall include but is not limited to the following:

(1) Complete description of the new electrical shore-tie circuit and configuration.

(2) Proper plugging and unplugging procedures using a CG vessel and their associated mating plug.

(3) Operation of the Ground Fault Detection system and the various alarms.

(4) Operation of the energy management system.

1.6 Differing Site Conditions

A. During the progress of the work, if subsurface or latent physical conditions are encountered at the site differing materially from those indicated in the Contract, or if unknown physical conditions of an unusual nature differing materially from those ordinarily encountered and generally recognized as inherent in the work provided for in the Contract are encountered at the site, the Contractor shall promptly notify the Contracting Officer in writing of the specific differing conditions before the Contractor disturbs the conditions or performs the affected work.

B. Upon receipt of written notification of differing site conditions from the Contractor, the Government will investigate the conditions, and if it is determined that the conditions materially differ and cause an increase or decrease in the cost or time required for the performance of any work under the Contract, an adjustment will be made, excluding loss of anticipated profits, and the Contract will be modified in writing accordingly.

1.7 Submittals

Government approval is required for submittals with a "G" designation. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Pre-Construction Submittals

Licensed Professionals; G

Mandatory Site Visit Letter/Email; G

Concrete Foundation Details; G

Stanchion Details; G

Advanced Metering Products; G

PART 2 PRODUCTS

2.1 All new electrical equipment shall be UL Listed and

rated for the environment it is being installed.

PART 3 EXECUTION

3.1 Safety

3.1.1 Personnel and Contractor Safety is the most

critical element of this work due to the nature of working at heights above the ocean. Contractor shall have their designated Safety Officer inspect all working platforms for safety compliance and personnel for proper PPE.

3.1.2 Personnel working over the water shall wear a DOT

Approved life vest and the proper fall protection.

3.1.3 Contractor shall hold an on-site safety brief

with all Contractor and Sub-Contractor personnel prior to work each day. This meeting shall be documented in writing and a copy submitted to the COR after each meeting.

3.2 Electrical Raceways

3.2.1 All electrical raceways shall be installed in a

neat and professional manner to the industry standards.

Raceways along the walkway shall be installed level and square with the wharf structure. Once below the wharf/Boathouse and out of direct sight, the Contractor may run raceways “as the crow flies” to reduce the overall raceway and conductor lengths. Refer to Specification Section 26 10 00/2.8.1.

3.2.2 Contractor shall carefully mark up the Drawing

Set to accurately identify the new conduit route for the required As-Built drawing submittal.

3.3 Underground Obstructions

3.3.1 The required area of trenching is known to have

underground utilities/obstructions; however, due to a lack of accurate underground site plans, it is the Contractor’s responsibility to identify and mark all underground obstructions.

3.3.2 Likely underground utilities in the vicinity of

the trenching are Electric, Potable Water, Communications, and Sewer.

3.3.3 Prior to digging, perform ground penetrating

radar (GPR) survey of the trenching area.

3.3.4 Pre-mark the area on the ground where the work

will take place, using white paint and/or flags. Note that pre-marking requirements vary slightly from state to state;

hence comply with the standards for the State of Massachusetts.

3.3.5 Make sure the utility marks stay intact during

your project. If the marks are compromised for any reason, remarking the site is mandatory prior to commencing underground work.

3.3.6 Pipes, cables, and wires can be buried at any

depth, so it is risky to dig in close proximity of a buried line. Observe State Law and standards on complying with a Safety Zone (or Tolerance Zone) requirement. The use of mechanized equipment is prohibited when digging within 18 inches of a buried facility. In this Safety Zone (or

Tolerance Zone), you must dig by hand, carefully, to avoid damage.

3.3.7 Contractor shall determine the final depths of

the underground raceway assuming all work is in strict accordance with the NEC.

3.4 General Excavation

Perform excavation of every type of material encountered within the limits of the project to the lines, grades, and elevations indicated and as specified. Excavate unsatisfactory materials encountered within the limits of the work below grade and replace with satisfactory materials as directed. Dispose unsatisfactory excavated material off site.

3.4.1 Bottom Preparation

Grade the bottoms of trenches accurately to provide uniform bearing and support for the bottom quadrant of each section of the pipe. Remove stones of ¾ inch or greater in any dimension, or as recommended by the pipe manufacturer, whichever is smaller, to avoid point bearing.

3.4.2 Removal of Unstable Material

Where unstable material is encountered in the bottom of the trench, remove such material and replace it to the proper grade with select granular material as provided in paragraph BACKFILLING AND COMPACTION. When removal of unstable material is required due to the Contractor's fault or neglect in performing the work, the Contractor is responsible for excavating the resulting material and replacing it without additional cost to the Government.

3.4.3 Final Grade of Surfaces to Support Concrete

Do not excavate to final grade until just before concrete is to be placed.

3.4.4 Buried Warning and Identification Tape

Provide buried utility lines with utility identification tape. Bury tape 12 inches below finished grade; under pavements and slabs, bury tape 6 inch below top of subgrade.

3.4.5 Backfilling and Compaction

Place backfill adjacent to any and all types of structures, and compact to at least 90 percent laboratory maximum density for cohesive materials or 95 percent laboratory maximum density for cohesionless materials, to prevent wedging action or eccentric loading upon or against the structure. Prepare ground surface on which backfill is to be placed as specified in paragraph GROUND SURFACE PREPARATION. Provide compaction requirements for backfill materials in conformance with the applicable portions of paragraphs GROUND SURFACE PREPARATION. Finish compaction by sheepsfoot rollers, pneumatic- tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment.

3.4.6 Trench Backfill

Backfill trenches to the original grade.

3.4.6.1 Replacement of Unyielding Material

Replace unyielding material removed from the bottom of the trench with select granular material or initial backfill material.

3.4.6.2 Replacement of Unstable Material

Replace unstable material removed from the bottom of the trench or excavation with select granular material placed in layers not exceeding 6 inch loose thickness.

3.4.6.3 Bedding and Initial Backfill

Place initial backfill material and compact it with approved tampers to a height of at least one foot above the utility. Bring up the backfill evenly on both sides of the utility for the full length. Take care to ensure thorough compaction of the fill under the haunches of the pipe or conduit. Compact backfill to top of pipe to 95 percent of ASTM D 698 maximum density.

3.4.6.4 Final Backfill

Fill the remainder of the trench, except for special materials for roadways, and railroads with satisfactory material. Place backfill material and compact as follows:

3.4.7 Sub-grade Preparation

3.4.7.1 Compaction

Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel- wheeled rollers, vibratory compactors, or other approved equipment. Except for paved areas and railroads, compact each layer of the embankment to at least 90 percent of laboratory maximum density.

3.4.7.2 Subgrade for Pavements

Compact subgrade for pavements to at least 90 percentage laboratory maximum density for the depth below the surface of the pavement shown.

3.5 Finishing

Finish the surface of excavations, embankments, and subgrades to a smooth and compact surface in accordance with the lines, grades, and cross sections or elevations shown. Provide the degree of finish for graded areas within

0.1 foot of the grades and elevations indicated except that the degree of finish for subgrades specified in paragraph

SUBGRADE PREPARATION.

--End of Section--

SECTION 01 32 00

CONSTRUCTION SCHEDULE/SCHEDULE OF VALUES

1.1 SUBMITTALS

Submit the following in accordance with Section 01 33 00, "Submittal Procedures."

SD-01 Preconstruction Submittals

Construction Schedule/Schedule of Values

1.2 CONSTRUCTION SCHEDULE

At the Pre-Construction Conference, submit a Construction Schedule and Schedule of Values in accordance with FAR Clause 52.236.15. The Schedule of Values shall be based on the actual breakdown of the bid price. The cost of insurance shall not be listed as a separate item but included as part of each item of work. The actual cost of bonds may be paid as the first progress payment when a receipt from the bonding company is presented to the Contracting Officer. For contracts under $25,000, a Schedule of Values is not required. In addition, keep the Government Inspector informed daily of the expected delivery dates for major pieces of equipment and materials.

Construction Schedule and Schedule of Values shall be incorporated into one form which clearly indicates the start and completion dates and unit value of all major work components.

Construction Schedule/Schedule of Values form shall incorporate at a minimum the following activities:

A. Bonds

B. Mobilization

C. Demobilization

D. Pre-Construction Submittals

E. Work Activities

F. In-Progress Submittals

G. Final Government Inspection

H. Close-Out Submittals; i.e. Warranties, Operation and

Maintenance Manuals, Posted Instructions

I. As-Built Drawings

J. Factors which Constitute Potential Interruptions to Station Operations

Pre-Construction Submittals are those activities which encompass the obtaining, submission, review and approval of submittals necessary prior to the start of the related site work. Contractor shall annotate all such activities into the progress schedule with their forecasted time periods.

These activity periods shall not be exclusive of the contract performance period. No site work shall commence until the respective submittals have been approved.

The value of all major work components within the project shall be identified on the Construction Schedule/Schedule of Values on a unit quantity and unit cost basis, e.g.

number of squares and cost per square of roofing, number of lineal feet and cost per lineal foot of conduit, number of panels and cost per panel etc. Lump sum items shall only be paid for when 100% complete.

The Construction Schedule/Schedule of Values as approved by the Government is not a substitute for quantities conveyed by the specification and drawings and those required for a complete job. Omissions and errors on the Construction Schedule/Schedule of Values are the responsibility of the Contractor.

Payments will not be made until the schedule of prices has been submitted to and approved by the Contracting Officer.

1.3 UPDATED SCHEDULES

Update the construction schedule and equipment delivery schedule at monthly intervals or when schedule has been revised. Reflect any changes occurring since the last update. Submit copies of the purchase orders and confirmation of the delivery dates as directed.

Not used.

PART 3 EXECUTION

3.1 PROGRESS UPDATES

3.1.1 General

A revised Construction Schedule/Schedule of Values shall be issued by the Contractor on a monthly basis. In addition, any revisions to the Construction Schedule/Schedule of Values such as modifications or delays shall be reflected by Contractor submission of an updated Construction Schedule/Schedule of Values.

3.1.2 Modifications

When a modification is issued by the Government, record the modification as the last activity of the Construction Schedule/Schedule of Values and include the value of the modification. Adjust the Schedule of Values to reflect the inclusion of the modification. Revise the Construction Schedule portion of the form to annotate the progress change. Enter all modifications in this manner in sequential order.

SECTION 01 33 00

SUBMITTAL PROCEDURES

1.1 DEFINITIONS

1.1.1 Submittal

Shop drawings, product data, samples, and administrative submittals presented for review and approval. Contract Clauses "FAR 52.236-5, Material and Workmanship," paragraph

(b) and "FAR 52.236-21, Specifications and Drawings for Construction," paragraphs (d), (e), and (f) apply to all "submittals."

1.1.2 Types of Submittals

All submittals are classified as indicated in paragraph "Submittal Descriptions (SD)". Submittals also are grouped as follows:

Shop drawings: As used in this section, drawings, schedules, diagrams, and other data prepared specifically for this contract, by contractor or through contractor by way of subcontractor, manufacturer, supplier, distributor, or other lower tier contractor, to illustrate portion of work.

Product data: Preprinted material such as illustrations, standard schedules, performance charts, instructions, brochures, diagrams, manufacturer's descriptive literature, catalog data, and other data to illustrate portion of work, but not prepared exclusively for this contract.

Administrative submittals: Data presented for reviews and approval to ensure that administrative requirements of project are adequately met but not to ensure directly that work is in accordance with design concept and in compliance with contract documents.

1.1.3 Submittal Descriptions (SD)

Submittal register Construction Schedule/Schedule of Values Health and safety plan Environmental protection plan

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials or equipment for some portion of the work

SD-05 Design Data

Calculations, analyses or other data pertaining to a part of work

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)

Final acceptance test and operational test procedure

SD-08 Manufacturer's Instructions

Preprinted material describing installation of a product, system or material, including special notices and Material Safety Data sheets concerning impedances, hazards and safety precautions

SD-10 Operation and Maintenance Data

Data intended to be incorporated in operations and maintenance manuals.

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism

As-built drawings

Special warranties

Posted operating instructions

Training plan

1.2 SUBMITTALS

Submit the following in accordance with the requirements of this section.

Submittal register

1.3 USE OF SUBMITTAL REGISTER

Prepare and maintain submittal register, as the work progresses. Do not change data in columns (c), (d), (e), and (f) as delivered by government.

Submittal Register

Submit submittal register. Do not change data in columns (c), (d), (e), and (f) as delivered by the government.

Verify that all submittals required for project are listed and add missing submittals. Complete the following on the register:

Column (a) Activity Number: Activity number from the project schedule.

Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.

Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.

Column (h) Contractor Approval Date: Date contractor needs approval of submittal.

Column (i) Contractor Material: Date that contractor needs material delivered to contractor control.

1.4 PROCEDURES FOR SUBMITTALS

1.4.1 Reviewing, Certifying, Approving Authority

Government organization shall be responsible for reviewing and certifying that submittals are in compliance with contract requirements. Approving authority on submittals is the CG Construction Project Manager unless otherwise specified for specific submittal.

1.4.2 Constraints

a. Submittals listed or specified in this contract shall conform to provisions of this section, unless explicitly stated otherwise.

b. Submittals shall be complete for each definable feature of work; components of definable feature interrelated as a system shall be submitted at same time.

c. When acceptability of a submittal is dependent on conditions, items, or materials included in separate subsequent submittals, submittal will be returned without review.

d. Approval of a separate material, product, or component does not imply approval of assembly in which item functions.

1.4.3 Scheduling

a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential requirements to resubmit.

b. Except as specified otherwise, allow review period, beginning with receipt by approving authority that includes at least 10 working days. Period of review for each re-submittal is the same as for initial submittal.

1.4.4 Variations

Variations from contract requirements require Government approval pursuant to contract Clause entitled "FAR 52.236- 21, Specifications and Drawings for Construction" and will be considered where advantageous to government.

1.4.4.1 Considering Variations

Discussion with Contracting Officer prior to submission will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).

1.4.4.2 Proposing Variations

When proposing variation, deliver written request to the contracting officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to government. If lower cost is a benefit, also include an estimate of the cost saving.

In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.

1.4.4.3 Warranting That Variation Are Compatible

When delivering a variation for approval, contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.

1.4.4.4 Review Schedule Is Modified

In addition to normal submittal review period, a period of 5 working days will be allowed for consideration by the Government of submittals with variations.

1.4.5 Contractor's Responsibilities

a. Determine and verify field measurements, materials, field construction criteria; review each submittal; and check and coordinate each submittal with requirements of the work and contract documents.

b. Transmit submittals to Contracting Officer in accordance with schedule on approved Submittal Register, and to prevent delays in the work, delays to government, or delays to separate contractors.

c. Advise the Contracting Officer of variations as required by paragraph entitled "Variations."

d. Correct and resubmit submittal as directed by approving authority. When resubmitting disapproved transmittals or transmittals noted for re-submittal, the contractor shall provide copy of that previously submitted transmittal including all reviewer comments for use by approving authority. Direct specific attention in writing or on resubmitted submittal, to revisions not requested by approving authority on previous submissions.

e. Furnish additional copies of submittal when requested by contracting officer, to a limit of 5 copies per submittal.

f. Complete work which must be accomplished as basis of a submittal in time to allow submittal to occur as scheduled.

g. Ensure no work has begun until submittals for that work have been returned as "approved," except to the extent that a portion of work must be accomplished as basis of submittal.

1.4.6 Government Responsibilities

a. Note date on which submittal was received from contractor on each Contract Item Approval Request Form.

b. Review each submittal; and check and coordinate each submittal with requirements of work and contract documents.

c. Review submittals for conformance with project design concepts and compliance with contract documents.

d. Ensure that material is clearly legible.

e. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.

f. Identify returned submittals with one of the actions defined in paragraph entitled "Actions Possible" and with markings appropriate for action indicated.

1.4.7 Actions Possible

Submittals will be returned with one of the following notations:

a. Submittals marked "approved" "approved as submitted" authorize contractor to proceed with work covered.

b. Submittals marked "approved" "see below" authorize contractor to proceed with work as noted provided contractor takes no exception to the notations.

c. Submittals marked "disapproved" indicate submittal is incomplete or does not comply with design concept or requirements of the contract documents and shall be resubmitted with appropriate changes. No work shall proceed for this item until re-submittal is approved.

1.5 FORMAT OF SUBMITTALS

1.5.1 Transmittal Form

Transmit each submittal, except sample installations and sample panels, to office of approving authority. Transmit submittals with transmittal form prescribed by contracting officer and standard for project. The transmittal form shall identify contractor, indicate date of submittal, and include information prescribed by transmittal form and required in paragraph entitled "Identifying Submittals."

Process transmittal forms to record actions regarding sample panels and sample installations.

1.5.2 Identifying Submittals

Identify submittals, except sample panel and sample installation, with the following information permanently adhered to or noted on each separate component of each submittal and noted on transmittal form. Mark each copy of each submittal identically, with the following:

a. Project title and location.

a. Construction contract number.

b. Section number of the specification section by which submittal is required.

c. Submittal description (SD) number of each component of submittal.

d. When a resubmission, alphabetic suffix on submittal description, for example, SD-10A, to indicate resubmission.

e. Name, address, and telephone number of subcontractor, supplier, manufacturer and any other second tier contractor associated with submittal.

f. Product identification and location in project.

1.5.1 Format for Product Data

a. Present product data submittals for each section as a complete, bound volume. Include table of contents, listing page and catalog item numbers for product data.

b. Indicate, by prominent notation, each product which is being submitted; indicate specification section number and paragraph number to which it pertains.

c. Supplement product data with material prepared for project to satisfy submittal requirements for which product data does not exist. Identify this material as developed specifically for project.

1.5.2 Format for Shop Drawings

a. Shop drawings shall not be less than 8 1/2 by 11 inches nor more than 30 by 42 inches.

b. Present 8 1/2 by 11 inches sized shop drawings as part of the bound volume for submittals required by section.

Present larger drawings in sets.

c. Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph entitled "Identifying Submittals."

d. Dimension drawings, except diagrams and schematic drawings; prepare drawings demonstrating interface with other trades to scale. Shop drawing dimensions shall be the same unit of measure as indicated on the contract drawings. Identify materials and products for work shown.

1.5.3 Format of Administrative Submittals

a. When submittal includes a document which is to be used in project or become part of project record, other than as a submittal, do not apply contractor's approval stamp to document, but to a separate sheet accompanying document.

b. Operation and Maintenance Manual Data: Submit in accordance with Section 01781, "Operation and Maintenance Data." Include components required in that section and the various technical sections.

1.6 QUANTITY OF SUBMITTALS

1.6.1 Number of Copies of Product Data

Submit three copies of submittals of product data.

1.6.2 Number of Copies of Shop Drawings

Submit shop drawings in compliance with quantity requirements specified for product data.

1.6.3 Number of Copies of Administrative Submittals

a. Unless otherwise specified, submit administrative submittals compliance with quantity requirements specified for product data.

PART 3 EXECUTION

SECTION 01 35 29

SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI A10.34 (R2012) Protection of the Public on or Adjacent to Construction Sites

CODE OF FEDERAL REGULATIONS (CFR)

29 CFR 1910 Occupational Safety and Health

Standards

29 CFR 1919 Gear Certification

29 CFR 1926 Safety and Health Regulations for Construction

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 241 (2013) Safeguarding

Construction, Alteration, and Demolition Operations

NFPA 70 (2014) National Electrical Code

NFPA 70E (2015) Electrical Safety in the

Workplace

THE INSTITUTE OF ELECTRICAL AND ELECTRONICS

ENGINEERS

IEEE C2 (2012) National Electrical

Safety Code

1.2 SUBMITTALS

SD-07 Certificates

Accident Prevention Plan (APP)

Reports Submit reports as their incidence occurs, in accordance with the requirements of the paragraph entitled, "Reports."

1.3 ACCIDENT PREVENTION PLAN (APP)

1.3.1 Contents of the Accident Prevention Plan

a. Name and safety related qualifications of safety officer (including training and any certifications).

b. Qualifications of competent and of qualified persons.

c. Identity of the individual who will complete exposure data (hours worked); accident investigations, reports and logs; and immediate notification of accidents to include subcontractors.

d. Emergency response plan. Include a map denoting the route to the nearest emergency care facility with emergency phone numbers. Contractor may be required to demonstrate emergency response.

e. Fall Protection and Prevention (FP&P) Plan. The plan shall be site specific and address all fall hazards in the work place. It shall address how to protect and prevent workers from falling to lower levels when they are exposed to fall hazards above 6 feet. A qualified person shall prepare the plan. The plan shall include fall protection and prevention systems, working platforms, equipment, methods employed, responsibilities, rescue and escape equipment and operations, training requirements, and monitoring methods.

f. Working Platforms: How does the Contractor intend on installing platforms under the Wharf/Boathouse elevated above the waters of Hingham Bay.

g. Identify the proper PPE that will be used to include DOT approved life vests.

h. Tidal Conditions: Research and discuss the tidal conditions in the Bay and how the conditions may or may not impact the work.

i. Severe Weather Plan. Procedures of ceasing on-site operations during lightning or upon reaching maximum allowed wind velocities

Not Used.

3.1 CONSTRUCTION

Comply with NFPA 241, the accident prevention plan, the activity hazard analysis and other related submittals and activity fire and safety regulations.

3.1.1 Unforeseen Hazardous Material

If material that may be hazardous to human health upon disturbance during construction operations is encountered, stop that portion of work and notify the Contracting Officer immediately. Within 14 calendar days the Government will determine if the material is hazardous.

If material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If material is hazardous and handling of the material is necessary to accomplish the work, the Government will issue a modification pursuant to "FAR 52.243-4, Changes" and "FAR 52.236-2, Differing Site Conditions."

3.2 PERSONNEL PROTECTION

3.2.1 Hazardous Noise

Provide hazardous noise signs, and hearing protection, wherever equipment and work procedures produce sound-pressure levels greater than 85 dBA steady state or 140 dBA impulse, regardless of the duration of the exposure.

3.2.2 Fall Protection

Enforce use of the fall protection device designated for each specific work activity in the FP&P plan and/or AHA all times when an employee is on a surface 6 feet or more above lower levels. Personal fall arrest systems are required when working from an articulating or extendible boom, scissor lifts, swing stages, or suspended platform.

Fall protection must comply with ANSI A10.32.

3.3 ELECTRICAL

3.3.1 Conduct of Electrical Work

Underground electrical spaces must be certified safe for entry before entering to conduct work. Cable intended to be cut must be positively identified and de-energized prior to performing each cut. Positive cable identification must be made prior to submitting any outage request for electrical systems. Arrangements are to be coordinated with the Contracting Officer and Station Utilities for identification.