USCGC WAESCHE (WMSL 751)
SPECIFICATION FOR DOCKSIDE REPAIRS
FY2017
Developed By: Kevin O’Brien
(Rev-00, 02 Jun 2016)
USCGC WAESCHE (WMSL-751) DOCKSIDE AVAILABILITY FY2017
ii (Rev-00)
TABLE OF CONTENTS
Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ................................................................................. vi Consolidated List of Critical Inspection Items ........................................................................................... vii Principal Characteristics ............................................................................................................................ viii General Requirements WORK ITEM 1: Main Propulsion Diesel Engine- DEI WORK ITEM 2: Main Propulsion Diesel Engine (MPDE),12,000 Hour Repair iii (Rev-00)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-00)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.
All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – as follows:
MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm
Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp
Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws::
www.gpoaccess.gov
The Government is aware of the following internet web links where contractors may procure commercial specifications:
American Welding Society (AWS): http://www.awspubs.com/index.php
ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/
NFPA: http://www.nfpa.org
SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace
COAST GUARD DRAWINGS
Coast Guard Drawing 750-WMSL 101-9, Rev A, Equipment Removal Route Drawing (NSC-1 & NSC-2
Only) (ASC101009)
Coast Guard Drawing 750-WMSL-100-1, Rev L, General Arrangements (ASC100001)
Coast Guard Drawing 750-WMSL-501-2, Rev E, Machinery Arrangements (ASC501001)
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors
Manual
Coast Guard Technical Publication (TP) 7024, 31-MAY-07, Main Diesel Engine - Removal Spaces and
Weights
Coast Guard Technical Publication (TP) 7025, 31-MAY-07, Main Diesel Engine - Fluids and Lubricants
Specifications (A001061/3
Coast Guard Technical Publication (TP) 7026, 31-MAY-07, Main Diesel Engine - Repair Tools
Coast Guard Technical Publication (TP) 7027, 31-MAY-07, Main Diesel Engine - Operating Instructions
Coast Guard Technical Publication (TP) 7028, 31-MAY-07, Main Diesel Engine - Maintenance Manual
Coast Guard Technical Publication (TP) 7031, 31-MAY-07, Main Diesel Engine - Parts Catalog
(M034562/01DE)
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and
Allied Processes http://www.assistdocs.com/search/search_basic.cfm http://www.uscg.mil/directives/default.asp http://www.gpoaccess.gov/ http://www.awspubs.com/index.php http://www.techstreet.com/ http://www.nfpa.org/ http://shopping.netsuite.com/sspcmarketplace v (Rev-00)
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
OTHER REFERENCES
MTU Technical Documentation S000082/00E (MTU Tech Pub S000082/00E), 2011, Functional
Descriptions, Operating Instructions, and Instructions for General Overhaul vi (Rev-00)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM
DESCRIPTION
NSN/PN QTY ESTIMATED
COST
($/UNIT)
1 N Diesel Engine
Inspection Kit
P/N: 584-DEI-KIT
NSN: 016280945
02 ea 3051.97
2 Y Injector Replacement
Kit
P/N: 584-INJ-RPL-KIT
NSN: 015911763
20 ea. 2377.54
2 Y Cylinder Head
Replacement Kit
P/N: 584-CYL-HD-RPLM
NSN: 016192838
20 ea. 15450.56
2 Y Cylinder Liner Kit P/N: 584-CYL-LINR-KIT
NSN: 016192672
20 ea. 3672.81
2 Y Fuel Injection Pump
Kit
P/N: 584-FL-INJ-PMP-KIT
NSN: 016192228
40 ea. 12245.35
2 Y Piston Engine P/N: 5840301117
NSN: 123349610
20 ea. 10180.72
2 Y Conrod Bearing P/N: 5840301960
NSN: 123587417
20 ea. 941.03
2 Y Jacket Water Pump LS
Replacement Kit
P/N: 584-JWPMPLS-RPLM
NSN: 016263405
1 ea. 13360.14
2 Y Jacket Water Pump RS
Replacement Kit
P/N: 584-JWPMPRS-RPLM
NSN: 016192545
1 ea. 13577.89
2 Y Sea water pump
Replacement Kit
P/N: 584-SWPMP-RPLM
NSN: 016192264
1 ea. 27071.07
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter vii (Rev-00)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5
(Inspection report particulars)):
Work
Item Title
01 Main Propulsion Diesel Engine - DEI
This section is not applicable to this package.
viii (Rev-00)
PRINCIPAL CHARACTERISTICS
418' WMSL
PHYSICAL
Length overall 418' 0"
Length between perpendiculars 390' 0"
Maximum beam 54' 0"
Beam @ 01 level 47' 9-1/8"
Depth (01 level @ side to baseline) 39' 2-3/4"
01 deck camber foredeck 1/4" in 1'-0"
Minimum berth depth 20' 0"
Height of highest projection Approximately 119'
Draft, design 14.40'
Design displacement 3925 long tons
MACHINERY
Two diesel engines MTU 20V, 20-cylinder 9,730 SHP each
One gas turbine General Electric LM2500; 29,500 SHP
Type of propulsion CODAG
Electrical system 24 Volt DC
Two controllable pitch propellers Rolls-Royce 5 blade, 14' 0" diameter; 229 RPM max
Two reduction gears RENK
One cross connect gear RENK
HULL
Hull material 5086 Aluminum
HSLA-80 Steel
ABS EH 36 Steel
ABS AH 36
Frame spacing
FWD of FR 9 2' 3"
FR 9 to FR 10 6' 9"
FR 10 to FR 98 4' 1"
FR 98 to FR 99 3'-8"
ELECTRICAL
Power Three 1360 kW, 450 V, 60 Hz, 3 Phase, 1800 RPM Caterpillar 3512B diesel engines with Baylor ship service generators
Shore tie cable Seven MIL-C-24368/2 (NATO) shore power receptacles, 400 A each
TANK CAPACITIES
Diesel oil 220,359 gal
Fresh water 12,454 gal
JP-5 Fuel 35,182 gal
1 (Rev-00)
00000_1015_FLT
REC_00000_FLT_Commercial Project @ CG Facility (1212)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and
'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is
Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
NOTE
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
2 (Rev-00)
3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.
3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec
6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).
NOTE
Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes
(provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.
3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 USCG facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC
Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable
Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is _________.
3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:
Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.
National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an
NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.
Air Emission Permit: Unit has a Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.
3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.
3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, 3 (Rev-00) and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The
Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility
Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System
(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste
Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the
Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;
ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the
Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix B, Requirements For
Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).
3.5.6 Additional Requirements. The Contractor shall be aware of the following:
3.5.6.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the
Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast
Guard facility without COR or KO-approval.
3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor shall prepare for and comply with local and state regulations.
3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor shall furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.
3.6 Local Policy. None.
3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:
3.7.1 SFLC Standard Specification 6310, Requirements for Preservation of Ship Structures.
3.7.1.1 SFLC Std Spec 6310, Page C-2, Section C1.5.1. Change from "lead-containing paint as 0.06%" to "lead-containing paint as 0.009%".
4 (Rev-00)
3.7.1.2 SFLC Std Spec 6310, Page 4, Section 2 References, Group- Other References. Add “The Society for
Protective Coatings (SSPC) Paint Application Guide No. 11, 2008, Protecting Edges, Crevices, and Irregular Steel
Surfaces by Stripe Coating”
3.8 Work Plan Contractor shall perform the work on the following work items in the first 2 weeks of the contract availability.
Work Item: Main Propulsion Diesel Engine- DEI
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
5 (Rev-00)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL #
WORK
ITEM #
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi).
If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
6 (Rev-00)
Name of QP-1/NACE Inspector Signature Cert. # Date / Time
7 (Rev-00)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL #
WORK
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE &
TIME
ACTIVITY
(Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION
(Frame & Deck, relation to equipment, etc.)
TEMPERATURE
% REL.
HUMID-ITY
DEW PT. SURFACE AMBIENT
ΔT
| DP - Surface
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. #
DATE /
TIME
8 (Rev-00)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL #
WORK
LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min Max Mean
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
Abrasive Manufacturer and Sieve Size: _________________________________
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings: ______________
9 (Rev-00)
10 (Rev-00)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL #
WORK
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min Max Mean
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
Abrasive Manufacturer and Sieve Size: _________________________________
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA
RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Mean Mil Reading (IAW ASTM D4417-Method B) for above 10 readings (by column):
_____ mils _____ mils _____ mils _____ mils _____ mils
11 (Rev-00)
12 (Rev-00)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL #
WORK
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15
DATE TEST LOCATIONS
CONDUCTIVITY
(MICROSIEMENS/CM)
13 (Rev-00)
14 (Rev-00)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL #
WORK
COATING MFG PRODUCT NAME BATCH #
INDUCTION
TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2
SPOT 1 2 3 4 5
AVERAGE
VALUE
*BASE METAL READING
(BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation
3 Before Adjustments After Adjustments
Avg.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation
3 Before Adjustments After Adjustments
Avg.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation
3 Before Adjustments After Adjustments
Avg.
APPLICATION METHOD (AIRLESS, CONVENTIONAL
SPRAY, ROLLED)
AVERAGE DFT
15 (Rev-00)
24300_JAH_1114_418
WORK ITEM 1: Main Propulsion Diesel Engine- DEI
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform DEI (Diesel Engine
Inspection on both MPDE’s listed in Table 1, onboard the cutter.
TABLE 1 – MPDE NAME PLATE DATA
EQUIPMENT
MODEL NUMBER /SERIAL
NUMBER
LOCATION
Main Propulsion Diesel Engine,9666
HP, MTU Detroit Diesel, Inc.
20V 1163 TB 93 /5840276
AFT Main Machinery Room (5-52-0-E)
Main Propulsion Diesel Engine,9666
HP, MTU Detroit Diesel, Inc.
20V 1163 TB 93 / 5840277
AFT Main Machinery Room (5-52-0-E)
1.2 Government-furnished property.
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST ($/UNIT)
N Diesel Engine Inspection Kit P/N: 584-DEI-KIT
NSN: 016280945
02 ea 3051.97
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 750-WMSL-100-001, Rev C, General Arrangements (ASC100001)
Coast Guard Drawing 750-WMSL-501-2, Rev E, Machinery Arrangements (ASC501001)
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 0000, 2014, General
Requirements
Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 6310, 2014, Requirements for Preservation of Ship Structures
Coast Guard Technical Publication (TP) 7024, 31-MAY-07, Main Diesel Engine - Removal
Spaces and Weights
Coast Guard Technical Publication (TP) 7025, 31-MAY-07, Main Diesel Engine - Fluids and
Lubricants Specifications (A001061/3
Coast Guard Technical Publication (TP) 7026, 31-MAY-07, Main Diesel Engine - Repair Tools
Coast Guard Technical Publication (TP) 7027, 31-MAY-07, Main Diesel Engine - Operating
Instructions
16 (Rev-00)
Coast Guard Technical Publication (TP) 7028, 31-MAY-07, Main Diesel Engine - Maintenance
Manual
Coast Guard Technical Publication (TP) 7031, 31-MAY-07, Main Diesel Engine - Parts Catalog
(M034562/01DE)
OTHER REFERENCES
None.
3. REQUIREMENTS
3.1 General.
3.1.1 CIR
3.5.11 Submit a separate final report for each engine noting the condition of each engine, any inspection results and LOS data plots.
3.1.2 Technical Representative. The Contractor shall provide the services of qualified Tech Rep, who is familiar with - MTU America, Inc. to accomplish the following tasks – on site:
Provide manufacturer's proprietary information, software, and tools pertinent to the equipment/system.
Assist with proper repair methods, and ensure compliance with manufacturer's procedures and standards during disassembly, inspection, repair, modification, calibration, and reassembly of the equipment/system.
Technical Representative shall be present for all disassembly, inspection, and reassembly of the Diesel Engine.
3.1.2.1 The Contractor shall ensure that the Tech Rep is a certified representative of MTU America, Inc.
3.1.2.2 The Contractor shall submit the name of the Tech Rep to the COR at the Arrival Conference.
3.1.2.3 The Contractor shall be required to have this Technical Representative present (mandatory), on site, while the following engine work is being performed:
Diesel Engine Inspection
3.1.2.4 Tech Rep. All work in this work item shall be performed by MTU America Inc personnel.
3.1.2.5 Point of Contact is: Mr. David Sears, Acting Director, Large Engine Business; MTU America
Inc. (510) 333-0701.
3.1.3 Protective measures. The Contractor shall furnish and install suitable covering to seal off and protect all non-affected surfaces/equipment and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, remove protective material and inspect for the presence of contamination. Clean all equipment and spaces, contaminated due to improper protection, to original condition of cleanliness.
17 (Rev-00)
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec
0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
Access covers.
Exhaust stack.
Piping.
Vent ducting.
Electrical Cables
3.2 Contractor Furnished Material and Equipment. The contractor shall supply all consumable materials, equipment, and tools required to perform the inspection on the Port and Starboard Main Diesel Engines.
Additional parts beyond consumables shall be supplied by the government and are shown above.
Additional parts which may be required shall be subject of a contract modification.
3.3 Operational Test. Ship’s force will conduct an operational test of the Starboard Main Diesel engine prior to inspection in presence of contractor and USCG inspector. Submit CFR.
3.4 Main Diesel Engine Description and Contract Performance Data. Each of the Main Diesel Engines is a 20 cylinder Model 20V1163TB63 manufactured by MTU. CG Tech Pubs references above describe each engine and will be available onboard the cutter for review. CG Tech pubs are available aboard the vessel.
3.5 Diesel Engine Inspection. Perform the standard diesel engine inspection on each of the two (2) Main
Propulsion Diesel Engines. The tech rep shall perform the following actions:
3.5.1 Cylinder Compression Readings. Take and record compression readings on each cylinder of each main diesel engine.
3.5.2 Valve Clearance Readings. Check the valve clearance on all valves on each engine cylinder head.
3.5.3 Turbocharger Inspections. Using a boroscope, inspect the HP and LP turbocharger wheels. Each engine has five (5) Hp and five (5) LP turbochargers. Submit CFR with photo documentation.
3.5.3.1 Remove plug screws and conduct boroscope inspections of turbochargers through plug screw holes on all low pressure intercoolers. Reinstall plug screws after completion of inspections. Coat plug screws with lithium grease prior to reinstallation.
3.5.4 Gear Case Inspections. Remove casing side covers and inspect the wear patterns on the main pump drive gears on each engine. Submit CFR with photo documentation.
3.5.5 Cylinder Liner Inspections. Using a boroscope, inspect intake and exhaust valves, and cylinder head liners and piston crowns on each cylinder. Submit CFR with photo documentation.
3.5.5.1 Remove air start valve plugs on each cylinder.
3.5.5.2 Bar over the engine as required to conduct boroscope examination of cylinder internals.
3.5.5.3 Reinstall and torque air start valve plugs on each cylinder Torque to 200 NM (+ or – 10 NM).
18 (Rev-00)
3.5.6 Air Bank Inspections. Remove the plug on the end of each charge air elbow and discharge of the
HP intercoolers on the “A” and “B” bank on each engine. Boroscope inspect the “A” and “B” bank manifolds on each engine. Reassemble the charge air pipes.
3.5.7 Piston cooling oil Filter Inspection: Remove one of the three Piston Cooling Oil Filters and cut open and inspect filter media for signs of contamination. Replace all three Piston Cooling filters from DEI kit.
3.5.8 Visual Inspections. Visually inspect each engine for leaks or other necessary repairs. Submit CFR for any necessary repairs.
3.5.9 Download engine operation data from the LOS program aboard the cutter.
3.5.10 Submit a report of cast numbers on all cylinders on both engines.
3.5.11 Submit a separate final report for each engine noting the condition of each engine, any inspection results and LOS data plots.
3.5.12 Reassemble all parts of each engine which were disassembled to perform inspections.
3.6 Operational Test. Ship’s force will conduct an operational test of each engine upon completion of inspections. Submit CFR.
4. NOTES
This section is not applicable to this work item.
19 (Rev-00)
23300_TAB_0516_751
WORK ITEM 2: Main Propulsion Diesel Engine (MPDE),12,000 Hour Repair
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform 12,000 hour maintenance on both MPDE for items listed on table 1.
TABLE 1 – MAINTENANCE ITEMS FOR MPDE #1 AND MPDE #2
ITEM MAINTENANCE TASK TASK # MPDE #1 MPDE #2
Emergency air shut-off flaps Inspection Only X
Jacket water thermostat Renew X
Centrifugal oil filter Check and replace elements X
Fuel filter Replace element X
Valve gear Check valve clearance X
Engine mounts Check Buffer clearance W1026 X
Fuel injectors Renew X
Engine coolant pump Renew W1384 X
Raw water pump Renew W1383 X
Cylinder heads Renew W1063 X
Cylinder liners Renew W1101 X
Fuel prefilter Replace filter element X5900 X
Preheater / Jacket water heater Inspect for leaks
X5602 X X
Preheater Renew X5601 X
Level probes (expansion tank) Inspect
X5501 X X
Lube-oil tank Inspect X X
Auxiliary priming unit Inspect X X
Cooler installation
Clean cooler and replace seals
(PCHE)
X X
Pressure reducing station
Clean air filter, renew if necessary. Renew diaphragm
(Block)
X7650
X7651
X X
Compressed-air starting system Inspect
X X
Fuel Injection pumps Renew X X
Charge-air preheating
Remove, clean and check control valve (TC valve)
X
Intercooler (low pressure)
Clean interior of cooler, check for damage
W1133 X
Conrod bearings Renew W1083 X
Gear train Perform visual inspection W1086 X
Governor actuator Inspect governor linkage X X
20 (Rev-00)
Vibration damper
Remove and inspect vibration dampener
W1129 X X
Pistons Renew W2044 X
Oil thermostat Renew W1128 X
Component maintenance
Starting air distributor: Inspect components, check settings.
Adjust if Necessary.
Fuel thermostat (if fitted): Fit new thermostat actuator.
Check rockers, roller tappets, pushrods and pushrod ball heads for wear.
Check engine alignment.
W2041
W2036
W2084
X X
1.2 Government-furnished property.
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST ($/UNIT)
Y Cylinder Liner Kit P/N: 584-CYL-LINR-KIT
NSN: 016192672
20 ea. 3672.81
Y Fuel Injection Pump Kit P/N: 584-FL-INJ-PMP-KIT
NSN: 016192228
40 ea. 12245.35
Y Injector Replacement Kit P/N: 584-INJ-RPL-KIT
NSN: 015911763
20 ea. 2377.54
Y Piston Engine P/N: 5840301117
NSN: 123349610
20 ea. 10180.72
Y Conrod Bearing P/N: 5840301960
NSN: 123587417
20 ea. 941.03
Y Cylinder Head Replacement
Kit
P/N: 584-CYL-HD-RPLM
NSN: 016192838
20 ea. 15450.56
Y Jacket Water Pump LS
Replacement Kit
P/N: 584-JWPMPLS-RPLM
NSN: 016263405
1 ea. 13360.14
Y Jacket Water Pump RS
Replacement Kit
P/N: 584-JWPMPRS-RPLM
NSN: 016192545
1 ea. 13577.89
Y Sea water pump
Replacement Kit
P/N: 584-SWPMP-RPLM
NSN: 016192264
1 ea. 27071.07
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 750-WMSL-100-1, Rev L, General Arrangements (ASC100001)
Coast Guard Drawing 750-WMSL-501-2, Rev E, Machinery Arrangements (ASC501001)
21 (Rev-00)
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
Coast Guard Technical Publication (TP) 7025, 31-MAY-07, Main Diesel Engine - Fluids and
Lubricants Specifications (A001061/3
Coast Guard Technical Publication (TP) 7026, 31-MAY-07, Main Diesel Engine - Repair Tools
Coast Guard Technical Publication (TP) 7027, 31-MAY-07, Main Diesel Engine - Operating
Instructions
Coast Guard Technical Publication (TP) 7028, 31-MAY-07, Main Diesel Engine - Maintenance
Manual
Coast Guard Technical Publication (TP) 7031, 31-MAY-07, Main Diesel Engine - Parts Catalog
(M034562/01DE)
OTHER REFERENCES
MTU Technical Documentation S000082/00E (MTU Tech Doc S000082/00E), 2011, Functional
Descriptions, Operating Instructions, and Instructions for General Overhaul
MTU Maintenance Schedule M050711/06E.
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Technical Representative. The Contractor shall provide the services of an OEM-certified Tech Rep, who is familiar with the MTU 20 V Series 1163 TB93 Main Propulsion Diesel Engine and its intake air and exhaust turbocharger controls, to accomplish the following tasks – on site:
Provide manufacturer's proprietary information, software, and tools pertinent to the equipment/system.
Perform proper repair methods and ensure compliance with manufacturer's procedures and standards during disassembly, inspection, repair, modification, calibration, reassembly, and operational testing of the equipment/system.
3.1.2.1 Ensure that the Tech Rep is a Certified Representative of MTU America, Inc., the OEM.
3.1.2.2 Submit the Tech Rep’s name and résumé to the COR at the arrival conference .
3.1.2.3 The Contractor shall be required to have this Technical Representative present (mandatory), on site, while the following engine work is being performed:
Disassembly
22 (Rev-00)
Inspection and qualification of parts
Reassembly
3.1.3 Protective measures - general. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, the
Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec
0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
Piping systems
Engine parts including exhaust piping
Electrical cables
Catwalks
Engine oil
Jacket Water
3.1.5 Work location. The concerned work area is AFT Main Machinery Room (AMMR) 5-52-01-E. See the applicable drawings in References in Paragraph 2 of this work item for guidance, locations, and details.
3.1.6 MPDE Information. The MPDE Name plate data is listed in the Table 2.
TABLE 2 – MPDE NAME PLATE DATA
EQUIPMENT MODEL NUMBER LOCATION
Port: Main Propulsion Diesel
Engine,9666 HP, MTU America , Inc.
20V 1163 TB 93 AFT Main Machinery Room (5-52-01-E)
STBD: Main Propulsion Diesel
Engine,9666 HP, MTU America, Inc.
20V 1163 TB 93 AFT Main Machinery Room (5-52-01-E)
3.1.7 Operational test - initial. Prior to commencement of work, the Contractor shall witness Coast
Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.
3.2 Maintence and Inspection. The Contractor shall be follow directions from Tech Rep and TP 7028 and
MTU Technical Documentation S000082/00E as needed to accomplish the maintence, inspections and repairs required for the 12000 hr Maintence Schedule items listed on Table 1. Submit CFR.
3.3 Materials with core return. The Contractor shall use the boxes and packing materials from the new parts to pack the used cores. Deliver the boxes with the used parts to COR.
3.4 Operational test – post repairs. After completion of all authorized work, the Contractor and CG
Inspector shall witness an operational test (by Coast Guard personnel) of the main diesel engines to prove satisfactory operating condition. Submit a CFR.
23 (Rev-00)
3.5 Touch-up preservation. The Contractor shall prepare and touch-up coat all disturbed surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, Appendix B (Cutter and Boat
Interior Painting Systems). Abide by all touch-up requirements outlined in SFLC Std Spec 0000, Appendix A (Requirements for Preservation of Ship Structures).
4. NOTES
This section is not applicable to this work item.