USCGC HOLLYHOCK (WLB 214)

SPECIFICATION FOR DRYDOCK REPAIRS

FY2017

Developed By: David A Rowland (Revision-0, 26 January 2017)

TABLE OF CONTENTS

ivRevisions Record vConsolidated List of References ixConsolidated List of Government-furnished Property xiConsolidated List of Critical Inspection Items xiiPrincipal Characteristics

1General Requirements

11WORK ITEM 1: Hull Plating (U/W Body), Inspect

14WORK ITEM 2: Hull Plating (U/W Body), Ultrasonic Testing

17WORK ITEM 3: Hull Plating (Freeboard), Ultrasonic Testing

19WORK ITEM 4: Appendages (U/W), Leak Test

22WORK ITEM 5: Propulsion Shaft Fairwaters and Rope Guards, Inspect

25WORK ITEM 6: Appendages (U/W) - Internal, Preserve

27WORK ITEM 7: Chain Locker(s), Clean and Inspect

29WORK ITEM 8: Voids (Non-Accessible), Leak Test

32WORK ITEM 9: Voids (Non-Accessible), Internal Surfaces, Preserve

34WORK ITEM 10: Tanks (Potable Water), Clean and Inspect

38WORK ITEM 11: Tanks (Ballast), Clean and Inspect

41WORK ITEM 12: Tanks (Dirty Oil and Waste), Clean and Inspect

44WORK ITEM 13: Controllable Pitch Propellers, Clean and Inspect

47WORK ITEM 14: Controllable Pitch Propeller, System Maintenance

54WORK ITEM 15: Controllable Pitch Propeller Hub, General Maintenance, Perform

62WORK ITEM 16: Fathometer Transducer, Renew

65WORK ITEM 17: Underwater (Speed) Log Transducer(s), Renew

67WORK ITEM 18: Fwd Scan Sonar Transducer, General Maintenance, Perform

76WORK ITEM 19: Sea Valves and Waster Pieces, Overhaul or Renew

81WORK ITEM 20: Sea Strainers - Duplex (All Sizes), Overhaul

85WORK ITEM 21: Sea Strainers - Simplex (All Sizes), Clean and Inspect

88WORK ITEM 22: Sea Bay, Clean and Inspect

91WORK ITEM 23: Sea Bay, Preserve 100%

93WORK ITEM 24: Rudder(s), Preserve (“100%”)

95WORK ITEM 25: Thruster Units (Bow And Stern), Overhaul

99WORK ITEM 26: Anchor Chain(s) and Ground Tackle, Inspect and Repair

106WORK ITEM 27: Grey Water Holding Tank(s), Clean and Inspect

110WORK ITEM 28: Sewage Holding Tank(s), Clean and Inspect

114WORK ITEM 29: Sewage Piping, Clean And Flush

118WORK ITEM 30: Tanks (Ballast), Preserve “Partial”

121WORK ITEM 31: Chain Lockers, Preserve - Partial

123WORK ITEM 32: Tanks (Dirty Oil and Waste), Preserve “Partial”

126WORK ITEM 33: Tanks (Potable Water), Preserve “Partial”

130WORK ITEM 34: U/W Body, Preserve (100%)

134WORK ITEM 35: Hull Plating Freeboard, Preserve “100%”

138WORK ITEM 36: Impressed Current Cathodic Protection System, Inspect and Maintain

144WORK ITEM 37: Impressed Current Cathodic Protection System Anodes, Renew

148WORK ITEM 38: Impressed Current Cathodic Protection System Reference Cells, Renew

152WORK ITEM 39: Impressed Current Cathodic Protection System Dielectric Shield, Repair

158WORK ITEM 40: Impressed Current Cathodic Protection System Dielectric Shield (Capastic Fairing), Renew

164WORK ITEM 41: Drydock

169WORK ITEM 42: Temporary Services, Provide - Cutter

172WORK ITEM 43: Sea Trial Performance, Support, Provide

176WORK ITEM 44: Bilges, Machinery Space, Clean and Inspect

179WORK ITEM 45: Bilges, Preserve

181WORK ITEM 46: Decks – Exterior (Buoy or Construction Deck), Preserve 100%

184WORK ITEM 47: Main Mast, Preserve, 100%

188WORK ITEM 48: Sounding Tube, Renew

190WORK ITEM 49: Twin Pivot Arm Davit, Overhaul

Revisions Record This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE
REV#
WORK ITEM#
CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

Consolidated List of References

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.

All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – as follows:

· MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm

· Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp

· Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws:: www.gpoaccess.gov The Government is aware of the following internet web links where contractors may procure commercial specifications:

· American Welding Society (AWS): http://www.awspubs.com/index.php

· ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/

· NFPA: http://www.nfpa.org

· SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace

COAST GUARD DRAWINGS

Coast Guard Drawing 175-WLM 568-002, Rev K, Bow Thruster Detail

Coast Guard Drawing 225 BWLB 633-002, Rev A, Cathodic Protection Passive

Coast Guard Drawing 225 WLB 184-001, Rev B, CRP-V850 Transducer Adapter Ring

Coast Guard Drawing 225 WLB 256-001, Rev M, Seawater Cooling System Diagram

Coast Guard Drawing 225 WLB 256-001, Rev P, Seawater Cooling System Diagram

Coast Guard Drawing 225 WLB 424-001, Rev G, Acoustic Navigation System Block & Isometric

Coast Guard Drawing 225 WLB 581-001, Rev E, Anchor Handling System Arrangement

Coast Guard Drawing 225 WLB 801-020, Rev B, Tank CAPACITY - 95% Curves

Coast Guard Drawing 225B WLB 114-001, Rev C, Shell Appendages

Coast Guard Drawing 225B WLB 114-002, Rev -, Flow Accelerating Fin

Coast Guard Drawing 225B WLB 568-001, Rev A, Bow Thruster A & D

Coast Guard Drawing 225B WLB 801-006, Rev D, Docking Drawing

Coast Guard Drawing 225B WLB 111-001, Rev A, Shell Expansion

Coast Guard Drawing 225B WLB 111-001, Rev A; Shell Expansion

Coast Guard Drawing 225B WLB 114-001, Rev C; Shell Appendages

Coast Guard Drawing 225B WLB 170-1, Rev H; MAST A & D

Coast Guard Drawing 225B WLB 256-001, Rev M, Seawater Cooling System Diagram

Coast Guard Drawing 225B WLB 256-001, Rev N, Seawater Cooling System Diagram

Coast Guard Drawing 225B WLB 528-001, Rev E, Plumbing and Interior Deck Drains

Coast Guard Drawing 225B WLB 562-002, Rev C, Rudder Structural A&D

Coast Guard Drawing 225B WLB 562-002, Rev C; Rudder Structural A & D

Coast Guard Drawing 225B WLB 581-001 Rev C, Anchor Handling System Arrangement

Coast Guard Drawing 225B WLB 593-001, Rev D, Sewage and Waste Water System Diagram

Coast Guard Drawing 225B WLB 593-001, Rev D, Sewage and Waste Water System

Coast Guard Drawing 225B WLB 593-009, Rev B, Sewage Holding Tank

Coast Guard Drawing 225B WLB 601-001, Rev F, General Arrangement Inboard & Outboard Profiles

Coast Guard Drawing 225B WLB 601-001, Rev L; General Arrangement Inboard & Outboard Profiles

Coast Guard Drawing 225B WLB 601-001, Rev L; General Arrangement Inboard and Outboard Profiles

Coast Guard Drawing 225B WLB 601-002 Rev K, Booklet of General Drawings

Coast Guard Drawing 225B WLB 601-002, Rev G, Booklet of General Drawings

Coast Guard Drawing 225B WLB 601-002, Rev H, Booklet of General Drawings

Coast Guard Drawing 225B WLB 601-002, Rev K; Booklet Of General Plans

Coast Guard Drawing 225B WLB 601-002, Rev L, Booklet off General Drawings

Coast Guard Drawing 225B WLB 633-001, Rev B, Cathodic Protection System Arrangement, Block Diagram, Wiring Deck Plan, and Elementary Diagrams

Coast Guard Drawing 225B WLB 801-001, Rev A, Lines and Offsets

Coast Guard Drawing 225B WLB 801-003, Rev A, Curves of Forms and Cross Curves of Stability

Coast Guard Drawing 225B WLB 801-005, Rev A Tank CAPACITY - 95% Curves

Coast Guard Drawing 225B WLB 801-006, Rev C; Docking Drawing

Coast Guard Drawing 225B WLB 801-006, Rev D; Docking Drawing

Coast Guard Drawing 225B WLB 801-006, Rev E, Docking Drawing

Coast Guard Drawing 225B-WLB 243-2, Rev E; Stern Tube and Bearing a & D

Coast Guard Drawing 225B-WLB 506-1, Rev B, Overflows, Air Escapes & Sndg Tubes Diagram

Coast Guard Drawing 225-WLB-201-001 Rev-F, Machinery Space Arrangement

Coast Guard Drawing 225-WLB-601-001 Rev-C, General Arrangements Inboard and Outboard Profile

Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem

Coast Guard Fleet Drawing FL 2804-22, Rev-, Consolidated Visual ID for Cutters

Coast Guard Yard Drawing 225-WLB-201-001, Rev F, Title Machinery Space Arrangement

COAST GUARD PUBLICATIONS

Coast Guard Technical Publication (TP) 3762, 15-OCT-04, Daul Point Davit - ATON Workboat - Model TWPIV5-0A

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual

Coast Guard Drawing 225B WLB 633-001, Rev B, Cathodic Protection System Arrangement, Block Diagram, Wiring Deck Plan, and Elementary Diagrams

Coast Guard Technical Publication (TP) 3446, Jun 2009, Doppler Speed Log, Model SRD-500 Dual Axis

Coast Guard Technical Publication (TP) 3498, Section A, Jul 2015, Buoy Chain Winch

Coast Guard Technical Publication (TP) 3524, 07-JAN-97, Manufacturer's Instruction Book-SWBS Group(s) 243-262

Coast Guard Technical Publication (TP) 3524, SWBS 245-B, Aug 2005, Instruction Manual for the Model 102 B Class Controllable Pitch Propeller and Shafting System

Coast Guard Technical Publication (TP) 3556, Jun 2009, Manufacturer’s Instruction Book-SWBS Group(s) 568, Bow and Stern Thruster – Model 125/3 STAY/FP

Coast Guard Technical Publication (TP) 3574, Mar 2009, SWBS Group 633-638

Coast Guard Technical Publication (TP) E-424-006, Version WLB97-1, Wesmar 3060-08/M-8/AC Forward Scan Sonar

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2014, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation

Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2014, Auxiliary Machine Systems

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2014, Drydocking

Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2014, Temporary Services

Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2014, Temporary Hull Accesses

OTHER REFERENCES

American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2011, Disinfection of Water-Storage Facilities

American National Standards Institute/NSF International (ANSI/NSF) 61, 2008, Drinking Water System Components - Health Effects

American National Standards Institute/NSF International (ANSI/NSF) 61, 2015, Drinking Water System Components - Health Effects

American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and Welding End

ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) D4138, 2013, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means

ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component Adhesives (An)

ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates

Commercial Item Descriptions (CID) A-A-59323, Rev A; Cloths, Cleaning, Low-Lint

DOD-STD-2187, Aug 1987, Chemical Cleaning of Salt Water Piping Systems

Federal Specification (Fed Spec) RR-C-271, Rev E, Dec 2010, Chain and Attachments, Welded and Weldless

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, Pressure Testing Of Steel Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002 Edition, Butterfly Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service

Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2008 Edition, Bronze Gate, Globe, Angle and Check Valves

MIL PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cut Back, Cold Application

MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning

MIL-C-24633, Apr 1998, Chain, Stud Link, Anchor, Low Alloy Steel, Flash Butt Welded

MIL-DTL-23549, Dec 2011, Grease, General Purpose

MIL-PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cut-Back, Cold-Application

MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant

Naval Sea Systems Command (NAVSEA) Underwater Ship Husbandry Manuals (UWSH) S0600-AA-PRO-160, Jan 2006, Chapter 16, Cofferdams

Naval Sea Systems Command (NAVSEA) Underwater Ship Husbandry Manuals (UWSH) S0600-AA-PRO-160, Jan 2011, Chapter 16, Cofferdams

ODOM Echotrac DF3200 MKII, Rev 2, Technical Manual

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) G-6032, 2014 Grease, Plug Valve, Gasoline and Oil Resistant, NATO Code Number G-363, Metric

The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2004, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2015, Solvent Cleaning

The Society for Protective Coatings (SSPC), January 2015, Paint Application Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating Thickness Requirements

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, 2007, Near-White Metal Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 6/NACE No. 3, 2007, Commercial Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough Cleaning

The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Blast Cleaning

The Society for Protective Coatings SSPC-SP 10/NACE No.2, Jan 2007, Near-White Blast Cleaning

The Society for Protective Coatings SSPC-SP 11, Jul 2012, Power Tool Cleaning to Bare Metal

Consolidated List of Government-furnished Property

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK ITEM
MTI
ITEM DESCRIPTION
NSN/PN
QTY
ESTIMATED COST

($/Unit)

14
N
Stat-O-Seal Washers
NSN: 5310-01-212-5987 PN: 0-4-3-5
12 ea.
55.61
14
N
O-Ring, Hub Flange Bolt Cover
NSN: 5331-00-983-9878 PN: 0-2-2-5
12 ea.
50.00
15
Y
**Blade Bolts
NSN: 5306-01-410-6893
4 ea.
1,854.12
15
N
Blade Bolt O-rings
NSN: 5330-01-408-7251 (0-3-2-11)
48 ea.
2.25
15
N
Blade Seal
NSN: 5331-01-623-0621 (2-472 KA174-75)
4 ea.
55.00
15
Y
*Lifting Device, Propeller Blade
NSN: 2020-01-F02-6825
1 ea.
100.00
16
Y
*** Fathometer Transducer, shallow water, 50-200 kHz (Airmar Technology SS505)
NSN: 5845-01-518-7231 PN: SS505
1 ea.
$2,278.99
16
N
***Fathometer Transducer, Deep Water, 24kHZ
NSN: 5845-01-496-9770 PN: TH28/20-41-516CG
1 ea.
$7,709.21
17
Y
***Sperry SRD 500 Doppler speed log
NSN: 5999-01-472-7499
1 ea.
16504.43
18
N
***3/8” Flax Packing
NSN: PN: 09.00749.0
1 ea.
45.00
18
N
***4” Zinc Donut Collar
NSN: PN: 95.11410.0
1 ea.
120.00
25
N
Seal Kit, Bow and Stern Thruster
NSN: 2010-01-555-9048
2 ea.
3,634.00
25
N
Seal Spacer
PN: B125SM44178
2 ea.
37
N
Anode, Corrosion Preventive
NSN: 5342-01-540-3444
4 ea.
3,525.00
37
N
Shell, mounting
PN: Siemens Water Technologies W2T98554

(Electrocatalytic 74226)

1 ea.
264.50
37
N
Mat, neoprene
Siemens Water Technologies W2T98553

(Electrocatalytic 74225) NSN: 5330-01-540-9556

1 ea.
35.26
37
N
Nut/washer, molded
PN: Siemens Water Technologies W3T106648

(Electrocatalytic 73547)

6 ea.
35.14
38
N
Electrode
Siemens Water Technologies W3T105012

(Electrocatalytic 32622) NSN: 5977-01-346-0750

2 ea.
1,300.02
41
Y
*Transducer Cover Plate
N/A
1 ea.
50.00
49
N
4 year Davit In-place Overhaul Kit
NSN: 2090-99-260-9258 or PN: 892-02058
1
115,000.00

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter

Consolidated List of Critical Inspection Items The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):

Work Item
Title
2
Hull Plating (U/W Body), Ultrasonic Testing
4
Appendages (U/W), Leak Test
8
Voids (Non-Accessible), Leak Test
13
Controllable Pitch Propellers, Clean and Inspect
14
Controllable Pitch Propeller, System Maintenance
15
Controllable Pitch Propeller Hub, General Maintenance, Perform
20
Sea Strainers - Duplex (All Sizes), Overhaul
21
Sea Strainers - Simplex (All Sizes), Clean and Inspect
22
Sea Bay, Clean and Inspect
26
Anchor Chain(s) and Ground Tackle, Inspect and Repair
34
U/W Body, Preserve (100%)
36
Impressed Current Cathodic Protection System, Inspect and Maintain
49
Twin Pivot Arm Davit, Overhaul

Principal Characteristics

225' WLB (B-CLASS)

Physical

Length overall
225' 0"
Length between perpendiculars
206' 0"
Maximum beam
46'
Designed draft
13' 0"
Full load displacement
1905.6 Long Tons SW
Light ship displacement
1500.7 Long Tons SW
Minimum operating displacement
1869.2 Long Tons SW
Mast height (above 12' waterline)
67' 5"
Anchor
Two 4000 lb standard Navy stockless anchors, 8 shots each, port and starboard, 1-3/8 die lock chain

Hull

Bilge keels (port & starboard)
Frames 42-79

Frame spacing

FR 0 to 12
21"
FR 12 to 30
22"
FR 30 to 102
24"

Machinery

Main propulsion
Diesel Reduction
Diesel engines
Two Caterpillar 3608, TA, 3100 BHP each @ 900 RPM
Number of propellers
1
Number of blades
4
Diameter
10'
Pitch
Controllable
RPM
254
Ship's service diesel generators
Two Caterpillar 3508 TA, 450 KW
Emergency diesel generator
One Caterpillar 3406 DITA, 280 KW
Shore tie
Two 450 VAC, 400 Amp, 3-wire
Shaft bearing, forward
Cooper Bearing 01-BCP-1400-EX-TL
Shaft bearing, aft
Water Lubricated Cutless Bearing

Tank CAPACITIES

Diesel oil
76,498 gal.
Fresh water capacity
8056 gal.
Hydraulic oil capacity
2785 gal.
Lube oil storage
764 gal.
Grey water tank
2700 gal.
Sewage holding tank
1700 gal.

00000_0316_FLT

REC_00000_FLT_Commercial Project @ Contractor’ Facility (1212)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

Coast Guard Drawings

None

Coast Guard Publications

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

Other References

None

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

NOTE

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.2 Fire watch requirements. The Contractor shall refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:

· Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.

· Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.

3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).

NOTE

Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes (provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.

3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.

3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 Contractor operated (non USCG) facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.

3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix A, Requirements For Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.

3.6 Local Policy. None.

3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:

3.7.1 SFLC Standard Specification 6310, Requirements for Preservation of Ship Structures.

3.7.1.1 SFLC Std Spec 6310, page C-2, Section C1.5.1. Change from "lead-containing paint as 0.06%" to "lead-containing paint as 0.009%".

3.7.1.2 SFLC Std Spec 6310, page 4, Section 2 References, Group- Other References. Add “The Society for Protective Coatings (SSPC) Paint Application Guide No. 11, 2008, Protecting Edges, Crevices, and Irregular Steel Surfaces by Stripe Coating”

3.7.1.3 SFLC Std Spec 6310, page Appendix C-6, add "Hempel Hempadur Multi-Strength GF 35870" with FED-STD-595 color "Black/Red" under ANTI-ABRASION COATING, ICE BREAKING CAPABLE VESSELS, <235’.

3.7.1.4 Standard Spec 6310, page Appendix A-7, Under "UNDERWATER (U/W) BODY/BOOT-TOP", Add line Column 1: Option for U/W Body and Boot-Top, Steel Hulls, <154', in Salt Water. Column 2: Blank. Column 3: SSPC-SP 10/NACE NO. 2 using grit conforming to MIL-A-22262 / (1.5-3.5) - or - SSPC-SP WJ-2(M)/NACE WJ-2(M). Columns 4 and 5: Same as "U/W Body and Boot-Top, Aluminum Hull, High Speed (>30 knots)".

3.7.2 SFLC Standard Specification 0000 General Requirements.

3.7.2.1 SFLC Std Spec 0000, paragraph 1.3 ‘Acronyms and term definitions’, page 5, “PCL (Paint Containing Lead)” definition replaced by, “Any paint or coating containing lead in excess of 0.009 percent by weight (1.0 mg/cm2 or 90 ppm). Lead Based Paint (LBP) is an interchangeable term with PCL.”

3.7.2.2 Change Std Spec 0000 paragraph 3.2.4.2.3(QP 1 inspector or tech rep duties) bullet, “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.19 of SFLC Std Spec 6310 (Critical drying time requirements)).” to “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.17 of SFLC Std Spec 6310 (Critical drying time requirements)).”

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

Vessel Name
Hull #
Work Item #
Work Item Title

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE & TIME
ACTIVITY (Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION (Frame & Deck, relation to equipment, etc.)
TEMPERATURE
% REL. HUMID-ITY
DEW PT.
SURFACE
AMBIENT
ΔT

| DP - Surface |

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min
Max
Mean

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

Abrasive Manufacturer:

Abrasive Sieve Size:

Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings:

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min
Max
Mean

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

Abrasive Manufacturer:

Abrasive Sieve Size:

Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Reading (mils)

Mean Reading (mils) IAW ASTM DD4417).

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)

SOLUBLE SALT CONDUCTIVITY Measurements IAW SSPC-GUIDE 15.

Date
Test Locations
Conductivity (Microsiemens/CM)
Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

Vessel Name
Hull #
Work Item #
Work Item Title
Coating Mfg
Product Name
Batch #
Induction Time
Coating System Sequence (Primer/Touchup/3rd Coat, etc.)

Dry Film Thickness (DFT) Measurements IAW SSPC-PA 2.

SPOT
1
2
3
4
5
AVERAGE VALUE

*BASE METAL READING (BMR) Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Application Method (Airless, Conventional Spray, Rolled)
Average DFT
Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

11000_0815_FLT

REC_11000_UWHIB_FLT_225B WLB (214 CGC HOLLYHOCK) Great Lakes (1211) WORK ITEM 1: Hull Plating (U/W Body), Inspect

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to inspect/survey the vessel’s Under Water (U/W) hull plating, including U/W appendages and coating system.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 225B WLB 111-001, Rev A; Shell Expansion Coast Guard Drawing 225B WLB 114-001, Rev C; Shell Appendages Coast Guard Drawing 225B WLB 562-002, Rev C; Rudder Structural A & D Coast Guard Drawing 225B WLB 801-006, Rev D; Docking Drawing

Coast Guard Publications

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Other References

ASTM International (ASTM) D4138, 2013, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means

The Society for Protective Coatings (SSPC), January 2015, Paint Application Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating Thickness Requirements

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Inspection. The Contractor shall accompany the Underwater Hull Inspection Board (UWHIB) in the performance of the below inspection tasks, as applicable, using the drawings listed in Section 2 (References) as guidance. The Contractor shall provide the following, to facilitate the UWHIB in assessing the condition of the designated U/W hull components and systems:

· A hull repair supervisor and a marker.

· Temporary staging and other necessary equipment, as applicable, for ensuring safe access to all areas of the U/W hull.

NOTES

1. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.

2. Some of the components and/or systems addressed in this work item may not be applicable to all vessel classes.

3.2.1 Hull plating.

3.2.1.1 The Contractor shall inspect the condition of the hull plating (including thruster tunnel plating, as applicable), for the presence of marine growth, deformation, and any evidence of major corrosion or electrolytic action.

3.2.1.2 The Contractor shall inspect the hull and keel areas, report on the condition of butt-welded seams, doubler plates, lap seams, and for any signs of damaged plating or unusual waviness in the plating.

3.2.2 Sea chests and all other cooling system intake components. The Contractor shall inspect all sea chests, tunnels, hull openings, and grates for general appearance, loose, damaged, or missing grates, loose or missing fasteners, condition of sea strainers and lockwire on bolts, marine growth on grating slots, and any obstructions in the openings that might prevent proper suction and discharge of water.

3.2.3 Rudders. The Contractor shall check general condition, condition around the drain plugs, and check for pitting, if any, on the leading and trailing edges.

3.2.4 Propeller and shaft associated components. The Contractor shall inspect the condition of propellers for signs of corrosion, pitting, erosion, fouling, cracks, dings, and nicks by side and blade; inspect fairwaters, rope guards, shafts, and mechanical seals - look for missing screws, physical damage to the blades, pitting, condition of dunce caps, and condition of securing devices.

3.2.5 Transducers. The Contractor shall check general condition for cuts, cracks, corrosion, and surface defects around the openings. Check transducer securing nuts for tightness, and inspect cables for chafing and other damage.

3.2.6 Anodes.

3.2.6.1 The Contractor shall remove all marine growth and oxide coating from all hull, rudder, shaft strut, sea chest, z-drive, and thruster tunnel zinc anodes, or water jet drives anodes, as applicable, using a light-wire brush.

3.2.6.2 The Contractor shall visually inspect all zinc anodes; check the soundness of mounting strap and stud welds, missing fasteners, and percentage of remaining material.

3.2.7 Coating system inspections. The Contractor shall accomplish the below inspections, in conjunction with the underwater hull inspection conducted by the Underwater Hull Inspection Board (UWHIB). Document the condition found as “Partial - Condition A”, “Partial - Condition B”, or “100%”, as applicable (see 4.1 (Definitions)). Submit a CFR.

NOTE

The following inspections are for determining the existing condition of the coating system for the underwater body surfaces, which are deemed “Critical-coated” surfaces; they must be carried out by a SSPC-QP-1 certified contractor/sub-Contractor or a NACE Inspector – see SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3.2.7.1 Visual. Perform a visual inspection of the existing U/W body coating system.

4. NOTES

4.1 Definitions.

4.1.1 "Partial – Condition A”: The condition that exists where the substrate is exposed in up to 33% of the entire U/W body.

4.1.2 "Partial - Condition B": The condition that exists where the coating system has incurred damage, but the substrate is not exposed in any location.

4.1.3 "100%”: The condition that exists where more than 33% of the U/W body hull substrate is exposed.

4.2 UWHIB convention. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.

11010_UT_0712_FLT

REC_11010_UT_FLT_225’ WLB ’B’ Class (ALL) (0911) WORK ITEM 2: Hull Plating (U/W Body), Ultrasonic Testing

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to conduct ultrasonic testing (UT) of U/W hull plating.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 225B WLB 111-001, Rev A; Shell Expansion Coast Guard Drawing 225B WLB 801-006, Rev C; Docking Drawing

Coast Guard Publications

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Other References

None.

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph:

· 3.2 (UT measurements).

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 UT measurements. The Contractor shall perform a total of 300 UT measurements of U/W hull surfaces, in locations designated by the Coast Guard Inspector, using Coast Guard Drawings 225B WLB 111-001 and 225B WLB 801-006 for guidance, in accordance with SFLC Std Spec 0740, Appendix C. Mark up a copy of Coast Guard Drawing 225B WLB 111-001 to show all locations selected for measurement and record all measurements in Table I (UT Measurements Summary Sheet - Port/Stbd Shell) provided at the end of this item. Submit A CIR, to also include the marked up drawing and completed Table I.

4. NOTES

4.1 UT Table. Table 1 provided below is for the recording of all UT measurements.

Table 1 - UT MEASUREMENTS SUMMARY SHEET PORT/STBD SHELL

SHOT #
STRAKE #
FWD/MID/AFT
ORIG PL
MEASURED PL
PERCENT
PLATE #
TOP/MID/BOT
THICKNESS
THICKNESS
WASTAGE

11010_1013_FLT

REC_11010_UT_FLT_225’ WLB ’B’ Class (ALL) (0911) WORK ITEM 3: Hull Plating (Freeboard), Ultrasonic Testing

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to conduct ultrasonic testing (UT) of freeboard hull plating.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 225B WLB 111-001, Rev A; Shell Expansion Coast Guard Publications

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Other References

None.

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 UT measurements. The Contractor shall perform a total of 100 UT measurements of freeboard hull surfaces, in locations designated by the Coast Guard Inspector, using Coast Guard Drawing 225B WLB 111-001 for guidance, in accordance with SFLC Std Spec 0740, Appendix C. Mark up a copy of Coast Guard Drawing 225B WLB 111-001 to show all locations selected for measurement and record all measurements in Table 1 (UT Measurements Summary Sheet - Port/Stbd Shell) provided at the end of this item. Submit CFR, to also include the marked up drawing and completed Table 1.

Table 1 - UT MEASUREMENTS SUMMARY SHEET PORT/STBD SHELL

SHOT #
STRAKE #
FWD/MID/AFT
ORIG PL
MEASURED PL
PERCENT
PLATE #
TOP/MID/BOT
THICKNESS
THICKNESS
WASTAGE

4. NOTES

This section is not applicable to this work item.

11400_0415_FLT

REC_11400_UWAppndgs_FLT_225’ WLB ‘B’ Class (ALL) (0414) WORK ITEM 4: Appendages (U/W), Leak Test

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to perform leak test of the U/W appendages.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 225B WLB 111-001, Rev A, Shell Expansion Coast Guard Drawing 225B WLB 114-001, Rev C, Shell Appendages Coast Guard Drawing 225B WLB 114-002, Rev -, Flow Accelerating Fin Coast Guard Drawing 225B WLB 801-006, Rev D, Docking Drawing

Coast Guard Publications

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Other References

ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component Adhesives (An)

MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph:

· 3.2 Leak test particulars.

· 3.4 Appendage air test.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Leak test. In the presence of the Coast Guard Inspector, the Contractor shall accomplish the following tasks for all appendages as designated in Table 1 below, using the Coast Guard drawings listed in Section 2 (References) as guidance:

· Remove and dispose of the existing drain plugs.

· Submit a CIR noting any liquids draining from any of the appendages – indicating the presence of a leak.

· Dispose of any drained liquids in accordance with all Federal, state, and local laws and regulations.

CAUTION

Some liquids that are drained may be may be classified as hazardous materials or hazardous waste depending on state and local regulations. The vessel environmental coordinator may assist with determination of waste category.

3.3 Plug renewal. Upon completion of all work on…