Specification
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AbstractEatonsNeckDredgeJan09.doc | DOC document | |
| AmendOneDredgingEatonsNeck2009.doc | DOC document | |
| EatonsNeckCOEpermitFY2009.pdf | ||
| WageRateEatonsNeckDredgingFY09.doc | DOC document | |
| EatonsNeckDredgeDrawingsFY09.pdf | ||
| BidBond.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DREDGING AT CG EATON’S NECK, PROJECT 409548
Table of Contents
DIVISION 01 GENERAL REQUIRMENTS
01 11 00 Summary of Work
01 14 00 Work Restrictions
01 32 00 Construction Schedule
01 33 00 Submittal Procedures
01 57 19 Temporary Environmental Controls
01 77 00 Closeout Procedures
DIVISION 35 WATERWAY AND MARINE CONSTRUCTION
35 20 23 Dredging
Appendix A
New York DEC permit 1-4726-00545/00002 w/drawing P005084
End of Table of Contents
DREDGING AT CG STA EATON’S NECK, PROJECT 409548
SECTION 01110 Page 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The work includes dredging by mechanical means, sand, gravel, and cobbles, from a channel connecting a mooring basin to Huntington Harbor and placing the material along a nearby shoreline and incidental related work.
1.1.2 Location
The work is located at Coast Guard Station Eaton’s Neck, Northport, NY, approximately as indicated.
1.1.3 Drawings
The work is shown on reference drawing number P005084, included in Appendix A with the state permit.
1.2 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.3 SUPERVISION
Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours.
1.4 PRECONSTRUCTION CONFERENCE
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule prices, shop drawings, and other submittals, scheduling programming, and prosecution of the work. Major subcontractors who will engage in the work shall also attend.
DREDGING AT CG STA EATON’S NECK, PROJECT 409548
SECTION 01110 Page 2
1.5 INSPECTION
The Contractor shall keep the Contracting Officer or duly appointed representative fully informed of contract operations and plans so that a representative may arrange to be present at various times that work is being performed.
1.5.1 Contractor’s Daily Log
The Contractor shall be complete the USCG Daily Log form at the end of each working day and deliver it to the Government Inspector. The Government Inspector will attest to its accuracy by initialing the form and forwarding that form to CEU Providence. The form will be provided to the Contractor by the Contracting Officer’s Representative.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
--End of Section--
DREDGING AT CG STA EATON’S NECK PROJECT 409548
SECTION 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
1.1 SPECIAL SCHEDULING REQUIREMENTS AND WORK RESTRICTIONS
A. The work is subject to time of year restrictions specified in permits issued for the work, included in Appendix A. All work shall be performed within the time restrictions specified in the permits.
B. Have all equipment, personnel, and materials necessary to perform the work on site before beginning the work.
C. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential disruption to operations.
D. Conduct dredging operations so that navigation through the channel is maintained at all times. Relocate and secure dredging equipment at the end of each work day away from the channel and areas of the mooring basin in use.
E. Dredging equipment is prohibited from operating on the adjacent spit of land located north of the channel.
F. Except when the Coast Guard shoreline is designated as the disposal site, obtain permission from the owner(s) of the shoreline area designated to receive the dredged materials if the contractor’s disposal method requires access to the shoreline over private property. It is the contractor’s responsibility to coordinate directly and reach agreement with the private property owners.
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification.
1.2.2 Working Hours
Regular working hours shall consist of an 8 1/2 hour period established by the Contractor Officer Monday through Friday, excluding Government holidays.
1.2.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements
SECTION 01 14 00 Page 2 to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer.
1.3 SECURITY REQUIREMENTS
1.3.1 Areas Not Covered by Contract
The Contractor will not be permitted to enter buildings or areas not covered by the work included in this contract, except by prior approval of the Officer-in-Charge of the facility.
1.3.2 Parking
Parking is prohibited along the waterfront area.
1.3.3 Personnel and Equipment
Comply with security regulations for personnel and equipment established by the Officer-in-Charge of the facility.
Section 01 32 00 Page 1
SECTION 01 32 00
CONSTRUCTION SCHEDULE/SCHEDULE OF VALUES
1.1 SUBMITTALS
Submit the following in accordance with Section 01 33 00, "Submittal Procedures."
SD-01 Preconstruction Submittals
Construction Schedule/Schedule of Values
1.2 CONSTRUCTION SCHEDULE
At the Pre-Construction Conference, submit a Construction Schedule and Schedule of Values in accordance with FAR Clause 52.236.15. The Schedule of Values shall be based on the actual breakdown of the bid price. The cost of insurance shall not be listed as a separate item but included as part of each item of work. The actual cost of bonds may be paid as the first progress payment when a receipt from the bonding company is presented to the Contracting Officer. For contracts under $25,000, a Schedule of Values is not required.
Construction Schedule and Schedule of Values shall be incorporated into one form which clearly indicates the start and completion dates and unit value of all major work components. The sample form provided in this section may be used. Optional forms may be used provided they include at a minimum all information conveyed on the sample form.
Construction Schedule/Schedule of Values form shall incorporate at a minimum the following activities:
a. Bonds
b. Mobilization
c. Demobilization
d. Pre-Construction Submittals
e. Work Activities
f. In-Progress Submittals
g. Final Government Inspection
h. Close-Out Submittals
i. Pre/post dredging surveys and quantity calculations
j. Factors which Constitute Potential Interruptions to Station Operations
Section 01 32 00 Page 2
Pre-Construction Submittals are those activities which encompass the obtaining, submission, review and approval of submittals necessary prior to the start of the related site work. Contractor shall annotate all such activities into the progress schedule with their forecasted time periods.
These activity periods shall not be exclusive of the contract performance period. No site work shall commence until the respective submittals have been approved.
The value of all major work components within the project shall be identified on the Construction Schedule/Schedule of Values on a unit quantity and unit cost basis. Lump sum items shall only be paid for when 100% complete.
The Construction Schedule/Schedule of Values as approved by the Government is not a substitute for quantities conveyed by the specification and drawings and those required for a complete job. Omissions and errors on the Construction Schedule/Schedule of Values are the responsibility of the Contractor.
Payments will not be made until the schedule of prices has been submitted to and approved by the Contracting Officer.
1.3 UPDATED SCHEDULES
Update the construction schedule and equipment delivery schedule at monthly intervals or when schedule has been revised. Reflect any changes occurring since the last update. Submit copies of the purchase orders and confirmation of the delivery dates as directed.
3.1 PROGRESS UPDATES
3.1.1 General
A revised Construction Schedule/Schedule of Values shall be issued by the Contractor on a monthly basis. In addition, any revisions to the Construction Schedule/Schedule of Values such as modifications or delays shall be reflected by Contractor submission of an updated Construction Schedule/Schedule of Values.
3.1.2 Modifications
When a modification is issued by the Government, record the modification as the last activity of the Construction Schedule/Schedule of Values and include the value of the modification. Adjust the Schedule of Values to reflect the inclusion of the modification. Revise the Construction Schedule portion of the form to annotate the progress change. Enter all modifications in this manner in sequential order.
SECTION 01 33 00 Page 1
SECTION 01 33 00
SUBMITTAL PROCEDURES
1.1 DEFINITIONS
1.1.1 Submittal
Shop drawings, product data, samples, and administrative submittals presented for review and approval. Contract Clauses "FAR 52.236-5, Material and Workmanship," paragraph (b) and "FAR 52.236-21, Specifications and Drawings for Construction," paragraphs (d), (e), and (f) apply to all "submittals."
1.1.2 Types of Submittals
All submittals are classified as indicated in paragraph "Submittal Descriptions (SD)". Submittals also are grouped as follows:
a. Shop drawings: As used in this section, drawings, schedules, diagrams, and other data prepared specifically for this contract, by contractor or through contractor by way of subcontractor, manufacturer, supplier, distributor, or other lower tier contractor, to illustrate portion of work.
b. Product data: Preprinted material such as illustrations, standard schedules, performance charts, instructions, brochures, diagrams, manufacturer's descriptive literature, catalog data, and other data to illustrate portion of work, but not prepared exclusively for this contract.
c. Administrative submittals: Data presented for reviews and approval to ensure that administrative requirements of project are adequately met but not to ensure directly that work is in accordance with design concept and in compliance with contract documents.
1.1.3 Submittal Descriptions (SD)
Construction Progress Schedule Submittal register Schedule of values Environmental protection plan Pre-dredge survey and quantity calculations
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the contractor for integrating the product or system into the project.
SECTION 01 33 00 Page 2
Drawings prepared by or for the contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Post-dredge survey and quantity calculations
1.1.4 Approving Authority
Person authorized to approve submittal.
1.1.5 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce construction and materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.2 SUBMITTALS
Submit the following in accordance with the requirements of this section.
Submittal register
1.3 USE OF SUBMITTAL REGISTER
Prepare and maintain submittal register, as the work progresses. Do not change data in columns (c), (d), (e), and (f) as delivered by government.
1.3.1 Submittal Register
Submit submittal register. Do not change data in columns (c), (d), (e), and
(f) as delivered by the government. Verify that all submittals required for project are listed and add missing submittals. Complete the following on the register:
Column (a) Activity Number: Activity number from the project schedule.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.
Column (h) Contractor Approval Date: Date contractor needs approval of submittal.
Column (i) Contractor Material: Date that contractor needs material delivered to contractor control.
SECTION 01 33 00 Page 3
1.4 PROCEDURES FOR SUBMITTALS
1.4.1 Reviewing, Certifying, Approving Authority
Government organization shall be responsible for reviewing and certifying that submittals are in compliance with contract requirements. Approving authority on submittals is the Project Manager unless otherwise specified for specific submittal.
1.4.2 Constraints
a. Submittals listed or specified in this contract shall conform to provisions of this section, unless explicitly stated otherwise.
b. Submittals shall be complete for each definable feature of work;
components of definable feature interrelated as a system shall be submitted at same time.
c. When acceptability of a submittal is dependent on conditions, items, or materials included in separate subsequent submittals, submittal will be returned without review.
d. Approval of a separate material, product, or component does not imply approval of assembly in which item functions.
1.4.3 Scheduling
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential requirements to resubmit.
b. Except as specified otherwise, allow review period, beginning with receipt by approving authority, that includes at least 10 working days. Period of review for each resubmittal is the same as for initial submittal.
1.4.4 Variations
Variations from contract requirements require Government approval pursuant to contract Clause entitled "FAR 52.236-21, Specifications and Drawings for Construction" and will be considered where advantageous to government.
1.4.4.1 Considering Variations
Discussion with contracting officer prior to submission, will help ensure functional and quality requirements are met and minimize rejections and resubmittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal
(VECP).
1.4.4.2 Proposing Variations
When proposing variation, deliver written request to the contracting officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to government. If lower cost is a benefit, also include an estimate of the cost saving. In addition to
SECTION 01 33 00 Page 4 documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.
1.4.4.3 Warranting That Variation Are Compatible
When delivering a variation for approval, contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.4.4.4 Review Schedule Is Modified
In addition to normal submittal review period, a period of 5 working days will be allowed for consideration by the Government of submittals with variations.
1.4.5 Contractor's Responsibilities
a. Determine and verify field measurements, materials, field construction criteria; review each submittal; and check and coordinate each submittal with requirements of the work and contract documents.
b. Transmit submittals to Contracting Officer in accordance with schedule on approved Submittal Register, and to prevent delays in the work, delays to government, or delays to separate contractors.
c. Advise contracting officer of variation, as required by paragraph entitled "Variations."
d. Correct and resubmit submittal as directed by approving authority.
When resubmitting disapproved transmittals or transmittals noted for resubmittal, the contractor shall provide copy of that previously submitted transmittal including all reviewer comments for use by approving authority. Direct specific attention in writing or on resubmitted submittal, to revisions not requested by approving authority on previous submissions.
e. Furnish additional copies of submittal when requested by contracting officer, to a limit of 20 copies per submittal.
f. Complete work which must be accomplished as basis of a submittal in time to allow submittal to occur as scheduled.
g. Ensure no work has begun until submittals for that work have been returned as "approved," except to the extent that a portion of work must be accomplished as basis of submittal.
1.4.6 Government Responsibilities
a. Note date on which submittal was received from contractor on each Contract Item Approval Request Form.
b. Review each submittal; and check and coordinate each submittal with requirements of work and contract documents.
c. Review submittals for conformance with project design concepts and compliance with contract documents.
SECTION 01 33 00 Page 5
d. Ensure that material is clearly legible.
e. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
f. Identify returned submittals with one of the actions defined in paragraph entitled "Actions Possible" and with markings appropriate for action indicated.
1.4.7 Actions Possible
Submittals will be returned with one of the following notations:
a. Submittals marked "approved" "approved as submitted" authorize contractor to proceed with work covered.
b. Submittals marked "approved" "see below" authorize contractor to proceed with work as noted provided contractor takes no exception to the notations.
c. Submittals marked "disapproved" indicate submittal is incomplete or does not comply with design concept or requirements of the contract documents and shall be resubmitted with appropriate changes. No work shall proceed for this item until resubmittal is approved.
1.5 FORMAT OF SUBMITTALS
1.5.1 Transmittal Form
Transmit each submittal, except sample installations and sample panels, to office of approving authority. Transmit submittals with transmittal form prescribed by contracting officer and standard for project. The transmittal form shall identify contractor, indicate date of submittal, and include information prescribed by transmittal form and required in paragraph entitled "Identifying Submittals." Process transmittal forms to record actions regarding sample panels and sample installations.
1.5.2 Identifying Submittals
Identify submittals, except sample panel and sample installation, with the following information permanently adhered to or noted on each separate component of each submittal and noted on transmittal form. Mark each copy of each submittal identically, with the following:
a. Project title and location.
b. Construction contract number.
c. Section number of the specification section by which submittal is required.
d. Submittal description (SD) number of each component of submittal.
e. When a resubmission, alphabetic suffix on submittal description, for example, SD-10A, to indicate resubmission.
SECTION 01 33 00 Page 6
f. Name, address, and telephone number of subcontractor, supplier, manufacturer and any other second tier contractor associated with submittal.
g. Product identification and location in project.
1.5.3 Format for Shop Drawings
a. Shop drawings shall not be less than 8 1/2 by 11 inches nor more than 30 by 42 inches.
b. Present 8 1/2 by 11 inches sized shop drawings as part of the bound volume for submittals required by section. Present larger drawings in sets.
c. Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph entitled "Identifying Submittals."
d. Dimension drawings, except diagrams and schematic drawings; prepare drawings demonstrating interface with other trades to scale. Shop drawing dimensions shall be the same unit of measure as indicated on the contract drawings. Identify materials and products for work shown.
1.5.4 Format of Administrative Submittals
When submittal includes a document which is to be used in project or become part of project record, other than as a submittal, do not apply contractor's approval stamp to document, but to a separate sheet accompanying document.
1.6 QUANTITY OF SUBMITTALS
1.6.1 Number of Copies of Product Data
Submit four copies of submittals of product data.
1.6.2 Number of Copies of Shop Drawings
Submit shop drawings in compliance with quantity requirements specified for product data.
1.6.3 Number of Copies of Administrative Submittals
Unless otherwise specified, submit administrative submittals compliance with quantity requirements specified for product data.
SUBMITTAL REGISTER
Specification Section Number or Item Number
SD No., and Type of Submittal Material or Product
Specification Paragraph Number.
Planned Submittal Date
Date Fwd to Appr Auth /Date Recd From Contr
Date Fwd to Other Reviewer
Date Recd From Other Reviewer
Action Code
Date of Action
Mailed to Contr / Recd From Appr Auth
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j)
Section
01 32 00
SD-01, Preconstruction Submittals
1.1
1 Construction Schedule/Schedule of Values
1.1
Section
01 57 19
SD-01 Preconstruction Submittals
1.3
2 Environmental Protection Plan
1.3.
SD-11, Closeout Submittals
1.3
3 Preconstruction Survey 1.3
4 Solid Waste Disposal Permit
1.3.
5 Waste determination documentation
1.3
6 Disposal documentation for hazardous and regulated waste
1.3
7 Solid waste disposal report
1.3.
8 Contractor Hazardous Material Inventory Log
1.3
SUBMITTAL REGISTER
Section
01 77 00
SD-11, Closeout Submittals
1.1
9 Post-dredge survey and quantity calculations
1.1
35 20 23 SD-02 Shop Drawings 1.1
10 Pre-dredge survey, cross sections, and quantity calculations
1.2
11 Post-dredge survey, cross sections, and quantity calculations
1.2
Section 01 57 19 Page 1
SECTION 01 57 19
TEMPORARY ENVIRONMENTAL CONTROLS
1 GENERAL
The main intent of this section of the specifications is to address waste that may be generated by the contractor’s personnel, equipment, and work methods employed to perform the work.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910.1200 Hazard Communication
40 CFR 112 Oil Pollution Prevention
40 CFR 241 Guidelines for Disposal of Solid Waste
40 CFR 243 Guidelines for the Storage and Collection of
Residential, Commercial, and Institutional Solid Waste
40 CFR 258 Subtitle D Landfill Requirements
40 CFR 260 Hazardous Waste Management Systems: General
40 CFR 261 Identification and Listing of Hazardous Waste
40 CFR 262 Generators of Hazardous Waste
40 CFR 263 Transporters of Hazardous Waste
40 CFR 264 Owners and Operators of Hazardous Waste
Treatment, Storage, and Disposal Facilities
40 CFR 265 Interim Status Standard for Owners and
Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities
40 CFR 268 Land Disposal Restrictions
40 CFR 279 Used Oil Regulations
40 CFR 280 Owners and Operators of Underground Storage
Tanks
40 CFR 300 National Oil and Hazardous Substances
Pollution Contingency Plan
Section 01 57 19 Page 2
40 CFR 355 Emergency Planning and Notification
49 CFR 173 Shipments and Packagings
49 CFR 178 Packagings
1.2 DEFINITIONS
1.2.1 Sediment
Soil and other debris that have eroded and have been transported by runoff water or wind.
1.2.2 Solid Waste
Garbage, refuse, debris, sludge, or other discharged material (except hazardous waste as defined in paragraph entitled "Hazardous Waste" or hazardous debris as defined in paragraph entitled "Hazardous Debris"), including solid, liquid, semisolid, or contained gaseous materials resulting from domestic, industrial, commercial, mining, or agricultural operations.
Material not regulated as solid waste are: nuclear source or byproduct materials regulated under the Federal Atomic Energy Act of 1954 as amended;
suspended or dissolved materials in domestic sewage effluent or irrigation return flows, or other regulated point source discharges; regulated air emissions; and fluids or wastes associated with natural gas or crude oil exploration or production.
a. Green waste: The vegetative matter from landscaping, land clearing and grubbing, including, but not limited to, grass, bushes, scrubs, small trees and saplings, tree stumps and plant roots. Marketable trees, grasses and plants that are indicated to remain, be re-located, or be re-used are not included.
b. Surplus soil: Existing soil that is in excess of what is required for this work, including aggregates intended, but not used, for on-site mixing of concrete, mortars and paving. Contaminated soil meeting the definition of hazardous material or hazardous waste is not included.
c. Inert construction and demolition debris: Broken or removed concrete, masonry, and rock asphalt paving; ceramics; roofing paper and shingles. Inert materials [may] [may not] be re-inforced with or contain ferrous wire, rods, accessories and weldments.
d. Wood: Dimension and non-dimension lumber, plywood, chipboard, hardboard. Treated and/or painted wood that meets the definition of lead contaminated or lead based contaminated paint is not included.
e. Scrap metal: Scrap and excess ferrous and non-ferrous metals such as re-inforcing steel, structural shapes, pipe and wire that are recovered or collected and disposed of as scrap. Scrap metal meeting the definition of hazardous material or hazardous waste is not included.
Section 01 57 19 Page 3
f. Paint cans: Metal cans that are empty of paints, solvents, thinners and adhesives. If permitted by the paint can label, a thin dry film may remain in the can.
g. Recyclables: Materials, equipment and assemblies such as doors, windows, door and window frames, plumbing fixtures, glazing and mirrors that are recovered and sold as recyclable. Metal meeting the definition of lead contaminated or lead based paint contaminated [may] [may not] be included as recyclable if sold to a scrap metal company. Paint cans [may] [may not] be included as recyclable if sold to a scrap metal company.
1.2.3 Debris
Non-hazardous solid material generated during the construction, demolition, or renovation of a structure which exceeds 2.5 inch particle size that is: a manufactured object; plant or animal matter; or natural geologic material (e.g. cobbles and boulders). A mixture of debris and other material such as soil or sludge is also subject to regulation as debris if the mixture is comprised primarily of debris by volume, based on visual inspection.
1.2.4 Hazardous Debris
As defined in paragraph entitled "Debris" of this section, debris that contains listed hazardous waste (either on the debris surface, or in its interstices, such as pore structure) per 40 CFR 261; or debris that exhibits a characteristic of hazardous waste per 40 CFR 261.
1.2.5 Chemical Wastes
This includes salts, acids, alkalies, herbicides, pesticides, and organic chemicals.
1.2.6 Garbage
Refuse and scraps resulting from preparation, cooking, dispensing, and consumption of food.
1.2.7 Hazardous Waste
Hazardous waste as defined in 40 CFR 261 or as defined by applicable State and local regulations.
1.2.8 Oily Waste
Petroleum products and bituminous materials.
1.2.9 Regulated Waste
Those solid waste that have specific additional Federal, state, or local controls for handling, storage, or disposal.
1.2.10 Hazardous Materials
Any material that is regulated as a hazardous material in accordance with 49 CFR 173, requires a Material Safety Data Sheet (MSDS) in accordance with 29
Section 01 57 19 Page 4
CFR 1910.1200, or which during end use, treatment, handling, storage, transportation or disposal meets or has components which meet or have the potential to meet the definition of a Hazardous Waste in accordance with 40 CFR 261. Throughout this specification, hazardous material includes hazardous chemicals.
1.3 SUBMITTALS
Environmental protection plan;
Some of the records listed below are also required as part of other submittals.
Preconstruction survey
Solid waste disposal permit
Waste determination documentation
Disposal documentation for hazardous and regulated waste
Solid waste disposal report
Contractor Hazardous Material Inventory Log;
1.4 REPORTS
1.4.1 Preconstruction Survey
Perform a preconstruction survey of the project site with the Contracting Officer, and take photographs showing existing environmental conditions in and adjacent to the site. Submit a report for the record.
1.4.2 Solid Waste Disposal Permit
Submit one copy of a State and local permit or license showing such agencies' approval of the disposal plan before transporting wastes off Government property.
1.4.3 Waste Determination Documentation
The Contractor shall submit all Waste Determination Documentation for all contractor derived wastes to be generated. The waste determination must be based upon either a constituent listing from the manufacturer used in conjunction with consideration of the process by which the waste was generated, EPA approved analytical data, or laboratory analysis (Material Safety Data Sheets (MSDS) by themselves are not adequate). All support documentation must be attached to the Waste Determination form.
Section 01 57 19 Page 5
1.4.4 Disposal Documentation for Hazardous and Regulated Waste
Submit a copy of the applicable EPA and State permit(s), manifest(s), or license(s) for transportation, treatment, storage, and disposal of hazardous and regulated waste by permitted facilities.
1.4.5 Solid Waste Disposal Report
Monthly the Contractor shall submit a solid waste disposal report to the Contracting Officer.
1.5 ENVIRONMENTAL PROTECTION REQUIREMENTS
Provide and maintain, during the life of the contract, environmental protection as defined. Plan for and provide environmental protective measures to control pollution that develops during normal construction practice. Plan for and provide environmental protective measures required to correct conditions that develop during the construction of permanent or temporary environmental features associated with the project. Comply with Federal, State, and local regulations pertaining to the environment, including water, air, solid waste, hazardous waste and substances, oily substances, and noise pollution.
1.5.1 Contractor Liabilities for Environmental Protection
The Contractor is advised that this project and the station are subject to Federal, State, and local regulatory agency inspections to review compliance with environmental laws and regulations. The Contractor shall fully cooperate with any representative from any Federal, State or local regulatory agency who may visit the job site and shall provide immediate notification to the Contracting Officer, who shall accompany them on any subsequent site inspections. The Contractor shall complete, maintain, and make available to the Contracting Officer, station, or regulatory agency personnel all documentation relating to environmental compliance under applicable Federal, State and local laws and regulations. The Contractor shall immediately notify the Contracting Officer if a Notice of Violation (NOV) is issued to the Contractor.
The Contractor shall be responsible for all damages to persons or property resulting from Contractor fault or negligence as well as for the payment of any civil fines or penalties which may be assessed by any Federal, State or local regulatory agency as a result of the Contractor's or any subcontractor's violation of any applicable Federal, State or local environmental law or regulation. Should a Notice of Violation (NOV), Notice of Noncompliance (NON), Notice of Deficiency (NOD), or similar regulatory agency notice be issued to the Government as facility owner/operator on account of the actions or inactions of the Contractor or one of its subcontractors in the performance of work under this contract, the Contractor shall fully cooperate with the Government in defending against regulatory assessment of any civil fines or penalties arising out of such actions or inactions.
1.6 CONTRACTOR HAZARDOUS MATERIAL INVENTORY LOG
Submit the "Contractor Hazardous Material Inventory Log" along with corresponding Material Safety Data Sheets (MSDS) to the Contracting Officer at the start and at the end of construction. Documentation for any
Section 01 57 19 Page 6 spills/releases, environmental reports or off-site transfers may be requested by the Contracting Officer.
2 PRODUCTS
3 EXECUTION
3.1 PROTECTION OF NATURAL RESOURCES
Preserve the natural resources within the project boundaries and outside the limits of permanent work. Restore to an equivalent or improved condition upon completion of work. Confine construction activities to within the limits of the work indicated or specified.
3.1.1 Land Resources
Land based dredging equipment operating from the adjacent spit north of the channel is prohibited.
3.1.2 Water Resources
3.1.2.1 Oily and Hazardous Substances
Prevent oil or hazardous substances from entering the ground, drainage areas, or navigable waters. In accordance with 40 CFR 112, surround all temporary fuel oil or petroleum storage tanks.
3.2 HISTORICAL AND ARCHAEOLOGICAL RESOURCES
Carefully protect in-place and report immediately to the Contracting Officer historical and archaeological items or human skeletal remains discovered in the course of work. Upon discovery, notify the Contracting Officer. Stop work in the immediate area of the discovery until directed by the Contracting Officer to resume work. The Government retains ownership and control over historical and archaeological resources.
3.3 CONTROL AND DISPOSAL OF SOLID WASTES
Pick up solid wastes, and place in covered containers which are regularly emptied. Do not prepare or cook food on the project site. Prevent contamination of the site or other areas when handling and disposing of wastes. At project completion, leave the areas clean. Recycling is encouraged and can be coordinated with the Contracting Officer and the activity recycling coordinator. Remove all solid waste (including non-hazardous debris) from Government property and dispose off-site at an approved landfill. Solid waste disposal off-site must comply with most stringent local, State, and Federal requirements including 40 CFR 241, 40 CFR 243, and 40 CFR 258.
3.4 CONTROL AND DISPOSAL OF HAZARDOUS WASTES
3.4.1 Management of Wastes
a. All material, whether hazardous or non-hazardous shall be disposed in accordance with all laws and provisions and all Federal, State or Local Regulations. Ensure all waste is properly characterized.
Section 01 57 19 Page 7
The result of each waste characterization (TCLP for RCRA materials) will dictate disposal requirements.
b. Contractor is responsible for segregation of waste. Collect lead-contamination waste, scrap, debris, bags, containers, equipment, and lead-contaminated clothing that may produce airborne concentrations of lead particles. Label the containers in accordance with 40 CFR 262.
c. Dispose of material classified as hazardous waste at an EPA or
State approved hazardous waste treatment, storage, or disposal facility off Government property.
d. Store waste materials in U.S. Department of Transportation (49 CFR
178) approved 208 liter 55 gallon drums. Properly label each drum to identify the type of waste (49 CFR 172) and the date the drum was filled. For hazardous waste, the collection drum requires marking/labeling in accordance with 40 CFR 262 during the accumulation/collection timeframe.
e. Handle, store, transport, and dispose hazardous waste in accordance with 40 CFR 260, 40 CFR 261, 40 CFR 262, 40 CFR 263, 40 CFR 264, and 40 CFR 265. Comply with land disposal restriction notification requirements as required by 40 CFR 268.
3.4.2 Disposal Documentation
a. All paperwork required by the transporter and/or disposal facility, including waste profiles and the Hazardous Waste Manifest, must be submitted to the Contracting Officer or authorized representative for approval prior to the date of the scheduled removal.
b. All shipments of Hazardous Waste must be accompanied by a Uniform
Hazardous Waste Manifest and a Land Disposal Restriction Notification. The Coast Guard shall be listed as the Generator on all hazardous waste manifest. The Contractor will verify with the Contracting Officer that the Generator Name and Mailing Address in Box 3 of the manifest are correct. Only authorized Coast Guard personnel shall sign hazardous waste manifests. The Contracting Officer shall provide the name of the authorized signatory to the Contractor. The Coast Guard shall retain all original Generator copies of the manifest.
c. Submit written evidence to demonstrate the hazardous waste treatment, storage, or disposal facility (TSD) is approved for lead disposal by the EPA, State or local regulatory agencies. Submit one copy of the completed hazardous waste manifest, signed and dated by the initial transporter in accordance with 40 CFR 262.
Contractor shall provide a certificate that the waste was accepted by the disposal facility.
3.5 POLLUTION PREVENTION/HAZARDOUS WASTE MINIMIZATION
The Contractor shall actively pursue minimizing the use of hazardous materials and the generation of hazardous waste.
Section 01 57 19 Page 8
3.6 HAZARDOUS MATERIAL CONTROL
The Contractor shall include hazardous material control procedures in the Safety Plan. The procedures shall address and ensure the proper handling of hazardous materials, including the appropriate transportation requirements.
The Contractor shall submit a MSDS and estimated quantities to be used for each hazardous material to the Contracting Officer prior to bringing the material on base. Typical materials requiring MSDS and quantity reporting include, but are not limited to, oil and latex based painting and caulking products, solvents, adhesives, aerosol, and petroleum products. At the end of the project, the Contractor shall provide the Contracting Officer with the maximum quantity of each material that was present at the site at any one time, the dates the material was present, the amount of each material that was used during the project, and how the material was used. The Contractor shall also ensure that hazardous materials are utilized in a manner that will minimize the amount of hazardous waste that is generated.
The Contractor shall ensure that all containers of hazardous materials have NFPA labels or their equivalent. Copies of the MSDS for hazardous materials shall be kept on site at all times and provided to the Contracting Officer at the end of the project. The Contractor shall certify that all hazardous materials removed from the site are hazardous materials and do not meet the definition of hazardous waste per 40 CFR 261.
3.7 PETROLEUM PRODUCTS
Conduct the fueling and lubricating of equipment and motor vehicles in a manner that protects against spills and evaporation. All used oil generated on site shall be managed in accordance with 40 CFR 279. The Contractor shall determine if any used oil generated while on-site exhibits a characteristic of hazardous waste. In addition, used oil containing 1000 parts per million of solvents will be considered a hazardous waste and disposed of at Contractor's expense. Used oil mixed with a hazardous waste will also be considered a hazardous waste. All hazardous waste will be managed in accordance with the paragraph entitled Hazardous Waste/Debris Management of this section and shall be managed in accordance with the approved Environmental Protection Plan.
3.8 RELEASES/SPILLS OF OIL AND HAZARDOUS SUBSTANCES
Take precautions to prevent releases/spills of oil and hazardous substances.
In the event of any releases of oil and hazardous substances, chemicals, or gases; immediately (within 15 minutes) notify the Base or Activity Fire Department, the activity's Command Duty Officer, and the Contracting Officer. The Contractor is responsible for verbal and written notifications as required by the federal 40 CFR 355, State, local regulations and Navy Instructions. Spill response shall be in accordance with 40 CFR 300 and applicable State and local regulations. Contain and clean up these spills without cost to the Government. If Government assistance is requested or required, the Contractor shall reimburse the Government for such assistance.
Provide copies of the written notification and documentation that a verbal notification was made within 20 days.
SECTION 01 77 00 Page 1
SECTION 01 77 00
CLOSEOUT PROCEDURES
1.1 SUBMITTALS
Post-dredge survey and quantity calculations
1.2 HAZARDOUS MATERIAL REPORTING
Submit hazardous material reporting information which includes actual quantities of hazardous materials stored and used during the project as specified in Section 01 57 29, "Temporary Environmental Controls."
SECTION 35 20 23 Page 1
SECTION 35 20 23
DREDGING
1.1 DEFINITION
Hard material is defined as material requiring blasting or the use of special equipment for economical removal, and includes boulders or fragments too large to be removed in one piece by the dredge.
1.2 SUBMITTALS
The following shall be submitted in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Pre-dredge survey, cross sections, and quantity calculations Post-dredge survey, cross sections, and quantity calculations
1.3 MATERIAL TO BE REMOVED
The material to be removed is material carried along the shoreline by natural currents, wind, and waves and consists of sand, gravel, cobbles.
1.3.1 Hard Material
The removal of hard material is not included.
1.4 ARTIFICIAL OBSTRUCTIONS
The Government has no knowledge of cables, pipes, or other artificial obstructions or of any wrecks, wreckage, or other material that would necessitate the use of or the employment of additional equipment for economical removal. If actual conditions differ from those stated or shown, or both, an adjustment in contract price or time for completion, or both, will be made in accordance with "FAR 52.236-2, Differing Site Conditions."
1.5 QUANTITY OF MATERIAL
The total estimated amount of material to be removed from within the specified limits, including side slopes is 5,000 cubic yards. The estimated quantity for bidding purposes and for application of the "FAR 52.212-11, Variation in Estimated Quantity" shall be 5,000 cubic yards. The quantity listed is an estimate only. Within the limits of available funds, complete the work specified whether the quantity involved is greater or less than that estimated.
1.6 OVERDEPTH DREDGING
Due to unavoidable inaccuracies in the dredging processes, different types of equipment, operator skill, and material composition, it is likely that material beyond the specified limits will have to be removed. The cost for the material removed beyond the specified limits, and disposal, although
SECTION 35 20 23 Page 2 necessary to achieve the specified limits, will not be paid as a separate item, but should be accounted for in the cost to dredge the material within the specified limits
1.7 SIDE SLOPES
Dredging on side slopes shall follow, as closely as practicable, the lines specified.
1.8 PERMIT
The Contractor shall comply with conditions and requirements of the State and Federal permits issued for the work and included in Appendix A
1.10 ENVIRONMENTAL PROTECTION REQUIREMENTS
Provide and maintain during the life of the contract, environmental protective measures. Also, provide environmental protective measures required to correct conditions, such as oil spills that occur during the dredging operations. Comply with Federal, State, and local regulations pertaining to water, air, and noise pollution.
1.11 LAYOUT WORK AND SURVEY
1.11.1 Layout and Survey
The contractor shall employ a licensed land and hydrographic surveyors to layout the limits of the work, establish vertical/horizontal controls and range lines as necessary to perform the work. The contractor shall establish and provide all buoys, ranges and other controls necessary to accomplish the work and facilitate inspection.
1.11.2 Pre-dredge Survey
A pre-dredge hydrographic and land survey shall be taken throughout the area to be dredged, including side slope areas that extend upland. The contractor shall take soundings throughout the dredge area on lines running transversely to the direction of the channel and/or primary direction of boat movement. The soundings shall be corrected to mean low water and shall be indicated by the contractor on the government provided copy of the contract drawing and forwarded to the Contracting Officer within 5 days of taking measurements. Space transverse lines a sufficient distance apart in order that an accurate quantity of material can be calculated, except that transverse lines shall not be spaced more than 25 feet apart.
1.11.3 Cross Sections
The contractor shall prepare cross-sections of the dredging area at each transverse line showing the existing surface contours and the specified limits and calculate the volume of material between the two indicating the amount of material to be dredged. Calculate the volume using the Average-end-Area method. Submit cross-section and volume computations data together with the pre-dredge survey.
SECTION 35 20 23 Page 3
1.11.4 Post-dredge Survey
After completion of all the dredging work, the contractor shall resurvey the area as specified for the pre-dredge survey and cross-section paragraphs above and recalculate the volume of material actually removed from within the specified limits. Submit survey, cross-sections, and computations to the Contracting Officer within ten days of performing the work.
1.11.5 Survey Submittals
The contractor shall submit the information specified above in print and drawn to scale. The information may be submitted electronically if it is in a format that is accessible with AutoCAD 2005 software.
3.1 INSPECTION
Inspect the work, keep records of work performed, and ensure that gages, targets, ranges, and other markers are in place and usable for the intended purpose. Furnish, at the request of the Contracting Officer, boats, boatmen, laborers, and materials necessary for inspecting, supervising, and surveying the work. When required, provide transportation for the Contracting Officer and inspectors to and from the disposal area and between the dredging plant and adjacent points on shore.
3.2 CONDUCT OF DREDGING WORK
3.2.1 Interference with Navigation
Minimize interference with the use of channels and passages. The Contracting Officer will direct the shifting or moving of dredges or the interruption of dredging operations to accommodate the movement of vessels and floating equipment, if necessary.
3.2.2 Lights
Each night, between sunset and sunrise and during periods of restricted visibility, provide lights for floating plants, ranges, and markers. Also, provide lights for buoys that could endanger or obstruct navigation. When night work is in progress, maintain lights from sunset to sunrise for the observation of dredging operations. Lighting shall conform to United States Coast Guard requirements for visibility and color.
3.2.3 Ranges, Gages, and Lines
Furnish, set, and maintain ranges, buoys, and markers needed to define the work and to facilitate inspection. Establish and maintain gages in locations observable from each part of the work so that the depth may be determined. Suspend dredging when the gages or ranges cannot be seen or followed.
SECTION 35 20 23 Page 4
3.2.4 Plant
Maintain the plant, scows, coamings, barges, and associated equipment to meet the requirements of the work.
3.2.5 Disposal of Excavated Material
Provide for safe transportation and disposal of dredged materials. The deposit of dredged materials in unauthorized places is forbidden. Comply with rules and regulations of local port and harbor governing authorities.
3.2.5.1 Method of Dredging and Disposal
Dredge and deposit material using mechanical methods. Due to past poor and/or failed performance, hydraulic dredging methods are prohibited.
Dredging and disposal shall be limited to floating equipment except that spreading of the material on the shoreline may be accomplished with land based equipment.
3.2.5.2 Disposal on Indicated Shoreline
Place material on the designated shoreline in accordance with permits issued for the work.
3.2.6 Navigation Warnings
Furnish and maintain navigation warning signs as appropriate for the work.
3.2.7 Method of Communication
Provide a system of communication between the dredge crew and the crew at the disposal area. A portable two-way radio is acceptable.
3.2.8 Salvaged Material
Anchors, chains, firearms, and other articles of value, which are brought to the surface during dredging operations, shall remain or become the property of the Government and shall be deposited on shore at a convenient location near the site of the work, as directed.
3.2.9 Plant Removal
Upon completion of the work, promptly remove plant, including ranges, buoys, piles, and other markers or obstructions.
3.2.10 Surveys During Progress of Work
Contract depth will be determined by soundings or sweepings taken behind the dredge as work progresses. The Contractor shall take progress soundings or sweepings.
3.3 FINAL EXAMINATION AND ACCEPTANCE
Sweep area to insure that…