SPECIFICATIONS HSCGG1-10-B-PFA004 Medium Voltage Feeder Distribution Replacement USCGA New London CT
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 10-PFA004 RESULTS.pdf | ||
| amendment2.pdf | ||
| amendment1.pdf | ||
| Dwgs.pdf | ||
| IFB-10-B-PFA004.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MEDIUM VOLTAGE FEEDER REPLACEMENT
PHASE 1
U.S. COAST GUARD ACADEMY
NEW LONDON, CT
PROJECT NO. 2512898
NOVEMBER 2009
G.J. CARABINE
DATE: November 13, 2009
U.S. Coast Guard Academy Project # 2512898 Medium Voltage Feeder Replacement
TABLE OF CONTENTS
DIVISION 1 - GENERAL REQUIREMENTS
01040 PROJECT COORDINATION
01100 SUMMARY OF WORK
01120 SPECIAL CONDITIONS (OSHA & ENVIRONMENTAL PROTECTION)
01250 CONTRACT MODIFICATION PROCEDURES
01290 PAYMENT PROCEDURES
01300 SUBMITTALS
01320 CONSTRUCTION PROGRESS DOCUMENTATION
01600 PRODUCT REQUIREMENTS
01700 EXECUTION REQUIREMENTS
01770 PROJECT CLOSEOUT
DIVISION 2 - SITE WORK
02220 DEMOLITION
02920 HYDROSEEDING
DIVISION 16 – ELECTRICAL
16050 BASIC ELECTRICAL MATERIALS AND METHODS
16060 GROUNDING AND BONDING
16075 ELECTRICAL IDENTIFICATION
16080 ELECTRICAL TESTING
16120 CONDUCTORS AND CABLES
16124 MEDIUM VOLTAGE CABLES
16302 UNDERGROUND TRANSMISSION & DISTRIBUTION
END OF TABLE OF CONTENTS
TABLE OF CONTENTS TOC - 1/1
SECTION 01010 - SUMMARY
PART 1 - GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Identification: Project consists of replacing the existing 5KV, 8KV and 15KV underground electrical distribution wiring with new 15KV conductors.
1. Project Location: U.S. Coast Guard Academy (15 Mohegan Avenue, New London, CT 06320).
B. The work consists of: Remove existing cables throughout the HV-1 feeder branch, clean the cable ducts, replace cable holders and pull new 15KV ethylene propylene rubber insulated cable (EPR) with an associated ground conductor in accordance with the specifications.
The work includes but is not limited to the following activities:
1. Removal and disposal of the existing underground medium voltage electrical distribution conductors and replacing them with new 15KV EPR conductors.
2. Replace damaged or missing cable racks and associated mounting hardware.
Provide new glass reinforced nylon cable clamps and cable supports.
3. Provide separable splices and terminations where needed for installation of a complete and operational distribution system.
4. Test all newly installed conductors for continuity and insulation integrity.
C. Project will be constructed under a general construction contract.
1.2 WORK SEQUENCE
A. The work shall be conducted by the contractor to provide the least possible interference to the activities of the government’s personnel.
B. All work shall be done such that existing utility systems not be interrupted except for scheduled outages for utility tie-ins. All utility system interruptions must be scheduled 10 days in advance with the Chief, Construction and Engineering
1.3 USE OF PREMISES
A. General: During the construction period the contractor shall have use of the premises for construction operations, including use of the site as specified by the Contracting
SUMMARY 01010 - 1/3
Officer. Material storage and work areas shall be as designated by the Contracting Officer’s Technical Representative (COTR).
B. Keep roadways serving the premises clear and available to the government and the government’s employees at all times. Do not use these areas for parking or storage of materials.
C. Use of the Existing Buildings:
1. Occupancy: All facilities at United States Coast Guard Academy are oc-cupied buildings.
2. Building Integrity: Maintain the building work-site in a weather-tight condition throughout the construction period. Repair damage caused by construction operations. Take all precautions necessary to protect the building and its contents during the construction period.
3. Toilet Rooms designated for use by the contractor’s personnel shall be specified by the COTR.
4. The building must remain in operation at all times except during brief util-ity changeover period.
D. All construction operations shall be performed between the hours of 7:30 a.m. and 4:00 p.m. local time, Monday through Friday. Submit request to the Contracting Officer at least 72 hours in advance for permission to work outside the normal working hours or on Saturdays, Sundays, or Federal holidays.
1.4 SAFETY PRECAUTION.
A. These construction documents and the construction work hereby contemplated shall be governed at all times by applicable provisions of Federal Regulations, including, but not limited to, the current edition, with the latest amendment(s) of the following:
1. William-Steiger Occupational Safety and Health Act of 1970, Public Law 91-596; Part 1926 – Occupational Safety and Health Standards, Chapter XVII of Title 29, Code of Federal Regulations (29 CFR Part 1926).
B. The contractor shall notify the Fire Marshal via the COTR prior to the start of any con-struction practices which may affect or impair any fire protection system or which may present a fire hazard (i.e., sanding, welding, grinding, applying hot tar, burning and utiliz-ing of any flame producing device).
SUMMARY 01010 - 2/3
1.5 GOVERNMENT OCCUPANCY
A. The government shall occupy the site and existing building during the entire con-struction period. The contractor shall schedule and perform the work so as not to interfere with the government’s operations and shall cooperate with the govern-ment during construction operations to minimize conflicts and facilitate govern-ment usage.
1.6 COORDINATION OF INSPECTION
A. The contractor shall contact the COTR prior to the start of any work.
1.7 CONTRACTOR PARKING AND STORAGE OF MATERIAL
A. The contractor will not be permitted to park adjacent to the work site but parking will be assigned near the work site. The contractor will be assigned an area near the work site for storage but not adjacent to the building. Construction Officer shall issue Contractor Parking Passes.
1.8 SITE MAINTENANCE
A. The contractor shall perform daily cleanup of work site, dumpster and storage area. All dumpsters shall have watertight covers.
PART 2 – PRODUCTS (Not applicable.)
PART 3 − EXECUTION (Not applicable.)
END OF SECTION 01010
SUMMARY 01010 - 3/3
SECTION 01040 - PROJECT COORDINATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings, terms and conditions of this contract, including the general requirements and other division specification sections, apply to this section.
1.2 SUMMARY
A. This section specifies administrative and supervisory requirements necessary for project coordination including but not necessarily limited to:
1. Coordination
2. Administrative and supervisory personnel
3. General installation provisions
4. Cleaning and protection
1.3 CONTRACTOR’S CONSTRUCTION SCHEDULE
A. Software: The contractor shall use Microsoft Project to prepare the construction schedule. The construction schedule shall be submitted within 15 days of NTP.
B. Construction Schedule Chart: Prepare a horizontal time-scaled Gantt chart progress schedule with the total project divided and subdivided into sufficient number of work activities to accurately graphically display the work schedule, sequence in which the work is to be accomplished, activity duration, and interdependence of activities. A bar shall depict the start, finish, and duration of each activity. The bar shall be shaded to indicate progress. In addition to construction activities, procurement times for critical items including submittal turn-around, shall be shown on the schedule. The diagram shall clearly show the activities of the critical path.
1.4 COORDINATION
A. Coordination: Coordinate construction activities included under various sections of these specifications to assure efficient and orderly installation of each part of the work. Coordinate construction operations included under different sections of the specifications that are dependent upon each other for proper installation, connection, and operation.
1. Where installation of one part of the work is dependent on installation of other components, either before or after its own installation, schedule construction activities in the sequence required to obtain the best results.
2. Where availability of space is limited, coordinate installation of different components to assure maximum accessibility for required maintenance, service and repair.
PROJECT COORDINATION 01040 - 1/4
3. Make adequate provisions to accommodate items scheduled for later installation.
B. Where necessary, prepare memoranda for distribution to each party involved outlining special procedures required for coordination. Include such items as required notices, reports, and attendance at meetings.
1. Prepare similar memoranda for the government and separate contractors where coordination of their work is required.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and ensure orderly progress of the work. Such administrative activities include, but are not limited to, the following
1. Preparation of schedules
2. Delivery and processing of submittals
3. Progress meetings
4. Progress close-out activities
D. Supervisory Personnel: Contractor shall be required to have a full-time superintendent on site while contractor personnel or sub-contract personnel conduct work, or to receive material deliveries.
E. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials.
1. Refer to other sections for disposition of salvaged materials that are designated as government's property.
1.5 SUBMITTALS
A. Staff Names: Within 5 working days of Notice to Proceed, submit a list of the contractor's principal staff assignments, including the superintendent and other key personnel in attendance at the site; identify individuals, their duties and responsibilities; and telephone numbers.
B. All submittals referenced in section section 01300 shall be provided within 15 calendar days of issuance of NTP.
PART 2 – PRODUCTS (Not applicable.)
PART 3 – EXECUTION
3.1 GENERAL INSTALLATION PROVISIONS
A. Inspection of Conditions: Require the installer of each major component to inspect both the substrate and conditions under which work is to be performed.
PROJECT COORDINATION 01040 - 2/4
Do not proceed until unsatisfactory conditions have been corrected in an acceptable manner.
B. Manufacturer's Instructions: Comply with manufacturer's installation instructions and recommendations, to the extent that those instructions and recommendations are more explicit or stringent than requirements contained in contract documents.
C. Inspect materials or equipment immediately upon delivery and again prior to installation. Reject damaged and defective items.
D. Provide attachment and connection devices and methods necessary for securing work. Secure work true to line and level. Allow for expansion and building movement.
E. Visual Effects: Provide uniform joint widths in exposed work. Arrange joints in exposed work to obtain the best visual effect. Refer questionable choices to the Contracting Officer for final decision.
F. Recheck measurements and dimensions, before starting each installation.
G. Install each component during weather conditions and project status that shall ensure the best possible results. Isolate each part of the completed construction from incompatible material as necessary to prevent deterioration.
H. Coordinate temporary enclosures with required inspections and tests to minimize the necessity of uncovering completed construction for that purpose.
I. Mounting Heights: Where mounting heights are not indicated install individual components at standard mounting heights recognized within the industry for the particular application indicated. Refer questionable mounting height decisions to the Contracting Officer for final decision.
3.2 CLEANING AND PROTECTION
A. During handling and installation, clean and protect construction in progress and adjoining materials in place. Apply protective covering where required to ensure protection from damage or deterioration at substantial completion.
B. Clean and maintain completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.
C. Limiting Exposures: Supervise construction activities to ensure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.
Where applicable, such exposures include, but are not limited to, the following:
1. Excessive static or dynamic loading
2. Excessively high or low temperatures
PROJECT COORDINATION 01040 - 3/4
3. Thermal shock
4. Excessively high or low humidity
5. Air contamination or pollution
6. Water or ice
7. Light
8. Puncture
9. Abrasion
10. Heavy traffic
11. Soiling, staining and corrosion
12. Electrical current
13. Improper lubrication
14. Unusual wear or other misuse
15. Contact between incompatible materials
16. Misalignment
17. Excessive weathering
18. Unprotected storage
19. Improper shipping or handling
20. Theft
21. Vandalism
END OF SECTION 01040
PROJECT COORDINATION 01040 - 4/4
U.S. Coast Guard Academy Project #2512898
SECTION 01120 - SPECIAL CONDITIONS (OSHA & ENVIRONMENTAL PROTECTION)
PART 1 - GENERAL
1.1 SUMMARY
A. The contractor is responsible for complying with all federal, state, and local environmental laws and requirements in the execution of this contract.
B. The contractor shall use the Contractor's Waste Management Guide to assist in the management of all regulated waste (hazardous waste and Connecticut regulated waste) generated at the Academy. This guide will be furnished at the preconstruction meeting.
1.2 HAZARDOUS WASTE OPERATIONS
A. Contractors whose employees are exposed to hazardous waste, respond to emergencies involving hazardous materials, or participate in any cleanup or investigation of a government identified uncontrolled waste site, must follow all the requirements of 29 CFR 1910.120 which includes Site Safety and Health Plans, Emergency Contingency Plans and proper employee training. The contractor, if required by 29 CFR 1910.120, shall submit to the government prior to the preconstruction meeting, the Site Safety and Health Plans, Emergency Contingency Plans and proof of adequate worker training.
1.3 HAZARDOUS MATERIALS
A. The contractor shall submit to the Chief, Construction and Engineering a copy of the contractor's OSHA-approved hazardous communication program as required by 29 CFR 1910.1200. This copy of the contractor's program shall be submitted one week prior to the preconstruction meeting.
B. The contractor shall submit to the Chief, Construction and Engineering a copy of all Material Safety Data Sheets (MSDS) for each chemical or hazardous material to be used in the execution of this contract. The MSDS shall be submitted one week prior to the preconstruction meeting. The government shall provide the contractor a copy of MSDS for Academy hazardous materials that the contractor may be exposed to during the course of the project.
C. The government, upon review of the contractor's MSDS, has the right to deny the contractor the use of chemicals or products which, in the government's judgment, pose an undue health risk, cause the generation or potential generation of hazardous waste, or result in the generation of other regulated wastes including wastewaters and air emissions.
D. The contractor shall have proper secondary containment for storage of all liquid hazardous materials at the work site. This secondary containment shall be
SPECIAL CONDITIONS (OSHA & ENVIROMENTAL PROTECTION) 01120 - 1/5
capable of containing 10% of the volume of all containers or 100% of the volume of the largest container whichever volume is the greater.
1.4 WASTE GENERATION
A. The contractor shall be responsible for the proper management and collection of all wastes generated. No wastes generated by the contractor shall be placed in any waste collection device located at the Academy.
B. The contractor shall provide waste collection containers for all wastes generated that include unregulated trash, regulated wastes (e.g., construction debris, unusable excavated materials, recyclable used oil), hazardous wastes, and wastewaters that cannot be discharged. The COTR shall designate to the contractor the sites for waste storage.
C. All regulated waste generated by the contractor shall be managed in accordance with all Connecticut Department of Environmental Protection (CTDEP) requirements (RSCA Title 22A, Environmental Protection). The contractor is responsible for properly collecting, managing and paying for the disposal of all regulated waste. The contractor shall submit to the government copies of all weight tickets from the disposal of regulated waste. All regulated waste shall be disposed of in permitted landfills, recycling, or treatment facilities. Procedures for the management of regulated waste will be reviewed at the preconstruction meeting.
D. All hazardous waste or potentially hazardous waste generated by the contractor shall be managed in accordance with all Resource Conservation and Recovery Act (RCRA 40 CFR 260 - 266, 268 and 270), and CTDEP requirements (RSCA 22a-449(c)-100 through 110 and 22a-449(c)-11). The contractor shall be responsible for the proper collection and management of all hazardous waste.
The contractor shall provide DOT approved shippable containers compatible for storing and for disposal of the collected contaminated material. The government will pay the cost for disposal of all hazardous waste. The contractor shall turn over custody of all hazardous waste to the government. The government reserves the option of either transferring hazardous waste to the Less-Than-90-Day- Accumulation Building at the Academy, or providing the services of a licensed hazardous waste transporter to pick-up the waste at the construction site for transport to a permitted Treatment, Storage, or Disposal Facility (TSDF). All hazardous waste will be manifested using the Academy's EPA hazardous waste generator identification number. Only the government shall sign all hazardous waste manifests and manifests for asbestos material. Procedures for the proper management of hazardous waste will be given to the contractor by the government at the preconstruction meeting.
E. The contractor shall not discharge wastewater to any sewer, sanitary or storm, without a permit or permission from the government. The contractor shall not discharge any wastewater to any building floor, grass area, sidewalk, or street
SPECIAL CONDITIONS (OSHA & ENVIROMENTAL PROTECTION) 01120 - 2/5
without the permission of the government. Regulated wastewater (hazardous or Connecticut-regulated waste) that is collected shall be managed according to the requirements of this section.
1.5 SPILLS AND RELEASES
A. The contractor shall be responsible for, and shall pay all costs for the cleanup and the disposal of wastes from any spills or releases of any hazardous materials (including all wastes) to the environment. All non-incidental spills and releases shall be reported immediately to the Academy's Fire and Emergency at extension 8555 (444-8555, if using a portable phone). Refer to the Contractor's Waste Management Guide for spill notification procedures.
B. If the contractor is performing a spill cleanup, the contractor shall perform the cleanup in a manner that complies with applicable federal, state, and local laws and requirements.
1.6 ABATEMENT OF AIR POLLUTION
A. The contractor shall comply with all federal, state, and local air pollution regulations, which include all CTDEP requirements of RSCA 22a-174.
B. The contractor shall not release any chlorofluorocarbons (CFCs) to the environment when executing this contract.
1.7 ABATEMENT OF MATERIALS CONTAINING ASBESTOS
A. GLOVE BAG OPERATIONS - The “Glove Bag” method provides a safe means for removal of small amounts of ACM on pipes and in small surface areas. The following procedures should be followed when the glove bag method is used to remove ACM.
1. Utilize personal protective clothing, such as the “Tyvek” suits, gloves and a respirator that has been provided and fitted by EH&S.
2. Isolate the area where the ACM is located. Place barrier tape across the doorways and at least 20 feet around the area where the ACM is located.
3. Place 6-mil plastic sheeting under the glove bag set-up.
4. Ensure that all ventilation units that service the area where the ACM is located are shut off and tagged out.
5. Don the respirator and perform a “negative” and “positive” pressure test. If you are unable to obtain a successful pressure test on the respirator, SPECIAL CONDITIONS (OSHA & ENVIROMENTAL PROTECTION) 01120 - 3/5 see your supervisor. DO NOT PROCEED WITH ACM WORK
WITHOUT A PROPER RESPIRATOR FIT.
6. Determine the area where the ACM is to be removed. Place the glove bag next to the pipe and measure how much area will need to be removed.
Tape the area on the pipe to delineate the area from which ACM will be removed. Tape the bottom seam of the glove bag. Slit the side seams of the glove bag to fit the pipe diameter. Seal the sides and top seam with tape after placing the necessary tools into the bag. Cut a small hole in the bag in the same area where the wetting wand will be placed during the actual ACM removal stage. Fill the bag with smoke from the smoke tube and seal the hole. Gently squeeze the bag and observe any leaking areas.
Tape the leaking areas to achieve an airtight seal. If the pipe lagging is badly damaged or deteriorated the ACM may require wetting or taping to prevent a further release of fibers.
7. Most glove bags will melt or deteriorate at temperatures of 130o F or more. For steam or hot water lines, therefore, it may be necessary to shut off the pipe valve to ensure that the bag does not deteriorate or that the worker does not receive burns.
8. Wet the ACM completely prior to removal and keep the ACM wet during the removal process. Use amended water in an airless spray pump.
A hand spray bottle may also be used. The hole created for the spray wand can also be used for the HEPA vacuum nozzle.
9. All visible ACM must be removed from the pipe using a hard brush and amended water while the glove bag is still in place. Wet wipe and spray the pipe with encapsulant prior to removing the glove bag. Special attention must be given to exposed ends of pipe lagging.
10. Place all tools into one of the armholes and pull inside out. Tape and cut the arm from the glove bag and remove the tools while they are still sealed in the arm or glove.
11. Wet the inside of the bag with amended water and place the vacuum nozzle into the bag to cause the bag to collapse. Unseal the bag and remove from the pipe. Place the bag into another 6-mil asbestos waste bag and seal tightly. This bag must be marked as an ASBESTOS DISPOSAL BAG with the proper Danger and warning labels:
SPECIAL CONDITIONS (OSHA & ENVIROMENTAL PROTECTION) 01120 - 4/5
DANGER
Contains Asbestos Fibers
Avoid Creating Dust Cancer and Lung Disease Hazard
12. The exposed section of pipe will now be closed and sealed with a non-asbestos material.
13. If the remaining pipe contains ACM, the pipe must be labeled
“DANGER ASBESTOS MATERIAL.”
1.8 BACK FLOW PREVENTORS
A. The contractor shall install back flow preventors on any connection made to public water utilities.
1.9 SARA TITLE III
A. The contractor shall report the usage of any SARA (Superfund Amendment Reauthorization Act) Title III Extremely Hazardous Substances (EHSs) (list found in Appendix A of 40 CFR 355) to the COTR at or before the preconstruction meeting.
2.0 USE OF PRIMERS AND PAINTS
A. The contractor shall not use any primers or paint that contain lead, chromium, cadmium, and barium without the written consent of the Environmental Officer.
END OF SECTION 01120
SPECIAL CONDITIONS (OSHA & ENVIROMENTAL PROTECTION) 01120 - 5/5
US Coast Guard Academy Project #2512898
SECTION 01250 - CONTRACT MODIFICATION PROCEDURES
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the contract, including general and supplementary conditions and other Division 1 specification sections, apply to this section.
1.2 SUMMARY
A. This section specifies administrative and procedural requirements for handling and processing contract modifications.
B. Related sections include the following:
1. Division 1 section "Product Requirements" for administrative procedures for handling requests for substitutions made after contract award.
1.3 MINOR CHANGES IN THE WORK
A. Facilities Engineering will issue through construction foreman supplemental instructions authorizing minor changes in the work, not involving adjustment to the contract sum or the contract time.
1.4 PROPOSAL REQUESTS
A. Government-initiated Proposal Requests: Contracting Officer will issue a detailed description of proposed changes in the work that may require adjustment to the contract sum or the contract time. If necessary, the description will include supplemental or revised drawings and specifications.
1. Proposal requests issued by government are for information only. Do not consider them instructions either to stop work in progress or to execute the proposed change.
2. Within 5 working days after receipt of proposal request, submit a quotation estimating cost adjustments to the contract sum and the contract time necessary to execute the change.
CONTRACT MODIFICATION PROCEDURES 01250 - 1/3
a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include an updated contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float time before requesting an extension of the contract time.
B. Contractor-initiated Proposals: If latent or unforeseen conditions require modifications to the contract, contractor may propose changes by submitting a request for change to the Contracting Officer.
1. Include a statement outlining reasons for the change and the effect of the change on the work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the contract sum and the contract time.
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include an updated contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float time before requesting an extension of the contract time.
5. Comply with requirements in Division 1 section "Product Requirements" if the proposed change requires substitution of one product or system for product or system specified.
C. Proposal Request Form: For change order proposals, use contractors standard form.
Contractor to provide sample of their standard form.
1.5 CHANGE ORDER PROCEDURES
A. On government’s approval of a proposal request, Contracting Officer will issue a change order for signatures of Contracting Officer and contractor.
1.6 CONSTRUCTION CHANGE DIRECTIVE
A. Work Change Directive: Contracting Officer may issue a work change directive. Work change directive instructs contractor to proceed with a change in the work, for subsequent inclusion in a change order.
CONTRACT MODIFICATION PROCEDURES 01250 - 2/3
1. Work change directive contains a complete description of change in the work. It also designates method to be followed to determine change in the contract sum or the contract time.
B. Documentation: Maintain detailed records on a time and material basis of work required by the work change directive.
1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the contract.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01250
CONTRACT MODIFICATION PROCEDURES 01250 - 3/3
SECTION 01290 - PAYMENT PROCEDURES
1.1 SUMMARY
A. This section specifies administrative and procedural requirements necessary to prepare and process applications for payment.
1.2 SCHEDULE OF VALUES
A. Coordination: Coordinate preparation of the schedule of values with preparation of contractor's construction schedule.
1. Correlate line items in the schedule of values with other required administrative forms and schedules, including submittals schedule and application for payment forms with continuation sheets.
2. Submit the schedule of values to Contracting Office at earliest possible date but no later than 30 days before the date scheduled for submittal of initial applications for payment.
3. Sub-schedules: Where the work is separated into phases requiring separately phased payments, provide sub-schedules showing values correlated with each phase of payment.
B. Format and Content: Use the specifications table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each specification section.
1. Identification: Include the following project identification on the schedule of values:
a. Project name and location
b. Project number
c. Contractor's name and address
d. Date of submittal
2. Arrange the schedule of values in tabular form with separate columns to indicate the following for each item listed:
a. Related specification section or division
b. Description of the work
c. Name of subcontractor
d. Name of manufacturer or fabricator
e. Name of supplier
PAYMENT PROCEDURES 01290 - 1/4
f. Change orders (numbers) that affect value
g. Dollar value
3. Provide a breakdown of the contract sum in enough detail to facilitate continued evaluation of applications for payment and progress reports. Coordinate with the specifications table of contents. Provide several line items for principal subcontract amounts, where appropriate.
4. Round amounts to nearest whole dollar; total shall equal the contract sum.
5. Provide a separate line item in the schedule of values for each part of the work where applications for payment may include materials or equipment purchased or fabricated and stored, but not yet installed.
6. Provide separate line items in the schedule of values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the work.
7. Allowances: Provide a separate line item in the schedule of values for each allowance. Show line-item value of unit-cost allowances, as a product of the unit cost, multiplied by measured quantity. Use information indicated in the contract documents to determine quantities.
8. Each item in the schedule of values and applications for payment shall be complete. Include total cost and proportionate share of general overhead and profit for each item.
a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the schedule of values or distributed as general overhead expense, at contractor's option.
9. Schedule Updating: Update and resubmit the schedule of values before the next applications for payment when change orders or construction change directives result in a change in the contract sum.
1.3 APPLICATIONS FOR PAYMENT
A. Each application for payment shall be consistent with previous applications and payments as certified by COTR and paid for by government.
1. Initial application for payment, application for payment at time of substantial completion, and final application for payment involve additional requirements.
B. Payment Application Times: The date for each progress payment is indicated in the agreement between government and contractor. The period of construction work covered by each application for payment is the period indicated in the agreement.
PAYMENT PROCEDURES 01290 - 2/4
C. Payment Application Forms: Use forms provided by Contracting Office.
D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of contractor. Contracting Office will return incomplete applications without action.
1. Entries shall match data on the schedule of values and contractor's construction schedule. Use updated schedules if revisions were made.
2. Include amounts of change orders and construction change directives issued before last day of construction period covered by application.
E. Waivers of Mechanic's Lien: With each application for payment, submit waivers of mechanic's lien from every entity who is lawfully entitled to file a mechanic's lien arising out of the contract and related to the work covered by the payment.
1. Submit partial waivers on each item for amount requested, before deduction for retainage, on each item.
2. When an application shows completion of an item, submit final or full waivers.
3. Government reserves the right to designate which entities involved in the work must submit waivers.
4. Waiver Delays: Submit each application for payment with contractor's waiver of mechanic's lien for construction period covered by the application.
a. Submit final application for payment with or preceded by final waivers from every entity involved with performance of the work covered by the application who is lawfully entitled to a lien.
F. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first application for payment include the following:
1. List of subcontractors.
2. Schedule of values.
3. Contractor's construction schedule (preliminary if not final).
4. Submittals schedule (preliminary if not final).
5. List of contractor's staff assignments.
6. Copies of building permits.
7. Copies of authorizations and licenses from authorities having jurisdiction for performance of the work.
8. Certificates of insurance and insurance policies.
9. Performance and payment bonds.
PAYMENT PROCEDURES 01290 - 3/4
G. Application for Payment at Substantial Completion: After issuing the Certificate of Substantial Completion, submit an application for payment showing 100 percent completion for portion of the work claimed as substantially complete.
1. Include documentation supporting claim that the work is substantially complete and a statement showing an accounting of changes to the contract sum.
2. This application shall reflect Certificates of Partial Substantial Completion issued previously for government occupancy of designated portions of the work.
H. Final Payment Application: Submit final application for payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:
1. Evidence of completion of project closeout requirements.
2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.
3. Updated final statement, accounting for final changes to the contract sum.
4. Evidence that claims have been settled.
5. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of substantial completion or when government took possession of and assumed responsibility for corresponding elements of the work.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01290
PAYMENT PROCEDURES 01290 - 4/4
SECTION 01300 − SUBMITTALS
PART 1 − GENERAL
1.1 DESCRIPTION
A. Wherever possible throughout the contract documents the minimum acceptable quality of workmanship and materials has been defined either by manufacturers name and catalog number with the salient characteristics or by reference to recognized industry standards.
B. To ensure that the specified products are furnished and installed in accordance with design intent, procedures have been established for advance submittal of design data and for its review and approval or rejection by the Chief, Construction and Engineering. Submittals shall be submitted using government furnished Contract Item Approval Request forms.
1.2 PRODUCT HANDLING
A. Make all submittals of shop drawings, samples, request for substitutions and other items, in strict accordance with the provisions of this section of these specifications.
1.3 SHOP DRAWINGS
A. Make all shop drawings accurately to a scale sufficiently large to show all pertinent features of the item and its method of connection to the work.
1.4 PRODUCT DATA
A. Modify manufacturer's standard schematic drawings as necessary to provide additional information applicable to project.
B. Manufacturers catalog sheets, brochures, diagrams, schedules, performance charts, illustrations and other standard descriptive data shall be clearly marked to identify pertinent materials, products, or models.
1.5 SAMPLES
A. Samples shall be of sufficient size and quantity to illustrate the functional characteristics of products or material, and a full range of color choices.
1.6 CERTIFICATE OF COMPLIANCE
A. Certificates of compliance for a material or product to be incorporated in the work shall be notarized, originate from the manufacturer, and shall include:
1. Reference to the project for which the material or product is intended
SUBMITTALS 01300 - 1/4
2. Where in the work the material or product is to be used
3. Reference to the paragraph with which the material or product complies
1.7 COLORS
A. Unless the precise color and pattern is specifically described in the contract documents, whenever a choice of color or pattern is available in a specified product, submit accurate color charts and pattern charts to the Chief, Construction and Engineering for his review and selection.
1.8 CONTRACTOR'S RESPONSIBILITIES
A. Review shop drawings, product data and samples prior to submission.
B. Verify field measurements, field construction criteria, catalog numbers and similar data.
C. Coordinate each submittal with requirements of work and/or contract documents.
D. Contractor's responsibility for errors and omissions in submittals is not relieved by Chief, Construction and Engineering review of submittals.
E. Contractors responsibility for deviations in submittals from requirements of contract is not relieved by review of submittals unless Chief, Construction and Engineering gives written acceptance of specific deviation.
F. Begin no work that requires submittals until return of submittals with Chief, Construction and Engineering approval and initials or signature indicating review.
1.9 SUBMISSION REQUIREMENTS
A. Submit sufficient copies of shop drawings and product data which contractor requires for distribution plus four copies which will be retained by Chief, Construction and Engineering.
B. Submit number of samples listed in each of the specification sections, or as specified herein.
C. Accompany submittals with letter, in duplicate, containing date, project title and number, contractor's name and address, the number of each submittal, and notification of deviations from contract documents.
D. The submittals shall include data and revision dates, project title and number, the names of the Contracting Officer, contractor, supplier, and manufacturer, product identification to adjacent structure or materials, field dimensions, specification section number, applicable standards, identification of deviations from contract documents, and contractor’s submittal, verification of field measurements and compliance with contract documents.
SUBMITTALS 01300 - 2/4
1.10 SUBMITTALS
A. Submittals are required for the following items: (refer to individual sections for specific submittal requirements. List is for reference only, not all submittal requirements are listed.)
SECTION ITEM
Schedule of Values
01040 Construction Schedule
01040 Staff Names
01120 Contractor's Hazardous Communication Plan
01120 Material Safety Data Sheets (MSDSs)
01700 Project Record Documents
01700 Operating and Maintenance Manuals
01770 Warranties
02220 Certificates, Demolition Plan
16050 Product Data, Shop Drawings
16060 Product Data, Field-Quality Test Reports
16080 Test Reports, Certificates
16120 Field Quality-Test Reports
16124 Shop Drawings, Producr Data, Test Reports, Certificates, Manufacturer Instructions & Field Reports
16302 Shop Drawings, Producr Data, Test Reports, Certificates, Manufacturer Instructions & Field Reports
1.11 RESUBMISSION REQUIREMENTS
A. Revise initial drawings as required and resubmit as specified for initial submittal.
B. Indicate on drawings any changes that have been made.
SUBMITTALS 01300 - 3/4
1.12 SUBMITTAL SCHEDULE
A. All submittals shall be provided to Chief, Construction and Engineering within 15 calendar days of NTP. For scheduling purposes, the contractor shall assume the government review time of submittals to average three weeks.
END OF SECTION 01300
SUBMITTALS 01300 - 4/4
SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION
1.1 SUMMARY
A. This section includes administrative and procedural requirements for documenting the progress of construction during performance of the work, including the following:
1. Contractor's construction schedule
2. Submittals schedule
3. Daily construction reports
4. Field condition reports
5. Construction photographs
B. See Division 1 section "Payment Procedures" for submitting the schedule of values.
1.2 DEFINITIONS
A. Critical Path: The longest continuous chain of activities through the network schedule that establishes the minimum overall project duration and contains no float.
B. Float: The measure of leeway in starting and completing an activity.
1. Float time is not for the exclusive use or benefit of either government or contractor, but is a jointly owned, expiring project resource available to both parties as needed to meet schedule milestones and contract completion date.
C. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.
D. Major Area: A story of construction, a separate building, or a similar significant construction element.
1.3 SUBMITTALS
A. Contractor's Construction Schedule: Submit four printed copies of initial schedule, one a reproducible print and one a blue- or black-line print, large enough to show entire schedule for entire construction period.
1. Activity Report: List of all activities sorted by activity number and then early start date, or actual start date if known.
CONSTRUCTION PROGRESS DOCUMENTATION 01320 - 1/4
2. Logic Report: List of preceding and succeeding activities for all activities, sorted in ascending order by activity number and then early start date, or actual start date if known.
3. Total Float Report: List of all activities sorted in ascending order of total float.
B. Daily Construction Reports: Submit two copies at weekly intervals.
C. Field Condition Reports: Submit two copies at time of discovery of differing conditions.
1.4 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.
B. Coordinate contractor's construction schedule with the schedule of values, list of subcontracts, submittals schedule, progress reports, payment requests, and other required schedules and reports.
1. Secure time commitments for performing critical elements of the work from parties involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
PART 2 - PRODUCTS
2.1 SUBMITTALS SCHEDULE
A. Preparation: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, re-submittal, ordering, manufacturing, fabrication, and delivery when establishing dates.
1. Coordinate submittals schedule with list of subcontracts, the schedule of values, and contractor's construction schedule.
2. Submit concurrently with the first complete submittal of contractor's construction schedule.
2.2 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Time Frame: Extend schedule from date established for the Notice to Proceed to date of final completion.
1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by change order.
CONSTRUCTION PROGRESS DOCUMENTATION 01320 - 2/4
2. Submittal Review Time: Include review and re-submittal times indicated in Division 1 section "Submittal Procedures" in schedule. Coordinate submittal review times in contractor's construction schedule with submittals schedule.
3. Startup and Testing Time: Include not less than ten days for startup and testing.
4. Substantial Completion: Indicate completion in advance of date established for substantial completion, and allow time for contracting office’s administrative procedures necessary for certification of substantial completion.
B. Constraints: Include constraints and work restrictions indicated in the contract documents and as follows in schedule, and show how the sequence of the work is affected.
1. Phasing: Arrange list of activities on schedule by phase.
2. Work by Government: Include a separate activity for each portion of the work performed by government.
3. Work Restrictions: Show the effect on the schedule of the following:
a. Coordination with existing construction
b. Limitations of continued occupancies
c. Uninterruptible services
d. Use of premises restrictions
e. Provisions for future construction
f. Seasonal variations
g. Environmental control
4. Work Stages: Indicate important stages of construction for each major portion of the work.
C. Milestones: Include milestones indicated in the contract documents in schedule, including, but not limited to, NTP, substantial completion, and final completion.
D. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using fragnets to demonstrate the effect of the proposed change on the overall project schedule.
2.3 CONTRACTOR'S CONSTRUCTION SCHEDULE
A. Software: The contractor shall use Microsoft Project to prepare the construction schedule. The construction schedule shall be submitted within 15 days of NTP.
B. Construction Schedule Chart: Prepare a horizontal time-scaled Gantt chart progress schedule with the total project divided and subdivided into sufficient number of work activities to accurately graphically display the work schedule, sequence in which the work is to be accomplished, activity duration, and interdependence of each activity.
The bar shall be shaded to indicate progress. In addition to construction activities, CONSTRUCTION PROGRESS DOCUMENTATION 01320 - 3/4 procurement times for critical items including submittal turn-around, shall be shown on the schedule. The diagram shall clearly show the activities of the critical path.
2.4 REPORTS
A. Daily Construction Reports: Prepare a daily construction report recording events at project site, including the following:
1. List of subcontractors
2. High and low temperatures and general weather conditions
3. Accidents
4. Stoppages, delays, shortages, and losses
5. Meter readings and similar recordings
6. Orders and requests of authorities having jurisdiction
7. Services connected and disconnected
8. Equipment or system tests and startups
B. Field Condition Reports: Immediately on discovery of a difference between field conditions and the contract documents, prepare a detailed report. Submit with a request for information. Include a detailed description of the differing conditions, together with recommendations for changing the contract documents.
PART 3 - EXECUTION
END OF SECTION 01320
CONSTRUCTION PROGRESS DOCUMENTATION 01320 - 4/4
SECTION 01600 - PRODUCT REQUIREMENTS
1.1 SUMMARY
A. This section includes administrative and procedural requirements for selecting products for use in project; product delivery, storage, and handling; manufacturers' standard warranties on products; special warranties; product substitutions; and comparable products.
B. See Division 1 section "Closeout Procedures" for submitting warranties for contract closeout.
C. See Divisions 16 sections for specific requirements for warranties on products and installations specified to be warranted.
1.2 DEFINITIONS
A. Products: Items purchased for incorporating into the work, whether purchased for project or taken from previously purchased stock. The term "product" includes the terms "material," "equipment," "system," and terms of similar intent.
1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation, shown or listed in manufacturer's published product literature that is current as of date of the contract documents.
2. New Products: Items that have not previously been incorporated into another project or facility. Products salvaged or recycled from other projects are not considered new products.
3. Comparable Product: Product that is demonstrated and approved through submittal process, or where indicated as a product substitution, to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.
B. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the contract documents and proposed by contractor.
C. Basis-of-Design Product Specification: Where a specific manufacturer's product is named and accompanied by the words "basis of design," including make or model number or other designation, to establish the significant qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics for purposes of evaluating comparable products of other named manufacturers.
PRODUCT REQUIREMENTS 01600 - 1/5
D. Manufacturer's Warranty: Preprinted written warranty published by individual manufacturer for a particular product and specifically endorsed by manufacturer to government.
E. Special Warranty: Written warranty required by or incorporated into the…